+ All Categories
Home > Documents > New Moran Nov. 15 report

New Moran Nov. 15 report

Date post: 02-Jun-2018
Category:
Upload: vtburb
View: 218 times
Download: 0 times
Share this document with a friend

of 51

Transcript
  • 8/10/2019 New Moran Nov. 15 report

    1/51

  • 8/10/2019 New Moran Nov. 15 report

    2/51

  • 8/10/2019 New Moran Nov. 15 report

    3/51

    New Moran, Inc.

    PO Box 8502

    Burlington, VT 05402

    MoranPlant.org

    steel columns for tenant use optimization, and providing current, safe access to the roof

    areas for public viewing. NMI expects to contract with EV for both Civil and Structural

    Engineering services.

    c. NMI contracted historic preservation consultant Emily Wadhams to review conceptual

    designs with regards to the Secretary of the Interior's Standards for Rehabilitation,

    confirm the suitability of the project for Rehabilitation Investment Tax Credits (RITC), and

    produce a preliminary report for review and approval by the Vermont Division for Historic

    Preservation and the National Park Service. While this scope was not required in NMIsMOU with the City until March, it proved to be a critical path component of thorough

    diligence with regards to both design and financing.

    d. John Sandor, the National Park Service (NPS) reviewer for the State of Vermont, visited

    the site on October 30th with Caitlin Corkins, the tax credit reviewer for the Vermont

    Division for Historic Preservation. Following this visit, NPS assessed NMIs preliminary

    plans with regard to the feasibility of receiving the Federal Rehabilitation Investment Tax

    Credit (see Addendum C). The results of this preliminary review letter are encouragingwith respect to tax credit feasibility. Despite the positive preliminary review, significant

    evaluation and design work are still ahead. In particular, the ability to achieve net-zero

    energy use will be particularly challenging to complete within traditional NPS guidelines.

    NMI has arranged for a comprehensive engineering and design study to address these

    variables.

    e. Pending the completion of the predevelopment diligence phase of the project, NMI will

    resume schematic design with SBA in December, 2014, in line with anticipated

    submission of permit applications in March, 2015.

    2. Conceptual Site Plan

  • 8/10/2019 New Moran Nov. 15 report

    4/51

    New Moran, Inc.

    PO Box 8502

    Burlington, VT 05402

    MoranPlant.org

    3. Development Budget

    a. Sources (Addendum E):

    i. Specific requests for City infrastructure investment

    1. $6.3M of TIF Allocation as approved by public vote in March, 2014.

    2. As part of the diligence completed in the last eight months, NMI is

    confident the landscape surrounding Moran on the northern waterfront

    represents an essential piece of creating a viable and vibrant campus for

    the Moran Plant, surrounding stakeholders and the public at large. Inaccordance, we have reflected an additional $2,854,187 within the NMI

    project budget to complete a combination of $230,000 in environmental

    remediation and $2,624,187 in site work and landscape architecture for

    the proposed site and public green space immediately surrounding the

    Moran building. The current sources for this work are charitable

    contributions and the resulting tax credit equity; our existing budget

    includes no additional City sources above $6.3M in TIF. If additional TIFor City funds were available for infrastructure investment, a cost share of

    the $2,854,187 necessary complete the undeveloped waterfront acreage

    surrounding Moran would leverage tax credit investment, reduce strain on

    the Moran Plant operations, and increase the creditworthiness of NMI.

    Please refer to Addendum D for proposed site boundaries, and proposed

    terms in Section 4, and Section 6 for discussion of operating reserves.

    b. Uses (Addendum E)

    4. Financing Plan

    a. Credit Enhancement Assumptions:

  • 8/10/2019 New Moran Nov. 15 report

    5/51

    New Moran, Inc.

