An Invensys Company Project No: 8SA-8-PJ-030 Revision No. B Doc. No. 8SA-8-PJ-030-SAT PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION SITE ACCEPTANCE TEST PLAN Date 8th Aug 2007 Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01 Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199 Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 1 of 43 NMR 602.10 Rev. B INVENSYS MIDDLE EAST (TRICONEX DIV.) PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION SITE ACCEPTANCE TEST PLAN NMR 602.10
Transcript
Page 1: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 1 of 43

NMR 602.10 Rev. B

INVENSYS MIDDLE EAST (TRICONEX DIV.)

PROJECT:

HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

NMR 602.10

Page 2: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 2 of 43

NMR 602.10 Rev. B

Table of Contents. 1. REVISION RECORD SHEET ................................................................................................................................... 3

2. DOCUMENT APPROVAL......................................................................................................................................... 5 2.1. YME / SAUDI ARAMCO........................................................................................................................................... 5 2.2. APPROVAL NOTES AND EXCEPTIONS...................................................................................................................... 5

3. INTRODUCTION ........................................................................................................................................................ 6 3.1. SCOPE ...................................................................................................................................................................... 6 3.2. APPLICABLE DOCUMENTS....................................................................................................................................... 6 3.3. TERMS AND ABBREVIATIONS.................................................................................................................................. 6

4. PREREQUISITE CHECK LIST................................................................................................................................ 8 4.1. MASTER DOCUMENTATION..................................................................................................................................... 8 4.2. PROCESSES COMPLETED ......................................................................................................................................... 9 4.3. TEST EQUIPMENT .................................................................................................................................................... 9 4.4. PERSONNEL REQUIREMENT................................................................................................................................... 10

5. TEST PROCEDURE.................................................................................................................................................. 11 5.1. TEST PLAN............................................................................................................................................................. 11 5.2. TEST RESULT RECORDING & DISCREPANCY RESOLUTION................................................................. 11 5.3. TEST SCHEDULE .................................................................................................................................................... 13 5.4. UNSTRUCTURED TESTING ..................................................................................................................................... 13

6. TEST PROCEDURE.................................................................................................................................................. 14 6.1. SYSTEM CONFIGURATION CHECKS WRT NEW HARDWARE SUPPLIED ................................................................... 14 6.2. VISUAL INSPECTION CHECKS................................................................................................................................ 15 6.3. ELECTRICAL CHECKS ............................................................................................................................................ 16 6.4. POWER CONNECTION CHECKS .............................................................................................................................. 17 6.5. WIRING CHECKS.................................................................................................................................................... 18 6.6. TRICON START-UP CHECKS WRT NEW HARDWARE SUPPLIED............................................................................... 19 6.7. SOE RETRIEVAL UTILITY CHECKS ....................................................................................................................... 20 6.8. TRICON CONFIGURATION & SPARES CHECKS WRT NEW HARDWARE SUPPLIED................................................... 21 6.9. FAILURE MODE & DIAGNOSTICS CHECKS ............................................................................................................ 22 6.10. SYSTEM PERFORMANCE CHECKS...................................................................................................................... 23

7. DETAILED TEST DESCRIPTION AND RESULTS ........................................................................................... 24 7.1. SYSTEM CONFIGURATION CHECKS WRT NEWLY SUPPLIED HARDWARE ...................................... 24

7.1.1. Tricon Inspection..................................................................................................................................... 24 7.1.2. Third Party Equipment Log .................................................................................................................. 24

7.2. VISUAL INSPECTION CHECKS ...................................................................................................................... 25 7.3. ELECTRICAL CHECKS..................................................................................................................................... 26 7.4. POWER CONNECTION CHECKS .................................................................................................................... 27

7.4.1. System Power (110V A.C. UPS) UP.................................................................................................... 27 7.4.2. Field Output Power (24V D.C. KEPCO) UP....................................................................................... 27 7.4.3. Distribution Check .................................................................................................................................. 27 7.4.4. System healthiness ................................................................................................................................ 27 7.4.5. Power Consumption ............................................................................................................................... 28

