+ All Categories
Home > Documents > New Approach of Using Jacked Anchors as Reinforcements in … · ground anchor wall superimposed...

New Approach of Using Jacked Anchors as Reinforcements in … · ground anchor wall superimposed...

Date post: 16-Aug-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
15
* Jacked anchor is a patented technology by Specialist Grouting Engineers Sdn. Bhd. ICOF 2003. Dundee, Scotland, 2003 New Approach of Using Jacked Anchors as Reinforcements in Soil Stabilisation Works for a Cut-And- Cover Tunnel with 17m Deep Excavation Liew, S. S., Tan, Y. C., Ng, H. B. & Lee, P. T. Gue & Partners Sdn Bhd, Malaysia Introduction This paper presents the design, installation and performance of a proprietary SGE jacked anchor* system supporting both the contiguous bored pile (C.B.P.) wall and soldier pile wall for a cut-and-cover tunnel construction with a successful excavation depth down to about 17m. The design technique used in this stabilizing system lies in between the reinforced soil theory and the conventional prestressed ground anchorage design with Rankine or Coulomb earth pressure theory. As such, finite element program, PLAXIS, is deployed to model the soil-structure interaction of the jacked anchors and the overall stress and strain distribution of the retained soil mass. From the analyses, it is observed that the jacked anchor, in fact, stiffens and reinforces the retained soil mass to behave as semi rigid gravity structure, which is fairly similar to the conventional gravity wall. The shear strain distribution of the finite element mesh also indicates higher shear strain behind the reinforced soil mass. The instrumentation scheme has yielded some useful information revealing the actual behaviour of the reinforced soil mass in terms of wall movements, and the load transfer between the jacked anchor and the surrounding soil during jacking, pull out tests and excavation in front of the wall. From the observation of the initial pull out test results, the pull out capacity of the jacked anchor does not appear to be related to the effective overburden stress at the initial stage, rather its mobilised shaft resistance is constricted to a narrow range from 20kPa to 30kPa. However, the thixotropy effect of soil has shown increased pull out capacity of the jacked anchor with time, but remains constant after probably 120 days. The effective increase of pull out capacity is generally in the range of
Transcript
Page 1: New Approach of Using Jacked Anchors as Reinforcements in … · ground anchor wall superimposed over the interpreted effective pressuremeter (PMT) stiffness modulus, in which the

∗ Jacked anchor is a patented technology by Specialist Grouting Engineers Sdn. Bhd. ICOF 2003. Dundee, Scotland, 2003

New Approach of Using Jacked Anchors as Reinforcements in Soil Stabilisation Works for a Cut-And-Cover Tunnel with 17m Deep Excavation

Liew, S. S., Tan, Y. C., Ng, H. B. & Lee, P. T. Gue & Partners Sdn Bhd, Malaysia

Introduction This paper presents the design, installation and performance of a proprietary SGE jacked anchor∗ system supporting both the contiguous bored pile (C.B.P.) wall and soldier pile wall for a cut-and-cover tunnel construction with a successful excavation depth down to about 17m. The design technique used in this stabilizing system lies in between the reinforced soil theory and the conventional prestressed ground anchorage design with Rankine or Coulomb earth pressure theory. As such, finite element program, PLAXIS, is deployed to model the soil-structure interaction of the jacked anchors and the overall stress and strain distribution of the retained soil mass. From the analyses, it is observed that the jacked anchor, in fact, stiffens and reinforces the retained soil mass to behave as semi rigid gravity structure, which is fairly similar to the conventional gravity wall. The shear strain distribution of the finite element mesh also indicates higher shear strain behind the reinforced soil mass. The instrumentation scheme has yielded some useful information revealing the actual behaviour of the reinforced soil mass in terms of wall movements, and the load transfer between the jacked anchor and the surrounding soil during jacking, pull out tests and excavation in front of the wall. From the observation of the initial pull out test results, the pull out capacity of the jacked anchor does not appear to be related to the effective overburden stress at the initial stage, rather its mobilised shaft resistance is constricted to a narrow range from 20kPa to 30kPa. However, the thixotropy effect of soil has shown increased pull out capacity of the jacked anchor with time, but remains constant after probably 120 days. The effective increase of pull out capacity is generally in the range of

Page 2: New Approach of Using Jacked Anchors as Reinforcements in … · ground anchor wall superimposed over the interpreted effective pressuremeter (PMT) stiffness modulus, in which the

2

70% to 90%. This seems to imply that the jacking process of the jacked anchor had temporarily altered the effective stress field distribution of the surrounding soil around the anchor through displacing the soil. With time, the effect of thixotropy with overburden pressure will become prominent after excess pore water pressure dissipation. Comparisons of this support system with the adjacent prestressed anchor wall are also presented.