    PO Box 8502

    Burlington, VT 05402

    MoranPlant.org

    and reserve funding formulas. The funds would be advanced at construction

    closing, and administered by an agreed-upon agent acting as a fiduciary on

    behalf of all the sources of financing.

    ii. Regarding any shared additional infrastructure investment discussed in Section

    3, the funds would offset existing sources for site work and environmental

    remediation. Pending an agreement with the City, those offset sources would

    create additional operating reserves and reduce required debt service carried by

    NMI. City funding would be requested in a similar fashion to the alreadyapproved TIF funds, as described above.

    c. Capital Fundraising Campaign Plan and updated milestones are detailed in Addendum

    F.

    5. Operating Budget & Pro Forma (see Addendum G)

    6. Determination of sufficient operating reservesa. The Development Budget (Addendum E) indicates an Operating and Lease-Up Reserve

    of $1.7M. As detailed in Addendum G, this reserve is adequate to capitalize

    approximately $1M in anticipated expenditures during years 1-5 of operation, plus a

    reserve equaling approximately one year of additional building operating expenses and

    the required distributions to the historic tax credit investor.

    b. The existing reserve detailed in Addendum E is, by our determination, the minimum

    viable amount without which we would reduce the scope of the project.

    c. The challenge of securing sufficient operating reserves and additional capital investment

    is an area of focus for the team. While elements of the project could be downsized to

    reduce total expenditure, NMTC and RITC funding provides direct leverage of

    $ $

  • 8/10/2019 New Moran Nov. 15 report

    6/51

    New Moran, Inc.

    PO Box 8502

    Burlington, VT 05402

    MoranPlant.org

    McArdle joined RP after thirteen years at the Vermont Community Foundation. McArdle

    assumed the lead role on the Moran project in August, while Richard Russell worked

    directly with prospective leadership donors.

    b. After more than seven months of research, prospect identification and fundraising visits,

    RP is confident in the ability to attract a total of $11M in charitable support for the Moran

    Plant redevelopment. The summary, conclusions and a gift structure for the campaign

    are attached (see Addendum I).

    8. Ground Lease and Property Tax Liability Assumptions (see Addendum J).

    9. Updated Project Schedule (see Addendum K).

    a. To date, NMI has tracked on schedule across the board.Following the delivery of this

    report, NMI will work with CEDO and the Mayor's Office to review a term sheet for City

    Council approval in January, followed by Development Agreement approval in March,

    2015. Simultaneously, we anticipate resuming schematic design with our design team inDecember, 2014, in line with anticipated submission of permit applications in March,

    2015. This puts NMI on track for a construction start in Spring 2016 and a grand opening

    in Spring, 2017.

    10. Letters of interest for project funding from a CDE for NMTC (see Addendum L).

    a. After preliminary discussion with multiple CDEs beginning in October, 2013, NMI

    retained the Washington, DC based The Binnick Group (TBG) in August to evaluate the

    availability of NMTC allocation from national CDEs. TBG reviewed the Moran Plant

    project to date, and developed a comprehensive Sell Sheet, which was distributed to

    seven CDEs across the country including Housing Vermonts Vermont Rural Ventures.

    $

  • 8/10/2019 New Moran Nov. 15 report

    7/51

    New Moran, Inc.

    PO Box 8502

    Burlington, VT 05402

    MoranPlant.org

    iii. A separate review was completed with the Flynn Center with regards to operating

    expenses. The Flynn campus is within 10% of the projected square footage of

    Moran, and represents similar use classes across their properties. Projected

    Moran expenses are proportionally appropriate to those of the Flynn Center, with

    some revisions made and an additional contingency included.

    c. While not a traditional market study, this review provided a representative evaluation of

    rent and occupancy assumptions given projected tenant mix on the Moran site. The

    conclusions from these three reviews, with discussion and subsequent revisions to theoperating model, are attached as Addendum M.

    12. Proposed Tenant Mix

    a. NMI continues to engage significant interest from prospective tenants and in multiple

    cases is advancing in-depth dialogue with regard to lease, terms, and intent. Multiple

    Letters of Intent are currently under negotiation, representing approximately 40% of

    annual operating revenue. The attached occupancy schedule (see Addendum N),reflects these dialogues and terms.

