+ All Categories
Home > Documents > NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient...

NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient...

Date post: 19-Mar-2021
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
36
NAYARA ENERGY LIMITED Refinery Division, Vadinar Excellence in Energy Management- 2018 Presenter: Nitinkumar Chokshi - General Manager Arpankumar Panchal - Manager
Transcript
Page 1: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

NAYARA ENERGY LIMITEDRefinery Division, Vadinar

Excellence in Energy Management- 2018

Presenter:Nitinkumar Chokshi - General ManagerArpankumar Panchal - Manager

Page 2: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

49 %

24.5 % 24.5 %

Brief introduction –Nayara Energy Limited

24.5 %

49.0 %

Page 3: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

Brief introduction –Nayara Energy Limited / Refinery Division

• 20 MMTPA Refinery / 11.8 Complexity

• Oil Terminal - Jetty and SBM Operations

• CPP (Captive Power Plant) – 600 MW

• Storage Facility

Page 4: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

Nayara Energy Limited- Refinery Process Flow

VGO MHC

DHDT

DCU

ISOM

CDU 2

CDU

CN

Blending

Mangala

NHT/CCR

Page 5: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

Unique Design Features

• Tallest crude column (90 metres height, 76 trays)

CDU 18 MMTPA

• Low pressure steam ejectors & vacuum pump.

VDU

• Converted to CDU from VBU.

• Capable to process ultra heavy crude on standalone basis.

CDU-II2 MMTPA

• Very high pressure hydro treatment

• Capable of producing Euro VI diesel

DHDT5.0 MMPTA

• 6 Coker drums

• One of the largest Coker unit in the world

DCU7.5 MMTPA

• First refinery to use Coal fired Boilers for meeting Steam and power demands of the refinery

CPP (Captive power plant)

• 2 Stage Regenerators

• Running on Maximizing Middle Distillate Mode

FCCU-3.9 MMTPA

• Producing Reformate with 101 RON

• NHT Revamped to 2.15 MMTPA in Feb’18.

NHT/CCR2.15/1.22 MMTPA

• Capable to processing feed with 5% Benzene and 10% C7+

• Revamped to 0.9 MMTPA in Feb’18.

ISOM Unit 0.9 MMTPA

• Converted to Mild Hydrocracker in Sept’2015 Turnaround Shutdown

VGO-MHC 6.5 MMTPA

Page 6: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

1. Specific Energy Consumption of Nayara Energy Limited

Refinery’s SEC in terms of MBN (MBTU/BBL/NRGF)

63.84

62.77

58.69 58.87

55

60

65

2014-15 2015-16 2016-17 2017-18

MB

N

MBN (MBTU/BBL/NRGF )

Refinery Turn Around was in FY 2015-16 & next Turn Around planned in FY 2018-19.

• Reduced from 63.84 to 58.87

• PAT Target is 60.35 for FY 2018-19

Page 7: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

Data Source : Ready Reckoner Jun’18 on www.ppac.org.in

58

.87

63

.2

64

.7

66

.7

68

.3 72

.4

72

.8 77

.1

77

.3

77

.7

79

.2

80

.8 84

.4 88

.6

91

.7

10

5.5 10

8

12

3.7

40

60

80

100

120

140

MB

N

Note: Reliance, HMEL & BORL MBN data not available

2a. Specific Energy Consumption of NAYARA -Comparison with other Indian Refineries

Specific Energy Consumption of Indian Refineries FY 2017-18

Page 8: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

2b. Specific Energy Consumption of NAYARA-Global Benchmarking

• Data Source : Global benchmarking study conducted by Solomon for Nayara.

92.00

80.01

78.0032

10

1

2

3

4

75.00

80.00

85.00

90.00

95.00

2012 2014 2016

QU

AR

TILE

EII

Refinery’s SEC in terms of EII (Energy Intensity Index)

Solomon study is done every alternate year.