The project details To improve the infrastructure facilities, Malaysian government is constructing the Light Rail Transit (LRT) for the new government administrative centre, namely Putrajaya, in phases. Most of the LRT routes are at very close proximity to the existing government buildings and often require temporary shoring system for the excavation and to protect the neighbouring structures. This project involves construction of a temporary shoring system for a 17m deep excavation using φ750mm and φ900mm contiguous bored pile (CBP) wall and soldier pile (SP) wall with maximum five rows of prestressed ground anchorage support in the original design. Due to the close proximity to the buildings, the designed ground anchorages are inclined at steep angle with relatively short anchor length to avoid hitting the building foundation, which are only 8m away from the wall. Figure 1 shows the plan view of the CBP wall. Figure 1 Layout Plan of CBP Wall with Two Different Support Systems

However, due to the difficulties and slow progress in constructing these prestressed ground anchors using full casing method as specified, an alternative proprietary jacked anchor system was then proposed at areas where there is no encroachment of the alternative support system to the building foundation. The alternative support system consists of upper 7 rows of 18m long and lower 2 rows of 12m mild steel pipes as jacked anchors respectively spaced at 850mm to 1000mm centre-to-centre lateral spacing. These steel pipes were laterally installed by hydraulic jack in between the gaps of CBP wall and SP wall. Liew et al. (2000) and Cheang et al. (1999) have presented the details of the installation process for the same type of jacked anchor in two Malaysia sites.

Building Boundary

CBP Wall Soldier Pile Wall

Soldier Pile Wall

Jacked Anchors

Jacked Anchors

Ground Anchors

Page 3: New Approach of Using Jacked Anchors as Reinforcements in … · ground anchor wall superimposed over the interpreted effective pressuremeter (PMT) stiffness modulus, in which the

3

Site geology and subsoil conditions The project site was initially an undulating palm oil estate underlain by meta-sedimentary Kajang formations and some alluvial deposits consisting of sandy clayey silts at low-lying areas. Subsequent earthwork operation has deposited a fill of about 10m thick with SPT’N values ranging from 5 to 13. Beneath the fill is the sandy/clayey silt with average SPT’N values of 20. Slightly weathered schist is found at the depth of about 40m. It is also expected that shale with intercalation of foliated phyllite, graphitic schist, sandstone and quartzite can be found within this meta-sedimentary formation.

Figure 2 shows the borehole layout and profile of the site whereas the interpreted subsoil profile and the engineering properties of the respective soil stratum are summarised in Figure 3 and Table 1 respectively. The Young’s modulus profile of subsoils interpreted from pressuremeter test results is also presented in Figure 3. The groundwater as measured from the standpipe and during subsurface exploration was about at level RL21.8m, which is 12m below the retained ground level of RL34m.

Figure 2 Layout of Boreholes and Borehole Profile

BH

LR

T2-20

BH

LR

T2-19

HL

RT

2

BH

LR

T2-21

BH

LR

T2-22

BH

LR

T2-18

BHLRT2-11

BHLRT2-16A

BHLRT2-16

INC 3

Page 4: New Approach of Using Jacked Anchors as Reinforcements in … · ground anchor wall superimposed over the interpreted effective pressuremeter (PMT) stiffness modulus, in which the

4

Figure 3 Interpreted Subsoil Profile

Table 1 Engineering Properties of subsoil

Layer γbulk

(kN/m3)

γdry

(kN/m3)

φ′ (°)

c′ (kN/m2)

ψ (°)

E′ (kN/m2)

E′ur

(kN/m2) υur

1 18.0 14.0 30 4 0 11,130 33,380 0.2 2 18.0 14.0 32 4 2 24,500 73,500 0.2 3 18.5 14.5 32 4 2 45,390 136,170 0.2 4 19.0 15.0 34 5 4 133,500 400,500 0.2

Structural details For the purpose of FEM analyses, the structural properties of CBP wall, jacked anchor and ground anchor are tabulated in Table 2.

