+ All Categories
Home > Documents > NIRAD Data Package for the NASA WB-57 Prepared by Darin Toohey University of Colorado, Boulder April...

NIRAD Data Package for the NASA WB-57 Prepared by Darin Toohey University of Colorado, Boulder April...

Date post: 15-Jan-2016
Category:
View: 217 times
Download: 0 times
Share this document with a friend
Popular Tags:
18
NIRAD Data Package for the NASA WB-57 Prepared by Darin Toohey University of Colorado, Boulder April 2004 Updated March 2005 Non-dispersed InfraRed Airborne CO 2 Detector (NIRAD)
Transcript
Page 1: NIRAD Data Package for the NASA WB-57 Prepared by Darin Toohey University of Colorado, Boulder April 2004 Updated March 2005 Non-dispersed InfraRed Airborne.

NIRAD Data Package for the NASA WB-57

Prepared by Darin TooheyUniversity of Colorado, Boulder

April 2004Updated March 2005

Non-dispersed InfraRed Airborne CO2 Detector (NIRAD)

Page 2: NIRAD Data Package for the NASA WB-57 Prepared by Darin Toohey University of Colorado, Boulder April 2004 Updated March 2005 Non-dispersed InfraRed Airborne.

This package has been updated to account for a change in mounting of NIRAD into the rack of the right wing pod in order to make room for the new fast ozone instrument during PUMA (April/May 2005). The individual components of NIRAD are the same. However, they are now packaged into a single box that will be mounted to the left rear of the wing pod rack.

Major changes to NIRAD, reflected in the revised slides below, are:

• Weight has been reduced 4 kg (~9 lb). New weight 66.5 lb

• The instrument is contained in a single box rather than three separate components as previously. New dimensions 10”(w) x 24”(l) x 14” (h)

• The box is mounted with six 10-32 cadmium plated stainless steel screws that are easily accessed for quicker installation and removal. New, simpler, structural calculation

• There is now a single gas line connection (as opposed to the original three) to make/break during installation and removal. New, simpler, operating procedures

• Minco heaters have been added to the gas-handling system to reduce changes in pressure regulator settings. New power diagram and specifications

• No changes to pressure system

Page 3: NIRAD Data Package for the NASA WB-57 Prepared by Darin Toohey University of Colorado, Boulder April 2004 Updated March 2005 Non-dispersed InfraRed Airborne.

1. Payload Description

Measurement: Carbon Dioxide (CO2)

Method: Non-dispersed infrared absorption spectroscopy relative to a reference gas with known CO2

Instrument Details: Right wing pod, 66.5 lb, 10”x24”x14” (lwh), <250 W (28V aircraft power at <10 A)

Sampling frequency: 10 Hz

Accuracy: < 0.1%

Precision: <0.03% at 10 Hz, <0.01% at 1 Hz, < 0.003% at 10 seconds

NIRAD consists of three systems: (1) CO2 detector, (2) power and data acquisition, and (3) gas-handling. All three systems have flown previously. The CO2 detector was first flown in 1999 as part of CORE+ instrument during RISO and ACCENT and again in 2004 during PUMA-A. There have been no changes to the detector, other than inspection and routine maintenance. The power and data acquisition system were new for PUMA-A, and are flown here without change, other than to software. The gas-handling system is the same as that flown in May 2004, except that it is now packaged into a single box that contains the detector and power/data system.

The detector is packaged in a vacuum housing to facilitate management of temperature and pressure. At power-up the housing is pumped down to ~300 hPa by one stage of a diaphragm pump and held at this pressure throughout the flight. Thus, at pressure altitudes < 300 hPa the pressure within the housing is above ambient. By design, if the pressure differential is significantly greater than about 5 psi, the O-ring seals leak. A redundant additional mechanical safety relief valve (set for ~15 psi or less) is placed on the housing.

