of 51
8/10/2019 New Moran Nov. 15 report
1/51
8/10/2019 New Moran Nov. 15 report
2/51
8/10/2019 New Moran Nov. 15 report
3/51
New Moran, Inc.
PO Box 8502
Burlington, VT 05402
MoranPlant.org
steel columns for tenant use optimization, and providing current, safe access to the roof
areas for public viewing. NMI expects to contract with EV for both Civil and Structural
Engineering services.
c. NMI contracted historic preservation consultant Emily Wadhams to review conceptual
designs with regards to the Secretary of the Interior's Standards for Rehabilitation,
confirm the suitability of the project for Rehabilitation Investment Tax Credits (RITC), and
produce a preliminary report for review and approval by the Vermont Division for Historic
Preservation and the National Park Service. While this scope was not required in NMIsMOU with the City until March, it proved to be a critical path component of thorough
diligence with regards to both design and financing.
d. John Sandor, the National Park Service (NPS) reviewer for the State of Vermont, visited
the site on October 30th with Caitlin Corkins, the tax credit reviewer for the Vermont
Division for Historic Preservation. Following this visit, NPS assessed NMIs preliminary
plans with regard to the feasibility of receiving the Federal Rehabilitation Investment Tax
Credit (see Addendum C). The results of this preliminary review letter are encouragingwith respect to tax credit feasibility. Despite the positive preliminary review, significant
evaluation and design work are still ahead. In particular, the ability to achieve net-zero
energy use will be particularly challenging to complete within traditional NPS guidelines.
NMI has arranged for a comprehensive engineering and design study to address these
variables.
e. Pending the completion of the predevelopment diligence phase of the project, NMI will
resume schematic design with SBA in December, 2014, in line with anticipated
submission of permit applications in March, 2015.
2. Conceptual Site Plan
8/10/2019 New Moran Nov. 15 report
4/51
New Moran, Inc.
PO Box 8502
Burlington, VT 05402
MoranPlant.org
3. Development Budget
a. Sources (Addendum E):
i. Specific requests for City infrastructure investment
1. $6.3M of TIF Allocation as approved by public vote in March, 2014.
2. As part of the diligence completed in the last eight months, NMI is
confident the landscape surrounding Moran on the northern waterfront
represents an essential piece of creating a viable and vibrant campus for
the Moran Plant, surrounding stakeholders and the public at large. Inaccordance, we have reflected an additional $2,854,187 within the NMI
project budget to complete a combination of $230,000 in environmental
remediation and $2,624,187 in site work and landscape architecture for
the proposed site and public green space immediately surrounding the
Moran building. The current sources for this work are charitable
contributions and the resulting tax credit equity; our existing budget
includes no additional City sources above $6.3M in TIF. If additional TIFor City funds were available for infrastructure investment, a cost share of
the $2,854,187 necessary complete the undeveloped waterfront acreage
surrounding Moran would leverage tax credit investment, reduce strain on
the Moran Plant operations, and increase the creditworthiness of NMI.
Please refer to Addendum D for proposed site boundaries, and proposed
terms in Section 4, and Section 6 for discussion of operating reserves.
b. Uses (Addendum E)
4. Financing Plan
a. Credit Enhancement Assumptions:
8/10/2019 New Moran Nov. 15 report
5/51
New Moran, Inc.
PO Box 8502
Burlington, VT 05402
MoranPlant.org
and reserve funding formulas. The funds would be advanced at construction
closing, and administered by an agreed-upon agent acting as a fiduciary on
behalf of all the sources of financing.
ii. Regarding any shared additional infrastructure investment discussed in Section
3, the funds would offset existing sources for site work and environmental
remediation. Pending an agreement with the City, those offset sources would
create additional operating reserves and reduce required debt service carried by
NMI. City funding would be requested in a similar fashion to the alreadyapproved TIF funds, as described above.
c. Capital Fundraising Campaign Plan and updated milestones are detailed in Addendum
F.