The maximum tensile and compressive structural working capacity of the jacked anchor is about 180kN whereas the structural tensile working capacity of the prestressed ground anchor is 125kN per PC strand (Grade 270 and 15.24mm diameter) with design safety factor of two.

Table 2 Engineering Properties of Structural Elements Structural Elements Axial Stiffness, EA Flexural Stiffness, EI φ900mm CBP wall 1.78×107 kN/m-run 9.018×105 kN-m2/m-run

Mild Steel Jacked Anchor (φ114mm, 4.5mm thk.)

3.173×105 kN/m-run 5.367×102 kN-m2/m-run

Ground Anchors 2.718×102 kN/PC strand -

Construction sequence The construction sequence of excavation, jacked anchor and prestressed ground anchor installation with the installation date is briefly presented in Figure 4.

0 10 20 30 40SPT'N

30

25

20

15

10

5

0

16 17 18 19 20Bulk Unit Weight (kN/m3)

0 40000 80000Young's Modulus (kPa)

0 20 40 60 80Atterberg Limits

LegendLL

PLMC

Layer 1 - Fill

(Clayey Silt)

Layer 2 - Clayey Silt

Layer 3 - Sandy Silt

Layer 4 - Sandy Silt

Page 5: New Approach of Using Jacked Anchors as Reinforcements in … · ground anchor wall superimposed over the interpreted effective pressuremeter (PMT) stiffness modulus, in which the

5

Figure 4 Construction Sequence, Excavation, levels of Jacked Anchor and Prestressed Ground Anchor

Page 6: New Approach of Using Jacked Anchors as Reinforcements in … · ground anchor wall superimposed over the interpreted effective pressuremeter (PMT) stiffness modulus, in which the

6

Test Results Many pull-out tests have been carried out at different time intervals after installation of the jacked anchors to verify the development of shaft resistance of the jacked anchors with time. The summarised results of all pull-out tests are presented in Figure 5. Not all pull-out tests have mobilised the ultimate capacity as they were only tested to 2.2 times the designated working pull-out capacity of the jacked anchors at various levels.

From Figure 5, the ultimate shaft resistance of all pull-out tests shows an obvious increasing capacity with time. This is primarily caused by the increase of effective radial stress surrounding the jacked anchor after dissipation of excess pore pressure induced by soil displacement during jacking process. It is also expected that the stiffness of the soil will increase indirectly in the similar manner. Tan et al (2001) have presented a methodology using cavity expansion method to assess the excess pore pressure response of a jacked anchor inclusion and its dissipation resulting in increase of pull-out capacity.

Figure 5 Mobilised Average Shaft Resistance with Time

Instrumentation In order to verify the design performance of both the alternative and compliance support systems, the following instruments as tabulated in Table 3 have been installed. Two instrumented sections have been installed at CBP wall using jacked anchor and prestressed ground anchor respectively for performance comparison.

0 5 10 15 20 25 30 35Time (Days)

0

510

15

20

25

3035

40

4550

55

6065

7075

80

85

90

Mo

bili

sed

Ave

rag

e S

haf

t R

esis

tan

ce (

kPa)

7.27

13.7

10.6

13.6

21.8

4.85

8.35

12.5

32

22.4

26.7

28.1

3

8

6.4

26.5

19.6

10.8

16.1

14.8

37.3

12

8.5

11.5

10

24

32.723.8

11

12.5

14.5

10.3

14.2

7.5

7.5

5.5

14

20.5

25

10

20.5

13.2

11.5

5

5.5

14

22

Pull Out TestsLevel 1Level 2 Level 3Level 4

Level 5 Level 6 Level 7 Level 8 Level 9

210 daysto

270 days

Note : Figures beside data points denotemobilised anchor head movement in mm

Page 7: New Approach of Using Jacked Anchors as Reinforcements in … · ground anchor wall superimposed over the interpreted effective pressuremeter (PMT) stiffness modulus, in which the

