Enhanced Frequency
Control Capability
(EFCC)
National Grid
Battery Storage Investigation Report - November 2015
EFCC Battery Storage Investigation
Report November 2015
Page 1
Executive Summary ................................................................................Error! Bookmark not defined.
Chapter 1 Purpose of this report.......................................................................................................4
Chapter 2 Use of Battery Storage within the EFCC project..............................................................6
2.1 The Main Drivers for using battery storage ....................................................................7
2.2 Innovation and Learning Outcomes................................................................................7
2.3 Impact of Future Energy Scenarios on system operability...............................................8
2.4 International Experience ..............................................................................................10
Chapter3 Evaluation of existing battery storage in the UK............................................................11
3.1 Timescales for EFCC trials .............................................................................................11
3.2 Short-listed battery units..............................................................................................11
3.3 Smarter Network Storage (SNS) at Leighton Buzzard...................................................12
3.4 Rise Carr (Darlington) ...................................................................................................13
3.5 Willenhall .....................................................................................................................15
Chapter 4 Belectric Energy Buffer Unit (EBU) Battery Storage......................................................16
Chapter 5 Commercial Analysis of shortlisted storage units ..........................................................18
5.1 Cost summary for Smarter Network Storage (SNS).......................................................18
5.2 Cost summary for Rise Carr (Darlington).......................................................................19
5.3 Cost summary for Willenhall ........................................................................................20
5.4 Cost Summary for Belectric Energy Buffer Unit.............................................................21
5.5 Summary ......................................................................................................................21
Chapter 6 Opportunity for combining solar PV and battery storage in EFCC ................................24
6.1 Trials for Solar PV and Battery Storage .........................................................................24
6.2 Belectric Contribution with solar PV and battery storage .............................................25
Chapter 7 Cost Benefit Analysis for future roll out of hybrid battery storage and solar PV............26
7.1 Cost Benefit Analysis Introduction................................................................................26
7.2 Cost benefit analysis: methodology and results............................................................27
7.2.1 High-level overview....................................................................................................... 27
7.2.2 Future additional enhanced response requirements.................................................... 28
7.2.3 Future additional costs to consumers ........................................................................... 31
7.2.4 Battery availability and service provision assumptions ................................................ 33
7.2.5 Battery rollout projections ............................................................................................ 34
7.2.6 Solar deployment and battery adoption projections.................................................... 35
7.2.7 Market potential for the hybrid project and possible consumer savings ..................... 37
7.2.8 Economic viability considerations ................................................................................. 42
7.3 Additional potential benefits........................................................................................45
7.4 Summary and Conclusions............................................................................................45
Chapter 8 Revised Project Schedule for Work Package 2.4 (Battery Storage) .............................47
Table of Contents
Page 2
EFCC Battery Storage Investigation
Report November 2015
Chapter 9 Legacy options for Belectric Battery Storage Unit .........................................................48
Chapter 10 Recommendations .........................................................................................................49
Appendix A Questionnaire sent to DNOs ..........................................................................................50
Appendix B Existing battery storage site evaluations .......................................................................51
Appendix C NPG Rise Carr 2.5MVA Battery Unit Detailed Costs.....................................................55
Appendix D Cost of Belectric Energy Buffer Unit (EBU) Battery Storage .........................................56
Appendix E Cost Benefit Analysis Assumptions ...............................................................................57
Appendix F Consumer cost of additional Enhanced Frequency Response......................................61
Appendix G Solar farm participation projections................................................................................62
Appendix H Availability requirements for enhanced frequency response .........................................63
Appendix I Data Tables for Figures 6 - 8 .........................................................................................64
Appendix J EFCC Project Hierarchy.................................................................................................65
References............................................................................................................................................66
Page 3
EFCC Battery Storage Investigation
Report November 2015
Executive Summary
The purpose of this report is to provide the summary of the investigation into the use of existing
battery storage facilities for the Network Innovation Competition funded project; Enhanced Frequency
Control Capability (EFCC). As part of this investigation, National Grid carried out the following
activities; starting from December 2014:
Further reviewing the battery storage technologies suitable for demonstrations of fast
frequency response in the EFCC project (in addition to the previous work carried out before
submission of EFCC proforma to Ofgem);
Engaging with the owners of these battery storage facilities which their technology was
deemed to be suitable for providing fast frequency response;
Carrying out site visit, request detailed implementation cost, timeline, and explore the
technical and commercial aspects of use of one of those facilities; and
Carrying out an impact assessment; taking into account the overall cost to the project, project
delivery risk and value to consumers.
Further on, we have performed a detailed cost benefit analysis (CBA) into the potential roll-
out of the hybrid battery storage-renewable generation as proposed in EFCC.
The main findings of this exercise include:
There are limited number of already installed battery storage facilities which are suitable for
providing the fast response, namely: Leighton Buzzard, Rise Carr (Darlington), and Willenhall.
The main challenges of using the existing sites include significant delays in delivering the
EFCC project, expensive modifications costs (in case of Leighton Buzzard it will be more
expensive than use of the new battery storage), and potential future costs that were not
possible to clarify at this stage.
More importantly, the inability to perform the demonstration of fast response capability of
renewable energy resources combined with battery storage (hybrid) as proposed in this
project, should we decide to use already installed battery storage.
The hybrid battery storage and renewable generation (solar PV) will be the first demonstration
of such concept in Great Britain, and will generate significant learning on the system benefits
in the context of the System Operability Framework, and Future Energy Scenarios. Our CBA
shows that should the EFCC trials being successful, a significant volume of extra response
can be avoided by having longer availability of service from Battery Storage and Solar PV.
This will in turn make the hybrid PV-Storage a financially attractive service option given the
increase in revenue from ancillary services that can be attributed to this type of service.
On the balance of cost, project implementation risks, and value for money for our consumers, and roll-
out potential we therefore recommend the use of new battery storage for EFCC project. This will
enable the project to proceed with the demonstrations needed for the future frequency control at
reduced cost from a wide range of resources.
Page 4
EFCC Battery Storage Investigation
Report November 2015
Chapter 1 Purpose of this report
Chapter 1 Purpose of this report
In order to meet carbon reduction targets, GB needs to significantly increase the volume of low
carbon energy technologies that are connected to the GB transmission system. The overall impact of
increasing these types of technology will be a reduction in system inertia.
System inertia is a characteristic of an electrical transmission that provides system robustness against
any frequency disturbances and is a result of the energy stored in the rotating mass of electrical
machines i.e. generators and motors.
As more renewable energy technologies such as wind, solar PV and other convertor based
technologies (e.g. interconnectors) are connected to the transmission system; there will be a
corresponding reduction in inertia since these technologies do not contribute to natural mechanical
inertia.
In the GB the transmission system, frequency is nominally 50Hz and the System Operator caters for
various imbalances caused by changes in demand or generation to maintain the frequency in
accordance with the National Electricity Transmission System Security and Quality of Supply
Standard (NETS SQSS). However, the lower the system inertia, the more susceptible a transmission
system is to a higher rate of change of frequency (RoCoF) in the event of the loss of a significant
volume of generation or demand and requires an increase in the speed and volume of frequency
response.
The EFCC Project Full Submission report (October 2014), provided cost benefit analysis to show that
under existing mechanisms to control frequency response used by National Grid, the future increase
in response requirement to control frequency is anticipated to be £200m-£250m per annum by 2020.
This cost is based on the Gone Green Future Energy Scenario as published by National Grid in 2014
that gives rise to an increase in RoCoF of 0.3Hz/s.
As set out within the EFCC Full Submission report, within Work Package 2.4, a proposal was put
forward to trial battery storage as part of a portfolio of service providers for fast frequency response.
The proposal included provision for investment in a new battery storage unit (plus two inverters for
increased active or reactive power). Costs were included for trials to be carried out at two different
locations, one of which would allow for combining battery storage with a solar PV plant.
Belectric were chosen as a project partner for the provision of battery storage and solar PV power
plant for frequency response within EFCC through a competitive tender process in line with all partner
selections against set criteria. These criteria included cost and contribution to ensure value for money;
organisation to rate reputation and expertise; understanding of project requirements and the ability to
deliver; offered solution that is innovative, low carbon, brings customer benefits and learning.
Belectric has developed, planned and built a number of hybrid projects where various energy sources
are combined and controlled, including PV, batteries, diesel and water power generators. For the
EFCC bid they provided detailed cost estimates that were verified and reviewed through a thorough
internal review process that included National Grid procurement and finance departments.
A new battery storage facility represented a significant proportion of the EFCC project costs
(approximately £1.1m). However, due to the containerised unit provided by Belectric, trials could be
undertaken at Redruth in Cornwall and Rainbow Solar Farm (3.8MWp) in Gloucestershire. This will
Page 5
EFCC Battery Storage Investigation
Report November 2015
Chapter 1 Purpose of this report
enable trials to be carried out at a location on the GB transmission system known to be susceptible to
operability challenges (Redruth) as well as gaining valuable learning from the battery unit sited at
Rainbow Solar Farm.
However, to ensure EFCC represents the best possible value for consumers in advance of any
expenditure, a Decision Point was included within the project timescales to allow National Grid to
investigate the use of existing battery storage sites within the UK.
This report details the outcomes of investigations considering technical and commercial implications
of using existing facilities within the EFCC project as well as impact on timescales. Comparison and
commercial analysis is presented between those sites deemed most appropriate for use for fast
frequency response versus the installation of an additional battery storage facility. Furthermore, the
benefits of a hybrid solar PV and battery storage solution are presented.
Since the initial report that was completed in June 2015, additional chapters and updates have been
made in this revision. The changes are as follows
Chapter 6 Update on use of Redruth site for battery storage; Belectric contribution to
solar PV and battery storage.
Chapter 7 Cost benefit analysis (CBA) for future roll out of hybrid battery storage and
solar PV. This chapter provides a detailed CBA identifying the number and
MW capacity of potential solar farms that could install battery storage and
projected future deployment if the EFCC project is successful.
Chapter 8 Revised Project Schedule for Work Package 2.4 (Battery Storage)
The original EFCC project schedule for this work package assumed an
investment decision point would be reached by August 2015 hence revised
timescales are proposed.
Chapter 9 Legacy options for Belectric Battery Storage Unit.
This chapter outlines the considerations that will be taken into account
towards the end of the project for future use of the new battery storage unit if
investment is approved.
Finally, a recommendation is proposed that establishes and quantifies the benefits, potential learning
within EFCC and value to consumers to enable Ofgem to determine if investment in further battery
storage should be made.
Page 6
EFCC Battery Storage Investigation
Report November 2015
Chapter 2 Use of Battery Storage within EFCC project
Chapter 2 Use of Battery Storage within the EFCC projectThe objective of the EFCC project is to develop and demonstrate an innovative new monitoring and
control system which will obtain accurate frequency data at a regional level, calculate the required
rate and volume of very fast response and then enable the initiation of this required response. The
control system will then be used to demonstrate the coordination of fast response from wind, large
scale thermal generation, demand side resources (DSR), solar PV and battery storage. Utilising the
output of these trials, a fully optimised and coordinated model will be developed which ensures the
appropriate mix of response is utilised. This will support the development of an appropriate
commercial framework at the end of the project.
Figure 1 below shows indicative GB regional zones for regional control and the proposed Alstom
scheme to monitor wide area frequency measurements and control the response providers.
Figure 1: Control System Architecture
Battery storage is regarded as a central part of the fast services to be trialled within the EFCC project.
Previous studies and practical solutions have demonstrated that battery storage is able to provide fast
and sustained response on various networks to maintain stability. Connected to the wide area
measurement of Alstom, the battery shall provide fast and local frequency response, based on central
and locally derived response signals. The goal is to counteract local frequency deviations in order to
neutralise them before they become a major disturbance. This has to be done close to the source of
disturbance and in a timeframe of well below 100ms, since this is the typically measured time of such
disturbances. The battery response trials shall be based on:
Page 7
EFCC Battery Storage Investigation
Report November 2015
Chapter 2 Use of Battery Storage within EFCC project
Maximum response to curtail reduction in frequency. Trial the fastest possible rise and
sustained response until frequency is restored or stored energy is used.
Frequency following (Proportional Control; output in response to variations in frequency).
This response could be enabled locally and controlled.
Set-point following initiated from a remote signal in combination with other response
providers. This mode could be used by the monitoring and control system to sustain a
frequency response.
In addition, a further trial could be to use historic data (i.e. over the previous few milliseconds) to
predict upcoming frequency drops.
While the above is a way of frequency stabilisation by actively responding to a measured signal
(“active response”), there is as well, a passive response which is crucial for grid stability: the grid
inertia. Grid inertia is traditionally supplied by the rotating mass of synchronous generators. Due to
increasing penetration levels of renewable energy in the network, the share of synchronous
generation is dropping rapidly as well as inertia. The reason behind this is lack of inertia of the
physical generation source (e.g. solar PV panel in case of solar energy and of the grid coupling
inverter). There is simply no mass turning. A battery – on the contrary – is capable of simulating
inertia, since it may provide a very high short circuit power. Given that this is combined with a fast
reacting inverter, it may provide a “virtual inertia” by very fast active control (<20ms). In this way it
may replace the inertia traditionally supplied by synchronous generators and shall be trialled during
the project.
2.1 The Main Drivers for using battery storage
Demonstrate the principle operability of a frequency control battery on the network.
Demonstrate different reaction speeds.
Demonstrate emulation of rotating generators and their inertia by implementing a very high
response rate (milliseconds or tens of milliseconds).
A direct connection to an external entity (i.e. the NETSO) shall be established, so definition of
working points, response statistics or direct command and control may be done from a central
point outside the unit.
2.2 Innovation and Learning Outcomes
Innovative command and control schemes will be implemented that enable the battery to act
similar to rotating machines, providing short-circuit power capacity, and respond to external
control signals.
Evaluation of the challenges of incorporating batteries in network regulation (e.g. various
States of Charge) and their advantages will be studied.
The financial benefits of operating a battery in the plant will be studied and the development
of a future financial compensation and commercial policy for battery operation will be outlined.
This will provide a vital new tool for National Grid as we continue to manage the GB system.
Page 8
EFCC Battery Storage Investigation
Report November 2015
Chapter 2 Use of Battery Storage within EFCC project
Allow a fuller assessment of the potential for greater competition in frequency response
service provision that can inform other Transmission Licensees.
