Pembuatan Direksi Kit
Start: Wed 27-05-15ID: 4
Finish: Fri 29-05-15 Dur: 3 days
Res:
Galian tanah untuk pondasi
Start: Mon 01-06-15ID: 7
Finish: Tue 09-06-15Dur: 7 days
Res:
Pengukuran dan pemasangan bouwplank
Start: Wed 27-05-15ID: 5
Finish: Fri 29-05-15 Dur: 3 days
Res:
Pembersihan lokasi pekerjaan
Start: Fri 22-05-15 ID: 3
Finish: Tue 26-05-15Dur: 3 days
Res:
PEKERJAAN TANAH GALIAN/ URUGAN PASIR DAN PONDASI
Start: Mon 01-06-15ID: 6
Finish: Mon 29-06-15Dur: 21 days
Res:
PEKERJAAN PEMBETONAN DAN PEMBESIAN
Start: Fri 26-06-15 ID: 14
Finish: Thu 16-07-15Dur: 15 days
Res:
PEKERJAAN DINDING
Start: Fri 03-07-15 ID: 25
Finish: Mon 21-09-15Dur: 57 days
Res:
PEKERJAAN PENDAHULUAN
Start: Fri 22-05-15 ID: 1
Finish: Fri 29-05-15 Dur: 6 days
Res:
Start: ID: 2
Finish: Dur:
Res:
Page 1
PEKERJAAN LANTAI
Start: Tue 22-09-15ID: 30
Finish: Fri 09-10-15 Dur: 14 days
Res:
PEKERJAAN ATAP
Start: Fri 24-07-15 ID: 33
Finish: Fri 14-08-15 Dur: 16 days
Res:
PEKERJAAN LANGIT-LANGIT / PLAFOND
Start: Mon 17-08-15ID: 42
Finish: Wed 26-08-15Dur: 8 days
Res:
Floor Drain
Start: Tue 22-09-15ID: 70
Finish: Tue 22-09-15Dur: 1 day
Res:
Kran air
Start: Tue 22-09-15ID: 69
Finish: Tue 22-09-15Dur: 1 day
Res:
Septictank
Start: Tue 22-09-15ID: 66
Finish: Tue 22-09-15Dur: 1 day
Res:
Page 2
PEKERJAAN SANITAIR DAN INSTALASI AIR
Start: Tue 22-09-15ID: 65
Finish: Thu 24-09-15Dur: 3 days
Res:
PEKERJAAN INSTALASI LISTRIK
Start: Thu 16-07-15ID: 58
Finish: Mon 20-07-15Dur: 3 days
Res:
PEK. KUSEN, DAUN PINTU DAN JENDELA
Start: Tue 07-07-15ID: 45
Finish: Wed 08-07-15Dur: 2 days
Res:
Pengecatan dinding
Start: Fri 25-09-15 ID: 74
Finish: Wed 30-09-15Dur: 4 days
Res:
Pengecatan Kusen
Start: Thu 01-10-15ID: 75
Finish: Thu 01-10-15Dur: 1 day
Res:
Bak Kontrol
Start: Fri 25-09-15 ID: 72
Finish: Fri 25-09-15 Dur: 1 day
Res:
Page 3
PEKERJAAN PENGECATAN
Start: Fri 25-09-15 ID: 73
Finish: Thu 01-10-15Dur: 5 days
Res:
Page 4
Pasangan pondasi batu bata
Start: Fri 12-06-15 ID: 11
Finish: Fri 12-06-15 Dur: 1 day
Res:
Pasangan pondasi batu kali
Start: Fri 12-06-15 ID: 10
Finish: Wed 24-06-15Dur: 9 days
Res:
Mengurug kembali bekas galian pondasi
Start: Thu 25-06-15ID: 12
Finish: Thu 25-06-15Dur: 1 day
Res:
Pondasi setempat (beton +besi +bekisting)
Start: Fri 12-06-15 ID: 16
Finish: Mon 15-06-15Dur: 2 days
Res:
Pemasangan Anstampeng
Start: Thu 11-06-15ID: 9
Finish: Thu 11-06-15Dur: 1 day
Res:
Urugan pasir bawah pondasi