7

Table 3 Instrumentation Details Wall Type Instrument Location

Inclinometer

I2 in CBP Pile A48 I3 at 1m behind jacked anchors

Load Cell

LC3, LC5, LC7 and LC9 at anchor levels L3, L5, L7 and L9

Strain Gauge

Vibrating wire strain gauges along L4 and L7 jacked anchors

φ900mm CBP Wall with Jacked

Anchors

Settlement Marker 1m behind CBP wall Inclinometer I1 in CBP Pile A13

Load Cell LC2, LC3, LC4 and LC5 at anchor levels L2, L3, L4 and L5

φ900mm CBP Wall with Ground

Anchors Settlement Marker 1m behind CBP wall

Mobilised Shaft Friction on Jacked Anchors during Pull-Out Tests Strain gauges have been installed on the two selected jacked anchors at levels L4 and L7 to monitor the load transfer behaviour of the mobilized shaft resistance during jacking process and pull out test at various time intervals after installation as shown in Figure 6. As only one strain gauge was installed at each section of L4 jacked anchor, significant flexural effect can be expected to affect the strain gauge reading during jacking process. This has been verified during jacking the L7 jacked anchor, in which the coupled pair of strain gauges have indicated significant flexural effect in the jacked anchors. However, the flexural effect is much minimized during pull-out test. It was also observed that lower shaft resistance has been mobilised at the L4 jacked anchor as compared to the L7 jacked anchor. For the two instrumented jacked anchors, higher mobilized shaft resistance is observed at the middle segment of the anchor during pull out test. Most instrumented segments of jacked anchor indicate ultimate shaft resistance has been achieved when the head displacement of jacked anchor reaches 5mm to 10mm. Generally, the pull out load curves of the two instrumented jacked anchors show increasing trend with time indicating stiffer behaviour.

Load Cells It is observable that the jacked anchor loads at the anchor-to-wall connection increase drastically from the nominal lock-off load with the excavation depth except the lowest jacked anchor, in which there is no significant excavation after installation of the lowest jacked anchor as compared to other jacked anchors at higher levels. Another reason for that could be due to relatively stiff soil stratum at lower level. The average excavation depth at each excavation stage is about 1.8m. Figure 7 shows the variation of jacked anchor load with time.

Page 8: New Approach of Using Jacked Anchors as Reinforcements in … · ground anchor wall superimposed over the interpreted effective pressuremeter (PMT) stiffness modulus, in which the

8

Figure 6 Pull Out Test Results for Instrumented Jacked Anchors L4 and L7

Figure 7 Jacked Anchor Load with Time

As for the prestressed ground anchor, designated prestress loads have been applied to the respective ground anchors during lock-off. However, some ground anchors have shown reduction of prestress as in Figure 8, which could be due to creeping of the relatively short fixed anchor length and potential relaxation of prestress as a result of vertical movement of CBP piles under high vertical load component from the prestressed ground anchor.

0 50 100 150 200 250 300Time (Days)

0102030405060708090

100110120130140150

Loa

d (k

N)

Level 3 - FEM ResultsLevel 5 - FEM Results

Level 7 - FEM ResultsLevel 9 - FEM Results

Loading at Jacked AnchorsLevel 3Level 5Level 7Level 9

3rd layer : 5/01/2002Load cell :12/01/2002

5th layer : 19/01/2002Load cell : 29/01/2002

7th layer : 22/02/2002Load cell : 6/03/2002

9th layer : 27/03/2002Load cell : 28/03/2002

0 10 20 30Head Displacement (mm)

0

50

100

150

200

250

Pul

l-Out

Loa

d (k

N)

120

80

40

0

Sha

ft R

esis

tanc

e (k

N/m

2 )

Pull-Out TestTest 1 ( 5 Days)

15-Jan-2002Test 2 (14 Days)

25-Jan-2002Test 3 (21 Days)

1-Feb-2002

Pipe Shaft ResistanceTest 1 : A-BTest 1 : B-CTest 1 : C-DTest 1 : D-ETest 1 : E-FTest 2 : A-BTest 2 : B-CTest 2 : C-DTest 2 : D-ETest 2 : E-FTest 3 : A-BTest 3 : B-CTest 3 : C-DTest 3 : D-ETest 3 : E-F

VWS G - A VWSG - B VWSG - C VWSG - D VWSG - E VWSG - F

18m

6.0m 9.0m 12.0m 15.0m0.6m 3.0m

0 10 20 30Head Displacement (mm)

0

50

100

150

200

250

Pul

l-Out

Loa

d (k

N)

120

80

40

0

Sha

ft R

esis

tanc

e (k

N/m

2 )

Pull-Out TestTest 1 ( 6 Days)

04-Mar-2002Test 2 (14 Days)

12-Mar-2002Test 3 (24 Days)