Demonstrate battery storage can best be coordinated to provide an optimised response
across a range of resource providers.
The response capabilities of new technologies are not currently being fully utilised. With the
increase in the amount of renewables connected to the GB electricity system, it is vital that a
more diverse range of resources are able to contribute to system stability in a more economic
and efficient way.
Potential for knowledge of the capability of batteries and solar PV power plants in delivering
grid services on different levels.
Support the development of performance requirements for roll out of an Enhanced Frequency
Control Capability as a new balancing service.
2.3 Impact of Future Energy Scenarios on system operability
Annually National Grid publishes four future energy scenarios that outline possible variations in
generation and demand patterns. Last year under the Gone Green scenario, predicted that in meeting
the UK renewable energy targets, solar PV would contribute 2.3GW of installed capacity by 2020.
The connection of embedded generation is increasing rapidly in GB. Due to its lower operational
voltage these installations are connected to Distribution Network Operators (DNOs), hence its output
will offset the total demand seen at the interface boundary between the transmission and distribution
systems.
In order to maintain the system frequency within statutory limits, the System Operator must balance
generation and demand. However, as the volume of intermittent generation sources grows, the
demand seen by the transmission system will become increasingly volatile and pose challenges in
predicting demand and therefore operation of the transmission system.
Figure 2 below, shows an average demand profile for an average Sunday in July for the Gone Green
future energy scenario. Historical data has been obtained between 2005 – 2008/9, excluding the
impact of embedded generation and has been scaled against the summer minimum demand values
to produce a base demand daily profile. Planned solar daily profiles have been derived from average
output profiles and scaled to 84% of capacity (14GW). The resultant transmission demand profile is
offset by the solar output. Between the dotted line, illustrating the natural load and the hard red line of
the planned embedded solar case there is some 18GW of difference over the course of a day.
Page 9
EFCC Battery Storage Investigation
Report November 2015
Chapter 2 Use of Battery Storage within EFCC project
Figure 2: Impact of increasing solar PV on the transmission demand pattern (2020)
Against such declining demand levels, there is a danger that in particular regions of the network
where there is high concentration of solar PV, there is potential for parts of the network to be
disconnected. This could arise when there is a frequency excursion that triggers LFDD (Low
Frequency Demand Disconnection) which is an operational method used to correct the imbalance
between generation and demand. If LFDD action occurs, the network could represent negative
demand and further contribute to any frequency disturbance which takes the system beyond normal
frequency containment limits.
In addition to managing the system with increasingly volatile periods of transmission demand, solar
PV is connected to the system via power electronics and therefore does not provide inertia. As
mentioned in Chapter 1, this means that a system with lower inertia will be susceptible to high RoCoF
necessitating increased frequency response to be held by the System Operator. Historically to
operate the system in low demand periods, generation is constrained and interconnector imports
restricted. However, as a greater proportion of generation is supplied from intermittent sources, more
frequency response will be required from alternatives to conventional generation such as those being
trialled in the EFCC project.
An alternative approach is to combine solar PV with battery storage. This will allow storage to be used
to better regulate or smooth the transmission demand profile or be used to provide response during
periods of rebalancing as other conventional plant ramps up to provide a sustained response to
maintain frequency within limits.
Use of batteries would offer the flexibility either to reduce the effective generation contribution to the
distribution system which is observed at these times of stress, or to provide additional fast response
to support frequency containment under high RoCoF events, instead of reliance upon the natural
inertia of (slower responding) conventional generation or LFDD action.
Page 10
EFCC Battery Storage Investigation
Report November 2015
Chapter 2 Use of Battery Storage within EFCC project
2.4 International Experience
In Germany renewable energy contributes significantly towards their total generation capacity. It has
been recognised that due to the higher volatility of generation and demand patterns, battery storage
can play an active part in smoothing this volatility as well as providing fast frequency response. The
four German TNOs, Tennet, Amprion, Transnet BW and 50Hertz have enabled renewables to
participate in the frequency reserve market by changing their bidding/procurement timescales and
established prequalifying criteria to fully benefit from the potential combining solar and battery plants
to ancillary services.
Last year in the US, the State of California passed legislation mandating that energy storage facilities
be installed to support the integration of additional solar and wind energy in order to meet their utility
owned energy storage target by 2020 (approximately 1.3GW)[6]
. It is the first state to do this, but is
recognition that storage systems can support the uptake of renewable technology connected to utility
networks in addition to providing standalone peak load reduction, voltage support and frequency
response services. As an example of this uptake, Invenergy (developer of clean power generation
and energy storage projects) has installed a 31.5MW battery storage in central Illinois which is located
near a wind farm project and solar plant to provide fast frequency response as well as other ancillary
services[7]
.
Furthermore, in order to integrate more wind energy into an island system in Alaska, the electricity
utility installed a 3MW battery storage system instead of connecting more diesel generation as
spinning reserve. In addition to mitigating the curtailment of energy from wind farms, the lead-acid
battery system is capable of providing frequency response within 0.5s if required[8]
.
The Zhangbei National Wind and Solar Energy Storage and Transmission Demonstration Project
includes a total of 17MW/70MWh of energy storage through a combination of lithium-ion and
vanadium redox flow battery technologies. The use of batteries supports the integration of wind, solar
and other renewable energy providing frequency regulation and voltage support to the grid[12]
.
Page 11
EFCC Battery Storage Investigation
Report November 2015
Chapter 3 Evaluation of existing battery storage in the UK
Chapter3 Evaluation of existing battery storage in the UKAs a starting point for evaluating existing storage facilities for potential use with the EFCC project,
information was collected using the Energy Storage Operators’ Forum published documentation. In
addition, a general enquiry was sent to all Distribution Network Operators (DNOs) that currently have
demonstration battery storage facilities or are due to install battery storage within the timescales of
the EFCC project. The email outlined our objectives, the reasons for the enquiry and the possibility of
participating in the project. In addition, a technical questionnaire was compiled and attached to the
enquiry to provide DNOs with information that the EFCC project would like to assess.
A full list of energy storage sites and associated technical criteria that was compiled from
documentation within the public domain as well as individual site specific details provided by DNOs.
This is shown in Appendix B.
From the initial information gathered, it was possible to eliminate a number of existing storage sites
for suitability for inclusion within the EFCC project based on the following criteria
1. Battery technology.
Flow type batteries as demonstrated at Nairn, FALCON and the DECC Energy Storage
demonstration sites[2]
were excluded on the basis that they will not provide the required fast
<0.5s response times to be trailed. Due to the time taken for electrolytes to mix that is
inherent with this technology to produce a change in power output, fast response times
cannot be achieved. Additionally, the power to capacity ratio of these batteries is not
favourable for short-term, high-power applications that are being trialled in the EFCC project.
2. Power output and Capacity
It is preferable for the battery unit to have a high power output so it will increase its
contribution to alleviating significant RoCoF by increasing or decreasing larger amounts of
power. Essentially for rapid frequency response it is beneficial to have more power delivered
at less installed capacity.
3. Connection to the system
The battery unit must be connected to the electricity network, hence units sited in the Scottish
Highlands that maintain security of supply could not be utilised for the project.
3.1 Timescales for EFCC trials
Within the EFCC project submission, the project plan outlined the installation and evaluation of a new
battery control system between October to December 2016 for integration with the Alstom monitoring
and control system. This is in advance of frequency response trials taking place from January 2017 to
September 2017.
3.2 Short-listed battery units
Three sites were chosen for further investigation as possible candidates for participation in the EFCC
project. These sites are Leighton Buzzard (6MW, 10MWh, Lithium Nickel Manganese Cobalt Oxide),
Darlington (2.5MW, 5MWh, Lithium Iron Phosphate), Willenhall (2MW, 1MWh, Lithium-Titanate).
The respective DNOs (UK Power Networks, Northern Power Grid, Western Power Distribution and)
were approached in order to discuss the viability of using these storage sites.
Page 12
EFCC Battery Storage Investigation
Report November 2015
Chapter 3 Evaluation of existing battery storage in the UK
3.3 Smarter Network Storage (SNS) at Leighton Buzzard
The Smarter Network Storage (SNS) project at Leighton Buzzard is an LCNF project that is to explore
multi-purpose use of battery storage from a technical and commercial perspective. The main driver for
battery storage at this site was to defer traditional reinforcement in order to maintain demand security
compliance at Leighton Buzzard, but the project is also trialling the provision of commercial ancillary
services to the transmission system.
Representatives from Belectric and National Grid attended a site visit to Leighton Buzzard to further
understand the battery and inverter technologies, how the site is controlled as well as the future
operational timescales within the lifetime of the project. One outcome from the visit is that it is unclear
if the control system can be modified to allow rapid response as per EFCC objectives.
The storage system is fully contained within a dedicated building adjacent to Leighton Buzzard
substation in Bedfordshire. The building also houses separate inverter and control rooms.
The battery size (6MW, 10MWh Li-NMC, Lithium Nickel Manganese Cobalt Oxide) offers a
power/capacity ratio of 0.6. There are 3 sets of 2MW battery stacks that are controlled by dedicated
energy storage management units that are controlled locally by a central control system that can be
accessed remotely. There is a forecasting and optimisation system for scheduling services which can
be enabled via a control room so there could be the possibility of trialling both local and remote
frequency response for EFCC. Overall, the speed of response will depend on the initiation being local
or remote. It is anticipated that the response time could be less than half a second but it is more likely
that the response time will be between 0.5s and 1s. The EFCC project is aiming for a target response
time of 0.1s.
SNS is currently trialling frequency response provision under National Grid’s existing ancillary
services (using a demand side aggregator); hence trialling with EFCC fits within their scope of
objectives.
The SNS project is due to complete in its entirety by December 2017 and it is the intention of UK
Power Networks to complete all their scheduled trials by December 2016. Given this, there is not an
exact alignment of timescales between the projects, and there is some risk that the trial period for
SNS could be extended in order to meet their project milestones.
UKPN has provided estimated costs for using SNS within EFCC. These are summarised in Chapter 5
in the Commercial Analysis section of this report. In addition, UKPN will be entering into commercial
contracts for the provision of ancillary services. The Commercial team in National Grid has estimated
a cost for these services that could be paid to UKPN in order to compensate for loss of revenue
during the trial period.
Page 13
EFCC Battery Storage Investigation
Report November 2015
Chapter 3 Evaluation of existing battery storage in the UK
Image 1 (courtesy of UKPN): Smarter Network Storage (SNS) at Leighton Buzzard (6MW, 10MWh, Li-NMC).
Image 2: Site visit to SNS at Leighton Buzzard
3.4 Rise Carr (Darlington)
Northern Power Grid (NPG), as part of their Customer-Led Network Revolution LCNF project,
installed a 2.5MW/5MWh LiFePO4 (Lithium Iron Phosphate) battery, unit at Rise Carr to investigate
how a battery can be used to facilitate the uptake of low carbon technologies.
Page 14
EFCC Battery Storage Investigation
Report November 2015
Chapter 3 Evaluation of existing battery storage in the UK
The project completed in December 2014 and currently NPG is considering future research and
commercial opportunities for the battery storage unit. In discussions with NPG, participating within the
EFCC project is being considered as an option, and a decision on the future utilisation of the battery is
expected summer 2015. Since the June issue of this report, NPG has stated that the Rise Carr site is
likely to be used for commercial ancillary services as well as local demand support. Indication has
been given that these commercial services could be suspended for use within EFCC although this is
to be confirmed.
The Rise Carr is built up of three separate shipping containers, 1 x Inverter section and 2 x Battery
Rack Containers and offers a power/capacity ratio of 0.5. Similarly to SNS, it can be controlled both
locally and remotely (including monitoring status and alarms, overall system data etc.). This is
achieved through dedicated software that can be used via a web browser. For remote control the
communication time is given as 20ms so a fast ramp response can be achieved in less than 100ms
which is the target response time for EFCC.
Estimated costs for its use within EFCC have been provided and these are summarised below in
Chapter 5 (Commercial Analysis) of this report. There is a possibility that NPG will undertake other
trials or even participate in the ancillary services in advance of the outlined trial period for EFCC. If
this occurs, for the duration of the EFCC trial period, it is likely NPG will have to suspend its ancillary
services activities and possibly compensated for loss of revenue. These services are bilaterally
contracted and since negotiations have not commenced, it is not possible to incorporate an
allowance. This cost exposure poses a risk for the EFCC project.
Image 3 (courtesy of NPG): Battery storage unit at Rise Carr, Darlington
Page 15
EFCC Battery Storage Investigation
Report November 2015
Chapter 3 Evaluation of existing battery storage in the UK
3.5 Willenhall
A 2MW/1MWh Li-Ti (Lithium-Titinate) battery unit is due to commission at Western Power
Distribution’s Willenhall substation at the end of July 2015. This is an EPSRC funded project to
investigate the characteristics of Li-Ti (this is the first battery of this type to be trialled in the UK), how
different battery chemistries can work together for grid use and the coordination of large storage with
EV (2nd
life) batteries. The project is being managed by the University of Sheffield who will be carrying
out research studies on Li-Ti cell degradation and integrating battery characteristics. Aston and
Southampton Universities are also involved in the project looking at the optimum use of 2nd
life EV
batteries and vehicle to grid research.
The battery is housed in a containerised unit sited on land leased from WPD. It has a power/capacity
ratio of 2 which is more favourable than the other sites for fast frequency response. There is a
dedicated management system that has a localised control interface, and in addition the University of
Sheffield has developed a bespoke remote control system that separately controls the battery
management system and the inverters. In this respect, any Alstom frequency control system for EFCC
will have to be integrated with the University of Sheffield system to enable frequency response
demonstrations. It is anticipated that a fast ramp response in line with the target response of 100ms
for EFCC can be achieved.
Funding for the project has provided the battery unit, inverters and associated assets for the
connection only. This is a purely research based project whereby the University of Sheffield is
endeavouring to gain as much learning as possible throughout the lifetime of the battery (guaranteed
for 10 years). As such, they are seeking interest in projects that could further the understanding of
how Li-Ti operates, although the provision of grid services is not the primary objective.
Estimated costs for use within EFCC have been provided and are summarised in the Commercial
Analysis section of this report. At the time of the June report, access to the battery for the EFCC
project could be made available from October 2016 (for control system modifications) through to the
end of the proposed trial period at the end of September 2017. Costs are associated with University
staff and contractor resource as there is no commercial cost exposure for EFCC as the Willenhall
project is for research purposes only.