Two 1.2 L epoxy-coated, fiber-wrapped aluminum bottles (DOT rated and certified) are filled to ~1600 psi before flight with zero air doped with CO2. These ‘standards’ are sampled repeatedly during flight to provide an accurate standard for reference to the NOAA/CMDL CO2 scale. Two-stage regulators provide a service pressure of ~25-30 psig throughout flight. The bottles and regulators are backed with safety relief valves.

The diaphragm pump is current-limited for a ‘soft start’ (that is, there is no electrical surge on startup, allowing for use of compact, highly efficient Vicor VI-100 DC/DC converters.

Page 4: NIRAD Data Package for the NASA WB-57 Prepared by Darin Toohey University of Colorado, Boulder April 2004 Updated March 2005 Non-dispersed InfraRed Airborne.

Instrument Schematic

PC-104 DC/DC

5VComputer + A/D System

Astec DC/DC

+15V

-15V LiCor electronics and pressure controllers

7805 7812

5V

12V

Pressure gauges and controllers

CO2 analyzer

Diaphragm pump

Electrical Outline

Vicor VI-100

28Vin

24V

100 W rating 20 W

2 W

15 W

10 W

50 W

Vicor VI-100

100 W rating

Heaters 75 W

Page 5: NIRAD Data Package for the NASA WB-57 Prepared by Darin Toohey University of Colorado, Boulder April 2004 Updated March 2005 Non-dispersed InfraRed Airborne.

2. Structural Analysis

(a) Itemized weight

Component Weight, kg Weight, lb

CO2 analyzer 7.00 15.4diaphragm pump 4.10 9.0MKS 248 Control valve 0.54 1.2solenoid deck 0.58 1.3gas standard 1w/relief valve 1.60 3.5gas standard 2 w/relief valve 1.60 3.5PC-104 computer stack 0.60 1.3dc/dc converter 1 0.10 0.2dc/dc converter 2 0.10 0.2gas regulator 1w/relief valve 1.00 2.2gas regulator2 w/relief valve 1.00 2.2cables, gas lines, fittings 2.16 4.4frame, structure, covers 9.55 21.0inlet 0.50 1.0

Total 30.23 kg 66.5 lb

Page 6: NIRAD Data Package for the NASA WB-57 Prepared by Darin Toohey University of Colorado, Boulder April 2004 Updated March 2005 Non-dispersed InfraRed Airborne.

2. Structural Analysis (click on Excel spreadsheet for supporting calculations)

2 – Mounting of box and frame to rackThe instrument box is mounted to the rack with six #10 cadmium coated, stainless steel bolts. Structural analysis shown in the accompanying excel file indicates that the lowest safety margin (380-480%, or a factor of nearly 5 over nominal ratings) is for the flange bending (vertical load plus horizontal overturning moments). Flange shearout has a safety margin of over 700%, and all other margins are at least a factor of ten over nominal ratings.

(b) Issues

There are two structural issues to consider for integration of NIRAD into the wing pod of the WB-57. The first issue involves the mounting of the individual components listed on the previous page into the box, the second involves mounting the box to the rack. These will be dealt with separately below.

1 - Mounting of individual components into the instrument boxDue to small masses, nearly all components are mounted within the respective housings with high safety margins (factor of 10 or larger). The component with the lowest safety factor is the diaphragm pump, which weighs 10 lbs and is mounted with four #10 stainless steel bolts to a 1/8” thick aluminum plate that forms the bottom of the box. Viton rubber sheets are used between the lugs of the pump and the plate to dampen vibration, although the Vacubrand pump used here was selected for its extraordinarily low vibration. The bolts are secured into locking captive washers (cinch nuts).

Structural analysis shows that all loads have safety margins of x5 or larger, the lowest being the vertical (up) load plus horizontal (forward/aft and left/right) overturning moments (margin = 10). Thus, it is determined that the pump is safely mounted to the box, and that all other components, which are smaller and lighter, do not represent safety issues.