• Reduced from 92.00 to 78.00

Page 9: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

Benefits

Investment

3a. List of ENCON Projects in last 3 years2017-18 (With Investment)

Increase in FCCU WGC compressor suction pressure.HPS reduced by 0.5 TPH

04.09

0.1

Desalination water Feed to CPU unit Pump - impeller trimming to min diameter (510mm). 79 KWH

04.25

0.5

Benefits

Investment

Installation of energy efficient Fan blades in Cooling Tower 210 KWH

11.30

9.1

LGO product Heat utilization in CDU-1 for increasing Desalter inlet temperature 1 Gcal/Hr.

12.51

6.6

Power saving in Sea water return pump 426 KWH

22.91

2.3

New exchanger train provided in reactor feed-effluent exchanger circuit in NHT. 2 Gcal/Hr.

25.96

90

LED installation at different locations in refinery.

545 KWH

14.67

11

In Base SRU – trap bypass &Desuperheater isolation passing valves replaced. 4 TPH of HPS

32.72

1.0

All figures are in Million Rupees.

Page 10: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

Benefits

Investment

3a. List of ENCON Projects in last 3 years2016-17 (With Investment)

HSD tank side stream mixture provision and stopping high capacity pump for circulation. Saving: 42 KWH

2.03

0.50

VFD drive installation in both boilers bottom ash submerged drag Chain conveyor. Saving 3.78 KWH

0.18

0.05

Benefits

Investment

Replacement of total 500 conventional lamps with high efficiency LED lamps. Power saving of 82.26 KWH

2.00

2.94

PIT- Higher Capacity blending pumps replaced with lower capacity pumps. 40 MWH/Month.

2.64

0.87

PIT - Impeller trimming for MS-III to Dispatch transfer pumps

Saving - 11 KWH

0.53

0.08

DCU - Replacement of MF overhead condenser

HP STEAM reduced by 5.96 TPH (4.71 Gcal/hr)

36.55

10.00

CDU-2 Pre heat improvement through Pinch study

FO Saving is 0.102 TPH, Net savings : 1 Gcal/hr

8.08

42.42

All figures are in Million Rupees.

Page 11: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

3a. List of ENCON Projects in last 3 years2015-16 (With Investment)

Cooling Tower stoppage

5.78

1.00

Benefits

Investment

Installation of liquid ring compressor in DCU unit

87.53

40.00

Use of Hydrogen rich sat gas as HMU feed resulted in increased yield and reduction in fuel gas requirement

434.45

60.50

All figures are in Million Rupees.

Page 12: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

Benefits

3b. List of ENCON Projects in last 3 years2017-18 (Without Investment)

Optimization of DHDS operating parameters.Stripper & Drier inlet temp reduction. 2.6 Gcal/Hr

34.03

Avoid sub-cooling of suspect condensate below 100°C.in ISOM unit through operational control 1.28 Gcal/Hr

11.93

Benefits

All figures are in Million Rupees.

Changing tap setting of lighting voltage transformer to lower the single phase voltage to 210 – 215V 0.7 KWH

0.04

Connecting under-loaded motors in star mode

0.01

Page 13: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

Benefits

3b. List of ENCON Projects in last 3 years2016-17 (Without Investment)

Vacuum Residue (VR) run down temperature increase in CDU-2 unit.

Saving - 0.21 Gcal /hr

2.58

Blow down optimization in FCCU unit.

Saving - .0.11 Gcal/Hr

5.93

Benefits

All figures are in Million Rupees.

Stoppage of Additional Lean Amine pump in DHDT unit

Power saving of 185.2 KWH

8.94

CPP - Optimisation of running drives through operational changes

Additional running drives were stopped.

84.76

Steam consumption reduction. By increasing amine concentration.Saving - 8 ton/hr

42.05

Page 14: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

Benefits

3b. List of ENCON Projects in last 3 years2015-16 (Without Investment)

One pump stopped in DM water transfer service by Pressure reduction.

1.79

Main Air blower amps reduced by 10 amps optimizing the IGV opening/closing blow off valve.

0.54

Benefits

All figures are in Million Rupees.

In Sulphur Recovery Unit, LP condenser Two fans of 22KW stopped.