Image 4 (courtesy of The University of Sheffield): Willenhall battery unit
Page 16
EFCC Battery Storage Investigation
Report November 2015
Chapter 4 Belectric Energy Buffer Unit (EBU) Battery Storage
Chapter 4 Belectric Energy Buffer Unit (EBU) Battery StorageThe Belectric solution consists of a 40” containerised high power lead acid battery that is optimised for
frequency regulation. It features a capacity of 948kWh and a deliverable power of 700-1400kW
depending on time and inverter configuration. The same battery type has shown to last 7000 full
cycles in frequency regulation (BEWAG battery, Berlin 1986-1994) and has been integrated into a
scalable and easily deployable stationary system using the technological advances of the last 20
years. The system is equipped with air conditioning and a powerful external venting for continual high
power applications, with automatic water refilling, electrolyte mixing and cell detailed battery
monitoring system to facilitate maintenance and remote operation. In addition it features a safety
system for hydrogen venting and charge control as well as an operating system which includes
operation, battery management and data provision (e.g. State of Charge, currently available power,
remaining total battery capacity) linked to a central SCADA system. It can be operated remotely and
has the same local and remote interface.
The battery system (developed from solar applications) is coupled to a GE based inverter skid in an
outdoor configuration complete with 11kV or 33kV transformer.
Image 5 (courtesy of Belectric): Energy Buffer Unit (EBU) battery storage
The inverter and the control system have been optimised for fast response times. Inverter based
control schemes such as virtual inertia and frequency generation, feature a reaction time less than
20ms. Control schemes invoking the operating system (frequency response, central command
response) feature a round trip time of under 100ms due to stringent loop time control and a real time
interface between control system and inverter.
Page 17
EFCC Battery Storage Investigation
Report November 2015
Chapter 4 Belectric Energy Buffer Unit (EBU) Battery Storage
Image 6 (courtesy of Belectric): EBU (battery storage) with inverter installation at Alt Daber, Germany
As the battery unit is containerised it can be relocated to further provide economises within the
project. Belectric has nominated two different sites (Rainbows Solar Farm, in Gloucestershire and
Redruth in Cornwall) where the battery can be sited during the project.
The two different locations for the battery unit were put forward as part of the EFCC submission for
separate reasons. The Redruth site was proposed in order to demonstrate independently how the
EBU can provide fast frequency response in a part of the network where there are existing challenges
in maintaining system stability. This will allow optimising of the Alstom monitoring and control system
in conjunction with this response provision in a known constrained part of the network.
Conversely, Rainbows Solar Farm was nominated to demonstrate how solar PV plant combined with
battery storage can provide additional learning for rapid frequency response. This is discussed further
later in this report in Chapter 6 “Opportunities for combining solar PV and battery storage in EFCC”.
4.1 Future use of potential Belectric Battery Unit
If a new Belectric battery unit (EBU) is to be used in the EFCC project, consideration must be given to
its ongoing use for the lifetime of the installation.
As mentioned in Chapter 3 “Evaluation of existing battery storage in the UK”, the rapid frequency trial
period is due to complete at the end of September 2017, which gives sufficient time to carry out
knowledge dissemination in advance of project closure at the end of March 2018.
The proposal for use of the EBU would be to participate within the new fast frequency commercial
framework to be developed by the EFCC project. The EBU would also be able to provide a range of
ancillary services to National Grid through existing mechanisms to assist in system stability.
Moreover, the system would be made available for further research activities to provide knowledge of
the viability and capability of the system. Further considerations of legacy options are detailed in
Chapter 9.
EFCC Battery Storage Investigation
Report November 2015
Chapter 5 Commercial Analysis of shortlisted storage units
Chapter 5 Commercial Analysis of shortlisted storage unitsThe analysis below outlines the cost estimates associated with using existing battery storage units at
Leighton Buzzard, Darlington and Willenhall. The base costs shown have been agreed with the
respective DNOs or in the case of Willenhall with the University of Sheffield. These costs are
commercially sensitive and as such will only be included in the report submitted to Ofgem and with
the not be made public.
As previously described in Chapter 3, SNS at Leighton Buzzard is due to enter into commercial
contractual arrangements with National Grid for frequency response. It is anticipated that during the
trial period for EFCC, SNS will not be able to fulfil these arrangements therefore the EFCC project will
need to reimburse their potential loss of revenue. Due to commercial sensitivity with differing
frequency response products that are negotiated, it is not possible to publically specify the contract
terms (e.g. price per MWh or time of use etc.). The Commercial Services department at National Grid
has estimated the cost of these services outlined in the report to Ofgem.
Similarly, the battery unit at Rise Carr may also need to be compensated for loss of revenue if they
enter into commercial contracts for frequency response but this is yet to be determined.
The engineering costs shown below for the existing battery storage sites include labour costs for
modifications to control and IS systems for the estimated 3 month period as set out in the schedules
in the EFCC Full Submission. Additionally, for some sites, consideration is given to warranty
extensions. It must be noted that these are high level estimates that are likely to change and be
subject to site surveys and further investigations to be undertaken during the project. The cost
breakdown for each site is outlined in the sections below.
5.1 Cost summary for Smarter Network Storage (SNS)
Cost (£k)
Addit
Alsto
enga
PRO
Page 18
ional project management 150
m additional project management cost including
gement with new project partner100
JECT TOTAL 1169
Table 1: Cost of use for SNS at Leighton Buzzard for EFCC
Commercially Sensitive Information
EFCC Battery Storage Investigation
Report November 2015
Chapter 5 Commercial Analysis of shortlisted storage units
S&C Electric and Younicos contractor costs are based on (EUR) 950 per day for a development
engineer to (EUR) 1200 per day for a senior technical consultant. From previous experience of
making changes to th ineer and senior
technical consultants
Extra contractor costs
category.
Operational T IS Architectur RTU / ENMA
systems)
UKPN are still to nego
their estimated budge
UKPN is currently und
part of existing comm
estimated provision o
(6MW low and 6MW h
The contingency estim
for uncertainty in carr
for any additional exp
requirements during t
5.2 Cost summa
Additi
Alstom
engag
PROJ
Table
eir control systems, UKPN agreed both development eng
from both companies may be required.
covering the following areas have been factored in at £1000 per day for each
elecoms resource (to cover any design or mods to communications systems)al resource (to cover any design or mods to existing system architectures)C integration technical resource (to cover any design or mods to SCADA
tiate warranties beyond the completion of the SNS project, but have confirmed
t of 1% of capex based on typical rates for other assets.
Commercially Sensitive Information
ertaking compliance tests to provide frequency response to National Grid as
ercial services products. Bilaterial negotiations are ongoing, though an
f operation and time of use has been calculated; £20MWh for 12MW response
igh) for approximately 10% of the year.
ate is based on half of total engineering design contractor costs (i.e. to account
ying out the modifications as it is unclear the extent required). It will also cater
enditure prior to installation of control equipment, or additional commissioning
he frequency response trial period.
ry for Rise Carr (Darlington)
Cost (£k)
Commercially Sensitive Information
Page 19
onal project management 150
additional project management cost including
ement with new project partner100
ECT TOTAL 444
2: Cost of use for Rise Carr at Darlington for EFCC
Commercially Sensitive Information
EFCC Battery Storage Investigation
Report November 2015
Chapter 5 Commercial Analysis of shortlisted storage units
The category for “Other Operation & Maintenance costs” includes maintenance, communications,
engineering support and future provision for battery cell replacement. The NPG engineering resource
includes installation and control engineering, commissioning and some project management costs.
Similarly, contract engineering has been estimated for design, commissioning and project
management activities.
NPG has provided a full breakdown of these costs with estimated time to be taken for each activity as
well as daily rates for each resource; this is shown in Appendix C.
It is to be noted that the base cost as provided by NPG is a budget estimate for the use of Rise Carrwithin the EFCC project.
5.3 Cost summary for Willenhall
Cost (£k)
Additi
Alstom
engag
PROJ
As mentioned earlieresulting in a lowerrevenue associated
Page 20
onal project management 150
additional project management cost including
ement with new project partner100
ECT TOTAL 483
Table 3: Cost of use for Willenhall for EFCC
r in the chapter, the battery unit at Willenhall is for research purposes only,potential cost of use, and therefore does not require compensation for lostwith commercial services provision.
Commercially Sensitive Information
Page 21
EFCC Battery Storage Investigation
Report November 2015
Chapter 5 Commercial Analysis of shortlisted storage units
5.4 Cost Summary for Belectric Energy Buffer Unit
Cost (£k)
Site preparation 14
Battery unit plus 1 inverter 520
Second inverter (to provide higher power) 96
Electrical equipment modifications at Rainbows solar PV plant 70
Electrical equipment connection at Redruth 128
IT and communications systems 24
Contingency 186
BASE TOTAL 1100
Additional project management 0
Alstom additional project management cost including
engagement with new project partner0
PROJECT TOTAL 1100
Table 4: Summary of battery storage cost of use within EFCC
As mentioned in Chapter 3 “Evaluation of existing battery storage in the UK” the total cost for the
Belectric solution includes provision to mobilise the battery storage unit at Redruth and Rainbows
Solar Farm. There are no additional project management costs as these have already been
accounted for within the project.
The detailed cost breakdown as provided in the EFCC Full Submission Document is shown in
Appendix D.
5.5 Summary
Table 5 below summarises the capability of each site for rapid frequency response, the total cost of
use for each site, and the viability of inclusion within EFCC project timescales.
Page 22
EFCC Battery Storage Investigation
Report November 2015
Chapter 5 Commercial Analysis of shortlisted storage units
Table 5: Summary of battery storage cost of use within EFCC
Capability for
rapid
frequency
response for
EFCC
Cost of
use (£k)
Inclusion of
compensation
for commercial
services
Availability/
Timescales for
EFCC
Additional
learning for EFCC
(hybrid-
renewable &
storage)
SNS(Leighton Buzzard)
Likely(1)
£1169 Yes Uncertain No
Rise Carr (Darlington) Likely(1)
£444 No Uncertain No
Willenhall Likely(1)
£483 Not Applicable Uncertain No
Belectric Yes £1100(2)
Not applicable Yes Yes
(1) The control system changes and integration into the EFCC control system is the uncertain element at this stage(2) Cost includes site preparation, installation of new battery unit, inverters and relocation of battery system
For the SNS project due to the existing control system configuration, there is uncertainty whether
even after the integration of the Alstom control and monitoring system, the target response for the
project can be realised. It is an ongoing innovation project and as such has its own specific objectives
that must be met. There is a risk to the EFCC project that fast frequency response trials will be
delayed if SNS objectives take priority over the EFCC project.
In the case of Rise Carr, there is uncertainty whether NPG will allow their site to participate in the
EFCC project. There is the possibility of obtaining rapid frequency response, though again, the extent
of control system modifications may negatively impact the EFCC project as it is likely that the site will
have ongoing commercial activities. Furthermore, there may be an additional cost exposure for
compensation for ancillary services. At this stage it is not possible to quantify what the ancillary
service cost may be as commercial contracts are not in place.
Both SNS and Rise Carr sites have lower C-rates (power/capacity ratio), that will not provide the
opportunity to trial low capacity/high-C-rate installations in order to obtain the full potential of rapid
frequency response and hence optimise the future value of rapid frequency response provision.
With respect to Willenhall, it has a more favourable C-rate it is anticipated that the target response to
RoCoF can be achieved. At time of writing, the University of Sheffield is actively seeking research
opportunities. Like the SNS project, it has specific objectives and other projects may be agreed upon
during the determination process that may not align with the EFCC project timescales.
For the Belectric solution, some discussion has taken place within the EFCC project so far, leading to
there being greater clarity regarding the control system interfaces between Belectric and Alstom
which reduces this risk. Moreover, since this would be a new installation the risk for access to carry
out modifications and carry out trials is mitigated.
Page 23
EFCC Battery Storage Investigation
Report November 2015
Chapter 5 Commercial Analysis of shortlisted storage units
The information gathered has shown that currently there is a limited portfolio of energy storage
technologies that are capable of providing fast frequency response. The three existing storage sites
that have been shortlisted all utilise Lithium Ion batteries. Allowing the installation of a lead-acid
battery unit provided by Belectric will provide valuable knowledge and learning from this technology in
the area of fast frequency response. It will also demonstrate to the wider industry that other battery
technologies can be utilised for fast frequency response and potentially other future ancillary services.
Only the installation of a Belectric battery unit will allow the full realisation of combining renewable
generation (solar PV) with battery storage to trial their full potential. The battery unit can also be
relocated to two different locations to provide increased learning of differing site and network
conditions within the EFCC project.
The cost benefit analysis included in the full EFCC project submission showed that under the Gone
Green future energy scenario, by 2020 and with the implementation of the EFCC project, the potential
cost saving to consumers would be approximately £200m per annum. The investigations of existing
battery storage units has shown that the estimated cost of additional learning that can be achieved
through investment in battery storage plus solar PV is in the order of £69k to £693k. Only with this
investment can the full realisation of EFCC objectives be achieved and therefore the full cost savings
passed on to consumers. This is explored further in next chapter.
Page 24
EFCC Battery Storage Investigation
Report November 2015
Chapter 6 Opportunity for combining solar PV and battery storage in EFCC
Chapter 6 Opportunity for combining solar PV and battery storage in EFCCIn the UK, there is ongoing work with innovation projects to allow battery storage resources to be
used for the provision of ancillary services to support the electricity system. This may lead to the
emergence of new commercial frameworks to allow storage to participate within existing commercial
markets.
However, the EFCC project is seeking not only to generate a new rapid frequency response
mechanism from non-conventional resources, but to understand and fully realise their full potential in
providing cost savings over conventional services.
Chapter 2 discussed how significant amounts of solar PV connected to the network is offsetting the
transmission system demand profile, and due to its variable output, makes maintaining the generation
and demand balance (hence frequency) more challenging. Furthermore, solar PV does not provide
natural inertia to the network. Battery storage can be used to alleviate the power imbalance and
provide fast frequency response when required. The EFCC project seeks to realise by demonstration
through the project, the benefit of combining battery storage with solar PV.
6.1 Trials for Solar PV and Battery Storage
The combination of solar PV and battery technologies will provide an opportunity to expand the scope
and therefore the learning outcomes over and above rapid frequency response trials for battery
storage alone. In order to increase the leverage and to reduce cost of frequency control, the battery-
based response shall be supplemented by PV-based response. For overall frequency control the
battery needs to be capable of providing equal response in either direction: positive and negative.