5. Operating Budget & Pro Forma (see Addendum G)
6. Determination of sufficient operating reservesa. The Development Budget (Addendum E) indicates an Operating and Lease-Up Reserve
of $1.7M. As detailed in Addendum G, this reserve is adequate to capitalize
approximately $1M in anticipated expenditures during years 1-5 of operation, plus a
reserve equaling approximately one year of additional building operating expenses and
the required distributions to the historic tax credit investor.
b. The existing reserve detailed in Addendum E is, by our determination, the minimum
viable amount without which we would reduce the scope of the project.
c. The challenge of securing sufficient operating reserves and additional capital investment
is an area of focus for the team. While elements of the project could be downsized to
reduce total expenditure, NMTC and RITC funding provides direct leverage of
$ $
8/10/2019 New Moran Nov. 15 report
6/51
New Moran, Inc.
PO Box 8502
Burlington, VT 05402
MoranPlant.org
McArdle joined RP after thirteen years at the Vermont Community Foundation. McArdle
assumed the lead role on the Moran project in August, while Richard Russell worked
directly with prospective leadership donors.
b. After more than seven months of research, prospect identification and fundraising visits,
RP is confident in the ability to attract a total of $11M in charitable support for the Moran
Plant redevelopment. The summary, conclusions and a gift structure for the campaign
are attached (see Addendum I).
8. Ground Lease and Property Tax Liability Assumptions (see Addendum J).
9. Updated Project Schedule (see Addendum K).
a. To date, NMI has tracked on schedule across the board.Following the delivery of this
report, NMI will work with CEDO and the Mayor's Office to review a term sheet for City
Council approval in January, followed by Development Agreement approval in March,
2015. Simultaneously, we anticipate resuming schematic design with our design team inDecember, 2014, in line with anticipated submission of permit applications in March,
2015. This puts NMI on track for a construction start in Spring 2016 and a grand opening
in Spring, 2017.
10. Letters of interest for project funding from a CDE for NMTC (see Addendum L).
a. After preliminary discussion with multiple CDEs beginning in October, 2013, NMI
retained the Washington, DC based The Binnick Group (TBG) in August to evaluate the
availability of NMTC allocation from national CDEs. TBG reviewed the Moran Plant
project to date, and developed a comprehensive Sell Sheet, which was distributed to
seven CDEs across the country including Housing Vermonts Vermont Rural Ventures.
$
8/10/2019 New Moran Nov. 15 report
7/51
New Moran, Inc.
PO Box 8502
Burlington, VT 05402
MoranPlant.org
iii. A separate review was completed with the Flynn Center with regards to operating
expenses. The Flynn campus is within 10% of the projected square footage of
Moran, and represents similar use classes across their properties. Projected
Moran expenses are proportionally appropriate to those of the Flynn Center, with
some revisions made and an additional contingency included.
c. While not a traditional market study, this review provided a representative evaluation of
rent and occupancy assumptions given projected tenant mix on the Moran site. The
conclusions from these three reviews, with discussion and subsequent revisions to theoperating model, are attached as Addendum M.
12. Proposed Tenant Mix
a. NMI continues to engage significant interest from prospective tenants and in multiple
cases is advancing in-depth dialogue with regard to lease, terms, and intent. Multiple
Letters of Intent are currently under negotiation, representing approximately 40% of
annual operating revenue. The attached occupancy schedule (see Addendum N),reflects these dialogues and terms.
13. Preliminary Review with Planning & Zoning Staff
a. NMI initiated a review with Sandrine Thibault on June 4th, 2014, and completed a
preliminary review with the Burlington Department of Planning & Zoning on October
14th, 2014. Those present included Director David E. White, Zoning Administrator Ken
Lerner, and Senior Planners Mary ONeil and Scott Gustin.
b. Based on the October 14th review, NMI began a comprehensive Public Trust Doctrine
investigation with legal counsel at Dinse Knapp McAndrew. Research began with a
focus on the Public Trust Doctrine under Vermont State statute and case law and, more
8/10/2019 New Moran Nov. 15 report
8/51
ADDENDUM A
Champions Council
8/10/2019 New Moran Nov. 15 report
9/51
New Moran, Inc.
PO Box 8502
Burlington, VT 05402
MoranPlant.org
Champions Council for the Moran Plant
From the initial conception of the New Moran concept, we have received extraordinary support for the
project from a number of business-owners and community leaders, which prompted the assembly of a
team of ambassadors and advisers that we call our Champions Council.
The Champions Council is a collection of community leaders willing to lend their name in support of thenon-profit New Moran, Inc. and the redevelopment of the Moran Plant.
We are have asked for support, both on a letterhead and in everyday conversation, from individuals
who offer perspective, bring gravitas, and demonstrate a range of support for the project. There is no
fiduciary or governance responsibility associated with this role.