0.23

Cold VR from PIT to DCU one pump stopped.

1.84

VGO Pressure Recovery Turbine-1 strainer replaced to improve the reliability and thus save energy.

11.30

Lighting optimized in Mini HMU as the unit is in idle condition.

0.54

In DCU, one condensate pump stopped and 15 M3/hr cold condensate consumption reduced by using stripped water consumption.

0.31

In DCU, LCGO side stripper MP steam reduced.

3.80

Page 15: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

Total Savings

Savings

With Investment

Without Investment

2017-18

128.41

46.01

2016-17

947.98

144.26

2015-16

535.58

27.40

Total

1611.97

217.67

All figures are in Million Rupees.

Page 16: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

3c. Road Map FY 2018-19

CDU-1: Impeller trimming of raw crude

booster pump

150.67

CDU-2: Vacuum Distillate (VD) low heat recovery. Potential: 2.0

Gcal/Hr

1752.00

Benefits

All figures are in SRFT/ANNUM.

Benefits

CPP PH-2 CW Pump (1 nos) bowl assembly

replacement

37.67

CDU-1: STEAM SYSTEM -Flash vessel provision.

Additional LPS generation : 0.311 TPH

174.35

CDU-1: Thermo-compressor provision.

Additional LPS generation : 0.85 TPH

476.50

CDU-1: HN product heat utilization as per pinch study report for

BFW heating

1927.20

Electrical: Optimizing distribution

transformer voltage level by adjusting

transformer tap setting

90.40

CCR Higher capacity Packinox replacement.

5256.00

Page 17: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

4a. Innovative Projects - CDU Column high delta P

❖ Issue: In CDU Column Increased pressure drop (ΔP) across Kero zone trays resulting Energy loss and quality failure of Kerosene and Heavy Naphtha due to suspected Phosphorous compounds typically used in Crude oil production deposition in Kero zone

• The only available option to overcome the issue was to shut down the unit and clean the section tray off any chocking which would have resulted both in throughput/Energy loss by adopting the concept unit shut down was avoided till planned turnaround and both quality and throughput requirement were met.

❑ Impact:

• Throughput Reduction and Energy loss

• Quality Impact

• Light Kerosene (LK) flash point low and high

freezing point affecting Jet fuel production

• Higher end point of Heavy Naphtha (HN) making

it unfit for OMPL grade naphtha production

❑ Action Taken

• Pressure survey carried out indicates trays 31-32

may be partially fouled/blocked

• Gamma Scanning by BARC

• Scheme to bypass tray 31-32 executed (LK PA

return to HK PA return at tray 37) . Piping

modifications carried out to further increase HK PA

duty

Page 18: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

Simplified Sketch of LK PA to HK PA Bypass Modification

Schematic diagram of innovation After and before modification data

4a. Innovative Projects - CDU Column high delta P

Page 19: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

4a. Innovative Projects - CDU Column high delta P

3.5

1704.3

1 Day

Savings

InvestmentMillion Rs

ImprovementMillion Rs

Payback

❖ Benefits achieved:

• Significant reduction in Column DP

observed post commissioning of LK PA

to HK PA bypass.

• T’put normalized

• Quality specs of LK and HN met

• Non productive energy requirement

was avoided.

❖Further Action

• Installation of new design Kero trays in

TA 2018

SAVINGS

Page 20: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

4b. Innovative Projects – Maximizing HN to Gasoline pool

❑ Limitation faced

• NHT charge heater capacity was found limitingwhich was decided to address by providingadditional heat exchangers in feed effluentcircuit.

• Temperature cross (17°C) observed in feed /effluent exchanger train.

• Sizing of over-head condenser for DIP columnat high reflux rate.

❑ Action Taken

• NHT-To get the required preheat, best suitable option

found was to provide the three common exchanger for

both trains without mixing Recycle Gas with feed.

• ISOM-Two drum configuration was used for DIP overhead

circuit this resolved the sizing problem and also resulted in

energy saving as reflux was diverted to the column at 15

Deg Higher temp than the run down.