This means, the battery needs to be at a state of charge (SoC) of around 60 % in order for it to have
the capacity to be charged and discharged at equal rate and for equal time. Locally combining the
battery with a response provider who might deliver negative response (by power curtailment) allows
the battery to raise its state of charge up to 95% and therefore provide more positive response for a
longer period of time (at the same time neglecting the negative response which is taken over by the
PV power plant). Provided this integration takes place on the same site, communication will be
sufficiently fast and failure rate will be sufficiently low in order to provide response at an acceptable
reliability. A combined system of this kind will significantly increase the value of a battery for the
system operator with negligible addition of cost (cost of curtailed PV energy). The value of this could
be trialled during the project. Hence the following can be undertaken
1. Work out operational scheme for lowering and raising SoC of the battery to comply with the
actual capability of the PV power plant to deliver negative response (corresponding to current
level of irradiation i.e. PV power.
2. Optimise the response distribution between battery and solar PV e.g.
Battery provides 100% of battery positive response, 0% of negative responses from 95%
SoC (State of Charge).
Battery provides 100% of battery positive response, 50% of negative responses from
80% SoC (State of Charge).
The objective is to have an optimal operation scheme minimizing the cost of PV power
curtailment and at the same time maximising the value of the battery as a response provider.
Page 25
EFCC Battery Storage Investigation
Report November 2015
Chapter 6 Opportunity for combining solar PV and battery storage in EFCC
3. Integrating a variable response unit into grid management.
A battery based frequency response unit has an efficiency typically in the range between 80% and
90%. The corresponding losses during battery operation have to be replaced by an external source.
This may well be done by the production of the adjacent PV power plant - especially, if the latter is
currently curtailed due to distribution network limitations.
6.2 Belectric Contribution with solar PV and battery storage
Belectric provides utility-grade PV power plants that enable safe, reliable, and efficient power
generation and proven experience with incorporating PV plants and battery storage for frequency
regulation.
Rainbows Solar Farm 3.8MWp near the village of WIllersey in Gloucester is currently operated by
Belectric. This site (also known as Willersey Solar Farm) has been nominated as a potential site
where the EBU and associated equipment can be installed in order to demonstrate how solar PV and
battery storage can provide additional learning for rapid frequency response in the EFCC project.
Belectric are currently in the process of progressing separate planning applications for solar PV and
battery storage at Redruth. In this respect, it is anticipated a solar PV plant will be constructed in
advance of EFCC trials commencing in 2017. In this respect, the proposed installation at Redruth will
be configured to allow trials for battery only (as previously outlined in the EFCC submission) as well
as battery plus solar PV hybrid. This will increase the potential learning gained of operational regimes
by locating the battery at different locations of the electricity network.
Page 26
EFCC Battery Storage Investigation
Report November 2015
Chapter 7 Cost Benefit Analysis of future roll out of Hybrid Battery
Storage and Solar PV
Chapter 7 Cost Benefit Analysis for future roll out of hybrid battery storage and solar PV
7.1 Cost Benefit Analysis Introduction
When awarding funding for the project, Ofgem included a requirement that the battery storage and
hybrid solar-battery solution of work package 2.4 be examined in more detail prior to the funding for
this element being released. Ofgem‘s project direction included the following condition:
“8. WORK PACKAGE 2.4 - STORAGE
The Funding Licensee must secure consent from the Authority before accessing the funds,
£1,122,820, for work package 2.4. The Funding Licensee must submit an application to the Authority
which presents options for work package 2.4. As part of this application, the Funding Licensee must:
Conduct an investigation into existing battery storage facilities and trials in the UK, considering
both technical and commercial information, to determine if existing facilities and/or trials can be
used for the Project.
The Funding Licensee must also present cost benefit analysis of potential learning from this work
package against the cost to consumers.
The Funding Licensee must present this information in a report to the Authority by 30 June 2015.
Based on the Funding Licensee’s application the Authority will determine whether the funds for work
package 2.4 will be released. If the Authority determines not to release these funds, the funds will be
returned to customers.”
National Grid submitted a storage review report to Ofgem on 30 June 2015 (EFCC Battery Storage
Investigation Report June 2015). Following this further clarification was requested from Ofgem in
particular relating to the cost benefit assessment.
This chapter details and explains the assumptions behind our estimates for the potential savings
attributable to the hybrid solar-battery installation put forward by the EFCC project. A range of
sensitivities have been considered and the resulting market potential could reach £54m-£83m/year by
2020, with estimated consumer savings of £38m-£59m, with a strong likelihood that these figures will
continue to rise to at least 2030.
Page 27
EFCC Battery Storage Investigation
Report November 2015
Chapter 7 Cost Benefit Analysis of future roll out of Hybrid Battery
Storage and Solar PV
7.2 Cost benefit analysis: methodology and results
7.2.1 High-level overview
Figure 3 below shows the stages involved in the cost benefit analysis (CBA) of the hybrid project and
maps out the associated subsections within this chapter. Each box represents a different stage in
which assumptions are made and/or results are calculated. The arrows show the dependencies and
implications of each stage. The boxes in blue are intermediary steps and the two orange boxes are
the final results of the cost benefit analysis. The numbers in the boxes indicate the corresponding
sections of this chapter of the report.
Figure 3: CBA methodology overview
Additional enhancedresponse requirements
(MW)(7.2.2)
Battery availability andexpected market share
(7.2.4)
Battery rolloutprojections (MW/year)
(7.2.5)
Solar deploymentprojections (MW/year)
and solar farm sizes(7.2.6)
Number of solar farmswith a battery
installation (7.2.6)
Consumer savings from hybrid rollout(£m/year)
(7.2.7)
Economic viability assessment(7.2.8)
Cost to consumers ofadditional response
(£m/year),(£m/MW/year) (7.2.3)
Page 28
EFCC Battery Storage Investigation
Report November 2015
Chapter 7 Cost Benefit Analysis of future roll out of Hybrid Battery
Storage and Solar PV
In summary the following questions have been posed and considered:
Based on SOF 2014 what volume (MW) of enhanced frequency response is expected to be
needed?
Based on an approximation of today’s frequency response costs, how much could the annual
additional cost be?
The EFCC project is exploring the potential for wind, CCGT, demand response, solar alone,
battery storage alone, and hybrid solar-battery to provide enhanced services. What proportion
of the future enhanced response requirement could the hybrid solar-battery solution under
investigation in EFCC provide?
o How many hybrid solar-battery installations would be required to achieve this?
o How does this compare with the number of existing and forecast solar farms of
suitable size?
o Is there a viable business case for the battery rollout projections?
What is the potential saving for consumers per annum in 2020 and 2025?
o How does this compare to the £1.1m required to facilitate this part of the EFCC
project?
Throughout the CBA, all costs are given in terms of current prices and exclude the effects of general
inflation.
The following sections explain the calculations and assumptions involved in each of the stages in the
figure above. A table summarising all of the modelling assumptions is contained in Appendix E.
7.2.2 Future additional enhanced response requirements
The main motivation for the EFCC project is the expected growth in the need for the provision of
enhanced frequency response in the near future. This is caused by three main factors;
decreasing system inertia,
decreasing availability of frequency response providers when renewable output is high
an increase in the largest ‘loss’ on the system that the system operator needs to cater for to
maintain system security.1.
As the amount of traditional generation with heavy spinning masses reduces the result is a reduction
in system inertia. This means the system reacts faster to sudden changes in supply and demand and
hence greater levels of response, or faster response, is needed. The projected system inertia level
during the summer under the Gone Green and Slow Progression future energy scenarios is shown in
Figure 4. It shows the system inertia decreasing by approximately 40% over the next 10 years. This
1 The ‘largest loss’ on the system is the largest single generation unit (or interconnector) that could be lost all at once due to afault.
Page 29
EFCC Battery Storage Investigation
Report November 2015
Chapter 7 Cost Benefit Analysis of future roll out of Hybrid Battery
Storage and Solar PV
will have a large impact on the need for enhanced frequency response during this period to ensure
the RoCoF (rate of change of frequency) limits are maintained2.
Figure 4: System inertia under the Gone Green and Slow Progression scenarios in summer
Analysis performed for the 2015 System Operability Framework (SOF) includes studies to determine
the level of enhanced response required to prevent the frequency from deviating outside of
operational limits in the event that the largest generator is lost in a fault. Figure 5 shows the results of
this analysis (the data for all four 2015 FES scenarios are shown in this Figure; Consumer Power
(CP), Gone Green (GG), No Progression (NP) and Slow Progression (SP).
2 National Grid System Operability Framework 2014, 2015. http://www2.nationalgrid.com/UK/Industry-information/Future-of-Energy/System-Operability-Framework/
Page 30
EFCC Battery Storage Investigation
Report November 2015
Chapter 7 Cost Benefit Analysis of future roll out of Hybrid Battery
Storage and Solar PV
Figure 5: Enhanced Frequency Response Requirements during summer periods under each 2015 future energyscenario resulting from frequency response analysis in SOF 2015
Figure 5 indicates that additional enhanced response will be needed after 2020 (or after 2025 under
Slow Progression) when response from existing providers to secure against the frequency deviation
limits becomes insufficient. In addition, from Figure 4, in order to secure against the RoCoF limits the
amount of enhanced frequency response will also need to increase from 2015-2025.
Using the information behind each of Figure 4 and Figure 5 it can be estimated how much enhanced
frequency response will be required to ensure that the system is secured against both the RoCoF and
frequency deviation limits. The response required up until 2025-2030 is driven by the decreasing
system inertia (Figure 4) and the response from 2025-2035 is predominantly driven by factors
contributing to results presented in Figure 5 as explained above.
For this CBA the central scenario is based on the data in National Grid’s 2015 future energy scenario
‘Gone Green’ (referred to as ‘Gone Green’ or ‘GG’) since under this scenario the UK 2020 energy
targets are met. For comparison the analysis has been extend to include the ‘Slow Progression’
scenario to show how results would change if the energy targets are met on a slower timescale. Slow
Progression is similar to Gone Green with the main difference being that the need for enhanced
response is delayed, (largely) due to the assumption that the largest plant in operation is constructed
at a later date.
The results of combining the two drivers of the increasing enhanced frequency response
requirements are presented in Figure 6. The data behind this figure is included in Table 18 in
Appendix I and is used in our assumptions for the battery rollout projections.
Page 31
EFCC Battery Storage Investigation
Report November 2015
Chapter 7 Cost Benefit Analysis of future roll out of Hybrid Battery
Storage and Solar PV
Figure 6: Additional enhanced frequency response requirements under our two scenarios (from all providers)
In this section estimates have been established for the amount of additional enhanced frequency
response required in each year from 2015-2035. The next section describes how we have estimated
the potential increased costs to consumers from procuring this additional response.
7.2.3 Future additional costs to consumers
Detailed modelling was performed as part of the original EFCC bid to determine the cost to
consumers of additional frequency response requirements in 2020. This determined that to procure
enhanced frequency response beyond current requirements, the cost to consumers could be in the
range of 250-300MW (estimated to be needed from 2020) the resulting cost to consumers will be
approximately £250m-£300m per year. Using these results from the detailed assessment it is possible
to extrapolate to determine the cost to consumers of procuring additional enhanced frequency
response in other years.
It was established that the EFCC project had the potential to reduce these costs by approximately
£150m-£200m per year, and that an estimated 250-300MW of enhanced response would be required
to achieve this. Using the results from the detailed assessment an extrapolation has been done to
determine the cost to consumers of procuring additional response without the success of the EFCC
project in future years.
In this CBA two different possible relationships between future costs and the additional enhanced
frequency response requirements have been modelled. As a means of sensitivity analysis; a linear
dependency (to model a situation where supply increases at no extra costs for each additional MW of
response required) and a quadratic dependency (where the cost of additional supply increases
Page 32
EFCC Battery Storage Investigation
Report November 2015
Chapter 7 Cost Benefit Analysis of future roll out of Hybrid Battery
Storage and Solar PV
disproportionately for each additional MW of response required) are chosen. Figure 18 in Appendix F
illustrates these two relationships. In the near future this relationship makes a very small difference to
the potential savings for consumers, but this difference becomes significant in the medium to long-
term future. Therefore the two modelling scenarios Gone Green (GG) and Slow Progression (SP) are
expanded to GGa, GGb, SPa and SPb, where ‘a’ refers to the linear price case and ‘b’ refers to the
quadratic price case. The results are shown in Figure 7 and the data behind this figure is provided in
Table 18 of Appendix I.
Figure 7: Cost to consumers in lieu of EFCC of procuring additional response in the Gone Green and SlowProgression scenarios and under the two cost-requirement dependency cases; linear (a – dashed line) and
quadratic (b – solid line).
It should be noted that the linear case is considered to be a lower bound since increasing response
requirements are likely to lead to an increase in cost per MW of response as the service becomes
more valuable to the system operator. The GG and SP scenarios with the same cost dependency
assumptions arrive at similar costs in each case but with a delay of approximately five years for the
Slow Progression scenario. It should also be noted that although there are large differences between
the two ‘a’ and ‘b’ options in the long-term, our CBA focuses predominantly on the 2018-2025 window.
The original EFCC bid considers only the potential savings in 2020. The more detailed analysis
presented here illustrates how any savings in 2020 will only be a fraction of the potential in future
years. Therefore the figures quoted for 2020 should be understood to be very conservative regarding
the potential benefits from the EFCC project. Although uncertainty surrounding assumptions
increases in later years there is a clear upward trend for the value of the project.
Having determined the future additional costs to the consumer of procuring frequency response in the
absence of the EFCC project, the potential for battery-solar hybrid projects to provide enhanced
frequency response in terms of availability and participation in the market is considered in the
following section.
Page 33
EFCC Battery Storage Investigation
Report November 2015
Chapter 7 Cost Benefit Analysis of future roll out of Hybrid Battery
Storage and Solar PV
7.2.4 Battery availability and service provision assumptions
In the following analysis all batteries are considered to be those located at solar farms in the hybrid
arrangement proposed by the EFCC project. For this CBA it is assumed that a battery used for
enhanced frequency response will be available approximately 95% of the time for providing the
service. Availability is one aspect of enhanced frequency response provision from batteries that EFCC
intends to explore. Since the proposed battery will be located at a solar farm with a higher rated
capacity than the battery, one operational model would be that solar power is used to charge the
battery after use, and during the day, to leave it charged for the overnight period if inertia is expected
to be low (such as the prediction of high winds).