We have asked all Champions to make a charitable contribution towards the project of an amount that
is meaningful for them at this point in the project, and that amount has varied for each champion. The
intended term of this support is through the opening of the building, Spring 2017, though the role is at
the discretion of each individual.
TheChampions Council includes:
! Benjy Adler, Skinny Pancake
! Jill Badalato, Dealer.com;
! Brian Boardman, Hickok and Boardman Real Estate;! Paul Bruhn, Preservation Trust of Vermont;
! Alex Crothers, Crothers Management Group;
! Marguerite Dibble gametheory;
8/10/2019 New Moran Nov. 15 report
10/51
ADDENDUM B
Conceptual Building Design
8/10/2019 New Moran Nov. 15 report
11/51
8/10/2019 New Moran Nov. 15 report
12/51
8/10/2019 New Moran Nov. 15 report
13/51
8/10/2019 New Moran Nov. 15 report
14/51
8/10/2019 New Moran Nov. 15 report
15/51
8/10/2019 New Moran Nov. 15 report
16/51
8/10/2019 New Moran Nov. 15 report
17/51
8/10/2019 New Moran Nov. 15 report
18/51
8/10/2019 New Moran Nov. 15 report
19/51
8/10/2019 New Moran Nov. 15 report
20/51
ADDENDUM C
National Park Service Review
8/10/2019 New Moran Nov. 15 report
21/51
Emily Wadhams
Historic Preservation Consulting
!"#So. Prospect St.Burlington, Vermont $!%$&
Tel: '$(.)!'."!*! cell: '$(.''&.##(&[email protected]
"#$%&'(""$)
*$"+, %-./01/2 34 5678
"9, :;/ ">??/2
"BA :2-BA/C1/2D
E#9', +0>=F G
8/10/2019 New Moran Nov. 15 report
22/51
8/10/2019 New Moran Nov. 15 report
23/51
8/10/2019 New Moran Nov. 15 report
24/51
ADDENDUM D
Conceptual Site Plan
8/10/2019 New Moran Nov. 15 report
25/51
8/10/2019 New Moran Nov. 15 report
26/51
ADDENDUM E
Development Budget
8/10/2019 New Moran Nov. 15 report
27/51
Addendum E - New Moran - Development Budget11/14/2014 % of Total C
Sources Of Funds Equity
Federal Historic Tax Credit (RITC) 4,106,019 12%
State Historic Tax Credit 250,000 1%
New Markets Tax Credit (NMTC) 9,586,007 29%
Senior Loan 1,875,000 6%
Charitable 11,000,000 33%
TIF Allocation 6,300,000 19%
Total Sources: 33,117,025 100% $
Uses of Funds
Acquisition Environmental Remediation 230,000 1%
Closing Costs 65,000 0%
Total Acquisition Cost 295,000 1% $
Hard Costs
Building Reconstruction 8,791,344 27%
Building Additions 3,397,808 10%
Demolition 545,058 2%
Site Work & Landscaping 2,624,187 8%Contingency & Escalation 3,071,679 9%
FFE - Public Spaces & Tenant Space Allow 300,155 1%
Living Machine 230,000 1%
Energy Production/Upgrades 1,320,372 4%
IT Infrastructure 100,000 0%
Tenant Fit-Up - Allowance 2,491,920 8%
Total Hard Costs 22,872,524 69% $
Design Architectural & Engineering 1,179,792 4%
Civil Engineering 117,920 0%
Commissioning 60,031 0%
8/10/2019 New Moran Nov. 15 report
28/51
Other Soft Costs
Accounting & Audit 80,000 0%
Capital Campaign 145,000 0%
Clerk of the Works 75,000 0%
Community Engagement 75,000 0%
Legal 900,000 3%
Marketing & Market Studies 85,000 0%
Permit Fees 424,737 1%
Program Development & Administration 260,000 1%Project Management & Financial Admin. 350,000 1%
Property Management 40,000 0%
Testing 25,000 0%
Contingency 125,000 0%
Total Other Soft Costs 2,584,737 8% $
Financing, Reserves & Carrying Charges
Reserves
NMTC Reserves 1,338,924 4%Operating/ Lease-Up Reserves 1,730,000 5%
Financing
Construction Period & Bridge Loan Interest 878,954 3%
Loan Fees & Expenses 125,000 0%
NMTC Audit & Fees during Const 17,500 0%
Carrying
Builders Risk & Liability Insur 112,000 0%
Maintenance & Security 27,000 0%
Utilities 18,000 0%Taxes 0%
Total Financing, Reserves & Carrying 4,247,378 13% $
8/10/2019 New Moran Nov. 15 report
29/51
ADDENDUM F
Financing Plan
8/10/2019 New Moran Nov. 15 report
30/51
Addendum F - New Moran - Capital Fundraising Plans11/14/14
Completed Q1 - 2015 Q2 - 2015
Source of Funds Amount
Federal Historic Tax Credit (RITC) $ 4,106,019
NPS review confirmsRITC eligibility.