Page 7: NIRAD Data Package for the NASA WB-57 Prepared by Darin Toohey University of Colorado, Boulder April 2004 Updated March 2005 Non-dispersed InfraRed Airborne.

LOCATION B116 B117 INPUT LOCATION

SYMBOL "FSy" "FSu" 2005 CO2 WB-57 Instrument B33

INPUT 1.4 2.0 Darin W. Toohey H33

CO2 instrument to Rack H34CO2 to rack: Crash Loads 3/19/2005 H35Darin W. Toohey 3/19/2005

Margin of Safety, Bolt Load (ult) = 14.13 X LOADS UP PLUS OVERTURNING MOMENTS IN Y & Z

Margin of Safety, Flange Bending (yield) = 3.81 X LOADS UP PLUS OVERTURNING MOMENTS IN Y & Z

Margin of Safety, Flange Bending(ult)= 4.78 X LOADS UP PLUS OVERTURNING MOMENTS IN Y & Z

Margin of Safety, Flange Shearout, (ult)= 453.99 Y & Z LOADS, pure shear loads

Margin of Safety, Flange Bearing, (ult)= 14.60 Y & Z LOADS, pure shear loads

Margin of Safety, Flange Shearout, (ult)= 7.35 under bolt head, X LOADS UP PLUS OVERTURNING MOMENTS IN Y & Z

Margin of Safety, Flange Bearing, (ult)= 11.32 under bolt head, X LOADS UP PLUS OVERTURNING MOMENTS IN Y & Z

Margin of Safety, BOSS SHEAR (ult)= 12.17 PULLOUT @ INSERT, X LOADS UP PLUS OVERTURNING MOMENTS IN Y & Z

Instrument Name: 2005 CO2 WB-57 Instrument INITIATOR: Darin W. TooheyPROJ ECT: CO2 instrument to Rack

*PROGRAM VARIABLES (ENTER VALUES INTO HEAVY BORDERED BOXES below) 3/19/2005 DATE:

NAME SYMBOL VALUE UNITS

WEIGHT W 65 lbs

[UP/DOWN] [FORE/AFT] [LATERAL]

ACCELERATION AXES Gx Gy Gz

G-FACTORS CASE 1 6.0 3.0 1.5

G-FACTORS CASE 2 6.0 0.0 0.0

G-FACTORS CASE 3 0.0 3.0 0.0

G-FACTORS CASE 4 0.0 0.0 1.5

W * Gn = Pn (lbs) Px Py Pz

LIMIT LOADS CASE 1 390.0 195.0 97.5

LIMIT LOADS CASE 2 390.0 0.0 0.0

LIMIT LOADS CASE 3 0.0 195.0 0.0

LIMIT LOADS CASE 4 0.0 0.0 97.5

Figure 1.0

NAME SYMBOL VALUE UNITS --------Notes and/or suggestions:---------

"X" Center of Gravity "CGx" 5.50 inches • Vertical distance from mounting interface to CG.

"Y" axis reaction arm "A" 23.00 inches • Usually center to center bolt pattern

"Z" axis reaction arm "B" 9.00 inches • Bolt centerline to opposite wall (compression)

# bolts resisting Px Bx 6 bolts • Use all the bolts for straight up pull.

# bolts resisting Py By 2 bolts • J ust the ones loaded in tension. (see below)

# bolts resisting Pz Bz 3 bolts • J ust the ones loaded in tension by the overturning moment

Pz (force) * X (distance). This moment lifts (tension)

AVERAGE BOX DENSITY D 0.0290 lbs/in 3̂ one side of the box but pushes down (compresses) the other.

*REFER TO CU/LASP SER_STRC_2, 9/11/95 (B.A.S.D SER #3290 REV. C , 11/15/84) FOR DETAILED ANALYSIS EXPLANATION.