    13. Preliminary Review with Planning & Zoning Staff

    a. NMI initiated a review with Sandrine Thibault on June 4th, 2014, and completed a

    preliminary review with the Burlington Department of Planning & Zoning on October

    14th, 2014. Those present included Director David E. White, Zoning Administrator Ken

    Lerner, and Senior Planners Mary ONeil and Scott Gustin.

    b. Based on the October 14th review, NMI began a comprehensive Public Trust Doctrine

    investigation with legal counsel at Dinse Knapp McAndrew. Research began with a

    focus on the Public Trust Doctrine under Vermont State statute and case law and, more

  • 8/10/2019 New Moran Nov. 15 report

    8/51

    ADDENDUM A

    Champions Council

  • 8/10/2019 New Moran Nov. 15 report

    9/51

    New Moran, Inc.

    PO Box 8502

    Burlington, VT 05402

    MoranPlant.org

    Champions Council for the Moran Plant

    From the initial conception of the New Moran concept, we have received extraordinary support for the

    project from a number of business-owners and community leaders, which prompted the assembly of a

    team of ambassadors and advisers that we call our Champions Council.

    The Champions Council is a collection of community leaders willing to lend their name in support of thenon-profit New Moran, Inc. and the redevelopment of the Moran Plant.

    We are have asked for support, both on a letterhead and in everyday conversation, from individuals

    who offer perspective, bring gravitas, and demonstrate a range of support for the project. There is no

    fiduciary or governance responsibility associated with this role.

    We have asked all Champions to make a charitable contribution towards the project of an amount that

    is meaningful for them at this point in the project, and that amount has varied for each champion. The

    intended term of this support is through the opening of the building, Spring 2017, though the role is at

    the discretion of each individual.

    TheChampions Council includes:

    ! Benjy Adler, Skinny Pancake

    ! Jill Badalato, Dealer.com;

    ! Brian Boardman, Hickok and Boardman Real Estate;! Paul Bruhn, Preservation Trust of Vermont;

    ! Alex Crothers, Crothers Management Group;

    ! Marguerite Dibble gametheory;

  • 8/10/2019 New Moran Nov. 15 report

    10/51

    ADDENDUM B

    Conceptual Building Design

  • 8/10/2019 New Moran Nov. 15 report

    11/51

  • 8/10/2019 New Moran Nov. 15 report

    12/51

  • 8/10/2019 New Moran Nov. 15 report

    13/51

  • 8/10/2019 New Moran Nov. 15 report

    14/51

  • 8/10/2019 New Moran Nov. 15 report

    15/51

  • 8/10/2019 New Moran Nov. 15 report

    16/51

  • 8/10/2019 New Moran Nov. 15 report

    17/51

  • 8/10/2019 New Moran Nov. 15 report

    18/51

  • 8/10/2019 New Moran Nov. 15 report

    19/51

  • 8/10/2019 New Moran Nov. 15 report

    20/51

    ADDENDUM C

    National Park Service Review

  • 8/10/2019 New Moran Nov. 15 report

    21/51

    Emily Wadhams

    Historic Preservation Consulting

    !"#So. Prospect St.Burlington, Vermont $!%$&

    Tel: '$(.)!'."!*! cell: '$(.''&.##(&[email protected]

    "#$%&'(""$)