Preliminary
discussions with
potential investors.
Coordinate with design
team.
Update regulators and
potential investors on
progress.
State Historic Tax Credit $ 250,000 Eligibility Confirmed.Meet with program
leaders. Identify and court
potential investors.
Submit application.
New Markets Tax Credit (NMTC) $ 9,586,007Prepare projectbrochure. Obtain
letters of interest from
CDEs.
Meet with CDEs. Review
multi-CDE projectstructure options.
Confirm application
timelines.
Update on progress.
Senior Loan $ 1,875,000
Debt service capacity
confirmed.
Preliminary discussion
with loan
administrator.
Confirm slow money loan
structure options.
Charitable $ 11,000,000 Campaign Feasibilityconfirmed. Initialpledges secured.
Donor cultivation andcampaign.
Donor cultivation andcampaign.
TIF Allocation $ 6,300,000 Voter Approval. Negotiate terms. Execute Agreement.
8/10/2019 New Moran Nov. 15 report
31/51
Q3 - 2015 Q4 - 2015 Q1 - 2016 Q2 - 2016
Submit Part 2
Application to NPS.
Underwriting completed byInvestors. Commitments,
subject to standard
contingencies, issued.
Approved Part 2 issued by
NPS.Closing.
Award. Investor commitment. Closing.
Submit applications toCDEs. Identify and
court potential
investors.
Underwriting completed by
CDEs and Investors.Commitments, subject to
standard contingencies,
issued.
Closing.
Distribute Offering. Secure commitments. Closing.
Donor cultivation andcampaign.
Donor cultivation andcampaign.
Donor cultivation andcampaign. Arrange bridge
financing.
Closing.
Update Update Confirmation Closing.
8/10/2019 New Moran Nov. 15 report
32/51
ADDENDUM G
Operating Budget and Pro Forma
8/10/2019 New Moran Nov. 15 report
33/51
8/10/2019 New Moran Nov. 15 report
34/51
8/10/2019 New Moran Nov. 15 report
35/51
ADDENDUM H
Fundraising Feasibility Study
8/10/2019 New Moran Nov. 15 report
36/51
67" 8&)9 %:'& ;":):)" +7" E(*(E:+@ ()M :)E.:)(+:&) &4 +7" AB'.:)3+&) E&>>B):+@ ()M >B):+@ ."(M"'5 ()M &*:):&) >(O"'5 &="' +7" *(5+ 5:P >&)+75 +& +"5+ ( 4B)M'(:5:)3 E(>*(:3) 3&(. &4 Q11 >:..:&) +7'&B37
2/ 4(E"R+&R4(E" >""+:)35 *'&5*"E+:=" M&)&'5 E(*(:5" +& +'()54&'> AB'.:)3+&)U5 #(+"'4'&)+ ()M ").:=") +7" E:+@ ,
()M M""* ()M #:M"5*'"(M *&+")+:(. 4&' *7:.()+7'&*:E 5B**&'+9 V)5*:':)3 ."(M"'5 ('" :) *.(E"9 67" +:>:)3 :5 ':37+9 67"
5B''&B)M:)3 *'&N"E+5 ('" E(+(.@+:E ()M E&>*.">")+('@9 67" E&>*."P 4:)()E:(. >&M". #&'O5W +7" ."="'(3:)3 &4 *B:++"M9 6& 5BEE""M :) '(:5:)3 +7" >B5+ +(O" :)+& (EE&B)+ +7" 4&..:)3? "PE"'*+"M
4'&> &B' 4:)(. '"*&'+J
X5+(>B):+@ ")3(3">")+ ()M M">&)5+'(+:)3 *B
8/10/2019 New Moran Nov. 15 report
37/51
ADDENDUM I
Campaign Gift Structure
8/10/2019 New Moran Nov. 15 report
38/51
!"#$ &'()* + ,# )"#$-
+ ,#
.&,-.*/$- 012$,$'3
41513'$"6*
$,$'3
!"#$$$#$$$ & " !"#$$$#$$$ !"#$$$#$$$
!$$$#$$$ ' ( !'#$$$#$$$ !)#$$$#$$$
!)$$#$$$ ) &) !'#)$$#$$$ !*#)$$#$$$
!')$#$$$ + ', !'#$$$#$$$ !-#)$$#$$$
!&$$#$$$ - '* !-$$#$$$ !&$#,$$#$$$
!)$#$$$ &' "( !($$#$$$ !&$$$#$$$
7,$'3- 89 ::: ;::
8/10/2019 New Moran Nov. 15 report
39/51
ADDENDUM J
Ground Lease and Property TaxLiability Assumptions
8/10/2019 New Moran Nov. 15 report
40/51
New Moran, Inc.
