May 12, 2005 ACC Review- Station 5 J.H. Chrzanowski - 1
NCSX
ACC Review ACC Review OfOf
Modular Coil Modular Coil Manufacturing FacilityManufacturing Facility
Station No. 5 [VPI]Station No. 5 [VPI]the NCSX Manufacturing Team the NCSX Manufacturing Team
May 12, 2005 ACC Review- Station 5 J.H. Chrzanowski - 2
NCSXGeneral Overview- Station No. 5
This ACC review is reviewing the safe guards and controls that are planned and implemented on the VPI Station No. 5.
Station 5 will be used to epoxy impregnate the modular and Toroidal Field coils following winding activities.
Quantity of coils to use Station 5 (18) modular coils (18) Toroidal field coils (1) Twisted Racetrack coil
May 12, 2005 ACC Review- Station 5 J.H. Chrzanowski - 3
NCSXModular Coil Types
Modular Coils
TF Coils
TRC Coil
May 12, 2005 ACC Review- Station 5 J.H. Chrzanowski - 4
NCSXModerate Hazard Facility
The NCSX Coil Manufacturing Facility has been designated a “Moderate” Hazard Facility”
This a result of the autoclave usage and the activities associated with the VPI of the MC
“NCSX-PHA-142-01” approved document, documents all of the known hazards associated with then MCWF
May 12, 2005 ACC Review- Station 5 J.H. Chrzanowski - 5
NCSXNCSX R&D – Safety is Integrated in All AspectsNCSX R&D – Safety is Integrated in All Aspects
Safety is an important element of the PPPL culture and is incorporated in all aspects of the development program and will be carried over to production
Integrated Safety Management (ISM)Job Hazard Analysis survey (JHA’s) is being developed
to identify hazards associated with the various tasks and the personnel protective equipment required with Station 5
Involvement of all safety groups in developing plans for manufacturing- IH, Construction safety, HP
May 12, 2005 ACC Review- Station 5 J.H. Chrzanowski - 6
NCSX
STATION 1
STATION 2
STATION 3
STATION 4
STATION 5
Modular Coil Manufacturing Facility
Location of Station 5
May 12, 2005 ACC Review- Station 5 J.H. Chrzanowski - 7
NCSXGeneral Description of Station #5 ActivitiesGeneral Description of Station #5 Activities
Station 5 Activities-Install coil in autoclave and prep for VPI-Mixing of epoxy-Vacuum leak checking systems-Working with vacuum/heat/pressure [autoclave]-Filling coil with epoxy (VPI)-Heat curing filled coil-Remove coil from autoclave
Work is covered by Procedure No. D-NCSX-MCF-003
May 12, 2005 ACC Review- Station 5 J.H. Chrzanowski - 8
NCSXSafety Related Activities
The following items are being addressed in the procedures and JHA Confined space- working in the autoclave Working on elevated surfaces- upper catwalks Working around hot surfaces Working with vacuum and pressure chamber General safety concerns-house cleaning, etc. Crane Operations
May 12, 2005 ACC Review- Station 5 J.H. Chrzanowski - 9
NCSXSafety ControlsSafety Controls
Personal protective equipment- face, glovesConfined space permitsTrainingApproved procedures
May 12, 2005 ACC Review- Station 5 J.H. Chrzanowski - 10
NCSXNCSX Coil Manufacturing Organizational ChartNCSX Coil Manufacturing Organizational Chart
Indicates a communication link, and not a management link between the participants
* Note: Designates primary station responsibility as well as sharing overall field management responsibilities.
Construction Safety Representative
Quality Control Representative
Coil Manufacturing Facility Manager
Jim Chrzanowski Industrial Hygiene Representative
Health Physics (HP) Representative
PPPL Responsible Line Manager
Larry Dudek
NCSX WBS 14 Manager
Dave Williamson
NCSX WBS 13 Manager
Mike Kalish
Field Supervisor *Steve RaftopoulosMETROLOGY
Field Supervisor *Jim Chrzanowski
Station No. 1Winding Form
Preparation(1) Lead Tech. + [1]
crew
Station No. 2, 3 & 4Winding stations
(3) Lead Techs + [4] crew
Station No. 5VPI
(1) Lead Tech. + [3] crew
Station No. 6Coil Testing
(1) Lead Tech. + [TBD] crew
Coil Test DirectorGeoff Gettelfinger
Field Supervisor Mike Kalish
Field Supervisor *Tom Meighan
May 12, 2005 ACC Review- Station 5 J.H. Chrzanowski - 11
NCSXManufacturing Documents- Station 5
NCSX-PLAN-CMFOP-00 [NCSX Manufacturing Facility Operations Plan]
Approved NEPA 1283 WP’s- 1188 (TRC),1138 (MC) and 1231 (TF) NCSX-MIT/QA-142-01-00 [MC MIT/QA Plan] Manufacturing Procedures
D-NCSX-MCF-003 [MC VPI Activities]D-NCSX-OP-EO-41 [Emergency Response
Procedure]D-NCSX-OP-G-162 [Autoclave Operating procedure]
May 12, 2005 ACC Review- Station 5 J.H. Chrzanowski - 12
NCSXModular Coil VPI Flow Diagram
May 12, 2005 ACC Review- Station 5 J.H. Chrzanowski - 13
NCSXVPI Delivery System
Epoxy Delivery System Supply & return
manifolds Epoxy control valves Epoxy Filters Valves assemblies are
disposable
May 12, 2005 ACC Review- Station 5 J.H. Chrzanowski - 14
NCSXAutoclave
May 12, 2005 ACC Review- Station 5 J.H. Chrzanowski - 15
NCSX
During the VPI process, the Modular Coil will be divided into 3 zones Zone 1- supply only Zone 2- supply and return Zone 3- return only
The autoclave will initially be maintained at vacuum matching the vacuum inside of the “bag mold” [minimize potential leaks]
As the coil reaches the ½ fill mark, the autoclave atmosphere will slowly shift from vacuum to pressure (5 psig max) to support the bag mold
Once filled, autoclave will return to atmospheric pressure prior to beginning the ramp up of temperature to cure the epoxy
Zone 1 [Fill]
(12) sprues
Zone 3[Return] (12) sprues
Zone 2 [Fill/return]
(24 sprues)
Vacuum-Pressure Impregnation (VPI)
May 12, 2005 ACC Review- Station 5 J.H. Chrzanowski - 16
NCSX
NCSX MODULAR COIL VPI CYCLE
10
20
30
40
60
50
70
80
90
130
100
110
140
0
120
6 12
18
24
30
36
605448
42
0
10
20
30
40
60
50
70
80
90
130
100
110
140
120
Coil Fill Period
Cure Time
Ramp down Period
Ramp up
period
Post Cure Time
Ramp up period
5 hours
18 hours
16 hours
6 hours @ 10 ° C ramp up per hour
11 hours @ 10 ° C ramp down per hour
Temperature degrees C
Hours “Scrambled Egg” test to verify Gel temperature
Viscosity measurementsEpoxy component
mixing