7.5. SIGNAL WIRING CHECKS............................................................................................................................... 29 7.6. TRICON START-UP CHECKS WRT NEWLY SUPPLIED HARDWARE..................................................... 30

Page 3: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 3 of 43

NMR 602.10 Rev. B

7.6.1. Modifying Application ............................................................................................................................ 30 7.6.2. Tricon Hardware Check ......................................................................................................................... 30

7.7. TRICON SOE RETRIEVAL UTILITY CHECKS.............................................................................................. 31 7.7.1. Running SOE ............................................................................................................................................ 31

7.8. ESD CONFIGURATION AND SPARES CHECKS WRT NEWLY SUPPLIED HARDWARE..................... 32 7.9. FAILURE MODE AND DIAGNOSTIC CHECKS ............................................................................................ 33

7.9.1. Tricon Power Supply Failure................................................................................................................ 33 7.9.2. Input Feed Failure ................................................................................................................................... 33 7.9.3. Complete Power Failure & Battery Backup Checks...................................................................... 33

7.10. PERFORMANCE CHECKS............................................................................................................................ 34 7.10.1. Hardware ................................................................................................................................................ 34 7.10.2. Application Program: ......................................................................................................................... 34 7.10.3. Scan Time Verification....................................................................................................................... 34 7.10.4. Tricon IO & Memory Point Allocation Verification .................................................................... 34

8. COMPLETION OF SAT CERTIFICATE.............................................................................................................. 35 APPENDIX B – IO LOOP CHECKSHEETS .................................................................................................................. 36 APPENDIX C – PUNCH LIST ........................................................................................................................................ 37 APPENDIX D – CHANGE CONTROL FORM.............................................................................................................. 38 APPENDIX E – POST SAT CHECK SHEET ....................................................................................................................... 43

1. REVISION RECORD SHEET

Rev. No. Revision Description Revised Pages Date

B ISSUED FOR CDR 8-AUG-2007

Page 4: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 4 of 43

NMR 602.10 Rev. B

Received By Date:

Return this sheet signed to Project Manager Fax +966 3 8010199 (Discard Previous revision, if any)

Page 5: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 5 of 43

NMR 602.10 Rev. B

2. DOCUMENT APPROVAL

2.1. YME / Saudi Aramco

Submitted for Approval by: Invensys Middle East (Triconex Div.)

Engineering Department, Al Khobar Office Submittal Date: 08 August 2007 Requested Approval Date: 15 August 2007 Submitted for Approval to: Project Manager

HARADH GOSP2 WIPS FACILITIES ESD EXPANSION PROJECT

Written By Rajesh Meghani, Lead Project Engineer Date: 07-AUGUST-2007 Approved By Ahmed Mazrouie, Project Manager Date: 08-AUGUST-2007 Approved By YME / Saudi Aramco Date:

2.2. Approval Notes and Exceptions

Page 6: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 6 of 43

NMR 602.10 Rev. B

3. INTRODUCTION

• The following sections describe the procedures for conducting Site Acceptance Test for HARADH GOSP2 WIPS FACILITIES ESD EXPANSION PROJECT.

3.1. Scope

The SAT document is intended to test and document that the ESD System of HARADH GOSP2 WIPS FACILITIES ESD EXPANSION PROJECT performs as it is intended to. The basic stage covered by the Test Document are:-

SAT test witnessed by the purchaser - Test certificates as in Section 5 & 6. Note that the SAT is outside Invensys current scope of supply. 3.2. Applicable Documents

1. Bill of Materials (NMR 602.4) - 8SA-8-PJ-030-BOM 2. Detailed Layout Drawing (NMR 602.6) - H14-J-BA-651140 3. Electrical Power Distribution & - H14-P-BA-651141 Grounding Drawing (NMR 602.7) 4. System Architecture Drawing (NMR 602.16) - H14-J-BA-651142 5. System Cable Schedule (NMR 602.17) - 8SA-8-PJ-030-SCS 6. Signal Wiring Database (NMR 602.19) - 8SA-8-PJ-030-SWD 7. Panel Signal Wiring & Termination - H14-J-BA-651143 Drawing (NMR 602.20) 3.3. Terms and Abbreviations