Start: Wed 10-06-15ID: 8
Finish: Wed 10-06-15Dur: 1 day
Res:
Page 5
Page 6
Page 7
Page 8
Pek. Pemasangan bekisting Kolom 15/20
Start: Fri 03-07-15 ID: 21
Finish: Thu 09-07-15Dur: 5 days
Res:
Pek. Pembesian kolom 15/15
Start: Thu 02-07-15ID: 18
Finish: Thu 02-07-15Dur: 1 day
Res:
Urugan tanah menambah elevasi lantai
Start: Fri 26-06-15 ID: 13
Finish: Mon 29-06-15Dur: 2 days
Res:
Rabat beton
Start: Tue 30-06-15ID: 17
Finish: Tue 30-06-15Dur: 1 day
Res:
Pek. Pemasangan bekisting Kolom 15/15
Start: Fri 03-07-15 ID: 20
Finish: Tue 14-07-15Dur: 8 days
Res:
pembetonan Kolom 15/15
Start: Wed 15-07-15ID: 22
Finish: Wed 15-07-15Dur: 1 day
Res:
pembetonan Kolom 15/20
Start: Fri 10-07-15 ID: 23
Finish: Fri 10-07-15 Dur: 1 day
Res:
Pek. Pasangan 1/2 bata 1 : 5
Start: Tue 07-07-15ID: 27
Finish: Thu 23-07-15Dur: 13 days
Res:
Pek. Pasangan 1/2 bata 1 : 3 ( trasram )
Start: Fri 03-07-15 ID: 26
Finish: Mon 06-07-15Dur: 2 days
Res:
Pek. Pembesian kolom 15/20
Start: Thu 02-07-15ID: 19
Finish: Thu 02-07-15Dur: 1 day
Res:
Pekerjaan Sloof 15 x 20 (pembesian + pembetonan + bekisting)
Start: Fri 26-06-15 ID: 15
Finish: Wed 01-07-15Dur: 4 days
Res:
Page 9
Page 10
Kusen Pintu/ Jendela
Start: Tue 07-07-15ID: 46
Finish: Tue 07-07-15Dur: 1 day
Res:
Pemasangan titik stop kontak
Start: Thu 16-07-15ID: 59
Finish: Fri 17-07-15 Dur: 2 days
Res:
Page 11
Page 12
Pekerjaan Ringbalk 15x10 (pembesian +pembetonan + bekisting)
Start: Thu 16-07-15ID: 24
Finish: Thu 16-07-15Dur: 1 day
Res:
Page 13
Pek. Acian
Start: Fri 28-08-15 ID: 29
Finish: Mon 21-09-15Dur: 17 days
Res:
Pek. Plesteran 1 : 5
Start: Fri 24-07-15 ID: 28
Finish: Thu 27-08-15Dur: 25 days
Res:
Pemasangan Keramik lantai kamar mandi 20x20
Start: Fri 09-10-15 ID: 32
Finish: Fri 09-10-15 Dur: 1 day
Res:
Pemasangan Keramik 40x40
Start: Tue 22-09-15ID: 31
Finish: Thu 08-10-15Dur: 13 days
Res:
Pemasangan balok jurai dalam 8/12
Start: Wed 29-07-15ID: 36
Finish: Wed 29-07-15Dur: 1 day
Res:
Pemasangan usuk 5/7 , reng 2/3
Start: Fri 31-07-15 ID: 38
Finish: Wed 05-08-15Dur: 4 days
Res:
Pemasangan gording 8/12
Start: Thu 30-07-15ID: 37
Finish: Thu 30-07-15Dur: 1 day
Res:
Pemasangan balok jurai luar 8/12
Start: Wed 29-07-15ID: 35
Finish: Wed 29-07-15Dur: 1 day
Res:
Pemasangan kuda kuda kayu 8/14
Start: Fri 24-07-15 ID: 34
Finish: Tue 28-07-15Dur: 3 days
Res:
Page 14
Daun Pintu
Start: Thu 09-07-15ID: 49
Finish: Mon 13-07-15Dur: 3 days
Res:
Daun Pintu PVC