PO Box 8502
Burlington, VT 05401
MoranPlant.org
Ground Lease and Property Tax Liability Assumptions
New Moran, Inc.
November 14, 2014
The northern waterfront is a complex site, and the Moran Plant is a uniquely challenging historicbuilding. Ground lease and property tax assumptions for the project are based on three areas offocus: Site Boundary, Allowable Uses and Property Tax Liability.
New Moran project principals retained Dinse Knapp McAndrew in April of 2014 as legal counsel. Inevaluating Ground Lease and Property Tax Liability Assumptions, DKM reviewed two relevant areasof interest: allowable uses under Public Trust Doctrine, and property tax liability.
With regards to ground lease, New Moran has assumed a long-term lease of the Moran Plantbuilding at $1/year. We assume the term of this lease will be negotiated, and propose a thirty yearlease, with an option to renew for an additional thirty years. We also propose a shared management
or licensing agreement for the currently undeveloped landscape surrounding the Moran Plant, asindicated in Addendum D and discussed below.
Site Boundary:
The site plan attached to this report as Addendum D outlines a 1.532 acre site directly surroundingthe Moran Plant (1.922 acres including the building). This site includes pedestrian, bike andvehicular access to Moran and the surrounding campus. It creates dramatic public space, directly on
the shoreline, and abuts the combined educational and recreational resources of the CommunitySailing Center, the new Burlington SkatePark, the expanded bike path, and the proposed BurlingtonHarbor Marina to the south. As designed, the site increases public access to the lakeshore, createsnew play space for children and families, manages stormwater, offers opportunities for
8/10/2019 New Moran Nov. 15 report
41/51
New Moran, Inc.
PO Box 8502
Burlington, VT 05401
MoranPlant.org
Allowable Uses
The Moran plant is located in the Downtown Waterfront Public Trust District (DW-PTD).According to the Burlington Comprehensive Development Ordinance (CDO), Section4.4.1(d)(2)(A), land in this zone may only be used for:
- Governmental facilities
- Indoor or outdoor parks and recreation uses and facilities
- Arts, educational and cultural activities
- Fresh water and other environmental activities
- Services accessory to a permissible use;
- Railroad, wharfing and storage uses; or
- Publicly accessible restrooms.
The Moran Plant and site as proposed includes two major uses: the preservation of a historicbuilding for arts, education and cultural activities, and an outdoor public space suited to recreational
uses, arts and cultural activities, environmental activities, including public education. It will alsoinclude public bathrooms.
Based on our preliminary research, it is our assumption that the Moran Plant building represents acohesive whole, serving as an allowable primary use under the Public Trust Doctrine.
Property Tax Liability
Property tax liability is not a black and white determination given the proposed use and managementstructure for the Moran Plant. After preliminary research, we are confident NMI will receive 501c3designation and the Vermont public, pious or charitable Vermont property tax exemption.