2oo3 Two out of Three voting AC Alternating current AI Analogue Input ANSI American National Standards Institute ASTM American Society for Testing and Materials AWG American Wire Gauge CCR Central Control Room CD-ROM Compact Disc – Read only memory CDR Critical Design Documents for Review C&I Control & Instrumentation

Page 7: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 7 of 43

NMR 602.10 Rev. B

CPU Central Processing Unit CSA Canadian Standards Association DC Direct Current DCS Distributed Control System ESD Emergency Shutdown System ETA External Termination Assembly FLD Functional Logic Diagrams GFD Ground Fault Detection GND Ground HPTB HART Protocol Termination Board IEC International Electro technical Commission I/O Input/Output I/P Input ITP Inspection and Test Plan IME Invensys Middle East FZE (Triconex Division) KOM Kick-off Meeting MCB Mini Circuit Breaker MCC Motor Control Center NEMA National Electrical Manufacturers Association NMR Non Material Requirement O/P Output OVD Output Voter Diagnostics PC Personal Computer PCS Process Control System PLC Programmable Logic Controller P&ID Piping and Instrumentation Diagram PSU Power Supply Unit QA Quality Assurance QC Quality Control QCP Quality Control Plan QM Quality Manual RAM Random Access Memory SA Saudi Aramco SAMSS Saudi Aramco Material System Specification SAT Site Acceptance Test SBL Solid Brass Link SER Sequence of Events Recorder SOE Sequence of Events TCP/IP Transmission Control Protocol/Internet Protocol TMR Triple Modular Redundancy Tribus Triplicated I/O bus TRICON Triconex Programmable Safety System TUV TUV Rheinland Institut fur Software, Elektronik, Bahntechnik UPS Uninterrupted Power Supply WBS Work Breakdown Structure YME Yokogawa Middle East B.S.C (c) YGW DCS Yokogawa DCS

Page 8: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 8 of 43

NMR 602.10 Rev. B

4. PREREQUISITE CHECK LIST

The following items shall be ready/completed prior to commencing of the SAT. 4.1. Master Documentation

There will be 1 set of SAT reference drawing / document for ESD system marked as MASTER during SAT.

Document Approved Document /

Drawing No.To be provided by

Bill of Materials 8SA-8-PJ-030-BOM IME

Detailed Layout Drawing H14-J-BA-651140 IME

Electrical Power Distribution and Grounding Drawing

H14-P-BA-651141 IME

System Architecture Drawing H14-J-BA-651142 IME

System Cable Schedule 8SA-8-PJ-030-SCS IME

Power Requirements 8SA-8-PJ-030-PWR IME

Signal Wiring Database 8SA-8-PJ-030-SWD IME

Functional Block Diagram Printouts 8SA-8-PJ-030-FBD IME

Panel Signal Wiring / Termination Drawing H14-J-BA-651143 IME

Tricon System Logbook - IME

Vendor Catalogues - IME

P&IDs - YME

Logic Diagrams - YME

Cause & Effect Diagrams, if any - YME

Page 9: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 9 of 43

NMR 602.10 Rev. B

4.2. Processes Completed

The following processes shall be ready/completed prior to start of the SAT. 1. Issued For Construction IME Documents (SAT Procedure) 2. Approved Site Acceptance Test Plan Document 4.3. Test Equipment

The following test equipment shall be ready prior to start of the SAT. 1. Power Sources – 110 V AC 2. ESD-Tristation / SOE PC with TS1131 programming software 3. 4-20mA Current source 4. Multimeter – Fluke 77 or equivalent 5. Fuse Removal tool

Page 10: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 10 of 43

NMR 602.10 Rev. B

4.4. Personnel Requirement

The following Personnel to be available for the Acceptance Test as described below. Invensys Project Engineer YME 1 Project Engineer SA 1 person each from Maintenance, Operation and Engineering discipline Other people like Administrative personnel may also be present for specific tasks, if required.