Challenge: To upgrade maximum possible Heavy naphtha produced to gasoline pool with minimum possiblechange in existing facility.

• 18% of capacity revamp was found possible in NHT unit without change in existing reactor shell size andthe using the existing recycle gas compressor.

• Light Naphtha feed contains about 15% iC5, (RON 93) & 20% increase in ISOM capacity was possible by justremoving iC5 in De-Isopentanizer (DIP) at upstream of PENEX reactor.

Page 21: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

RG from RGC

To RGC separator

FEED

P-001A/S

E-001A-F

F-001

110°C68.0 °C

280 °C

335 °C

330 °C

40 °C

EA-001

Reactor

4b. Innovative Projects – NHT Revamp

RG from RGC

To RGC separator

FEED

P-001A/S/B

E-001A-F

F-001

93 °C

68.0 °C

287 °C

335 °C

330 °C

40 °C

EA-001

390 M3/Hr

330 M3/Hr

Heater

Heater

Before

After

Reactor

Page 22: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

Light Naphtha From NHT

Feed Treater

PENEX Reactor

Stabilizer

LPG Stripper

DIH Column

DIP Column

LPG

Fuel Gas

Isomerate

LPG

iC5 – iso Pentane

4b. Innovative Projects – ISOM Revamp

140 M3/Hr

170 M3/Hr

Page 23: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

➢ Benefits :

• 16% of Heavy Naphtha product was

converted to high value gasoline pool.

➢Energy savings effect:

• 2 Gcal/Hr. fuel saved in NHT charge

heater by additional HE train

• Operation of Iso-Pentane side stripper

using DIP bottom hot stream for

reboiler resulted in 1.5 Gcal/Hr of

energy saving.

90

45.4

2 Years

InvestmentMillion Rs

ImprovementMillion Rs

Payback

SAVINGS 3.5 MMkcal/Hr

4b. Innovative Projects – Maximizing HN to Gasoline pool

Page 24: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

5. Renewable Energy Utilization

• Solar photovoltaic cell in security watch

tower in remote location.

• Small windmill installed to provide lights to

security cabin

• Solar Operated Traffic Flasher Lights

installed near Refinery Main gate &

Township gate.

• Solar Heater provided at Oil Club.

• Emission free- electrically powered Golf

Carts and Fuel Free- Bicycles are used in the

Refinery.

• Bio gas plant based on canteen food waste.

• Day light harvesting in warehouse.

Page 25: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

6. Utilization of waste material as fuel - Bio Gas plant

• Bio-gas plant is installed to dispose Kitchen waste, which also produce Natural gas and

manure. Natural gas is utilized as fuel in Kitchen and manure in Greenbelt.

• Capacity : 500 kg/Day kitchen waste

• Bio Gas generation about 50 m3 / day equivalent to 20 Kg of LPG.

Page 26: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

6.Utilization of waste material as fuel- Spent Carbon Disposal

Project Title :-

• Disposal of Spent Carbon by reusing it as Alternate Fuel in CPP coal based Boiler.

Spent catalyst disposal method:-

• Spent Carbon is generated from Kerosene Merichem Unit, Sulphur Recovery Unit

and Utilities.

• Normal mode of the Disposal is outside parties by incineration. It was decided to

dispose it by using as a fuel in CPP coal based Boilers

Total savings per year = Rs. 39,24,000

Page 27: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

CO2e (MT) Emissions

Scope 1

Scope 2

Scope 3

Scope 1 +2

2017-18

5.8620

0.0022

0.0013

5.8640

2016-17

5.9580

0.0026

0.0003

5.9610

2015-16

5.5810

0.0122

0.002

5.5930

Scope 1: Direct GHG emissionsScope 2: Electricity indirect GHG emissionsScope 3: Other indirect GHG emissions

7. GHG Inventorisation

Page 28: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

7. Green Belt at NAYARA

Horticulture at Refinery (1064 Acres)

Type Description Total No.