    *$"+, %-./01/2 34 5678

    "9, :;/ ">??/2

    "BA :2-BA/C1/2D

    E#9', +0>=F G

  • 8/10/2019 New Moran Nov. 15 report

    22/51

  • 8/10/2019 New Moran Nov. 15 report

    23/51

  • 8/10/2019 New Moran Nov. 15 report

    24/51

    ADDENDUM D

    Conceptual Site Plan

  • 8/10/2019 New Moran Nov. 15 report

    25/51

  • 8/10/2019 New Moran Nov. 15 report

    26/51

    ADDENDUM E

    Development Budget

  • 8/10/2019 New Moran Nov. 15 report

    27/51

    Addendum E - New Moran - Development Budget11/14/2014 % of Total C

    Sources Of Funds Equity

    Federal Historic Tax Credit (RITC) 4,106,019 12%

    State Historic Tax Credit 250,000 1%

    New Markets Tax Credit (NMTC) 9,586,007 29%

    Senior Loan 1,875,000 6%

    Charitable 11,000,000 33%

    TIF Allocation 6,300,000 19%

    Total Sources: 33,117,025 100% $

    Uses of Funds

    Acquisition Environmental Remediation 230,000 1%

    Closing Costs 65,000 0%

    Total Acquisition Cost 295,000 1% $

    Hard Costs

    Building Reconstruction 8,791,344 27%

    Building Additions 3,397,808 10%

    Demolition 545,058 2%

    Site Work & Landscaping 2,624,187 8%Contingency & Escalation 3,071,679 9%

    FFE - Public Spaces & Tenant Space Allow 300,155 1%

    Living Machine 230,000 1%

    Energy Production/Upgrades 1,320,372 4%

    IT Infrastructure 100,000 0%

    Tenant Fit-Up - Allowance 2,491,920 8%

    Total Hard Costs 22,872,524 69% $

    Design Architectural & Engineering 1,179,792 4%

    Civil Engineering 117,920 0%

    Commissioning 60,031 0%

  • 8/10/2019 New Moran Nov. 15 report

    28/51

    Other Soft Costs

    Accounting & Audit 80,000 0%

    Capital Campaign 145,000 0%

    Clerk of the Works 75,000 0%

    Community Engagement 75,000 0%

    Legal 900,000 3%

    Marketing & Market Studies 85,000 0%

    Permit Fees 424,737 1%

    Program Development & Administration 260,000 1%Project Management & Financial Admin. 350,000 1%

    Property Management 40,000 0%

    Testing 25,000 0%

    Contingency 125,000 0%

    Total Other Soft Costs 2,584,737 8% $

    Financing, Reserves & Carrying Charges

    Reserves

    NMTC Reserves 1,338,924 4%Operating/ Lease-Up Reserves 1,730,000 5%

    Financing

    Construction Period & Bridge Loan Interest 878,954 3%

    Loan Fees & Expenses 125,000 0%

    NMTC Audit & Fees during Const 17,500 0%

    Carrying

    Builders Risk & Liability Insur 112,000 0%

    Maintenance & Security 27,000 0%

    Utilities 18,000 0%Taxes 0%

    Total Financing, Reserves & Carrying 4,247,378 13% $

  • 8/10/2019 New Moran Nov. 15 report

    29/51

    ADDENDUM F

    Financing Plan

  • 8/10/2019 New Moran Nov. 15 report

    30/51

    Addendum F - New Moran - Capital Fundraising Plans11/14/14

    Completed Q1 - 2015 Q2 - 2015

    Source of Funds Amount

    Federal Historic Tax Credit (RITC) $ 4,106,019

    NPS review confirmsRITC eligibility.

    Preliminary

    discussions with

    potential investors.

    Coordinate with design

    team.

    Update regulators and

    potential investors on

    progress.

    State Historic Tax Credit $ 250,000 Eligibility Confirmed.Meet with program

    leaders. Identify and court

    potential investors.

    Submit application.

    New Markets Tax Credit (NMTC) $ 9,586,007Prepare projectbrochure. Obtain

    letters of interest from

    CDEs.

    Meet with CDEs. Review

    multi-CDE projectstructure options.

    Confirm application

    timelines.

    Update on progress.

    Senior Loan $ 1,875,000

    Debt service capacity

    confirmed.

    Preliminary discussion

    with loan

    administrator.

    Confirm slow money loan

    structure options.

    Charitable $ 11,000,000 Campaign Feasibilityconfirmed. Initialpledges secured.

    Donor cultivation andcampaign.

    Donor cultivation andcampaign.

    TIF Allocation $ 6,300,000 Voter Approval. Negotiate terms. Execute Agreement.