Start: Thu 09-07-15ID: 50
Finish: Thu 09-07-15Dur: 1 day
Res:
Pemasangan Kaca Jendela
Start: Tue 28-07-15ID: 52
Finish: Tue 28-07-15Dur: 1 day
Res:
Pemasangan doorholder Pintu
Start: Tue 14-07-15ID: 53
Finish: Tue 14-07-15Dur: 1 day
Res:
Pemasangan doorholder Pintu PVC
Start: Fri 10-07-15 ID: 54
Finish: Fri 10-07-15 Dur: 1 day
Res:
Pemasangan Kunci pintu
Start: Wed 15-07-15ID: 55
Finish: Wed 15-07-15Dur: 1 day
Res:
Pemasangan Grendel jendela
Start: Wed 29-07-15ID: 57
Finish: Wed 29-07-15Dur: 1 day
Res:
Pasang Kloset Jongkok
Start: Mon 28-09-15ID: 71
Finish: Mon 28-09-15Dur: 1 day
Res:
Pemasangan Engsel jendela
Start: Wed 08-07-15ID: 48
Finish: Wed 08-07-15Dur: 1 day
Res:
Daun Jendela
Start: Thu 09-07-15ID: 51
Finish: Mon 27-07-15Dur: 13 days
Res:
Pemasangan Engsel pintu
Start: Wed 08-07-15ID: 47
Finish: Wed 08-07-15Dur: 1 day
Res:
Pemsangan saklar tunggal
Start: Mon 20-07-15ID: 60
Finish: Mon 20-07-15Dur: 1 day
Res:
Pemasangan saklar ganda
Start: Mon 20-07-15ID: 61
Finish: Mon 20-07-15Dur: 1 day
Res:
Instalasi Air Bersih
Start: Mon 28-09-15ID: 68
Finish: Mon 28-09-15Dur: 1 day
Res:
Instalasi Air Kotor
Start: Tue 22-09-15ID: 67
Finish: Tue 22-09-15Dur: 1 day
Res:
Page 15
Page 16
Page 17
Pemasangan Talang seng BJLS 30 (leba 60cm)
Start: Thu 06-08-15ID: 39
Finish: Fri 07-08-15 Dur: 2 days
Res:
Pas. Plafond Gypsum 9mm
Start: Mon 24-08-15ID: 44
Finish: Wed 26-08-15Dur: 3 days
Res:
Pas. Rangka plafond
Start: Mon 17-08-15ID: 43
Finish: Fri 21-08-15 Dur: 5 days
Res:
Pemasangan Genteng
Start: Mon 10-08-15ID: 41
Finish: Fri 14-08-15 Dur: 5 days
Res:
Pemasangan listplank kayu 2/20
Start: Thu 06-08-15ID: 40
Finish: Fri 07-08-15 Dur: 2 days
Res:
Page 18
Pemasangan Grendel Pintu
Start: Thu 16-07-15ID: 56
Finish: Thu 16-07-15Dur: 1 day
Res:
Page 19
Page 20
Page 21
Pemasangan titik Lampu neon 10 watt Phillips
Start: Thu 27-08-15ID: 62
Finish: Fri 28-08-15 Dur: 2 days
Res:
Pemasangan titik Lampu neon 15 watt Phillips
Start: Mon 31-08-15ID: 63
Finish: Mon 31-08-15Dur: 1 day
Res:
Pemasangan titik Lampu neon 20 watt Phillips
Start: Tue 01-09-15ID: 64
Finish: Tue 01-09-15Dur: 1 day
Res:
Page 22
Page 23
Page 24
Critical
Noncritical
Critical Milestone
Milestone
Critical Summary
Summary
Critical Inserted
Inserted
Critical Marked
Marked
Critical External
External
Project Summary
Highlighted Critical
Highlighted Noncritical
Page 25
Project: networkdiagramayinDate: Fri 22-05-15