• (AUTOMATIC) CALCULATION OF Pr's or loads/bolt station from page one inputsPr =(( W*Gx/Bx) + (W*Gy*CGx/By*A) +(W*Gz*CGx/Bz*b))

NAME SYMBOL VALUE UNITS

LOAD CASE 1 (MAX X) Pr 1 108.2 lbs •Load/bolt station; CASE 1

LOAD CASE 2 (MAX Y) Pr 2 65.0 lbs •Load/bolt station ; CASE 2

LOAD CASE 3 (MAX Z) Pr 3 23.3 lbs •Load/bolt station ; CASE 3

LOAD CASE 4 (MAX QS) Pr 4 19.9 lbs •Load/bolt station ; CASE 4

Pr (max ) = 108.2 lbs ••The maximum load/bolt station @ the box wall above the for LOAD CASES 1 thru 4.

NAME SYMBOL VALUE UNITSLocation of bolt with respect to flange edgeslength 1 L1 0.5 inches •(Wall to centerline of bolt)length 2 L2 5 inches •(Centerline of bolt to end of flange)

Kick Load Rk 10.8 lbs •Rk (kick load) = Pr*L1/L2 OFF SCREEN TABLE OF BOLT STRENGTHS

Bolt Reaction Rb 119.0 lbs • Rb = Pr(max) + Rk) uts dia

L2

Rk

L1

Rb

"CGx

Page 8: NIRAD Data Package for the NASA WB-57 Prepared by Darin Toohey University of Colorado, Boulder April 2004 Updated March 2005 Non-dispersed InfraRed Airborne.

3. Electrical Load Analysis

Instrument Name: NIRAD

  AMPS  Voltage Nominal Maximum Peak Inrush Notes

28 VDC 4.0 7.0   Values based on measurements in lab and estimates of pump performance versus pressure

115 VAC 60 HZ (Single Phase)        115 VAC 400 HZ (Single Phase)        

115 VAC 400 HZ (Three Phase - A)        115 VAC 400 HZ (Three Phase - B)        115 VAC 400 HZ (Three Phase- C)        

Maximum value will occur on ascent, immediately following power-up, where the pressure is largest and temperatures are lowest. This is due to loading of diaphragm pump and heaters. Nominal current draw will depend on cruise altitude – lower values pertaining to highest altitudes

Momentary (< 0.1s) surges of ~0.3 A may occur due to valve switching at ~120 second intervals

Page 9: NIRAD Data Package for the NASA WB-57 Prepared by Darin Toohey University of Colorado, Boulder April 2004 Updated March 2005 Non-dispersed InfraRed Airborne.

4. Pressure/vacuum systems

NIRAD has three systems that fall under the category of pressure/vacuum (P/V) systems – flow system (P and V), gas handling system (P), and detector housing (P and V). These will be discussed separately below.

A. The flow system consists of a Vacuubrand MD VarioSP 4-stage diaphragm pump, two stages of which compress air to ~ 1000 hPa (15 psi) absolute pressure from ambient pressure under all flight conditions, and two stages that serve to pull air through the flow system ultimately venting to ambient air. A safety relief valve set to ~5 psig serves to limit potential over-pressure situations (see C below). All materials are capable of withstanding an overpressure of ~45 psig without damage.

B. The gas-handling system consists of two Structural Composites Industries (SCI) 1.2 L epoxy-coated fiber-wrapped Al bottles (ALT 296C-32449 and ALT296C-32479) both DOT-E 7277-3000). Bottles were recertified in April 2004. The bottles are filled with CO2-doped air to a service pressure of ~1600 psi before each flight, thus serving as standards for in-flight calibration. The bottles are backed with Nupro series R3A (177-R3A-K1-E) stainless steel safety relief valves that can be set at Ellington Field prior to use.