  • 8/10/2019 New Moran Nov. 15 report

    31/51

    Q3 - 2015 Q4 - 2015 Q1 - 2016 Q2 - 2016

    Submit Part 2

    Application to NPS.

    Underwriting completed byInvestors. Commitments,

    subject to standard

    contingencies, issued.

    Approved Part 2 issued by

    NPS.Closing.

    Award. Investor commitment. Closing.

    Submit applications toCDEs. Identify and

    court potential

    investors.

    Underwriting completed by

    CDEs and Investors.Commitments, subject to

    standard contingencies,

    issued.

    Closing.

    Distribute Offering. Secure commitments. Closing.

    Donor cultivation andcampaign.

    Donor cultivation andcampaign.

    Donor cultivation andcampaign. Arrange bridge

    financing.

    Closing.

    Update Update Confirmation Closing.

  • 8/10/2019 New Moran Nov. 15 report

    32/51

    ADDENDUM G

    Operating Budget and Pro Forma

  • 8/10/2019 New Moran Nov. 15 report

    33/51

  • 8/10/2019 New Moran Nov. 15 report

    34/51

  • 8/10/2019 New Moran Nov. 15 report

    35/51

    ADDENDUM H

    Fundraising Feasibility Study

  • 8/10/2019 New Moran Nov. 15 report

    36/51

    67" 8&)9 %:'& ;":):)" +7" E(*(E:+@ ()M :)E.:)(+:&) &4 +7" AB'.:)3+&) E&>>B):+@ ()M >B):+@ ."(M"'5 ()M &*:):&) >(O"'5 &="' +7" *(5+ 5:P >&)+75 +& +"5+ ( 4B)M'(:5:)3 E(>*(:3) 3&(. &4 Q11 >:..:&) +7'&B37

    2/ 4(E"R+&R4(E" >""+:)35 *'&5*"E+:=" M&)&'5 E(*(:5" +& +'()54&'> AB'.:)3+&)U5 #(+"'4'&)+ ()M ").:=") +7" E:+@ ,

    ()M M""* ()M #:M"5*'"(M *&+")+:(. 4&' *7:.()+7'&*:E 5B**&'+9 V)5*:':)3 ."(M"'5 ('" :) *.(E"9 67" +:>:)3 :5 ':37+9 67"

    5B''&B)M:)3 *'&N"E+5 ('" E(+(.@+:E ()M E&>*.">")+('@9 67" E&>*."P 4:)()E:(. >&M". #&'O5W +7" ."="'(3:)3 &4 *B:++"M9 6& 5BEE""M :) '(:5:)3 +7" >B5+ +(O" :)+& (EE&B)+ +7" 4&..:)3? "PE"'*+"M

    4'&> &B' 4:)(. '"*&'+J

    X5+(>B):+@ ")3(3">")+ ()M M">&)5+'(+:)3 *B

  • 8/10/2019 New Moran Nov. 15 report

    37/51

    ADDENDUM I

    Campaign Gift Structure

  • 8/10/2019 New Moran Nov. 15 report

    38/51

    !"#$ &'()* + ,# )"#$-

    + ,#

    .&,-.*/$- 012$,$'3

    41513'$"6*

    $,$'3

    !"#$$$#$$$ & " !"#$$$#$$$ !"#$$$#$$$

    !$$$#$$$ ' ( !'#$$$#$$$ !)#$$$#$$$

    !)$$#$$$ ) &) !'#)$$#$$$ !*#)$$#$$$

    !')$#$$$ + ', !'#$$$#$$$ !-#)$$#$$$

    !&$$#$$$ - '* !-$$#$$$ !&$#,$$#$$$

    !)$#$$$ &' "( !($$#$$$ !&$$$#$$$

    7,$'3- 89 ::: ;::

  • 8/10/2019 New Moran Nov. 15 report

    39/51

    ADDENDUM J

    Ground Lease and Property TaxLiability Assumptions

  • 8/10/2019 New Moran Nov. 15 report

    40/51

    New Moran, Inc.

    PO Box 8502

    Burlington, VT 05401

    MoranPlant.org

    Ground Lease and Property Tax Liability Assumptions

    New Moran, Inc.

