+ All Categories

NetOR

Date post: 30-May-2018
Category:
Upload: kevin-punzalan
View: 218 times
Download: 0 times
Share this document with a friend

of 20

Transcript
  • 8/14/2019 NetOR

    1/20

    Operations Research

  • 8/14/2019 NetOR

    2/20

    PROJECT MANAGEMENT The Strategic Importance of Project

    ManagementScheduling large, often one-time projects is a

    difficult challenge to operations managers andis one of the 10 OM decisions. The stakes inproject management are high Millions of dollars in cost overruns have been wasted dueto poor planning on projects, unnecessarydelays have occurred due to poor scheduling,and companies have gone bankrupt due topoor controls.

  • 8/14/2019 NetOR

    3/20

    PROJECT MANAGEMENT The management of large projects involves

    three phases;2. Planning. This phase involves goal setting,

    defining the project, and team organization.3. Scheduling. This phase relates people,

    money, and supplies to specific activitiesand relates activities to each other.

    4. Controlling. Here the firm monitorsresources, costs, quality, and budgets. It

    also revises or changes plans and shiftsresources to meet time and cost demands.

  • 8/14/2019 NetOR

    4/20

    PROJECT PLANNINGProjects can be defined as a series of related tasks

    directed toward a major output. A projectorganization is developed to make sureexisting programs continue to run smoothly ona day-to-day basis while new projects aresuccessfully completed. The projectorganization works best when;

    2. Work can be defined with a specific goal anddeadline

    3. The job is unique or somewhat unfamiliar to

    the existing organization4. The work contains complex interrelated tasks

    requiring specialized skills5. The project is temporary but critical to the

    organization.

  • 8/14/2019 NetOR

    5/20

    PROJECT SCHEDULINGProject scheduling involves sequencing and

    allotting time to all project activities. At thisstage, managers decide how long eachactivity will take and compute how manypeople and materials will be needed at each

    stage of production.Managers also chart separate schedules for

    personnel needs by type of skill(management, engineering or pouring

    concrete).

  • 8/14/2019 NetOR

    6/20

    PROJECT SCHEDULING To summarize, whatever the approach taken

    by a project manager, project schedulingserves several purposes:

    2. It shows the relationship of each activity toothers and to the whole project

    3. It identifies the precedence relationshipsamong activities

    4. It encourages the setting of realistic timeand cost estimates for each activity.

    5. It helps make better use of people, money,and material by identifying criticalbottlenecks in the project

  • 8/14/2019 NetOR

    7/20

    PROJECT CONTROLLING

    The control of large projects, like the control of any management system, involves closemonitoring of resources, costs, quality, andbudgets. Control means using a feedback

    loop to revise the project plan and havingthe ability to shift resources to where theyare needed most.

  • 8/14/2019 NetOR

    8/20

    PROJECT MANAGEMENT TECHNIQUESProgram Evaluation and Review Techniques

    A technique to enable managers toschedule, monitor, and control large andcomplex projects by employing three timeestimates for each activity.

    Critical Path Method (CPM)A network technique using only one timefactor per activity that enables managers toschedule, monitor, and control large andcomplex projects.

    Critical Path The computed longest time path(s) througha network.

  • 8/14/2019 NetOR

    9/20

    TECHNIQUES

    PERT and CPM are important because they canhelp answer questions such as thefollowing about projects with thousands of activities:

    2. When will the entire project be completed?3. What are the critical activities or tasks in

    the project-that is, the ones that will delaythe entire project if they are late?

    4. Which are the noncritical activities-theones that can run late without delaying thewhole projects completion?

  • 8/14/2019 NetOR

    10/20

    PROJECT MANAGEMENT TECHNIQUES4. What is the probability that the project will

    be completed by a specific date?5. At any particular date, is the project on

    schedule, behind schedule, or ahead of schedule?

    6. On any given date, is the money spentequal to, less than, or greater than thebudgeted amount?

    7. Are there enough resources available tofinish the project on time?

    8. If the project is to be finished in a shorteramount of time, what is the best way toaccomplish this goal at the least cost?

  • 8/14/2019 NetOR

    11/20

    Network ConventionsIf the diagram had looked like the one following,

    both activities a and b would have to becompleted before activity c could begin, but aand b could be performed at the same time;performance of a is independent of performance of b.

    b

    a

    c

  • 8/14/2019 NetOR

    12/20

    Network Conventions

    If activity a must precede b and c, theappropriate network would look like this:

    a

    c

  • 8/14/2019 NetOR

    13/20

  • 8/14/2019 NetOR

    14/20

    Network ConventionsWhen two activities both have the same

    beginning and ending nodes, a dummy nodeand activity is used to preserve the separateidentity of each activity. In the diagram below,activities a and b must be completed beforeactivity c can be started.

    Dummy Activity/Broken Line

    a c

    b

  • 8/14/2019 NetOR

    15/20

    Example #1: Given the followinginformation

    11 wks

    3 wks

    6 wks

    1 wk

    9 wks4 wks

    8 wks

  • 8/14/2019 NetOR

    16/20

    Determine:

    a. The length of each pathb. The critical pathc. The expected length of the project

    d. Amount of slack time for each path

  • 8/14/2019 NetOR

    17/20

    Example #2:

    Compute the earliest starting time and earliestfinishing time for each activity.

  • 8/14/2019 NetOR

    18/20

    Example #3: The network diagram for a project is shown in

    the accompanying figure, with three timeestimates for each activity. Activity times arein months.

    b. Compute the expected time for each activityand the expected duration for each path.

    c. Identify the critical path.d. Compute the variance of each activity and the

    variance of each path.

  • 8/14/2019 NetOR

    19/20

    Diagram for Example #3

    2-4-6

    3-5-7

    4-6-8

    2-3-5

    5-7-9

    3-4-6

    3-4-5

    1-3-4

    2-3-6

  • 8/14/2019 NetOR

    20/20


Recommended