Page 11: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 11 of 43

NMR 602.10 Rev. B

5. TEST PROCEDURE

5.1. Test Plan

The Site Acceptance Test (SAT) comprises of the following test elements each with a test certificate and one consolidated punch list report. The test elements for the SAT are as follows:

System configuration Check wrt new hardware supplied Visual Inspection Check Electrical Checks Power Connection Check Wiring Check Tricon Start-up Check wrt new hardware supplied SOE Retrieval Configuration & Spares Check wrt new hardware supplied Failure Mode & Diagnostics Check Performance Records Check Completion

Once the system has been tested based on the above criteria, the test records will be completed and supplied to YME/SA. The test results for the SAT will be recorded in sections 7, Appendix-B &E.

Appendix E contains a post-SAT check sheet covering final inspection prior to actual start up of plant.

5.2. TEST RESULT RECORDING & DISCREPANCY RESOLUTION

The control of the IME SAT is outlined below: - The test record sheets supplied in the Section-7 to this document will be annotated according to the results obtained. A test record may be repeated to test a corrected punch listed point (or points). Where the test record refers to master documents the appropriate section of the master document can either be highlighted in green or pages stamped as ‘Verified’ and signed off. The highlighted / stamped / marked up documents then form part of the test records. Issues / Discrepancies / Clarifications will be recorded on a Punch list sheet as the tests proceed. On completion of the SAT a consolidated Punch List will be point-by-point agreed, confirmed and written by Invensys. Punch List Form is as attached in Appendix – C.

Page 12: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 12 of 43

NMR 602.10 Rev. B

Documentation errors shall be red lined on the original master document and punch listed. The punch-listed point shall be verified as complete when the master document is re-issued and the old red lined document stamped ‘superseded’. Logic errors shall be red lined on the Triconex logic print outs and punch listed. If the error is a minor programming error the punch-listed point may be corrected during the SAT test, in which case the red lined modification can be highlighted in green and the punch list point marked as verified. Once resolved the consolidated Punch List points will be verified as implemented / completed by all parties. The Punch List verification will be done at an agreed time. All modifications will be recorded on the Punch List, if the modification is a correction to the program / hardware due to error or misinterpretation by Invensys, this recording shall be sufficient instruction to Invensys to complete the correction. Master copies of the documentation, if affected will be updated. If the modification is a change of design, this will be recorded on a Hardware or Software Change Request, to be authorised by appropriate technical parties and a Project Impact Report completed to review commercial aspects of change. The Change Control Forms are as attached in Appendix – D. In clearing the Punch List, Hardware and Software Change Requests will be generated (in effect requested by the punch list) and logged in the appropriate registers. This mechanism will then track the fixes and their test status. Tricon faults observed once the SAT has started will be logged on a Hardware Change Request form reserved for Tricon faults. Note that the action may simple, say, to reset the fault using the TS1131 software as some field wiring faults can occur during the course of the SAT in case of ESD system. In addition YME/SA may wish to run a Test Log - a free form logbook detailing order of events, observations, comments, or appropriate narratives of the SAT. If utilised, the test log will be closed on completion of the SAT. Once the SAT is initiated the software comes under formal design change control and the Tricon software version number shall be tracked with every Download All / Download Change.

Page 13: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 13 of 43

NMR 602.10 Rev. B

5.3. Test Schedule

SAT will be scheduled to commence from _________ upto _________ (both days are included). Following tasks will be carried out during this period for each of the ESD system. Each day of testing will be carried out minimum in line with the following schedule. However, daily site activities will be decided by SA. Day # Activities SAT Ref. Section # Day____ 1. System Overview

2. System configuration Checks wrt new hardware supplied 4.1 3. Visual Inspection Checks 4.2

Day____ 1. Electrical Checks 4.3

2. Power Connection Checks 4.4 3. Wiring Checks 4.5 4. Tricon Start-up Checks wrt new hardware supplied 4.6 5. SOE Retrieval Utility Checks 4.7

Day ____ 1. Tricon Configuration & Spare Checks wrt new hardware supplied 4.8 2. Failure Mode & Diagnostics Checks 4.9 3. Performance Record Checks 4.10 4. Wrap-up 5. SAT completion and Signoff 5.4. Unstructured Testing

At the last day, YME/SA can take for non-destructive unstructured testing.

