+ All Categories
Home > Documents > New DQLPU type A

New DQLPU type A

Date post: 24-Feb-2016
Category:
Upload: marla
View: 31 times
Download: 0 times
Share this document with a friend
Description:
TE-MPE-EP. New DQLPU type A. TE-MPE-EP, VF, 23-Nov-2012 . Production of 1300 new protection units. TE-MPE-EP. Why a new DQLPU type A?. To improve protection of 1232 dipole magnets thanks to : Integration of the enhanced quench heater supervision - PowerPoint PPT Presentation
Popular Tags:
17
TE-MPE-EP New DQLPU type A Production of 1300 new protection units TE-MPE-EP, VF, 23-Nov-2012
Transcript
Page 1: New DQLPU  type  A

TE-MPE-EP

New DQLPU type A

Production of 1300 new protection units

TE-M

PE-E

P, V

F, 23

-Nov

-201

2

Page 2: New DQLPU  type  A

TE-MPE-EPTE

-MPE

-EP,

VF,

23-N

ov-2

012

Why a new DQLPU type A?

• To improve protection of 1232 dipole magnets thanks to:

Integration of the enhanced quench heater supervision Compatibility with new fully redundant linear power supplies

• Remote commands,…

Page 3: New DQLPU  type  A

TE-M

PE-E

P, V

F, 23

-Nov

-201

2

DQLPU: old / new configuration

SYKO DQQDL#A DQQDL#B DQAMC

Fip connector Current front view

New front view

External linear DC power supplies

Fip connector

Programming connector

x 1300

Page 4: New DQLPU  type  A

Internal hardware change in the new implementationTE

-MPE

-EP,

VF,

23-N

ov-2

012

Motherboard (viewed from inside): 1300 boards to be produced

DQQDL#A DQQDL#B DQCSU SPARE DQHSU DQAMC

DQAMC: • Communication board to

the supervision.• 100 boards to be

produced.

FIP con./PROG.

V taps Voltages power supplies DQHSU Input signals UHDS+trigger and Spare I loop in/out

Re-use local quench detector

Crate supervision unit:• Supervise all

voltages. • Test presence of

the current loop. • Remote power

cycling. • 1350 boards to be

produced.

For future upgrades

Quench heater supervision unit. • DQHDS voltage

measurement.• Fast current and

voltage recording during a discharge of DQHDS through the Heaters.

• 1350 boards to be produced.

Fip connector + DQAMC• reprogramming connector and future

nanoFip board emplacement. • 1350 boards to be produced.

Page 5: New DQLPU  type  A

TE-MPE-EPTE

-MPE

-EP,

VF,

23-N

ov-2

012

Why during LS1?

What are the risks and/or the impact if not done during LS1?

• More physical interventions will be necessary due to more SEUs on uFip circuits (higher energy).

• Risk of not detecting fault in quench heaters.

To take advantage of this long shutdown • To improve the reliability of this equipment. E.g. fully redundant power

supplies. • To have more diagnostic tools such as the state of the quench heaters or to

localise a interruption of the quench loop current . • To save some physical interventions by some remote commands. Remark: Old DQLPU_A is highly dependable. Might be difficult to reproduce this dependability, given the increased complexity of the new system.

Page 6: New DQLPU  type  A

TE-MPE-EPTE

-MPE

-EP,

VF,

23-N

ov-2

012

Production of DQPLUs• Starts beginning of

February

Final Assembly• Starts in June

Final Tests• July→December

Reinstallation• January 2014• 2 sectors• See LS1

schedule Rev 1.5

300 crates ready by 01/2014:9 racks/day45 racks/week4weeks/sector

Timeline

Page 7: New DQLPU  type  A

ManpowerTE

-MPE

-EP,

VF,

23-N

ov-2

012

External

AGH Poland: 2 people (WP n.3)Assembling crates and working on the test bench

BE-OP: 1 personSupport for the programmation of the test bench for DYPBs (yellow racks)

Internal(EP section)

- Design- Type tests- Firmware- Upgrade QPS Low Level supervision (see Jens’s presentation)- Procurement of components- Definition of test benches- Production of test benches

Identification of missing ressources: Ressources as usual very tight

Page 8: New DQLPU  type  A

Resources from other MPE sections:

New DQLPUType A

EMProduction of

circuits boardsAssembling of

Boards Mechanical drawings

Routing of some cards

MSSoftware analysis

tools:Quench heater data analysis

Post-operational check sequences

Device configuration

database

PESupport for

re-commissionin

g the LHC

EECommon

operation on the yellow racks: test

benchDefinition of

interface between

DQLIM and DQLPU

Page 9: New DQLPU  type  A

Resources from other groups:

New DQLPUType A

TRANSPORT

See Bruno’s talk

CABLINGEN-EL:

Fieldbus network upgrade

Electricity network

Extension cables

CONTROLSUpgrade of

QPS supervision

(see Jens’talk): BE-CO, EN-ICE, BE-OP

Page 10: New DQLPU  type  A

Potential issues

Company orders from internal purchaseservices may not be delivered

Building 281not ready on time

Late delivery components

Conflict with other activities (CSCM, LINAC4)

TE-M

PE-E

P, V

F, 23

-Nov

-201

2

Page 11: New DQLPU  type  A

Safety measures

• Personal safety:

Bd.281: standard procedure like any other laboratory space. No particular risk to test the DQLPUs, except for the Hipot test at

2.5KV, which will require H1T/H2T habilitation.Safety inspection required with EE (Mathieu) for the machine tools and

mechanics space.