During periods when inertia is high and it is not needed for frequency response the battery can be
operated for other purposes and access other revenue streams. No assumptions have been made
about the revenue available to a battery from other services and markets, but it is likely that any
battery installed would be operated for multiple purposes. Certainly the prevention of solar curtailment
will be a natural choice for the battery.
Of all of the additional enhanced frequency response required in future, the proportion that batteries
could provide will depend on the number of batteries installed in GB, the cost-competitiveness of
other potential providers, and the technical capabilities of batteries compared to other providers. For
this CBA a range of 30%-45% is used for the contribution of batteries to the provision of additional
enhanced frequency response from 2020 onwards.
Current market intelligence for an enhanced response service is showing battery storage as playing a
significant role amongst other service providers (i.e. greater than 80%). However, this is based on the
existing industry perception of the value of frequency response provision within business as usual
services. The EFCC project is trialling other technologies for enhanced frequency response that
currently don’t provide these services to National Grid (e.g. wind, solar) in addition to CCGT and
demand side response. In so doing, it is anticipated that the demonstration of the various technology
capabilities as well as the development of a supporting commercial service (Work Package 6), will
bring more providers into the market. As these aspects are being explored within the EFCC project,
any estimate made now of the market share attributable to batteries is very subjective but will become
more evident as the project develops.
In the figures that follow a central value of 37.5% ‘market share’ for the batteries is used, with error
bars representing the effects of considering the whole 30%-45% range.
Having established battery participation assumptions regarding enhanced frequency response
provision, the next section determines the required rollout of batteries needed to meet the service
provision levels required.
Page 34
EFCC Battery Storage Investigation
Report November 2015
Chapter 7 Cost Benefit Analysis of future roll out of Hybrid Battery
Storage and Solar PV
7.2.5 Battery rollout projections
Using the assumptions set out in the previous section regarding battery availability and market share,
the projected rollout of batteries in solar farms under our Gone Green and Slow Progression
scenarios can be established. Starting with the total additional enhanced frequency response
requirements for each year, this is multiplied by the percentage of the provision estimated from the
batteries (30%-45% range) and divided by 95% for availability. The projected number of batteries
deployed in 2019 has been reduced to allow for a small delay in installation pick-up following the
completion of EFCC.
The potential savings from the EFCC project used in the CBA for the original bid document were
based on the forecasts for the single year 2020 without providing additional details for later dates.
Here, the analysis continues the rollout projections beyond these years to give an indication of what
could be possible, acknowledging the increasing uncertainty as we go forward in time. Importantly, we
do not require these projections beyond 2020 to meet the savings targets. The data behind this figure
is provided in Table 18 of Appendix I.
Figure 8: Battery rollout projections. Error bars show the difference when market share changes to 30% (lower)and 45% (upper) from the central 37.5% value.
The rollout of batteries to provide enhanced frequency response requires a corresponding level of
solar farm participation. In the next section estimates for the requirements for solar farms to adopt the
hybrid battery model are considered along with the feasibility of such participation.
Page 35
EFCC Battery Storage Investigation
Report November 2015
Chapter 7 Cost Benefit Analysis of future roll out of Hybrid Battery
Storage and Solar PV
7.2.6 Solar deployment and battery adoption projections
Having established the rollout projections for batteries under different sensitivity cases for each
scenario consideration is now given to the projected deployment of solar PV farms of sufficient size to
incorporate a 1MW or greater battery. This will allow us to determine the relative levels of installed
solar PV and batteries, along with the number of solar farms that are expected to adopt a battery for
enhanced frequency response.
In the first stage of this assessment focus is given to the potential rollout of hybrid solar-battery
solutions based on MW capacity. In the second stage examination focus is given to how many solar-
hybrid installations could be required to achieve this capacity.
National Grid’s 2015 FES includes projections for the deployment of solar farms larger than 1MW
from 2015 to 2035. The latest information obtained detailing the sizes of solar farms both existing and
in all stages of development indicates that by 2018 approximately 77% of solar farms will be larger
than 4MW3. Figure 9 shows 77% of the projected levels of installed solar capacity under the Gone
Green and Slow Progression scenarios which we assume is the amount of installed capacity of solar
PV that could be in farms large enough to adopt a battery.
Taking the 4MW as an assumed minimum size of solar plant (because the EFCC project proposes to
trial a 1MW battery at a 3.8MW solar farm) and assuming that batteries need to be at least 1MW in
size, we consider ‘eligible’ farms for batteries to be at least 4MW.
Figure 9: Solar (solid line) and battery (dashed line) installation projections alongside potential for batteryinstallations (dash-dot line). Potential battery installations calculated as 25% of solar installed capacity (greater
than 4MW).
3Solar Deal Tracker, IHS 2015.
Page 36
EFCC Battery Storage Investigation
Report November 2015
Chapter 7 Cost Benefit Analysis of future roll out of Hybrid Battery
Storage and Solar PV
It may prove to be economically attractive for smaller solar installations to invest and participate in the
new ancillary service(s) that EFCC is seeking to trial. The cost of secure communication infrastructure
and complexity of instruction and monitoring will probably be among the limiting factors. Conversely,
larger solar farms could install larger batteries. The viability of the battery size to solar farm ratio is
one aspect of the hybrid solution the EFCC project proposes to explore.
The dashed lines in Figure 9 show the deployment of batteries under the fastest/highest and
slowest/lowest scenarios (Gone Green with a 45% market share and Slow Progression with a 30%
market share, respectively) that have been assumed for this CBA. For reference the estimated full
potential level of ‘eligible’ installed solar capacity (orange and yellow dash-dot lines) has been
included, which clearly illustrates that the assumptions in this CBA for hybrid solar-battery rollout
require low levels of participation from solar farms, with potential for much greater rollout, and
therefore value, from this aspect of the EFCC project.
Based on the latest data available for the sizes of solar farm it is possible to estimate how many solar
farms would need to adopt a battery in order to meet the capacity-based battery rollout projections in
each scenario. We assume that batteries will be installed at farms larger than 4MW and that the
battery size will be approximately one quarter of the rated ac power capacity of the solar farm. We
also assume that the number of participating solar farms in each size range is proportional to the
number of solar farms in the size range. More information on the assumptions made for these
calculations is given in Appendix G.
Figure 10 shows the approximate number of solar farms expected to adopt a battery under each
scenario. If more of the larger solar farms install batteries of approximately ¼ of the solar installed
capacity or larger, then fewer farms would need to adopt a battery to reach the projected rollouts
assumed. Since it is probable that larger solar farms are more likely to install batteries than smaller
farms due to economies of scale and greater potential of curtailment, our estimates are at the
conservative end of the spectrum (likely that fewer solar farms will need to participate to hit projected
targets).
Figure 10: Number of participating solar farms under each scenario
Page 37
EFCC Battery Storage Investigation
Report November 2015
Chapter 7 Cost Benefit Analysis of future roll out of Hybrid Battery
Storage and Solar PV
We estimate that the number of solar farms larger than 4MW will grow from approximately 500 to 800
farms between 2019 and 20354. The low levels of battery rollout required gives confidence that our
battery installation projections are feasible and that participation from a conservatively low proportion
of the solar farms5
would achieve the savings described later in this CBA.
Having established the required battery rollout and solar participation, in the next section the market
potential for enhanced frequency response is considered, and estimates provided for the potential
consumer savings from the EFCC project.
7.2.7 Market potential for the hybrid project and possible consumer savings
The additional costs of procuring additional frequency response in future have been discussed in
section 7.2.3. These costs represent the market potential for a new enhanced frequency response
service. Having determined the future costs from extrapolation of the 2020 modelling data these have
been divided by the MW required each year to obtain the extrapolated cost per MW of response out to
2035. Multiplying by the response required from batteries in each year, which takes market share
assumptions into account, it is possible to obtain the maximum that a purely economically driven
consumer would be willing to pay for the enhanced response from batteries. This is the market
potential for the service.
Figure 11 shows the results for the two Gone Green scenarios. This clearly shows that there is large
potential for savings beyond 2020, which will depend largely on how the value of enhanced frequency
response changes and what percent of the service is provided by batteries (represented by the error
bars). As stated previously, the estimated market potential in 2020 has very conservatively ignored
the increasing trend in potential savings.
4Based on an approximate ratio of installed solar capacity in farms greater than 4MW to number of solar farms of
10:1 (Solar Deal Tracker, IHS 2015)5
Approximately 10% of solar farms in 2020 would be participating under Gone Green, rising to around 20%participation 2025 assuming a ratio of 10MW installed capacity to 1 farm
Page 38
EFCC Battery Storage Investigation
Report November 2015
Chapter 7 Cost Benefit Analysis of future roll out of Hybrid Battery
Storage and Solar PV
Figure 11: Market potential for batteries under GGa and GGb, with error bars showing the effects of considering arange for the market share; 30-45% around the central value of 37.5%
The equivalent results under our Slow Progression scenarios are shown in Figure 12. Although it
takes longer for the savings to be realised, ultimately the results are very similar to the Gone Green
scenarios. This gives us confidence in the long-term value of the EFCC project.
Figure 12: Market potential for batteries under SPa and SPb
Page 39
EFCC Battery Storage Investigation
Report November 2015
Chapter 7 Cost Benefit Analysis of future roll out of Hybrid Battery
Storage and Solar PV
The market potential for batteries in 2020, 2025 and 2030 are shown in closer detail under each
scenario in the following figures.
Figure 13: Market Potential in 2020 (£m/year)
The market potential for batteries under Gone Green in 2020 is in the range of approximately £55m-
£80m.
Figure 14: Market Potential in 2025
In 2025 under Gone Green the market potential has increased significantly and shows a much larger
spread due to the uncertainties in our assumptions (£150m/year – £440m/year). The delay under
Slow Progression is marked but still covers the £70m/year - £125m/year range.
Page 40
EFCC Battery Storage Investigation
Report November 2015
Chapter 7 Cost Benefit Analysis of future roll out of Hybrid Battery
Storage and Solar PV
Figure 15: Market Potential in 2030
Naturally by 2030 a wide spread of market potential across the four scenarios is shown including
sensitivity analysis (£155m/year - £460m/year). The assumptions surrounding the value of enhanced
frequency response play a larger role as seen from the difference between the ‘a’ and ‘b’ (linear and
quadratic consumer cost savings) scenarios. Even under SPa (Slow Progression, linear cost saving),
the most conservative scenario in terms of market potential for hybrid solar-battery we see levels of
approximately £150m/year by 2030.
The potential savings for consumers are bounded above by the market potential. This is the maximum
amount that consumers would be prepared to pay for enhanced response because any higher and
the alternative existing service providers would be cheaper. Up until this point no assumptions have
been about how much batteries would be paid for providing enhanced frequency response. To
propose a £/MWh value for the service would presuppose the result of a tendering process for a
service that will be developed as part of the EFCC project. However, in order to get an estimate for
the potential savings to the consumer of the project, we have chosen to assume a value for the price
per MWh of enhanced frequency response availability, to show the impact on consumer savings.
These payments to batteries are subtracted for the response service from the market potential to
estimate the potential savings for consumers under these assumptions. The results are highly
dependent on the number of players in the market, the costs of batteries, and the hours of the year
that we contract the service for, among other variables. Operation cost and service contract provision
will be investigated as part of the EFCC project.
For this CBA it is assumed that the number of hours in the year when the enhanced frequency
response service will be tendered for will be approximately the same as the number of hours in the
year when the rate of change of frequency (RoCoF) is greater than 0.125Hz/s. This was calculated as
a percentage of the year as part of the modelling for the 2015 System Operability Framework. Further
details are given in Appendix H. For each year we can therefore determine the number of hours when
the batteries will be contracted, with the MW rating already determined in section 7.2.5. An availability
payment of £XX/MW/h is assumed for the enhanced frequency response6
in all years. This value has
been used as it represents an approximate cost National Grid has already discussed with response
6This value is highly subjective and should not be taken as representative of the price that National Grid expects
for tenders for this service.
Page 41
EFCC Battery Storage Investigation
Report November 2015
Chapter 7 Cost Benefit Analysis of future roll out of Hybrid Battery
Storage and Solar PV
providers for contracting static frequency response. It can be argued that the availability payment
could be higher for future low inertia scenarios as the service becomes more valuable to maintain
system stability. The potential payment to batteries and other service providers being trialled will be
explored in the development of the new commercial service as part of the EFCC project. In addition,
future enhanced frequency response providers are expected to be called upon to provide frequency
response very few times over the course of the year; hence utilisation payments have been ignored in
the analysis.
The figures below show a comparison between the market potential and savings to consumers in
2020 and 2025 under our two scenarios. The results are shown as a range across all sensitivities
within each of the Gone Green and Slow Progression scenarios (a and b for the three market share
sensitivities).
Figure 16: Market potential and one estimate for consumer savings under Gone Green in 2020 and 2025
Page 42
EFCC Battery Storage Investigation
Report November 2015
Chapter 7 Cost Benefit Analysis of future roll out of Hybrid Battery
Storage and Solar PV
Figure 17: Market potential and one estimate for consumer savings under Slow Progression in 2020 and 2025
These figures show that in both scenarios, by 2020 for Gone Green, (closer to 2025 for Slow
Progression); the potential savings to the consumer from the EFCC project are far higher than the
funds requested (£1,122,820). The savings presented are savings per year, expected to increase
year on year at least towards 2030. As the price of batteries reduces and more players enter the
market the cost to consumers of procuring the response will decrease. The importance of the EFCC
project is to determine the optimal commercial framework to allow full market participation and to
understand the technical capabilities of a range of potentially viable technologies to ensure service
reliability and optimal contracting.
Having shown the economic viability of the EFCC project under a range of assumptions, the final
stage in our assessment is to consider the economic viability of our battery-solar hybrid rollout.
7.2.8 Economic viability considerations
In this section the validity of battery rollout projections is outlined by examining the economic
feasibility of a battery built to provide enhanced frequency response is considered. The approach is to
compare the net present value of the revenue for a battery over its lifetime with the estimated net
present value of the lifetime costs. Under the assumptions outlined, a battery built in 2019 that
becomes fully operational by 2020 could expect a return on investment of approximately 17%. In
future years the revenue per MW of installed capacity will increase and the cost of batteries is
expected to decrease, hence a slow initial rollout that grows over time has a strong chance of
economic viability. The methods and results are discussed below.
