Nehru Place-Place making ProjectJanuary, 2015
3- slidePROJECT SUMMARY:
PROPOSED MASTER PLAN
MLCP + OFFICE + RETAIL ON GROUND
MLCP + RETAIL ON GROUND
MLCP + RETAIL ON GROUND
CONVENTION CENTRE
HOTEL MLCP + RETAILRETAIL + OFFICE + SERVICE APARTMENTS
RETAIL + OFFICE + SERVICE APARTMENTS
HOTEL BUS TERMINAL + DEPOT + RETAIL
PLANNING – DESIGN PROPOSAL
d
OPERATION & MAINTENANCE MODEL - PPPBus Terminal
98 Crores
Multi Level Car Parking
NMT & pedestrain Infrastructure
Public spaces and Social Ammenities
New Commercial Development
Project Cost 485 Crores
Project IRR146% 35%
Breakeven Period4 yrs(119 Crores)
Equity IRR
FinancialViability
347% 75%
611 Crores
19%
28%
10 Yrs(617 Crores)
Project Viable
NA
Project Viable Project Viable
Parking & Public Space Management
?
Proposed Way Forward
• Creation of a multi stakeholder platform under the leadership of DDA/ SDMC• Constitution of a high level committee comprising of key stakeholders in the Nehru Place project
•UTTIPEC•SDMC•CPWD•DTC•DMRC
• To review and approve recommendations for the area• Facilitate implementation of the recommended interventions
PROJECT DETAILS:
7
Access & Connectivity
Vehicle & Parking
Management
Multi-Modal Integration
Pedestrian & Public Spaces
Cleanliness & Safety
Parameters of a vibrant commercial district
New Friends Colony
East of Kailash
Sant Nagar
Kailash Colony
Chitranjan Park
Pamposh EnclaveG K 1
G K 2
• Planned in 1969, operational in early 1980s as a commercial business district surrounded by residential areas
• 38 Hectares of prime real estate in the heart of South Delhi
• Currently a regional commercial centre served by two major roads, 2 Metro lines and 24 bus routes
• Less than 2/3rd developed portion has 5.8 lakh sq.m. built commercial development
• Attracts 1,30,000 visitors and 32,000 vehicles daily
OUTER RING ROAD
LALA LAJPAT RAI MARG
NEHRU PLACE DISTRICT CENTRE
Parking consumes public space
Unwelcoming & hostile access
Desolate & unsafe at night
Lacks maintenance, amenities
New Friends Colony
East of Kailash
Sant Nagar
Kailash Colony
Chitranjan Park
Pamposh EnclaveG K 1
G K 2
OUTER RING ROAD
LALA LAJPAT RAI MARG
NEHRU PLACE – DISTRICT CENTRE
An underperforming and underutilized, 38 hectares of prime public asset
Renewal - Regeneration Project: Nehru Place District Centre
May’13 Project conceptualised by UTTIPEC
June’13 Project initiated: Shakti commissioned technical partners at the request of UTTIPEC
Nov’13 Draft designs developed in consultation with UTTIPEC and the local stakeholders
Dec’13 Designs approved by UTTIPEC
Jan’14 Project discussed with Engineering Member, DDA
May’14 Project discussed with Commissioner, SDMC
Today Project discussion with VC, DDA for guidance on next steps
New Friends Colony
East of Kailash
Sant Nagar
Kailash Colony
Chitranjan Park
Pamposh EnclaveG K 1
G K 2
OUTER RING ROAD
LALA LAJPAT RAI MARG
NEHRU PLACE – DISTRICT CENTRE
An underperforming and underutilized, 38 hectares of prime public asset
Parking Planning Management
Key Interventions identified
d
16
Traffic and pedestrian counts: 6 locations
Parking survey: 25 Sites
Boarding and alighting survey: 4, Bus and Metro Stations
User survey: 2000 commuters and visitors
Establishment survey: 500 commercial establishments
Topographic survey: 38 hectares, 10km
Activity Survey: Day, night, weekday and weekend
Photo documentation
Data Collection
• 9500 ECS (Phase 1 & 2)• 1000 in 1 MLCP –
5000sqm – 4 floors• 8500 at grade – 68000
sqm (Stacked)• 20% of precinct area
Demand in BAU Scenario (2021)
• 5500 ECS• 3500 in 4 MLCP –
15000sqm• 2000 ECS at grade –
48000 sq.m.• 18% of precinct area
Planned Capacity (2021) • 12000 ECS
• 10000 in 5 MLCP – 18000sqm
• 2000 at grade – 48000 sqm
• 20% of precinct area
As per Master Plan Norms (2021)
• 6600 ECS (Phase 1)• 1000 in 1 MLCP – 5000
sqm – 4 floors• 5600 at grade – 46000
sq.m.• 14% of precinct area
PARKING DEMAND vs CAPACITY SCENARIOS
Best Case Supply Scenario MLCP Vs At-grade to be balanced
Base year Demand (2013)
Current Price
Short Term (<2 hrs)
At Grade MLCP
20 30
Long Term (>2 hrs)
40 60
Demand Capacity
87% of capacity
5000 MLCP, 500 Surface
No. of Visitors Parking space consumed
8% of precinct area
*-As per Transport Department notification
At grade parking encroaching street space Only 30% of MLCP used
Current Scenario Proposed Scenario
Proposed Price
Short Term
At Grade MLCP
125* 45
Long Term
475* 180
What is driving parking demand?