C. The detector vacuum housing is custom built from six 2024-T3 aluminum plates machined for reduced weight. Only the bottom plate is structural. The four side plates are welded together to provide an adequate vacuum seal. This weld is not structural. Viton O-rings seal the top and bottom plates to the rectangular sides of the housing. Vacuum is maintained by actively pumping on the sealed box, and any small leaks are compensated for by venting the flow through the LiCor analyzer into the box. At low altitudes, the housing is at a lower pressure than ambient. Above ~35,000 feet, the housing is maintained several psi above ambient pressure. At these low pressure differentials, the box remains sealed. However, laboratory tests in a bell jar (photos available upon request) show that the housing can withstand ~10-12 psig positive differential. However, under larger positive differentials the O-ring seal on the top lid distorts sufficiently (~0.015”-0.020”) to allow release of pressure. Thus, the housing is best characterized as a ‘leaky vessel’ whose primary function is to provide a ballast volume to aide in pressure control of the LiCor 6251 CO2 analyzer. The pressure within the housing is maintained electronically using an MKS-1250 pressure controller. As outlined in the figure on the following page, should the electronics fail, the valves will normally close, and the pressure within the housing will come to the same as that of the compressor stage of the diaphragm pump. Therefore, the safety relief valve described in A is best placed at the immediate outlet of the diaphragm pump.

Page 10: NIRAD Data Package for the NASA WB-57 Prepared by Darin Toohey University of Colorado, Boulder April 2004 Updated March 2005 Non-dispersed InfraRed Airborne.

Housing

Vent to box

Housing pressure determined by this feedback loop

5 psig safety relief valve

Normally closed valves

Page 11: NIRAD Data Package for the NASA WB-57 Prepared by Darin Toohey University of Colorado, Boulder April 2004 Updated March 2005 Non-dispersed InfraRed Airborne.

5. Laser systems - none

6. Hazard Source Checklist

Enumerate or mark N/A 

N/A - Flammable/combustible material, fluid (liquid, vapor, or gas) N/A - Toxic/corrosive/hot/cold material, fluid (liquid, vapor, or gas)  X - High pressure system (static or dynamic) We fly two CO2-in-air standards for in-flight calibration. These cylinders (Structural Composites Industries Model 374, DOT-E 7277-3000 spec) are 1.25 l in volume and filled to a pressure of ~1600 psi 109 bar) and are fitted with Nupro series R3A (177-R3A-K1-E) pressure relief valves preset to ~2200 psi. Pressure is reduced by a Scott 51-14D two-stage regulator equipped with a safety relief valve or a Veriflo HIR100 single-stage regulator equipped with a Swagelok CA Series (SS-4CPA2-EP-50) pressure relief valve.  X - Evacuated container (implosion) The Licor detector housing (see photo) is designed to maintain the detector at a ‘near ambient’ pressure and room temperature so that the system remains stable over short (100-1000 seconds) timescales. The preferred operating pressure and temperature of the instrument is ~250 hPa and 30 oC, such that the housing pressure is electronically controlled to be ~250 hPa. Therefore, under nominal operation, the pressure in the housing is below ambient to pressure altitudes of 250 hPa (~11-12 km), altitudes above which the pressure differential reverses and the housing is slightly above (~2-3 psig) ambient. The housing contains static O-ring seals between the sidewalls and the cover and bottom plates. These seals tighten under negative pressure but are designed intentionally to leak under positive pressure differentials in excess of ~7-10 psig.  Under passive conditions (e.g. instrument power failure), the pressure within the housing relaxes to ambient. In the case of failure of electronic pressure control, but continuous operation of the compressor pump, the pressure within the housing can increase to the pressure of the compressed air or the O-ring cracking pressure, whichever is lower (e.g. ~7-10 psig). The housing is tested by sealing to ~1 atm and pumping in a bell jar to an ambient pressure of ~0.5 psi. Photos of the test will be supplied prior to flight.

N/A - Frangible materialN/A - Stress corrosion susceptible materialN/A - Inadequate structural design (i.e., low safety factor) N/A - High intensity light source (including laser) N/A - Ionizing/electromagnetic radiation  

Page 12: NIRAD Data Package for the NASA WB-57 Prepared by Darin Toohey University of Colorado, Boulder April 2004 Updated March 2005 Non-dispersed InfraRed Airborne.