• Tunnel equipment:

As usual, but access only required for uninstallation and reinstallation. All the DQLPUs must be cleared by RP before taking them out and NO

destructive operation foreseen on the reused equipment. That means no soldering work on them.

TE-M

PE-E

P, V

F, 23

-Nov

-201

2

Page 12: New DQLPU  type  A

What SW tools are planned to be used? Are they ready to be used? Who will provide them?

Before installation

• Firmware DQLPU + all circuits boards: EP (internally)

• Test bench: DQLPU functional tester: EP --> LabWindows/CVI

• Functional test DYPB: BE-OP>LabVIEW

• Working progress

After installation

• QPS console (QPS expert): Java: managed by BE-OP, EN-ICE

• QPS high level supervision(PVSS): EN-ICE

• Configuration database: MS section

• Post operational checks: to be defined but probably MS section

• Analysis of Quench heater data: to be defined, but probably by MS or PE section (in Java or LabVIEW)

SW tools

TE-M

PE-E

P, V

F, 23

-Nov

-201

2

Page 13: New DQLPU  type  A

Questions

• Is there any benefit to further automate the process of your tasks (testing, commissioning)? YES

What would be the effort implied?

– Automatic tools for commissioning IST. E.g. interlock tests. To be defined.– Current tools already done in LabVIEW but might be better to move them to Java.– Work package for MS section (to be defined).

• What is the long term strategy regarding to maintainability of testing equipment and related software?

– Test benches will be maintained by EP section (Building 281). – Tools for system exploitation: there are still LabVIEW and Java based tools: common strategy to be defined

to have a unique platform. • Do you foresee other potential showstoppers? (Like delay for supplying components, administrative constraints..).

– Implementation of the power supplies redundancy in DQLPU type B: to be done on-site (no external resource).– In case of problems it must be understood that the DQLPU upgrade and the R2E activities are critical for the

restart of the machine (priority must be given).– Other less critical tasks may be delayed if necessary, during Christmas shutdown for instance.– FinanceTE

-MPE

-EP,

VF,

23-N

ov-2

012

Page 14: New DQLPU  type  A

Current status for new boards

Motherboard

EP design starts week 48(Spyros)

Waiting for a third quote for

5200+2600 press-fit connectors

(Nicolas)

DQCSU

EP design starts week 48(Vincent)

Protype for all Analog and digital stages done and tested (Reiner)Major part of components

ordered

DQHSU

Almost ready to launch the production

Second protype tested and approved

(Jens/Reiner) Major part of

components ordered

Extension board

EP design starts week 50(Vincent)

Type test doneVery basic board

Tim

e fra

me

Actio

n al

read

y ta

ken

TE-M

PE-E

P, V

F, 23

-Nov

-201

2

Page 15: New DQLPU  type  A

Current status for re-used boards

DQAMCRe-use all old DQAMC +

200 spares in the pipeline

New firmware (EP)

DQQDLRe-use all old DQQDL +

200 new ones to be tested (Nicolas)

New firmware (EP)

TE-M

PE-E

P, V

F, 23

-Nov

-201

2

Page 16: New DQLPU  type  A

Current status for mechanical enclosures

All parts, but

Tender form sent week 46Standard delay: 4 weeks

ATOS: 10 prototypes end of January

Backpanel

To be designed

EM: week 49

TE-M

PE-E

P, V

F, 23

-Nov

-201

2

Page 17: New DQLPU  type  A

Current status for connectors for mechanical enclosures

Harting Han

32B/42Prototype of

matrix (set of 32 pins linked together)Week 48

Waiting for a quote for 2600

connectors(EE/EP)

Harting Han E

modulesPrototype of

matrix (set of 6 pins linked together)Week 48

Waiting for a quote(EP)

Burndy 12

5200 pieces

Waiting for a quote.

(Nicolas)

Harting Q12

Transmission of signals from current

pulses transformers to the motherboard.

Tests to be performed to verify the quality of

the transmission of signals before

acceptance

If not concluding, BNC

connectors would be the

alternative

Tim

e fra

me

Actio

n al

read

y ta

ken

TE-M

PE-E

P, V

F, 23

-Nov

-201

2


Recommended