Gre

en

Be

lt(8

47

Acre

s)

Mango trees 1,07,137

Pomegranate trees 1,960

Forest Species 1,91,298

Total Plants 3,00,395

Land

scape

(21

7 A

cres)

Refinery Landscape area(m2) 3,37,443

Avenue & Mass Plantation(m2)

3,59,955

Township & city based (m2) 1,82,204

Total Landscape 8,79,602

Page 29: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

9. Team work, Employee Involvement & Monitoring

1.Daily monitoring system -

Daily ENCON report unit wise

2.Review meeting chaired by –

Director and head of Refinery

MRM – Management Review Meeting (Quarterly)

MPR - Monthly Performance Review (Monthly)

3. Separate budget for Energy Conservation -

Yes

4. Energy efficiency / awareness training program -

Quarterly ENMS 50001:2011 training

Brain storming session unit wise and with ENMS co-ordinator.

Page 30: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

10. Implementation of ISO 50001:2011-EnMS

• First certified in 2014

• Recertified in 2017

Page 31: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

ISO 45001:2018 Certificate

Page 32: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

Other information- Awards

Awards Issuing Authority

Nayara Energy Ltd. received the “Excellent Energy Efficient Unit” award in 18th National Award for Excellence in Energy Management 2017

Confederation of Indian Industry (CII)

Nayara Energy Ltd. won First Prize in CII (WR) Safety, Health and Environment (SHE) Excellence & Innovation Award 2017

Confederation of Indian Industry (CII)

Nayara Energy Ltd. won Oil & Gas Conservation Fortnight Award 2016 for Furnace/Boiler Installation Effectiveness in Lowest Heat Loss from Furnace/Boiler Shell(BTU/hr/ft²)

Ministry of Petroleum & Natural Gas

Nayara Energy Ltd. won International Safety Award in the category of Health and Safety Management 2016

British Safety Council

Nayara Energy Ltd. won Skoch BSE Award - Merit of Certificate for Petroleum Refining in the category of Occupational Health and Safety

SKOCH Group

Nayara Energy Ltd. won the National Safety Award for Performance Year 2015 based on Accident-free Year

DGFASLI, Ministry of Labour and Employment, Government of India

Nayara Energy Ltd. Awarded for “Excellence in Management of Environment” for the year 2016

Indian Chemical Council (ICC

Page 33: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

Best Practices Implemented on Energy Front

• Involvement of Top Management by putting forward ”Energy” as one of the elements contributing

towards achieving “World Class refinery” tag.

• Dedicating energy task force team formed comprising of experts from various cross functional roles

to promote energy initiatives.

• Promoting culture for continuous EnCon idea generation/ out of the box/ innovation quest for

energy optimization at each unit level.

• APC module implemented to optimize the operation in various unit.

• Indirect losses on slop processing, yield loss and product quality giveaway minimized by diligent

Operation.

• Minimizing power consumption through optimum selection/loading of drives.

• Monitoring all Fluid coupling drives & variable frequency drives.

• Distillation temp, pressure adjustments with changing feed rates /qualities

Page 34: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

Best Practices Implemented on Energy Front

• Close monitoring of high energy intensive equipment performance, e.g.

Furnaces & Boilers, rotating equipments distillation columns.

• Carrying out a comprehensive Hydrocarbon Loss Audit.

• Online monitoring of all Flare valves to minimize flare loss.

• Third party audit (Energy, F&L, Electrical) in Refinery.

• Prepared Energy mapping of each unit.

• Developed energy Metrics of each unit.

• Low grade heat utilization.

• Outsourcing steam traps management to minimize steam losses.

• Improved accuracy of loss estimation.

Page 35: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

Best Practices Implemented on Energy Front

Encouragement/ Information

Idea Generation –MOC Portal

GRM/Energy/

HSEF

ENCON Team

RLT

Page 36: NAYARA ENERGY LIMITED - Green Business Centre · 2018. 9. 13. · Installation of energy efficient Fan blades in Cooling Tower 210 KWH 11.30 9.1 LGO product Heat utilization in CDU-1

Arpankumar PanchalManager Process(M) [email protected]

Nitinkumar ChokshiGeneral Manager Lead EnCON(M) [email protected]


Recommended