Page 14: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 14 of 43

NMR 602.10 Rev. B

6. TEST PROCEDURE

The following sections cover in general about the intent, cross-referenced sections in this document and criteria for each kind of test to be carried out during SAT. 6.1. System Configuration Checks wrt new hardware supplied

OUTLINE:

All hardware manufactured for this project is subject to client's visual inspection to confirm that all system components and accessories are in accordance with the specifications.

OBJECTIVE:

The purpose of this test is to verify that the following are in accordance with the reference drawings / documents.

1. Model No. of each component.

2. Quantity of each component.

3. Location of each component. REFERENCE DOCUMENT/DRAWING:

1. Bill of Materials

2. Detailed Layout Drawing

3. Tricon System Logbook TEST DETAILS:

1. Visually inspect each component based on the above objectives & verify that it is in order. Refer to Section 7.1.

CRITERIA: Each component shall confirm to the reference documents.

Page 15: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 15 of 43

NMR 602.10 Rev. B

6.2. Visual Inspection Checks

OUTLINE: All components and accessories supplied by Invensys or Third party are certified free from scratches and any deformities that might impair the product quality and appearance. In addition to this all components are to be labelled correctly. OBJECTIVE: The purpose of this test is to ensure that all components and accessories are free from scratches, deformities and is properly labelled for identification. REFERENCE DOCUMENT/DRAWING:

1. Detailed Layout Drawing

2. System Cable Schedule TEST DETAILS:

1. Visually inspect each component based on the above objectives & verify that it is in order. Refer to Section 7.2.

CRITERIA: There should not be any external defects such as deformities / scratches that might impair the product quality or appearance and all components must be labelled properly for easy identification.

Page 16: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 16 of 43

NMR 602.10 Rev. B

6.3. Electrical Checks

OUTLINE: All electrical components and wiring for this project is subject to client's inspection to confirm that all electrical wire type, size and colour are in accordance with the specifications. OBJECTIVE: The purpose of this test is to ensure that all electrical wires are of proper type, size and colour. REFERENCE DOCUMENT/DRAWING:

1. System Design Document

2. Electrical Power Distribution and Grounding Drawing

TEST DETAILS: Refer to Section 7.3. CRITERIA: All electrical wires should be of proper type, size and colour as per specification.

Page 17: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 17 of 43

NMR 602.10 Rev. B

6.4. Power Connection Checks

OUTLINE: All power and earth connections are in accordance with the approved drawings and documents. OBJECTIVE: The purpose of this test is to ensure proper power and earth connection as well as system voltage level prior to power on. REFERENCE DOCUMENT/DRAWING:

1. Electrical Power Distribution and Grounding Drawing

TEST DETAILS: Refer to Section 7.4. CRITERIA: The power connection should be proper prior to power on the cabinets.

Page 18: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 18 of 43

NMR 602.10 Rev. B

6.5. Wiring Checks

OUTLINE: All signal wiring connections are in accordance with the approved drawings and documents. OBJECTIVE: The purpose of this test is to ensure proper signal wiring connection prior to Loop checks and Tricon Application Program Check. REFERENCE DOCUMENT/DRAWING: 1. Wiring Diagram TEST DETAILS: Refer to Section 7.5. CRITERIA: All signal wiring terminal numbers and wire markers are as per referenced drawings.

Page 19: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 19 of 43

NMR 602.10 Rev. B

6.6. Tricon Start-up Checks wrt new hardware supplied

OUTLINE: Successfully start up of the Tricon ESD expansion chassis # 10. OBJECTIVE: The purpose of this test is to ensure the successful start up of the Tricon expansion chassis # 10. REFERENCE DOCUMENT/DRAWING:

1. System Architecture Drawing

TEST DETAILS: Refer to Section 7.6. CRITERIA: Tricon expansion chassis # 10 should have a successful start-up and all tricon modules should have “Active” and “Pass” LED ‘ON’.