X - Rotating device

The diaphragm pump consists of a rotating armature driven by brushless 24 VDC, and small flywheel to reduce vibration. Friction in the diaphragms is sufficient to stop rotation within a few seconds of power loss.

 N/A - Extendible/deployable/articulating experiment element (collision)

N/A - Stowage restraint failure

N/A - Stored energy device (i.e., mechanical spring under compression)

Vacuum vent failure (i.e., loss of pressure/atmosphere)

N/A - Heat transfer (habitable area over-temperature)

N/A - Over-temperature explosive rupture (including electrical battery)

N/A - High/Low touch temperature

N/A - Hardware cooling/heating loss (i.e., loss of thermal control)

N/A - Pyrotechnic/explosive device

X - Propulsion system (pressurized gas or liquid/solid propellant)

Gas bottles and regulators, as described above. The bottles are clamped to a ½” thick 2024-Al machined plate surrounded by a 1/16” thick aluminum housing and bolted to the rack within the wingpod via the Al plate. The largest diameter tubing maintained at high pressure is ¼” stainless steel contained within the bottle housing. The force of any inadvertent release of pressure is smaller than the safety margins for structural components in this same housing (e.g. bottle and regulator).

N/A - High acoustic noise level

N/A - Toxic off-gassing material

N/A - Mercury/mercury compound

N/A - Organic/microbiological (pathogenic) contamination source

N/A - Sharp corner/edge/protrusion/protuberance

N/A - Flammable/combustible material, fluid ignition source (ı.e., short circuit; under-sized wiring/fuse/circuit breaker)

N/A - High voltage (electrical shock)

N/A - High static electrical discharge producer

N/A - Software error or computer fault

N/A - Carcinogenic material

Other:

Page 13: NIRAD Data Package for the NASA WB-57 Prepared by Darin Toohey University of Colorado, Boulder April 2004 Updated March 2005 Non-dispersed InfraRed Airborne.

7. Ground support requirements

1. Power – 15 A, 120 VAC, for AC/DC converter to test instrument and for a laptop computer to reduce data

2. We will have two investigator-provided size A cylinders of compressed air doped with CO2 for use as standards for NIRAD.

3. We have no chemicals

4. Typical working hours 8 am to 7 pm, 7 days, but access to aircraft after normal hours will not be necessary

5. No special equipment is needed for handling equipment

6. Storage for ~3 shipping boxes 36”x20”x20” and two gas cylinders.

8. Hazardous materials – none

9. MSDS – n/a

Page 14: NIRAD Data Package for the NASA WB-57 Prepared by Darin Toohey University of Colorado, Boulder April 2004 Updated March 2005 Non-dispersed InfraRed Airborne.

1. Preflight checkout A. Connect monitor and keyboard to instrument B. Turn on 28 V power to right wingC. Turn instrument on (position 2) Condition - fail light should turn on with “instrument on” and go off within 60 seconds

D. Watch GSE screen for several minutes to verify proper operationE. Turn instrument off F. Can power down 28 V to wing at any timeG. ~20 minutes before take off, open valves to gas bottles 3 turns

2. Preflight procedureA. G. ~20 minutes before take off, open valves to gas bottles 3 turns

3. FlightA. Instrument on - as soon as convenient after take offCondition - fail light should turn on with “instrument on” and go off within 60 seconds

B. Instrument off - on descent, as soon as convenient below 20,000 feet

Fail procedure If fail light comes on during flight, cycle power to instrument

(instrument off, wait 10 seconds, instrument on). In proper operation, fail light should extinguish within 20 seconds of “instrument on” command. If, after three attempts, instrument fail light will not go out, leave instrument power on (assume that fail light circuit is faulty)

3. Post-flightA. Close two valves to gas bottles

10. Mission procedures

Page 15: NIRAD Data Package for the NASA WB-57 Prepared by Darin Toohey University of Colorado, Boulder April 2004 Updated March 2005 Non-dispersed InfraRed Airborne.