22-Mar-2002

Pipe Shaft ResistanceTest 1 : C-DTest 1 : D-ETest 1 : E-FTest 2 : C-DTest 2 : D-ETest 2 : E-FTest 3 : C-DTest 3 : D-ETest 3 : E-F

VWSG - C VWSG - D VWSG - E VWSG - F1.6m 4.6m 7.6m 10.6m

Page 9: New Approach of Using Jacked Anchors as Reinforcements in … · ground anchor wall superimposed over the interpreted effective pressuremeter (PMT) stiffness modulus, in which the

9

Figure 8 Prestressed Ground Anchor Load with Time

Wall Movements The wall movements at both the jacked anchors and prestressed ground anchor walls have been monitored using the inclinometers installed inside the CBP wall. Figure 9 shows the monitored wall movements during various stages of excavation at both walls. The jacked anchor wall has moved about 35mm at the final excavation with relatively fixed toe embedment, whereas the prestressed ground anchor wall has moved about 46mm with the wall toe rotated, which implies the overall wall movement could be more and the more passive resistance at the wall embedment has been mobilized to maintain overall wall stability.

Figure 9 Wall Movements at Jacked Anchor Wall and Ground Anchor Wall

0 50 100 150 200 250 300Time (Days)

0

50

100

150

200

250

300

350

400

450

500

550

600L

oa

d (

kN

)

Level 2 - FEM Results

Level 3 - FEM Results

Level 4 - FEM Results

Level 5 - FEM Results

Loading at Ground Anchor

Level 2

Level 3

Level 4

Level 5

Load cell : 19/01/2002

Load cell : 20/03/2002

Load cell : 19/02/2002

Load cell : 22/02/2002

0 1 0 20 3 0 40

Wall Movement (mm)

2 6

2 4

2 2

2 0

1 8

1 6

1 4

1 2

1 0

8

6

4

2

0

Dep

th (m

)

M ea su red Wall De fle ct ionStage 1Stage 2Stage 3Stage 4Stage 5Stage 6Stage 7Stage 8Stage 9Fin al Sta ge

12

3

4

5

6

7

9

8

F

- FEM Wall Deflection at Each Stages 8

0 10 20 30 40 50

Wall Movement (mm)

Measured Wall DeflectionStage 1Stage 2Stage 3Stage 4Stage 5Final Stage

- FEM Wall Deflectionat Each Stage

1

3

2 4 5 F

1

Page 10: New Approach of Using Jacked Anchors as Reinforcements in … · ground anchor wall superimposed over the interpreted effective pressuremeter (PMT) stiffness modulus, in which the

10

Settlement Markers The ground settlement behind the CBP wall at various construction stages is shown in Figure 10. The ground settlement results indicate the performance of jacked anchor support system is far better than the prestressed ground anchor system. Generally, the ratios of ground settlement to wall movement of jacked anchor wall and ground anchor wall are 1.57 and 3.37 respectively.

Figure 10 Ground Settlement behind the CBP Wall

FEM modelling Two dimensional finite element method (FEM) with 6-node elements computer program “PLAXIS” was used to model and back-analyse the performance of the CBP wall supported by both jacked anchors and prestressed ground anchors. “Hardening Soil” model (Brinkgreve, 2002), which is suitable for residual soil, was used as soil model. The input parameters for the “Hardening soil” model are summarized in Table 1. The φ900mm CBP wall and jacked anchors were modelled as beam element whereas the prestressed ground anchors were modelled as elastoplastic spring node-to-node element for the free length and geotextile interface element for the fixed length. Interface elements were also applied to the wall-soil and anchor-soil contacts. In numerical modelling, the CBP wall was assumed as “wished-in-place” condition before the excavation started, and the undrained analysis incorporated with groundwater calculation was performed under 2-D plane strain condition for the expected short construction period. The axial and flexural stiffness of the respective structural elements are tabulated in Table 2.

