New BC3 RF BuildingLIU-SPS 200 MHz RF power
upgrade
New proposed area : BC3
All main RF equipments around
Close to RF workshop
Take advantage of ‘nearly empty’ GT10 gallery to install 350 mm RF coaxial transmission linesEasiest path to the pit
Access through 929 RF workshop
Reserved place for BB3 transformers
if needed in the future to replace oil transformers to cast resin transformers
Close to BA3 + BB3 = BC3
La dalle pour nouveaux transformateurs 28m x 4m
BAE3 PhilipsBA3 Siemens
RF Faraday Cage
BB3800 MHz
929 RFworkshop
BC3 New RF Amplifiers
GT10 Gallery
Total surfaces: Basement : 19.5 m x 36.5 m = 710 m2 Mezzanine : 475 m2 Total = 1185 m2
Total surfaces for RF: Basement = 550 m2 Mezzanine = 475 m2 Total = 1025 m2
RF amplifiers :
Tubes solution : 1030 m2 Tubes & combiners = 330 m2 Drivers & controls = 200 m2 Power supplies = 300 m2 Cooling = 200 m2
SSA solution : 1185 m2 SSA = 825 m2 Controls = 180 m2 Power supplies & cooling = 180 m2
Surfaces
36.5 m
19.5 m
Schedule2011 2012 2013 2015 2016 2017 20192014
StudiesTendering
ConstructionInstallation
CommissioningStart up
2018
StudiesConstruction
coaxial lines, Pickups
New power couplers
Cavities
Pickups
vacuumCV, EL
StudiesAuthorizatio
nsConstruction
Services (CV, EL) #2
Spare sections
LLRF Design and proto
LLRF TestsLLRF Series
New RF Building
LSS3 Tunnel Integration
New RF Power Amplifiers and LLRF
2012 : Authorizations
2013 : Construction, NOT linked with LS1
Building ready end 2014 before first amplifier installation
Services ready six months later for commissioning
BudgetItem Staff
FTE yearsTotal price
(FSU included) kCHF
Building Civil Engineering(Michael Poehler)
Basement (30 x 30) m2 x 4000 CHF/m2
First floor (15 x 30) m2 x 2000 CHF/m2
2.5 4’500
Building Ventilation(Mauro Nonis, based on Isolde last study)
1.5 1’000
Electrical Network High Power(Joel Lahaye)
Study, documentations, HV transformers 2 x 2 MVA, HV
cubicles, HV cabling, HV accessories
1.5 800
RF Power Amplifiers(including: RF power, Cooling, HVPS, Controls)
800 kW cw (1600 kW pulsed) x 5.0 CHF/W
(based on 800 MHz 2010 prices, 5.5 CHF/W for 60 kW, not including
combiners)
(RF power) 6.0(HVPS) 1.5
(CV) 2.5(RF Controls) 1.5
11’500
Coaxial lines 2 x 25 x 6 m x 6500 CHF/6m 1.0 500
Cavities modifications 4 x 150 kCHF + 2 x 100 kCHF 2.0 800
Main power Couplers 10 x 100 kCHF 2.0 1’000
Beam Control 2 x 700 kCHF 3.0 1’400
Total 28 26’500
Initial estimate (all inclusive)
Basement 900 m2 + Mezzanine 450 m2 = 4’500 kCHF / 2.5 FTE
CV & EL = 1’800 kCHF / 3.0 FTE
Total = 6’300 kCHF / 5.5 FTE
Building will be a bit smaller, budget difference will be useful for ‘un-scheduled’ issues
Dep-Group Persons
BE-RF
Eric Montesinos, Thomas Bohl, Wolfgang Höfle, Urs Wehrle, Elena Shaposhnikova, Philippe Baudrenghien, SPS power team
BE-ABP Patrick Bestmann, Yannis Papaphilippou
BE-ASR Paula Carvalho Correia, Emmanuel Paulat
BE-BI Christian Boccard, Patrick Odier
DGS-SEE Guillaume Fontana, Cécile Pinto
EN-CV Michel Obrecht, Mauro Nonis
EN-ELGuillaume Gros, Joël Lahaye, Christophe Crombez
EN-HE Caterina Bertone, Pascal Brunero, Serge Pelletier, Yann Seraphin
Teams in charge
EN-MEF Frédéric Galleazzi, Yvon Muttoni, David McFarlane
GS-SELuz-Anastasia Lopez-Hernandez, Evelyne Crocci-Torti, Antoine Kosmicki
TE-VSC Paolo Chiggiato, Antonio Mongelluzzo
TE-MSC Jérémie Bauche