NIRAD Installation Instructions

1. Install Box to Wing Pod Rack (install before ozone)

Remove front and rear skins (if applicable)

A. Place box on left rear of rack about 1inch from left rear corner – pressure gauges should be visible from back of rack

B. From above, insert three #10 socket cap bolts with flat washers to left rail of rack – tighten with allen wrench

C. From below, Insert three #10 bolts socket cap bolts with flat washers to inner angle bracket, tighten with allen wrench

2. Attach TubingA. Connect ¼” black tubing from inlet to feedthrough port on

rear panel of instrument - #1 to “Cal 1” and #2 to “Cal 2” B. Tighten swagelok nuts finger tight plus ¼ turn with 9/16”

box wrench

4. Attach Power CableA. Connect power connector to the circular connector on the

front of the pump/computer box

Page 16: NIRAD Data Package for the NASA WB-57 Prepared by Darin Toohey University of Colorado, Boulder April 2004 Updated March 2005 Non-dispersed InfraRed Airborne.

Removal Instructions

1. Remove Power Cable A. Disconnect circular power cable at front of pump/computer box

(black box)

2. Disconnect TubingA. Disconnect sample line from ¼” swagelok union at inlet and

from bulkhead feedthrough on back panel of instrument

3. Remove ozone instrument

4. Remove Instrument Box from RackA. Use allen wrench to loosen and remove three #10 bolts and flat

washers from below angle bracket on starboard side of instrument.

B. Use allen wrench to loosen and remove three #10 bolts and flat washers from above on port side of instrument

C. Lift and remove instrument

Page 17: NIRAD Data Package for the NASA WB-57 Prepared by Darin Toohey University of Colorado, Boulder April 2004 Updated March 2005 Non-dispersed InfraRed Airborne.

NIRAD CO2 On-board bottle filling proceduresMay 12, 2004

Prepared by Darin TooheyUniversity of Colorado

Note: all procedures carried out with bottle out of the rack and on a lab bench

1. Prepare ground bottleA. Attach high pressure regulator to ground bottle, calibration

gas 1.B. Set regulator pressure to zero by turning regulator handle

counterclockwise to stop.C. Open bottle valve – record bottle pressure on checklistD. Turn regulator handle clockwise to raise pressure to ~200

psi, close bottle valveE. Open regulator valve to empty regulatorF. Repeat steps C through R three times to purge gas from

regulator

2. Connect ground bottle to flight bottle systemA. Attach 1/8” swagelok nut to flight bottle fill line, tighten

finger tightB. Open ground bottle cylinder valve, record pressure on

checklistC. Raise regulator pressure to ~200 psiD. Open regulator valve, fill transfer line to 200 psiE. Close regulator valveF. Crack 1/8” swagelok fitting at fill line, releasing pressureG. Repeat steps D-F three times to purge air from transfer line

Page 18: NIRAD Data Package for the NASA WB-57 Prepared by Darin Toohey University of Colorado, Boulder April 2004 Updated March 2005 Non-dispersed InfraRed Airborne.

3. Fill flight bottle

• Raise ground bottle regulator pressure to ~500 psi

• Open regulator valve

• Open transfer/fill valve slowly, bleeding air into flight cylinder

• When flight bottle pressure matches regulator pressure, raise regulator pressure in ~100 psi increments until the pressure in the flight bottle is within ~100 psi of the ground bottle pressure – to a maximum of 1600 psi

• Record flight and ground bottle pressures in checklist

• Close transfer/fill valve

• Close regulator valve and ground bottle main valve

• With 7/16 open end wrench, break 1/8” swagelok nut at transfer line to slowly release pressure in transfer line

• Disconnect transfer line

• Open regulator valve to release pressure in regulator

• Remove regulator and transfer to second ground bottle

• Repeat steps 1-3 to fill second bottle


Recommended