NEW TOWN HEIGHTS DLF KAKKANADWORK PROGRESS REPORT FOR THE MONTH OF NOV 2010
Click to proceed..
8/8/2019 New Town Heights DLF - Kakkanad (Work Progress Report for the Month of Nov 2010)
2/12
Dear Sir,
We are glad to inform you that the construction activities are in full swing atNew Town Heights DLF Kakkanad, in all the launched towers. Please findbelow the Tower wise progress report.
Tower 6 / Block N
9th floor slab casting work in progress. Apartment block work completed till 4th floor and is progressing on the 5th floor.
Tower 6 / Block P 9th floor slab shuttering work in progress.
Apartment block work completed till 4th floor and is progressing on the 5th floor.
Tower 6 / Block Q 10th floor slab casting completed. Column work for the 11th floor in progress. Apartment block work completed till 4th floor and is progressing on the 5th & 6th floors
Tower 5 / Block K 8th floor slab casting work completed.
Tower 5 / Block L 6th floor slab casting in progress
Block work in progress
Tower 5 / Block M 6th floor slab casting completed
7th floor slab shuttering work in progress Block work in progress
8/8/2019 New Town Heights DLF - Kakkanad (Work Progress Report for the Month of Nov 2010)
3/12
We are also attaching the site progress photographs along with this.
Tower 4 / Block H
Stitched slab work in progress
Tower 4 / Block J
1st level slab shuttering in progress
Tower 3 / Block G 8th floor slab casting work in progress.
Tower 2a / Block D 2nd floor slab casting work in progress.
Tower 2b / Block E
1st floor slab shuttering work completed.
Tower 2b / Block F Ground floor slab casting completed.
Tower 1 / Block A 7th floor slab casting wok in progress Block work in progress
Tower 1 / Block B 11th floor slab casting in progress
Block work in progress
Tower 1 / Block C 5th floor slab casting in progress.
Block work in progress
8/8/2019 New Town Heights DLF - Kakkanad (Work Progress Report for the Month of Nov 2010)
4/12
TOWER 6, BLOCK N 9th
floor slab casting work inprogress
TOWER 6, BLOCK P 9thfloor slab shuttering work
in progress.
8/8/2019 New Town Heights DLF - Kakkanad (Work Progress Report for the Month of Nov 2010)
5/12
TOWER 6, BLOCK Q
10th floor slab castingworks completed
TOWER 5, BLOCK K 8th
floor slab casting workscompleted
8/8/2019 New Town Heights DLF - Kakkanad (Work Progress Report for the Month of Nov 2010)
6/12
TOWER 5, BLOCK L 6th floor slab casting
work in progress
TOWER 5, BLOCK M 6th floor slab casting
completed. 7th floor slabshuttering work in
progress
8/8/2019 New Town Heights DLF - Kakkanad (Work Progress Report for the Month of Nov 2010)
7/12
TOWER 4, BLOCK H Pile cap works &
stitched slab in progress
TOWER 4, BLOCK J 1st level slab shuttering
works in progress
8/8/2019 New Town Heights DLF - Kakkanad (Work Progress Report for the Month of Nov 2010)
8/12
TOWER 3, BLOCK G 8th
floor slab casting work inprogress
TOWER 2a, BLOCK D 2nd
floor slab casting work inprogress.
8/8/2019 New Town Heights DLF - Kakkanad (Work Progress Report for the Month of Nov 2010)
9/12
TOWER 2b, BLOCKE 1st floor slab
shuttering workscompleted.
TOWER 2b,
BLOCK F Groundfloor slab castingwork completed
8/8/2019 New Town Heights DLF - Kakkanad (Work Progress Report for the Month of Nov 2010)
10/12
TOWER 1, BLOCK A 7th floor slab casting
work in progress.
TOWER 1, BLOCK B 11th
floor slab casting in progress
8/8/2019 New Town Heights DLF - Kakkanad (Work Progress Report for the Month of Nov 2010)
11/12
TOWER 1, BLOCK C 5th floor slab casting
work in progress.
Club House piling work inprogress
8/8/2019 New Town Heights DLF - Kakkanad (Work Progress Report for the Month of Nov 2010)
12/12