PLANNING
Ideally, the area should have access from all directions
Astha Kunj, restricting access from North
Currently majority of access is from the South and the west
PLANNING
Within precinct, public transport is at the periphery while personal vehicles have close access while
PLANNING
Improved circulation of public transport within the commercial area is recommended
PLANNING
Circulation of private vehicles needs to be managed better
1833
861
1000
783
646
PLANNING
Parking needs to be concentrated in a few Multi-level car parks
1833
861
1000
783
646
270150
25 25
30
PLANNING
Few off-street parking spaces proposed for short term parking
PLANNING
Vehicular circulation plan for various streets is changed accordingly
PLANNING
Pedestrian connectivity and circulation increased to the entire area
PLANNING
Proposed designs incorporate the upcoming DDA establishments
PLANNING
Additional links providing non-motorised transport access are proposed
PROPOSED MASTER PLAN
MLCP + OFFICE + RETAIL ON GROUND
MLCP + RETAIL ON GROUND
MLCP + RETAIL ON GROUND
CONVENTION CENTRE
HOTEL MLCP + RETAILRETAIL + OFFICE + SERVICE APARTMENTS
RETAIL + OFFICE + SERVICE APARTMENTS
HOTEL BUS TERMINAL + DEPOT + RETAIL
PLANNING – DESIGN PROPOSAL
PROBLEMS
EXISTING NEHRU PLACE INTERNAL PLAZA
SOLUTIONS
PROPOSED RETROFITTING: INTERNAL PLAZA
PROBLEMS
EXISTING NEHRU PLACE INTERNAL PLAZA
SOLUTIONS
PROPOSED PLAZA WITH LIGHTING, SIGNAGE, etc.
PROBLEMS
EXISTING PARKING ON GROUND
SOLUTIONS
PROPOSED PUBLIC SPACE ON RECLAIMED SPACE
PROBLEMS
EXISTING BUS TRMINAL
SOLUTIONS
PROPOSED REDESIGN OF BUS TRMINAL
Multi Level Car Parking
NMT & pedestrain Infrastructure
Public spaces and Social Ammenities
New Commercial Development
Bus Terminal
474 Crores 30.34 Crores 103 Crores 485 Crores
21% -VE 146% 35%
Breakeven Period
8 yrs(473.65)4 yrs(119 Crores)
30%
FinancialViability Project Viable Unviable
347% 75%
98 Crores
-VE
NA
-VE
Unviable
-VE
NA NA
Project Viable Project Viable
Project Cost
Project IRR
Equity IRR
Terminal Development
& Management
Real Estate Development
& Management
DTCDDA
MANAGEMENT MODEL BY PPP
d
OPERATION & MAINTENANCEBus Terminal
98 Crores
Multi Level Car Parking
NMT & pedestrain Infrastructure
Public spaces and Social Ammenities
New Commercial Development
Project Cost 485 Crores
Project IRR146% 35%
Breakeven Period 4 yrs(119
Crores)
Equity IRR
FinancialViability
347% 75%
611 Crores
19%
28%
10 Yrs(617 Crores)
Project Viable
NA
Project Viable Project Viable
Parking & Public Space Management
?
Proposed Way Forward
• Creation of a multi stakeholder platform under the leadership of DDA• Constitution of a high level committee comprising of key stakeholders in the Nehru Place
project •UTTIPEC•SDMC•CPWD•DTC•DMRC
• To review and approve recommendations for the area• Facilitate implementation of the recommended interventions