8/10/2019 New Moran Nov. 15 report
42/51
ADDENDUM K
Updated Project Schedule
8/10/2019 New Moran Nov. 15 report
43/51
MORAN PLANT PROJECTED SCHEDULE 11.14.14 DRAFT
Scope Milestone Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
P roposa l Pub li c T IF Vo te
Managament Incorporate New Entity
MOU (NMI and City of BTV)
Findings Report
Preliminary Market Analysis
Parking Study
Project Term Sheet
Development Agreement
Major Tenant Commitments
Begin Formal NM/BTV Lease
Commence Full Operation
Finance Capital Campaign Feasibil ity
Major Donor Cultivation
Capital Campaign
Financing Commitments
Closing
Design Assemble A&E P roposa ls
Historic Preservation Analysis
Schematic Design
Design Development
Construction Drawings
Permi ts DRB - Des ign Permi ts
DPW - Construction Permits
Construction Contractor Selected
Construction
Grand Opening
2014 2015 2016 2017
8/10/2019 New Moran Nov. 15 report
44/51
ADDENDUM L
New Market Tax CreditsLetters of Interest
8/10/2019 New Moran Nov. 15 report
45/51
Moran Plant Redevelopment - Summary of New Market Tax Credit Letters of Interest
Name of CDE Service Area Status Amount
Vermont Rural Ventures (VRV) Statewide Received N/A Letter of Engagement*
Urban Action Community Development LLC (UACD) National Received $7MM*
Urban Research Park CDE, LLC (URP) National Received $7MMUSBCDE, LLC National Received $5MM*
CCG Community Partners, LLC (CCG) National Received $7MM
MHIC NE New Markets CDE II LLC (MHIC) Multi-State Received $10MM*
HEDC New Markets, Inc. (National Development Council) National Received $7MM*
Total 41-43MM**
*Denotes probable long-term interest in project
**Indicates 36M in levels of interest plus an estimated 5-7M from VRV
8/10/2019 New Moran Nov. 15 report
46/51
ADDENDUM M
Preliminary Market Analysis Report
8/10/2019 New Moran Nov. 15 report
47/51
8/10/2019 New Moran Nov. 15 report
48/51
New Moran, Inc.
PO Box 8502
Burlington, VT 05401
MoranPlant.org
i. Projected recoverable expenses for the Moran building include in-house
management, programming and marketing. While in one building, the services are
loosely comparable to those of Church Street Marketplace, and the included
recoverable expenses echo the Marketplace fee structure. While introducing an
additional expense, the presence of programming and marketing have been
deemed essential to commercial viability of many prospective tenants at Moran,
and particularly in the winter.
ii. With that, recoverable expenses were adjusted based on operating expenses for
comparable spaces on the waterfront, resulting in a ~15% decrease in recoverable
expenses.
iii. Non-recoverable expenses, which represent the administrative, staff and
professional costs of operating New Moran, Inc. were increased to reflect
additional marketing, community engagement and professional services, along
with a greater annual contingency.
d. Finally, the process by which tenants are reviewed under the Public Trust Doctrine willhave an effect on the ease of securing new tenants over time. This can be addressed
through a clear articulation of an agreed upon framework for tenant evaluation and
acquisition which is both adaptable and enduring. There is more discussion in Addendum
J of the report to which this is attached.
2. Two members of the NMI Board of Directors with significant experience in creative office and
incubator spaces provided insight and financial modeling to project potential use, tenant structure
and alternative financing structures within the Burlington community. The conclusions were:
a. The Moran Plant represents an iconic, dynamic and potentially highly desirable space for
creative collaboration, cultural and educational programming, and further development of
Burlington as a hub for technology environmentalism and social innovation The unique
N M I
8/10/2019 New Moran Nov. 15 report
49/51
New Moran, Inc.
PO Box 8502
Burlington, VT 05401
MoranPlant.org
3. A separate review was completed with the Flynn Center with regards to operating expenses. The
Flynn campus is within 10% of the projected square footage of Moran, and represents similar use
classes across their properties. As a non-profit managed historic structure, with significant
programming on an annual, and even daily basis, the Flynn provided a unique comparison.
Projected Moran expenses are proportionally appropriate to those of the Flynn Center, with some
revisions made and an additional contingency included.
While not a traditional market study, this preliminary review provided a representative evaluation of rentand occupancy assumptions given projected tenant mix on the Moran site. As the building design
advances, and relationships with potential tenants mature, the operating model and projected rents will
be refined. As detailed in the MOU signed between NMI and the City in August, 2014, a more thorough
market study confirming updated projections will be conducted during the Development phase of the
project.
8/10/2019 New Moran Nov. 15 report
50/51
ADDENDUM N
Proposed Tenant Mix
8/10/2019 New Moran Nov. 15 report
51/51