Page 43
EFCC Battery Storage Investigation
Report November 2015
Chapter 7 Cost Benefit Analysis of future roll out of Hybrid Battery
Storage and Solar PV
Table 6 below contains the assumptions in the cost benefit analysis for a 1MW battery under the
Gone Green and Slow Progression scenarios.
Table 6: Battery economic viability assessment assumptions
Assumption Justification and comments Potential learning from EFCC
Battery lifespan 10 yearsLiterature typically quotes 8-15 yearsdepending on usage
Understanding of how usagefor enhanced frequencyresponse affects lifespan anddegradation
Battery CAPEX £1,122,820
Cost of the battery-solar hybrid EFCCproject. Likely to decrease as the costof batteries decreases but we don’tassume this
Battery OPEX £10,000/yr
Literature quotes fixed OPEX forLithium-ion batteries used forfrequency response as $6500-$9200/MW-yr, we round up to beconservative
7
Clear learning outcome fromthe project
WACC 5.3%Upper limit of the WACC quoted forthe cap and floor to be applied to theUK interconnector regime
8
Discount rate 3.5% Standard UK discount rate n/a
Service payment £XX/MWhApproximate current cost of existingfrequency response
Commercial arrangements tobe fully explored
Service availabilityAccording toRoCoFrequirements
See Appendix H for full detailsAvailability and operationalmodels will be investigated
The data behind the economic viability assessment for a 1MW battery under the Gone Green and
Slow Progression scenarios are presented in Table 7.
7Table B-28 in DOE/EPRI 2013 Electricity Storage Handbook in Collaboration with NRECA
8OFGEM Financeability study on the development of a regulatory regime for interconnector investment based on
a cap and floor approach, 2013. The WACC values are quoted as 4.3% (floor), 4.7% (midpoint) and 5.3% (cap)and we chose the cap value since it is the most conservative of the three values.
Page 44
EFCC Battery Storage Investigation
Report November 2015
Chapter 7 Cost Benefit Analysis of future roll out of Hybrid Battery
Storage and Solar PV
Table 7: Economic viability assessment for a 1MW battery built in 2019, beginning operation in 2020 under Gone
Green and Slow Progression
Year CAPEX (£) OPEX (£)Revenue (£/MW-yr)
Gone Green Slow Progression
2019 1,122,820 0 02020 10,000 181770 1664402021 10,000 188778 1703822022 10,000 195786 1743242023 10,000 202794 1782662024 10,000 209802 1822082025 10,000 216810 1861502026 10,000 216810 1861502027 10,000 216810 1938152028 10,000 216810 2014802029 10,000 216810 209145
Total Net PresentValue:
1,230,2591,436,425
1,285,598
Benefits – Costs: 206,167 55,340Return on
Investment (%):16.8% 4.5%
The business case for batteries in 2020 is far stronger under Gone Green than under Slow
Progression, which supports our rollout projections for Gone Green being over twice as high in the
first few years following the EFCC project compared with under Slow Progression. The number of
batteries installed in 2020 under Gone Green is reached under Slow Progression by 2025. The
equivalent results as above for a battery constructed by 2025 under Slow Progression suggest that
the expected return on investment over the battery lifetime is approximately 21%. This supports our
battery rollout projections for Slow Progression which reach similar levels to the 2020 Gone Green
scenarios by 2025.
Assuming a battery is built in 2024 for operation in 2025 and using the same methodology already
presented, under Gone Green there is a potential return on investment of 117% which is extremely
high. This suggests that over time under Gone Green the price for enhanced frequency response
could reduce significantly from our estimated £XX/MWh, inducing greater savings for consumers.
In addition to the revenue available to batteries for enhanced frequency response other revenue
streams may be available, particularly in the short-term when it is not expected that enhanced
frequency response will be contracted for every hour of the year. Additional balancing services,
energy market participation and reducing the effects of solar curtailment (if brought in) are all options
which would improve the business case for a battery. Battery costs are expected to decrease over the
coming years which in further increases the economic viability of battery-solar hybrid projects.
Page 45
EFCC Battery Storage Investigation
Report November 2015
Chapter 7 Cost Benefit Analysis of future roll out of Hybrid Battery
Storage and Solar PV
These results show that there is sufficient market potential to justify the predicted deployment rate of
our battery rollout projections. This section has assessed the financial costs, benefits and economic
viability of our assumptions. The next section considers the additional learnings from the EFCC
project.
7.3 Additional potential benefits
The response capabilities of new technologies are not currently being fully realised and trials within
the EFCC project will demonstrate how battery storage and solar can be coordinated to provide an
optimised response across a range of resource providers.
Specifically for a hybrid battery storage and solar PV installation, there is potential to optimise the
operational flexibility (e.g. battery storage of otherwise curtailed solar energy or utilisation of batteries
for frequency response overnight typically when system inertia is reduced). In addition, negative
frequency response (curtailment) can be obtained from solar while the maximum positive frequency
response is obtained from the battery. Trials undertaken within the EFCC project will inform the
development of prospective operating models and provide a better understanding of battery
availabilities. The development of specific performance requirements will be investigated in order to
define the roll out of an Enhanced Frequency Control Capability as a new balancing service, taking
into account specific challenges of incorporating batteries for network regulation (e.g. various States
of Charge).
The development of a commercial policy is a key element within the EFCC project. In parallel with the
technology trials, a fuller assessment of the potential for future frequency response service provision
from batteries and solar. This holistic assessment will provide insight into the market share of
response that the EFCC service providers could contribute towards. It will also facilitate industry
acceptance in order to enable realisation of the potential consumer cost savings at the end of the
project.
7.4 Summary and Conclusions
The hybrid battery-solar project forms an important part of the EFCC project. It will allow us to
understand how battery storage and solar farms can be coordinated to provide optimised enhanced
frequency response. The EFCC project will establish reliable knowledge of the technical capabilities
and limitations of this technology and of optimal approaches for utilisation. Given the increasing
challenges and associated costs of procuring frequency response for system stability and security, it
is important that new and reliable providers of enhanced frequency response are identified to
minimise the costs to consumers of a low carbon future.
This cost benefit analysis has set out the potential savings to consumers following the successful
completion of the EFCC project, specifically from the hybrid solar-battery possibility, and the
subsequent deployment of batteries at solar farms.
Page 46
EFCC Battery Storage Investigation
Report November 2015
Chapter 7 Cost Benefit Analysis of future roll out of Hybrid Battery
Storage and Solar PV
At each stage the rationale behind each assumption made has been provided together with an
assessment of how realistic the assumption is and four scenarios have been considered to test the
sensitivity of the assessment to key assumptions.
A thorough assessment of future additional enhanced response requirements has been carried
out as part of the System Operability Framework 2015 assessments: ~250MW by 2020
ultimately rising to ~800MW
Calculation of the resulting additional costs to consumers in lieu of the EFCC project has been
explained in detail with two potential cases over time: £150-£200m pa by 2020 (nominal)
potentially rising to £0.5bn to £1bn
Assumptions have been detailed for battery availability (95%) and share of the enhanced
frequency response market (30%-45%), and the methodology for battery rollout projections
explained in full
Using the National Grid 2015 FES we have assessed how many of the projected solar farms over
the next 20 years would need to adopt a battery to meet our battery rollout projections and found
it to be a low number compared to the amount of installed solar farms of sufficient size: ~10% of
solar farms >4MW
Savings have been compared with the rollout cost of the batteries and have shown that a large
margin exists, which implies that the battery rollout projections are likely to be economically
viable: 16.8% for batteries operational by 2020 under Gone Green.
The potential savings to consumers under a range of conditions has been explored and found to be
far higher than the £1.1m investment required for this part of the EFCC project.
Based on the assumption necessarily made to establish potential future rollout costs and savings the
market potential could reach £54m-£83m/year by 2020 (with estimated consumer savings of £38m-
£59m) and far more in years beyond.
Page 47
EFCC Battery Storage Investigation
Report November 2015
Chapter 8 Revised Project Schedule for Work Package 2.4 (Battery Storage)
Chapter 8 Revised Project Schedule for Work Package 2.4 (Battery Storage)
The original EFCC project schedule for this work package made an allowance for an investment
decision point from the Authority by August 2015 with some contingency provision built in to cater for
equipment lead times and planning activities. In practice, the time in completing a detailed cost benefit
analysis and subsequent discussion with the Authority have been sufficient to materially change the
original project schedule.
Belectric and National Grid have reassessed the work activities for battery storage and propose the
following changes to Work Package 2.4.
Work
Package
Description Existing
Start Date
Existing
End Date
Proposed
Start Date
Proposed
End Date
2.4.1 Site preparation Apr-16 Sep-16 May-16 Oct-16
2.4.2 Install equipment Jul-16 Dec-16 Aug-16 Jan-17
2.4.3 Establish and modify
relevant IT systems
Jan-16 Mar-16 Feb-16 Apr-16
2.4.4 Establish and test
communication
Oct-16 Dec-16 Nov-16 Jan-17
2.4.5 Test and demonstrate
response capability
Jan-17 Sep-17 Feb-17 Nov-17
Table 8: Revised timescales for WP2.4 activities
As a consequence of these changes to activity dates, there would be an impact on the Successful
Delivery Reward Criteria (SDRC) detailed in the Project Direction. A new date for this work is
proposed in Table 9 below.
Work Package
SDRC
Description Existing SDRC
Date
Proposed SDRC
Date
2.4.5 Complete demonstration of storage
response to frequency events and their
capability to respond to proportion to rate
of change of frequency
1st
October 2017 1st
December 2017
Table 9: Revised SDRC for WP2.4.5
If investment in the Belectric battery storage unit is approved by the Authority for the project to
progress with a hybrid solar PV and battery storage trial, then National Grid will formally request an
amendment to the Project Direction to change this SDRC.
Page 48
EFCC Battery Storage Investigation
Report November 2015
Chapter 9 Legacy options for Belectric Storage Unit
Chapter 9 Legacy options for Belectric Battery Storage Unit
Investment in the battery storage unit provided by Belectric will for the first time demonstrate
frequency response from lead-acid technology in GB. As outlined in Chapter 4, this unit is
containerised and will be relocated during the project to enable trials to take place in differing parts of
the transmission network
However, as the battery storage unit would be funded under the Network Innovation Competition
(NIC) mechanism, National Grid will make the unit available to third parties to deliver knowledge of
the capability of the system. Due to the containerised solution, this offers a wide range of future
possibilities for use and research opportunities for the battery unit at the end of the EFCC project.
Below are the considerations that will be taken into account towards the end of the project when
reviewing the ongoing usage of the battery with regards to the potential consumer benefits
Cost of operating and maintaining the battery in order to retain it for use by other innovation
projects
Potential use either by National Grid or other Network Operators to carry out further trials or
projects
If no interest is expressed from the regulated community, the possibility of other parties to buy
the unit in the open market.
As the project will close in March 2018, at this stage it is not possible to fully evaluate these options
for the battery that could arise. Each possibility will be reviewed and assessed by the Project Steering
Committee and recommendations made via the project governance structure for final approval by
National Grid’s System Operator (SO) Innovation Board. The EFCC Project Hierarchy is shown in
Appendix J
Page 49
EFCC Battery Storage Investigation
Report November 2015
Chapter 10 Recommendations
Chapter 10 Recommendations
This report proposes that the Belectric battery storage unit be included within the EFCC project. It is
the only option that is known to be capable of delivering the outcomes of rapid frequency response for
the project, while mitigating the uncertainty of incurring further costs without risking delays to project
timescales.
The Belectric battery will be the first based on flooded lead-acid technology (which is significantly
cheaper than lithium-ion) will be used as a standalone frequency response unit in GB. This will give a
comparison of investment cost, operational cost, lifetime and reliability between the two mentioned
technologies. Furthermore, there is only one large-scale lead acid battery under construction on the
island system of the Shetlands (1MW, 3MWh). This battery uses Valve Regulated Lead-Acid (VRLA)
cells, limiting it to low C-rates (low power at a given installed capacity due to gel filled cells). VRLA
batteries do not compare well with flooded lead acid batteries, since they deliver largely smaller C-
rates than flooded batteries that minimises their effectiveness for providing rapid frequency response.
Additionally they have a shorter lifespan (1500 cycles).
The combination of solar PV and battery storage within EFCC will generate learning on the benefit of
linking technologies and how they can play a role in solving future network operability challenges. Any
technical limitations will only be known if site trials to combine technologies are carried out. An
important detail for Transmission Network Owners is the limited capacity of a battery has to be taken
into account, whenever centralised control schemes and commercial models are developed. Currently
a number of international approaches concentrate on the pooling of units with limited capacity (e.g.
battery, flywheels, etc...) and with unlimited capacity (e.g. gas turbines, coal fired power plants).
Detailed cost benefit analysis for a hybrid solar and battery storage solution has highlighted the
potential savings to consumers following the successful completion of the EFCC project, including
potential deployment of batteries at solar farms. The potential savings to consumers under a range of
scenarios has shown to substantially exceed the £1.1m investment requested for the Belectric battery
unit.
Given the CBA assumptions, on comparing savings with the rollout cost of the batteries, battery
rollout projections are likely to be economically viable; 16.8% for batteries operational by 2020 under
Gone Green. The market potential could reach £54m-£83m/year by 2020 (with estimated consumer
savings of £38m-£59m) and could exceed this in future years.
With the Belectric battery storage and solar PV solution, consumers will benefit from the full
optimisation of EFCC outcomes from a realistic response portfolio of a wide range of service
providers and industry acceptance based on realistic data. As highlighted in the EFFC Full
Submission, this will enable the realisation of total potential cost saving to consumers of
approximately £200m per annum.
Page 50
EFCC Battery Storage Investigation
Report November 2015
Appendix A Questionnaire sent to DNOs
Appendix A Questionnaire sent to DNOsOn sending out an email enquiry to DNOs about their storage sites, a request was made to complete
the questionnaire below.
What Battery technologies were used in the individual projects (Li-Ion, NAS, Lead-Acid,…)?
- What ratio Capacity vs. Power is achieved?
- Are these units able to also deliver reactive power i.e. voltage control?
How is the battery operated - locally controlled, or distant control?