    November 14, 2014

    The northern waterfront is a complex site, and the Moran Plant is a uniquely challenging historicbuilding. Ground lease and property tax assumptions for the project are based on three areas offocus: Site Boundary, Allowable Uses and Property Tax Liability.

    New Moran project principals retained Dinse Knapp McAndrew in April of 2014 as legal counsel. Inevaluating Ground Lease and Property Tax Liability Assumptions, DKM reviewed two relevant areasof interest: allowable uses under Public Trust Doctrine, and property tax liability.

    With regards to ground lease, New Moran has assumed a long-term lease of the Moran Plantbuilding at $1/year. We assume the term of this lease will be negotiated, and propose a thirty yearlease, with an option to renew for an additional thirty years. We also propose a shared management

    or licensing agreement for the currently undeveloped landscape surrounding the Moran Plant, asindicated in Addendum D and discussed below.

    Site Boundary:

    The site plan attached to this report as Addendum D outlines a 1.532 acre site directly surroundingthe Moran Plant (1.922 acres including the building). This site includes pedestrian, bike andvehicular access to Moran and the surrounding campus. It creates dramatic public space, directly on

    the shoreline, and abuts the combined educational and recreational resources of the CommunitySailing Center, the new Burlington SkatePark, the expanded bike path, and the proposed BurlingtonHarbor Marina to the south. As designed, the site increases public access to the lakeshore, createsnew play space for children and families, manages stormwater, offers opportunities for

  • 8/10/2019 New Moran Nov. 15 report

    41/51

    New Moran, Inc.

    PO Box 8502

    Burlington, VT 05401

    MoranPlant.org

    Allowable Uses

    The Moran plant is located in the Downtown Waterfront Public Trust District (DW-PTD).According to the Burlington Comprehensive Development Ordinance (CDO), Section4.4.1(d)(2)(A), land in this zone may only be used for:

    - Governmental facilities

    - Indoor or outdoor parks and recreation uses and facilities

    - Arts, educational and cultural activities

    - Fresh water and other environmental activities

    - Services accessory to a permissible use;

    - Railroad, wharfing and storage uses; or

    - Publicly accessible restrooms.

    The Moran Plant and site as proposed includes two major uses: the preservation of a historicbuilding for arts, education and cultural activities, and an outdoor public space suited to recreational

    uses, arts and cultural activities, environmental activities, including public education. It will alsoinclude public bathrooms.

    Based on our preliminary research, it is our assumption that the Moran Plant building represents acohesive whole, serving as an allowable primary use under the Public Trust Doctrine.

    Property Tax Liability

    Property tax liability is not a black and white determination given the proposed use and managementstructure for the Moran Plant. After preliminary research, we are confident NMI will receive 501c3designation and the Vermont public, pious or charitable Vermont property tax exemption.

  • 8/10/2019 New Moran Nov. 15 report

    42/51

    ADDENDUM K

    Updated Project Schedule

  • 8/10/2019 New Moran Nov. 15 report

    43/51

    MORAN PLANT PROJECTED SCHEDULE 11.14.14 DRAFT

    Scope Milestone Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    P roposa l Pub li c T IF Vo te

    Managament Incorporate New Entity

    MOU (NMI and City of BTV)

    Findings Report

    Preliminary Market Analysis

    Parking Study

    Project Term Sheet

    Development Agreement

    Major Tenant Commitments

    Begin Formal NM/BTV Lease

    Commence Full Operation

    Finance Capital Campaign Feasibil ity

    Major Donor Cultivation

    Capital Campaign

    Financing Commitments

    Closing

    Design Assemble A&E P roposa ls

    Historic Preservation Analysis

    Schematic Design

    Design Development

    Construction Drawings

    Permi ts DRB - Des ign Permi ts

    DPW - Construction Permits

    Construction Contractor Selected

    Construction

    Grand Opening

    2014 2015 2016 2017

  • 8/10/2019 New Moran Nov. 15 report

    44/51

    ADDENDUM L

    New Market Tax CreditsLetters of Interest

  • 8/10/2019 New Moran Nov. 15 report

    45/51

    Moran Plant Redevelopment - Summary of New Market Tax Credit Letters of Interest

    Name of CDE Service Area Status Amount

    Vermont Rural Ventures (VRV) Statewide Received N/A Letter of Engagement*

    Urban Action Community Development LLC (UACD) National Received $7MM*

    Urban Research Park CDE, LLC (URP) National Received $7MMUSBCDE, LLC National Received $5MM*