Page 20: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 20 of 43

NMR 602.10 Rev. B

6.7. SOE Retrieval Utility Checks

OUTLINE: The SOE functionality wrt newly added points to be checked. OBJECTIVE: The purpose of this test is to check SOE functionality wrt newly added points. REFERENCE DOCUMENT/DRAWING:

1. System Architecture Drawing

TEST DETAILS: Refer to Section 7.7. CRITERIA: Tricon SOE Retrieval is ready to start collecting the new events.

Page 21: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 21 of 43

NMR 602.10 Rev. B

6.8. Tricon Configuration & Spares Checks wrt new hardware supplied

OUTLINE: All IO points as per I/O Database need to be configured in the Tricon ESD System. OBJECTIVE: This checks the basic configuration of the TRICON project file against the quantities in the I/O database. REFERENCE DOCUMENT/DRAWING:

1. Wiring Database 2. Wiring Diagram

TEST DETAILS: Refer to Section 7.8. CRITERIA: All IO points should be configured in Tricon Application Program.

Page 22: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 22 of 43

NMR 602.10 Rev. B

6.9. Failure Mode & Diagnostics Checks

OUTLINE: The diagnostics of the Tricon in the presence of different type of failure modes such as single leg failure, I/O PLC failure, Dual leg failure, power supply failure and complete failure. OBJECTIVE: The purpose of these tests is to ensure the operation of the Tricon in the presence of a module failure. Please note that random modules may be chosen to carry out this test. REFERENCE DOCUMENT/DRAWING:

1. System Design Document

TEST DETAILS:

Refer to Section 7.9. CRITERIA: Successful Failure modes operation of Tricon ESD system.

Page 23: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 23 of 43

NMR 602.10 Rev. B

6.10. System Performance Checks

OUTLINE: The performance of the Tricon System to be verified. OBJECTIVE: The purpose of this test is to record the performance of the Tricon System. TEST DETAILS:

Refer to Section 7.10. CRITERIA: Tricon System performance is within limit.

Page 24: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 24 of 43

NMR 602.10 Rev. B

7. DETAILED TEST DESCRIPTION AND RESULTS

The following test procedures cover the test tasks and results for each kind of test to be carried out during SAT. 7.1. SYSTEM CONFIGURATION CHECKS WRT NEWLY SUPPLIED

HARDWARE

System Name: 7.1.1. Tricon Inspection Check model numbers, revisions, quantity of the Tricon modules Check Bill of materials for Tricon ESD System 7.1.2. Third Party Equipment Log Check and record all serial numbers when available for third party major equipment Record all third party equipment purchase locations when possible

Overall System Configuration Checks – Test Complete

YME/SA Date IME Date

Page 25: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 25 of 43

NMR 602.10 Rev. B

7.2. VISUAL INSPECTION CHECKS

The following visual checks shall be carried out:

Paintwork free from scratches, blemishes, deformities All mechanical connections are secure and fit properly Nuts / bolts / screws / fasteners are tight All ETA labels are fitted All Device labels are fitted All terminal block labels are fitted All system (pre-fab) cables are labelled All chassis interconnect IO Bus cables are labelled A, B, or C Randomly check crimped ends and screw connections All Tricon modules are in correct chassis / slot Verify that all system cables from chassis to ETA at Marshalling cabinet are

connected correctly Visual Inspection Checks – Test Complete

YME/SA Date IME Date

Page 26: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 26 of 43

NMR 602.10 Rev. B

7.3. ELECTRICAL CHECKS

Wire Type / Colour Application 2.5/4/6mm2 multistranded copper conductor, 600V, 105C, PVC Insulation – Black