- How fast is the communication in case of distant control? Is it deterministic?
- What is measured in case of local control?
By what scheme does is currently operate?
- Frequency response?
- Load shifting?
- Emulation of rotating generators i.e. virtual inertia?
- RoCoF control?
What speed of response can they realize?
What kinds of inverters were used?
- What kind of control do they have implemented (current control or voltage control?)
Are they black start capable?
Are they containerized or require a dedicated building?
Where are the units situated? e.g. isolated, in a substation,…?
- Is there any storage system which is situated inside a PV power plant (and connected at the
same point of interconnection?)
Page 51
EFCC Battery Storage Investigation
Report November 2015
Appendix B Existing battery storage site evaluations
Appendix B Existing battery storage site evaluations
Table 10 below shows the compiled data initially received in response to the questionnaire, from UK
Power Networks (UKPN), Northern Power Grid (NPG) and Western Power Distribution (WPD) for
those sites eventually shortlisted.
Table 10: Questionnaire responses from UKPN, NPG and WPD for shortlisted sites
Project Name
Smarter Network
Storage
Leighton Buzzard
CLNR
Rise Carr/DarlingtonWillenhall
Distribution Network Operator UK Power Networks Northern Power Grid Western Power Distribution
Capacity 10MWh Capacity 500MWh Capacity 1MWh
Power 6 MW 2,5 MW 2 MW
Battery Technology Lithium Ion Lithium Ion Lithium Ion
Reactive Power Yes Yes Yes
Operated (Locally/Remote) Remote Local and Remote Local and Remote
Type/speed of remote communicationsRemote control yet to be fully
tested
Fast response time is (under 100
mill iseconds)Fibre
Local control (measures)
Network configuration, voltage,
loading, frequency amongst
others
Voltage, current, reactive powerVT, primary substation demand and
frequency control
Current Operation e.g Frequency Regulation,
Primary Reserve, Peak Shaving, Voltage
Regulation, Peak load Management
Static and dynamic frequency
response, load shiftingLoad shifting
Peak shaving, ancil lary balancing
services & arbitrage.
Emulation of rotating generators (synthetic
inertia?)No No Not yet confirmed
RoCoF control? No No TBC
Speed of response Designed to be <500msResponse time of battery ramp output
from 0-100% is 20ms
Inverters used
6 x 1MW/1.25MVA Power
Conversion Systems from S & C
Electric
2 x 1.25 MW Bi-Directional AC/DC Power
Converter Provided by ‘Dynapower’
Company LLC - USA
ABB 2MVA Inverter
Black Start Capable?Yes but no scheme currently
implemented in SNS project
Currently not configured for black start
due to G59 requirements
Yes but prevented due to G59
protection
Location Existing Substation Existing Substation Adjacent to substation
Relevant for EFCC? YES YES YES
If not relevant for EFCC - why? Not applicable Not applicable Not applicable
Containerized? Bespoke Container Bespoke Container Bespoke Container
Integration into PV
power plantNo No Neglible PV plant
Comments
on-site controllers support both Modbus
TCP and DNP3 protocols for the control
interface.
Due to commission end of July 2015.
Frequency response available, but
designed to have RoCoF / Vector
Phase Shift protection instal led as
part of G59 instal lation.
Page 52
EFCC Battery Storage Investigation
Report November 2015
Appendix B Existing battery storage site evaluations
Table 11 below shows data for existing energy storage sites received from Western Power
Distribution in response to the questionnaire.
Project Name Sola Bristol FALCON Solar Storage Solar Storage
Isentropic
Pumped
Heat Energy
Storage
Distribution Network
OperatorWestern Power Distribution Western Power Distribution Western Power Distribution Western Power Distribution Western Power Distribution
Capacity 5 x 100kWh Capacity Min 300kVA Min 300kVA 5.6MWh
Power 5 x 50kW 300kWh 300kWh1.4MW for 4hours
(75% efficiency)
Battery Technology Lead AcidSodium Nickel
ChlorideTBC TBC Thermal
Reactive Power Yes Yes Yes Yes Yes
Operated (Locally/Remote) Local and Remote Local and RemoteLocal and Remote control via
operatorLocal and Remote Local and Remote
Type/speed of remote
communicationsGPRS communications
WiMAX point to point radio.
Typical less than 200ms round
trip
TBC (l ikely to be requested via
operator manually)TBC (probably UHF) UHF
Local control (measures)
Solar PV output, AC property
demand, DC property
demand and voltage
Voltage, frequency & LV
substation demand
TBC (l ikely to be voltage, real power,
reactive power of the site which
include PV output)
TBC (expect Voltage & PV
output as a minimum)
Voltage & primary substation
demand
Current Operation e.g
Frequency Regulation,
Primary Reserve, Peak
Shaving, Voltage Regulation,
Peak load Management
Domestic demand reduction
& Network support
Peak Shaving, Frequency
control, manually kVA output &
Voltage control
TBC (expected to be Network Peak
Shaving, generation output control
and Voltage control as a minimum)
Capable of ancil lary balancing but
outside of the trial scope.
Tbc (expected to be Network
Peak Shaving, generation
output control and Voltage
control as a minimum)
Peak Shaving, Balancing Var flow.
and arbitrage.
Capable of ancil lary balancing but
outside of the trial scope.
Emulation of rotating
generators (synthetic
inertia?)
No Not confirmed TBC but probably not TBC Real inertia from rotating mass
RoCoF control? No No TBC TBC Yes
Speed of responseTBC
TBC TBC
Inverters used Studer off grid invertersPrinceton Power
InvertersTBC TBC No inverters required
Black Start Capable?
Protection, Inverters are
capable of off grid
environments but currently
not configured for black
start due to G59
requirements
Protection, Inverters are
capable of off grid
environments but currently not
configured for black start due
to G59 requirements
TBC (probably not) Tbc (probably not)Has capability but G59 protection
requirements prevent this
LocationDomestic Installation and
Existing SubstationExisting Substation On PV generation site On PV generation site Existing Substation
Relevant for EFCC? No No No No No
If not relevant for EFCC - why? Power/capacity too small
Power/capacity is too small
also slow response due to Flow
Battery type
Power/capacity too small Power/capacity too small
Not battery storage and the
response time of the system is far
too high for the given project
Containerized?No, custom installation at each
siteTBC TBC Within a building
Integration into PV
power plantYes No Yes Yes No
Comments
Vector Phase Shift protection
instal led as part of G59
instal lation
Vector Phase Shift protection
installed as part of G59
instal lation
Project in procurement phase. Any
frequency response TBC. However,
RoCoF / Vector Phase Shift
protection instal led as part of G59
instal lation
Project in procurement phase.
Any frequency response TBC.
However, RoCoF / Vector Phase
Shift protection instal led as
part of G59 instal lation
Frequency response available, but
designed to have RoCoF / Vector
Phase Shift protection installed as
part of G59 instal lation. Real
inertia provided by rotating mass
12kWh Capacity split
between 32 single phase
units ~ 2kW capacity
Table 11: Questionnaire responses for WPD energy storage sites
Page 53
EFCC Battery Storage Investigation
Report November 2015
Appendix B Existing battery storage site evaluations
The following table (Table 12) show data for existing energy storage sites compiled from publically
available information.
Table 12: Data for other energy storage sites
Project NameCLNR
High Northgate
CLNR
Wooler Ramsey
CLNR
Maltby
CLNR
Wooler St Mary
CLNR
Harrowgate Hill
Distribution Network OperatorNorthern Power
Grid
Northern Power
Grid
Northern Power
Grid
Northern Power
Grid
Northern Power
Grid
Capacity 200kWh Capacity 200kWh Capacity 100kWh Capacity 100kWh Capacity 100kWh Capacity
Power 100 kW 50 kW
Battery Technology Lithium Ion Lithium Ion Lithium Ion Lithium Ion Lithium Ion
Reactive Power
Operated (Locally/Remote) Remote Remote Remote Remote
Type/speed of remote communications
Local control (measures) N/A N/A N/A N/A
Current Operation e.g Frequency
Regulation, Primary Reserve, Peak
Shaving, Voltage Regulation, Peak
load Management
Emulation of rotating generators
(synthetic inertia?)
RoCoF control?
Speed of response
Inverters used
Black Start Capable?
Location Existing Substation Existing Substation New Substation Existing SubstationExisting
Substation
Relevant for EFCC? No No No No No
If not relevant for EFCC - why?Power/capacity is
too small
Power/capacity is
too small
Power/capacity is
too small
Power/capacity is
too small
Power/capacity is
too small
Containerized? Bespoke Container Bespoke Container Bespoke Container Bespoke Container Bespoke Container
Integration into PV
power plant
Comments
Page 54
EFCC Battery Storage Investigation
Report November 2015
Appendix B Existing battery storage site evaluations
Project Name ChalveyOrkney Energy
Storage Park
NINES
Shetland
NINES
Shetland
Nairn Flow
Battery TrialHemsby
Distribution Network
OperatorSSE SSE SSE SSE SSE UK Power Networks
Capacity25kWh Capacity
(ave efficiency 80%)500kWh Capacity 6MWh Capacity 3MWh Capacity 150kWh 200kWh Capacity
Power 2 MW 1 MW 1 MW 100kWp 200 kW
Battery Technology Lithium Ion Lithium Ion Sodium Sulphur Lead AcidZinc-Bromine
Flow BatteryLithium Ion
Reactive Power
Operated (Local ly/Remote) Local and Remote Local and Remote
Type/speed of remote
communications
Local control (measures)
Current Operation e.g
Frequency Regulation,
Primary Reserve, Peak
Shaving, Voltage Regulation,
Peak load Management
Emulation of rotating
generators (synthetic
inertia?)
RoCoF control?
Speed of response
Inverters usedFour quadrant
power converterDC/AC inverter
Three-phase
DC/AC inverter
Between AC
and DC bus
Black Start Capable?
Location Existing Substation Existing Substation Existing Substation Existing SubstationExisting
SubstationNew Substation
Relevant for EFCC? No Yes No No No No
If not relevant for EFCC - why?Power/capacity is
too small
Not connected to
the National Grid, so
no use for the EFCC
project
Decomissioned
Not connected to
the National Grid,
so no use for the
EFCC project
Power/capacity is
too small also
slow response
due to Flow
Battery type
Power/capacity
too small
Containerized? ISO 40 foot container Dedicated building Dedicated buildingOff the shelf
containerBespoke Container
Integration into PV
power plant
Comments
EFCC Battery Storage Investigation
Report November 2015
Appendix C NPG Rise Carr 2.5MVA Battery Unit Detailed Costs
Appendix C NPG Rise Carr 2.5MVA Battery Unit Detailed CostsTable 13 and 14 below are detailed costs for the use of the Rise Carr site as provided by Northern
Power Grid.
Page 55
Commercially Sensitive Information
Page 56
EFCC Battery Storage Investigation
Report November 2015
Appendix D Cost of Belectric Energy Buffer Unit (EBU) Battery Storage
Appendix D Cost of Belectric Energy Buffer Unit (EBU) Battery StorageTable 15 below are the detailed costs associated with the Belectric battery storage unit as provided in
the EFCC Full Submission report in October 2014.
Lab
ou
r
Eq
uip
men
t
Co
ntra
cto
rs IT
IPR
Co
sts
Tra
vel
&E
xp
en
ses
Paym
en
tsto
users
Co
ntig
en
cy
Deco
mm
issio
nin
g
Oth
er
Site preparation Y2 0 0 33.67 0 0 0 0 0
Install equipment Y2 0 0 72.39 0 0 0 0 0
Install equipment Y3 0 0 72.39 0 0 0 0 0
Establish and modify relevant IT
systems Y2 0 0 32.71 0 0 0 0 0
Establish and test communication
Y3 0 0 32.71 0 0 0 0 0
Establish and test communication -
Equipment & IT Y2 0 572 0 4 0 0 0 0
Test and demonstrate response
capability Y3 0 0 25.65 0 0 0 0 0
Test and demonstrate response
capability Y4 0 0 51.31 0 0 0 0 0
Travel expenses - Y2 0 0 0 0 0 2 0 0
Travel expenses - Y3 0 0 0 0 0 4 0 0
Travel expenses - Y4 0 0 0 0 0 4 0 0
Contingency Y2 0 0 0 0 0 0 0 62
Contingency Y3 0 0 0 0 0 0 0 62
Contingency Y4 0 0 0 0 0 0 0 62
Category totals 572 320.82 4 0 10 0 186
TOTAL
Total Cost £K
1092.82
Table 15: Cost of Belectric battery storage unit
Page 57
EFCC Battery Storage Investigation
Report November 2015
Appendix E Cost Benefit Analysis Assumptions
Appendix E Cost Benefit Analysis Assumptions
Table 16: Cost benefit analysis Assumptions
ASSUMPTION JUSTIFICATION SENSITIVITY ADDITIONAL COMMENTS LEARNING FROM EFCC
System inertia changes overtime according to the 2015Gone Green scenario
Gone Green meets the 2020energy targets
n/a Impacts the additional enhancedresponse requirements assumptionsto around 2025
n/a
Additional enhanced responserequirements are as shown inFigure 6
From initial modelling forEFCC CBA and extrapolatedusing system inertia andSOF frequency responseresults (Figure 4 and Figure5)
Requirements accordingto Gone Green and SlowProgression scenarios(Slow Progression isdelayed requirements)
n/a
Batteries have 95% availabilityfor enhanced frequencyresponse
Infrequent usage allowsbatteries to be availablemost of the since they canbe charged during the dayfor overnight periods
n/a Coordination between responsedelivered by solar PV alone, PV plusbattery storage and storage only isdifferent in terms of duration andlevel of response.
Trials to be carried outon these solar andbattery combinations todeliver learning. Batteryavailability will beclarified from theproject.