Back-Analyses and discussions Figure 9 shows the lateral wall movements of the CBP wall supported by jacked anchors and prestressed ground anchors. In general, reasonably close agreement in the lateral wall movement profile of jacked anchor wall and prestressed ground anchor wall has been achieved during the back-analyses except at the final stage of excavation for the prestressed ground anchor wall where the wall movement is slightly underestimated. This could be due to the load relaxation and creeping of some prestressed ground anchors with time, particularly those at levels 2 and 3 as shown in Figure 8, that are not taken into account in the FEM

0 20 40 60 80 100 120 140

Time (Days)

160

150140130

120110100

90

807060

50403020

100

Set

tlem

ent

(mm

)

Ground Settlement atJacked Anchor Wall (Measured)

Jacked Anchor Wall (FEM Results)

Ground Anchor Wall (Measured)

Ground Anchor Wall (FEM Results)

Page 11: New Approach of Using Jacked Anchors as Reinforcements in … · ground anchor wall superimposed over the interpreted effective pressuremeter (PMT) stiffness modulus, in which the

11

modelling. Generally, the FEM results match well with the measured lateral wall movement profile in most excavation stages for both jacked anchor and ground anchor walls. On the other hand, ground settlement markers installed at about 1m behind the CBP wall indicate larger settlement magnitude compared to the FEM results as shown in Figure 10. Figure 11 shows the dimensionless plot of the analysed and measured ground surface settlement profiles as recommended by Clough & O’Rourke (1990). The maximum wall movement of CBP wall at final excavation is about 0.002H, which is tally well with the average maximum movement of cast-in-situ rigid wall on hard clay and sandy soil layers presented by Clough & O’Rourke (1990). However, Ou et al (1993) has also presented the ratio of maximum wall deflection to excavation depth in the range from 0.002 to 0.005 in numbers of deep excavation in Taipei basin.

Figure 11 Dimensionless Ground Surface Settlement Profile.

In Malaysia, it is a common practice to use correlation of Standard Penetration Test (SPT) to obtain both strength and stiffness parameters of the residual soils for geotechnical design, despite some researchers disagree one in-situ test can derive both strength and stiffness parameters. In this case study, the FEM back-analysis results show that effective Young’s modulus (E′) of the upper clayey silt and lower sandy silt subsoils are about 2150 SPT’N and 2600 SPT′N respectively. The first correlation agreed well with the correlation as proposed by Tan et al. (2002) for 27m deep excavation in the weathered meta-sedimentary formation, namely Kenny Hill formation. The suggested unloading/reloading stiffness (E′ur) used in the ‘Hardening Soil’ Model is about three (3) times of effective Young’s Modulus (E′). Figure 12 shows the back-analysed effective Young’s Modulus in the FEM analysis for the prestressed ground anchor wall superimposed over the interpreted effective pressuremeter (PMT) stiffness modulus, in which the back-analysed E′ is generally at lower bound of the interpreted pressuremeter stiffness modulus. Whereas the back-

0.2

0.15

0.1

0.05

0

ettlem

ent / E

xca

vation D

epth

(%

)

25 20 15 10 5 0

Distance from Wall / Excavation Depth

Clough & O’Rourke

(1990)

Page 12: New Approach of Using Jacked Anchors as Reinforcements in … · ground anchor wall superimposed over the interpreted effective pressuremeter (PMT) stiffness modulus, in which the

12

analysed E′ for the jacked anchor wall is generally about 30% more than that for the prestressed ground anchor wall. Figure 12 Interpreted E′ from SPT’N and Pressuremeter Test (PMT)

Figure 13 Soil Shear Strain within the Jacked Anchor Retaining System

30

25

20

15

10

5

0

Dep

th (m

)

0.0x100 3.0x104 6.0x104 9.0x104 1.2x105 1.5x105 1.8x105

Effective Young's Mudulus, E' (kPa)

LegendInterpreted E' (PMT)

Interpreted E' (SPT)

E' After Jacked Anchor Inclusion

Page 13: New Approach of Using Jacked Anchors as Reinforcements in … · ground anchor wall superimposed over the interpreted effective pressuremeter (PMT) stiffness modulus, in which the

13

From Figure 13, the shear strains within the reinforced soil mass as a result of jacked anchor inclusion are mostly less than 0.15%. There is a relatively larger shear strains ranging between 0.26% and 0.38% developed along the potential slip surface of the active zone behind the reinforced soil mass. This potential band of slip surface appears to suggest that the reinforced soil mass tends to slide laterally along the base under the huge active earth pressure behind the reinforced mass. The inclusion of jacked anchors has restricted the development of active zone within the reinforced soil mass. In accompany to the wall geometry and the potential failure mechanism, it is expected that huge shear force and flexural stresses would be induced at the embedded wall and the passive zone will be highly mobilized, particularly at the excavation level. In fact, the highest shear strain in the FEM analysis is actually located at the passive zone in front of the wall embedment.