    CCG Community Partners, LLC (CCG) National Received $7MM

    MHIC NE New Markets CDE II LLC (MHIC) Multi-State Received $10MM*

    HEDC New Markets, Inc. (National Development Council) National Received $7MM*

    Total 41-43MM**

    *Denotes probable long-term interest in project

    **Indicates 36M in levels of interest plus an estimated 5-7M from VRV

  • 8/10/2019 New Moran Nov. 15 report

    46/51

    ADDENDUM M

    Preliminary Market Analysis Report

  • 8/10/2019 New Moran Nov. 15 report

    47/51

  • 8/10/2019 New Moran Nov. 15 report

    48/51

    New Moran, Inc.

    PO Box 8502

    Burlington, VT 05401

    MoranPlant.org

    i. Projected recoverable expenses for the Moran building include in-house

    management, programming and marketing. While in one building, the services are

    loosely comparable to those of Church Street Marketplace, and the included

    recoverable expenses echo the Marketplace fee structure. While introducing an

    additional expense, the presence of programming and marketing have been

    deemed essential to commercial viability of many prospective tenants at Moran,

    and particularly in the winter.

    ii. With that, recoverable expenses were adjusted based on operating expenses for

    comparable spaces on the waterfront, resulting in a ~15% decrease in recoverable

    expenses.

    iii. Non-recoverable expenses, which represent the administrative, staff and

    professional costs of operating New Moran, Inc. were increased to reflect

    additional marketing, community engagement and professional services, along

    with a greater annual contingency.

    d. Finally, the process by which tenants are reviewed under the Public Trust Doctrine willhave an effect on the ease of securing new tenants over time. This can be addressed

    through a clear articulation of an agreed upon framework for tenant evaluation and

    acquisition which is both adaptable and enduring. There is more discussion in Addendum

    J of the report to which this is attached.

    2. Two members of the NMI Board of Directors with significant experience in creative office and

    incubator spaces provided insight and financial modeling to project potential use, tenant structure

    and alternative financing structures within the Burlington community. The conclusions were:

    a. The Moran Plant represents an iconic, dynamic and potentially highly desirable space for

    creative collaboration, cultural and educational programming, and further development of

    Burlington as a hub for technology environmentalism and social innovation The unique

    N M I

  • 8/10/2019 New Moran Nov. 15 report

    49/51

    New Moran, Inc.

    PO Box 8502

    Burlington, VT 05401

    MoranPlant.org

    3. A separate review was completed with the Flynn Center with regards to operating expenses. The

    Flynn campus is within 10% of the projected square footage of Moran, and represents similar use

    classes across their properties. As a non-profit managed historic structure, with significant

    programming on an annual, and even daily basis, the Flynn provided a unique comparison.

    Projected Moran expenses are proportionally appropriate to those of the Flynn Center, with some

    revisions made and an additional contingency included.

    While not a traditional market study, this preliminary review provided a representative evaluation of rentand occupancy assumptions given projected tenant mix on the Moran site. As the building design

    advances, and relationships with potential tenants mature, the operating model and projected rents will

    be refined. As detailed in the MOU signed between NMI and the City in August, 2014, a more thorough

    market study confirming updated projections will be conducted during the Development phase of the

    project.

  • 8/10/2019 New Moran Nov. 15 report

    50/51

    ADDENDUM N

    Proposed Tenant Mix

  • 8/10/2019 New Moran Nov. 15 report

    51/51


Recommended