Batteries have a 10 yearlifespan
Literature typically quotes
8-15 years depending on
usage
n/a Understanding of howusage for enhancedfrequency responseaffects lifespan anddegradation
Battery CAPEX £1,122,820 Cost of the battery-solarhybrid EFCC project. Likelyto decrease as the cost ofbatteries decreases but wedon’t assume this
n/a
Page 58
EFCC Battery Storage Investigation
Report November 2015
Appendix E Cost Benefit Analysis Assumptions
ASSUMPTION JUSTIFICATION SENSITIVITY ADDITIONAL COMMENTS LEARNING FROM EFCC
Battery OPEX £10,000/yr Literature quotes fixedOPEX for Lithium-ionbatteries used for frequencyresponse as $6500-$9200/MW-yr, we round upto be conservative
9
n/a Clear learning outcomefrom the project
No similar projects areconstructed before thecompletion of the EFCC projectand the earliest new batteriescould become operationalwould be 2019
Reasonable andconservative to assume therollout of such projects willonly start after thecompletion of EFCC
2020 in the delayedrollout scenario
Assume the battery rollout startsslowly and picks up pace as marketconfidence grows and technicallearnings have been achieved
n/a
Weighted Average Cost ofCapital (WACC) 5.3%
Upper limit of the WACCquoted for the cap and floorto be applied to the UKinterconnector regime
10
Discount rate 3.5% Standard UK discount rate n/aService payment £XX/MWh Approximate current cost of
existing frequency responseCommercial service to bedeveloped in WorkPackage 6
Service availability based onRoCoF requirements
See Appendix H for fulldetails
Availability andoperational models willbe investigated
9Table B-28 in DOE/EPRI 2013 Electricity Storage Handbook in Collaboration with NRECA
10OFGEM Financeability study on the development of a regulatory regime for interconnector investment based on a cap and floor approach, 2013. The WACC
values are quoted as 4.3% (floor), 4.7% (midpoint) and 5.3% (cap) and we chose the cap value since it is the most conservative of the three values.
Page 59
EFCC Battery Storage Investigation
Report November 2015
Appendix E Cost Benefit Analysis Assumptions
ASSUMPTION JUSTIFICATION SENSITIVITY ADDITIONAL COMMENTS LEARNING FROM EFCC
Batteries comprise 37.5% ofthe enhanced frequencyresponse market share from2020 onwards
Batteries have the potentialto comprise a large amountof the market share due totheir technical capabilitiesonce their rollout getsunderway
Low value (30% of themarket share) and highvalue (45% of the marketshare) and rollout delay tohit assumed market shareby 2025
A large sensitivity range has beenchosen as the market share willdepend on technical and commerciallearnings from the EFCC project
Far better understandingpossible of potentialmarket share forbatteries from projectlearning outcomes
Total savings toconsumers/additionalenhanced responserequirements are calculatedfrom data behind Figure 18(£m/MW)
Detailed assessmentrevealed total savings of£150m for 250MWadditional responserequired, £200m for300MW response required
Linear dependencybetween price and MWcompared to quadraticdependency (Appendix F)
As more response is needed it islikely that the cost/MW will alsoincrease, therefore the linear optionis a lower bound. Quadraticdependency is one option to modelthe increasing costs
This will be clarifiedduring the project withthe development of thecommercial service
Solar deployment of farmsabove 1MW from 2015-2035follows the Gone Green orSlow Progression scenarios
National Grid produces theFES using an evidence-based approach
The Slow Progressionscenario is used as a lowerbound and corresponds tothe delayed responserequirements from above
Both scenarios forecast almostidentical levels of solar deploymentuntil 2027 when Gone Green sees aslightly greater deployment
n/a
77% of solar deployment willexist in farms of size greaterthan 4MW
Our current knowledge ofall solar projects plannedthrough to operationalshows this figure
n/a Relevant because EFCC plans to use a1MW battery for a 3.8MW solarfarm, so we assume 1MW batteriescan be deployed on all farms above4MW (approximately)
n/a
The distribution of sizes ofsolar farms will remain thesame going forward
We do not have anyevidence to suggest how itcould change
n/a This allows us to estimate thenumber of farms we expect to installa battery according to the rollout,however larger batteries wouldrequire fewer participating farms
n/a
Page 60
EFCC Battery Storage Investigation
Report November 2015
Appendix E Cost Benefit Analysis Assumptions
ASSUMPTION JUSTIFICATION SENSITIVITY ADDITIONAL COMMENTS LEARNING FROM EFCC
Solar farms will typically installbatteries with a rated capacityof ¼ of the rated capacity ofthe solar farm
This is approximately theratio in the EFCC projectand the first time a hybridsolar PV and battery storageinstallation would betrialled
n/a This number is approximate but ahighly accurate figure is not crucialfor the results of this CBA
The benefits andchallenges of this ratiowill be assessed in theproject
A battery combined withrenewable generation is likelyto increase the availability offrequency response service andvolume that can be achieved
Existing pool of frequencyresponse providers islimited to conventionalgeneration plant anddemand side
n/a How much contribution that can beattributed to renewable generationsuch as solar PV is currently unknown
Proposed hybrid solar PVand battery storage trialswill provide learning onavailability andcontribution ofrenewables alongsideother providers
Complete integration ofbattery to the grid (notechnological barriers toutilisation)
Hybrid solar PV and batterystorage likely to use spareinverter capacity of the PVfarm
n/a No network reinforcements will berequired to integrate the battery
Site specific technicallimitations will beinvestigated anddisseminated as learningfrom the project
Hybrid solar PV and batterystorage installation onlyparticipates in the EFCC newfrequency response market
See Section 7.2.6 n/a Solar farms combined with batterystorage are capable of providingother grid services (e.g. voltagesupport)
Any additional learningon technicalperformance capabilitiesobtained during EFCCtrials will be gathered fordissemination
Page 61
EFCC Battery Storage Investigation
Report November 2015
Appendix F Consumer cost of additional Enhanced Frequency Response
Appendix F Consumer cost of additional Enhanced Frequency Response
Figure 18: Cost to consumers of procuring additional enhanced frequency response. We consider two differentrelationships to provide sensitivity analysis to our modelling.
Page 62
EFCC Battery Storage Investigation
Report November 2015
Appendix G Solar farm participation projections
Appendix G Solar farm participation projections
National Grid has access to data on the details of solar farms in all stages of development. The
histogram below shows the number of farms in each size category. The most common size of solar
farm is 4-5MW which constitutes 12% of the installed solar capacity in GB (farms not domestic
panels). We assume that the distribution of the sizes of solar farm remains the same as the number of
solar farms increases. To determine how many farms adopt a battery, we allocate the battery installed
capacity proportionally to each size category of solar farm and calculate how many solar farms in
each size category are required to install the batteries allocated.
For example, under Gone Green in 2020 we expect 32MW battery storage. Batteries sized 5-6MW
comprise 6% of the installed capacity of solar PV above 4MW, hence we allocate approximately
1.85MW of batteries to solar farms in this size category. The mean size of farm in this category is
approximately 5.5MW and so at 25% of capacity we would expect each farm to adopt a battery of size
1.4MW. Therefore 2 solar farms in this category would be needed to adopt a battery in order to cover
the 1.85MW battery installation assumed. This is of course a conservative estimate, and it is highly
likely that fewer solar farms would need to participate than we estimate with this method.
Figure 19: Histogram of solar farm installed capacities for solar farms in all stages of development from potentialto operational.
Page 63
EFCC Battery Storage Investigation
Report November 2015
Appendix H Availability requirements for enhanced frequency response
Appendix H Availability requirements for enhanced frequency response
Assessments contributing to the National Grid 2015 SOF have determined the percentage of the year
when the rate of change of frequency (RoCoF) is greater than the existing setting of 0.125Hz/s. The
following tables show are assumptions for the number of hours the enhanced frequency response will
contract availability from providers, based on this data.
We assume that the hybrid batteries contract to be available for the full hours shown, and that the 5%
unavailability is due to faults or other un-planned issues rather than opting out of a contract.
Since usage is rare the payments for the service are considered to be restricted to availability
payments (£XX/MWh).
Gone Green Slow Progression
% of year hours % of year hours
2019 78.8% 6903 73.2% 6412
2020 83.0% 7271 76.0% 6658
2021 86.2% 7551 77.8% 6815
2022 89.4% 7831 79.6% 6973
2023 92.6% 8112 81.4% 7131
2024 95.8% 8392 83.2% 7288
2025 99.0% 8672 85.0% 7446
2026 99.0% 8672 85.0% 7446
2027 99.0% 8672 88.5% 7753
2028 99.0% 8672 92.0% 8059
2029 99.0% 8672 95.5% 8366
2030onwards
99.0% 8672 99.0% 8672
Table 17: Percentage of the year when RoCoF > 0.125Hz/s and resulting hours of enhanced frequency responsecontracting
Page 64
EFCC Battery Storage Investigation
Report November 2015
Appendix I Data Tables for Figures 6 - 8
Appendix I Data Tables for Figures 6 - 8
Table 18: Data for figures 6-8
Figure 6 Figure 7 Figure 8
Description Additional Enhanced ResponseRequirements (MW)
Cost to the consumer without EFCC(£m/year)
Battery rollout projections (percentage refers to percentage of enhancedfrequency response market attained) (MW)
Scenario GG a&b SP a&b GGa GGb SPa SPb GG 30% GG 37.5% GG 45% SP 30% SP 37.5% SP 45%
2015 0 0 0 0 0 0 0 0 0 0 0 0
2016 30 10 19 9 6 3 0 0 0 0 0 0
2017 60 25 38 21 16 7 0 0 0 0 0 0
2018 110 45 70 45 29 15 0 0 0 0 0 0
2019 175 75 111 86 48 27 28 35 42 11 14 17
2020 275 110 175 172 70 45 87 109 130 35 43 52
2021 375 150 239 283 95 69 118 148 178 47 59 71
2022 475 190 302 420 121 98 150 188 225 60 75 90
2023 575 240 366 583 153 139 182 227 272 76 95 114
2024 660 300 420 742 191 197 208 261 313 95 118 142
2025 750 360 477 931 229 264 237 296 355 114 142 171
2026 760 420 484 954 267 341 240 300 360 133 166 199
2027 770 490 490 976 312 443 243 304 365 155 193 232
2028 770 590 490 976 375 610 243 304 365 186 233 279
2029 770 700 490 976 445 824 243 304 365 221 276 332
2030 770 770 490 976 490 976 243 304 365 243 304 365
2031 770 770 490 976 490 976 243 304 365 243 304 365
2032 770 770 490 976 490 976 243 304 365 243 304 365
2033 770 770 490 976 490 976 243 304 365 243 304 365
2034 770 770 490 976 490 976 243 304 365 243 304 365
2035 770 770 490 976 490 976 243 304 365 243 304 365
Page 65
EFCC Battery Storage Investigation
Report November 2015
Appendix J EFCC Project Hierarchy
Appendix J EFCC Project Hierarchy
System Operator (SO) Innovation Board
Governance, oversight, business alignment, approval of strategic decisions, conflict
resolution.
Project Sponsor
Richard Smith, Head of Network Strategy, National Grid
Provide project direction and alignment with strategic business objectives, ensure business
issues are resolved in a timely manner and provide an escalation route for key risks.
Project Steering Committee
Each project partner has provided a dedicated lead representative (as named in Figure 1) and
employed appropriate additional resource support to ensure successful delivery of project
objectives. The project has benefitted from the continuity of resource within the partner
organisations that had been involved with the project proposal submission.
The Steering Committee is responsible for developing and undertaking project activities,
completing deliverables, raising, evaluating and mitigating identified risks and authorising
changes to the project plan.
Project Director (Vandad Hamidi), Technical Project Manager (Charlotte Grant), and Project
Manager (Lisa Cressy) track and challenge progress against the project plan, manage
interdependencies and risks ensuring interventions are in place, escalate concerns, whilst
ensuring National Grid Project Management procedures are adhered to.
Page 66
EFCC Battery Storage Investigation
Report November 2015
References
References
1. EFCC Full Submission Report to Ofgem.
http://www.nationalgridconnecting.com/The_balance_of_power/the-news.html
2. Energy Storage Operators Forum (ESOF) A Good Practice Guide to Electrical Energy Storage
http://www.eatechnology.com/products-and-services/create-smarter-grids/electrical-energy-
storage/energy-storage-operators-forum/esof-good-practice-guide
3. Akhil, Abbas A, Georgianne Huff, Aileen B Currier, Benjamin C Kaun, Dan M Rastler, StellaChen, Stella Bingqing Chen, Andrew L Cotter, Dale T Bradshaw, and William D Gauntlett. 2013.DOE/EPRI 2013 Electricity Storage Handbook in Collaboration with NRECA. Sandia NationalLaboratories.http://energy.gov/oe/downloads/doeepri-2013-electricity-storage-handbook-collaboration-nreca-july-2013
4. UKPN Report for SNS Project at Leighton Buzzard.
5. International Electrotechnical Commission (IEC) White Paper on Electrical Energy Storage;http://www.iec.ch/whitepaper/pdf/iecWP-energystorage-LR-en.pdf
6. Centre for sustainable energy; “Optimizing the use of solar power with energy storage, 26th
Jan
2015; https://energycenter.org/article/optimizing-use-solar-power-energy-storage
7. Utility Drive, Invenergy bringing over 60MW of storage online for PJM frequency regulation,Herman K.Trabish, May 19 2015http://www.utilitydive.com/news/invenergy-bringing-over-60-mw-of-storage-online-for-pjm-frequency-regulatio/399140/
8. Utility Drive, “How utility and policymakers can maintain and boost renewable energy’s value”,
Herman K.Trabish, May 7 2015. http://www.utilitydive.com/news/how-utilities-and-policymakers-
can-maintain-and-boost-renewable-energys-
va/394643/?utm_source=Sailthru&utm_medium=email&utm_term=Utility%20Dive%3A%20Solar
&utm_campaign=Issue%3A%202015-05-07%20Utility%20Dive%20Solar
9. International Renewable Energy Agency (IRENA), Battery Storage Case Studies, 2015.
http:http://www.irena.org/DocumentDownloads/Publications/IRENA_Battery_Storage_case_studi
es_2015.pdf
10. UK Distribution Network Operators. 2013. Electricity North West. Accessed December 14, 2014.http://www.enwl.co.uk/docs/default-source/future-documents/state-of-charge-of-gb-final.pdf?sfvrsn=0.
11. INSIGHT_E, Bo Normark, How can batteries support the EU electricity network, November 2014.http://www.insightenergy.org/ckeditor_assets/attachments/48/pr1.pdf
12. DOE Energy Storage Database, Sandia National Laboratories, United States Department ofEnergy, http://www.energystorageexchange.org/projects
13. Clark, M.S, 2008 “Lead-Antimony, lead-calcium, lead-selenium, VRLA, Ni-CD. What’s in aname?” http://www.battcon.com/PapersFinal2009/ClarkPaper2009FINAL_12.pdf