Figure 14 Total Ground Displacement of the Jacked Anchor Retaining System

From the total ground displacement contour as shown in Figure 14, it can be observed that the reinforced soil mass has more displacement at the upper portion with gradually reduced trend towards the lower portion, in which the displacement is cumulative.

Conclusions and recommendations Based on the discussions in the earlier sections, the following conclusions can be made: i. The jacked anchor wall behaves as a semi reinforced soil wall with

better overall performance as compared to the prestressed anchored wall. Intensive soil-structure interaction can be observed between the soil and the jacked anchors. As a result, earth pressure immediately

Page 14: New Approach of Using Jacked Anchors as Reinforcements in … · ground anchor wall superimposed over the interpreted effective pressuremeter (PMT) stiffness modulus, in which the

14

behind the jacked anchor CBP wall is much less as compared to the one with prestressed ground anchors. This is because part of the resistance to the active zone within the reinforced area has been provided through the interfacial resistance of the jacked anchors before it is fully transferred to the wall. Therefore, it is conservative to use conventional Rankine or Coulomb earth pressure for assessing the bending stresses of the wall.

ii. Observable shearing zone, which could be developed into slip surface defining the failure mechanism of the retaining system forming the active wedge, has occurred behind the jacked anchor wall.

iii. There is significant thixotropy and stiffening effects after the jacked anchor installation, which significantly improve the overall performance of the wall. In this case study, there is an increase in stiffness by about 30%. Therefore, selection of design parameters shall take into consideration of such effect.

iv. The backed-calculated engineering parameters between the ground anchor wall and the jacked anchor wall can give indication of the stiffening effect.

v. The instrumentation and back-analyses have yielded very useful information in this study.

vi. Finite element method can be successfully deployed to analyse the complicated interaction of the entire soil-structure system and therefore to assess the ultimate and serviceability conditions of the retaining system.

There are also recommendations for the future research of this support system as follows: i. Strain gauges shall be installed in pairs at the jacked anchor section to

avoid flexural effect in the interpretation. ii. Settlement profile behind the wall and even behind the end of jacked

anchors shall be monitored to confirm the settlement trough above the active wedge, which could be a concern to the structures sit on top of the active wedge.

iii. More inclinometer results are needed behind the jacked anchors to indicate the formation of the active wedge.

iv. More researches on the generation of excess pore water pressure and its dissipation around and along the jacked anchor during inclusion to the retained soil shall be carried out to assess the set-up of interfacial resistance.

References 1. Brinkgreve, R.B.J. Plaxis- Finite Element Code for Soil and Rock Analyses-

Version 8, A.A.Balkema, 2002.

Page 15: New Approach of Using Jacked Anchors as Reinforcements in … · ground anchor wall superimposed over the interpreted effective pressuremeter (PMT) stiffness modulus, in which the

15

2. Cheang, W.L., Tan, S.A., Yong, K.Y., Gue, S.S,, Aw, H.C., Yu, H.T., Liew, Y.L. Soil Nailing of a Deep Excavation in Soft Soil, Proceedings of the 5th International Symposium on Field Measurement in Geomechanics, Singapore, Balkema, 1999.

3. Clough, G.W. and O’Rourke, T.D. Construction-induced Movements of In-situ wall, Proceedings, Design and Performance of Earth Retaining Structures, ASCE Special Conference, Ithaca, New York, 1990.

4. Liew S. S., Tan Y. C. & Chen C. S. Design, Installation and Performance of Jack-in-Pipe Anchorage System for Temporary Retaining Structures. GEOENG 2000, Melbourne, Australia, 2000.

5. Ou, C.Y., Hsieh, P.G. and Chiou, D.C. Characteristics of Ground Surface Settlement During Excavation, Can. Geotech. J., Vol.30. No.5 , 1993.

6. Tan S. A., Cheang W. L. Yong K. Y. & Dasari G. R. The resistance of jacked-in pipe inclusions in soft soil. International Symposium on Earth Reinforcement, IS Kyushu 2001, Fukuoka, Japan 14-16 Nov. 2001.

7. Tan Y. C., Liew S. S., Gue S. S. & Taha M. R. A Numerical Analysis of Anchored Diaphragm Walls for a Deep Basement in Kuala Lumpur, Malaysia. 14th South East Asia Geotechnical Conference, Hong Kong, 2002.


Recommended