AC – Live

2.5/4/6mm2 multistranded copper conductor, 600V, 105C, PVC Insulation – White

AC – Neutral

2.5/4/6mm2 multistranded copper conductor, 600V, 105C, PVC Insulation – Green

AC Safety & Shield ground

2.5/4/10mm2 multistranded copper conductor, 600V, 105C, PVC Insulation – Red

DC supply positive

2.5/4/10mm2 multistranded copper conductor, 600V, 105C, PVC Insulation – Black

DC supply negative

2.5/6mm2 multistranded copper conductor, 600V, 105C, PVC Insulation – Green with Yellow Trace

DC Reference ground

1.5mm2 multistranded copper conductor, 600V, 105C, PVC Insulation – Black

Signal positive

1.5mm2 multistranded copper conductor, 600V, 105C, PVC Insulation – White

Signal negative

All cabinet wiring shall be inspected prior to power-up. ESD System and Marshalling Cabinets:

Random Cabinet power wiring visual or continuity checked against drawing Random Ferrule tagging visual check, should be clear and readable Random Point to point (resistance test) Random Point to ground (resistance test)

Note: Earth bonding test shall not exceed 0.5 ohms between bonded item and appropriate earth bus bar Electrical Checks – Test Complete

YME/SA Date IME Date

Page 27: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 27 of 43

NMR 602.10 Rev. B

7.4. POWER CONNECTION CHECKS

The following test is to ensure proper power feed is connected to the expansion chassis # 10 prior to power on.

Check expansion chassis # 10 are connected to a suitable earthing point in the cabinet

Check expansion chassis # 10 is powered through MCBs 11 and 12 in the system cabinet ESD-SYS-04.

Check all MCBs for the correct rating protection (refer to Electrical Power Distribution & Grounding Drg.)

7.4.1. System Power (110V A.C. UPS) UP

Switch ‘ON’ individual MCBs and check voltage on its output terminals, ensure the

respective output devices are ‘ON’ such as Tricon expansion chassis. Ensure all Tricon modules are in ‘PASS’ and ‘ACTIVE’.

7.4.2. Field Output Power (24V D.C. KEPCO) UP

Check voltage on the input side of the power distribution terminals (keeping the fused terminals ‘OPEN’).

7.4.3. Distribution Check

On the primary power distribution terminals, ‘CLOSE’ the fused terminals (+ve) one by one and check voltage at the primary power input terminals of respective ETA.

On the secondary power distribution terminals, ‘CLOSE’ the fused terminals (+ve) one by one and check voltage at the secondary power input terminals of respective ETA.

7.4.4. System healthiness Ensure the system healthiness as below:

Ensure the expansion chassis power supply does not show any alarm Ensure no ‘Load Fuse’ alarm on the Tricon DO modules after power up of the 24v DC

field power supply (KEPCO).

Page 28: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 28 of 43

NMR 602.10 Rev. B

7.4.5. Power Consumption For each type of power feeds, measure voltage and total system current with system in ‘no- load’ condition and record the results: Voltage Current 110V AC Primary Feed ------------- ------------- 110V AC Secondary Feed ------------- ------------- 24V DC Kepco Primary power supply ------------- ------------- 24V DC Kepco Secondary power supply ------------- ------------- Power Connection Checks – Test Complete

YME/SA Date IME Date

Page 29: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 29 of 43

NMR 602.10 Rev. B

7.5. SIGNAL WIRING CHECKS

Randomly thel signal wiring shall be inspected prior to Loop checks and Application Program (Logic Simulation) checking. ESD System and Marshalling Cabinets:

Cabinet wiring visual or continuity checked against drawing Ferrule tagging visual check, should be clear and readable Point to point (resistance test) Point to ground (resistance test)

Note: Earth bonding test shall not exceed 0.5 ohms between bonded item and appropriate earth bus bar Wiring Checks – Test Complete

YME/SA Date IME Date

Page 30: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 30 of 43

NMR 602.10 Rev. B

7.6. TRICON START-UP CHECKS WRT NEWLY SUPPLIED HARDWARE

Existing Tristation / SOE PC with the software installed will be used for the expansion Project.

7.6.1. Modifying Application

Take a backup of the existing latest PT2 file on a removable medis. Run TriStation 1131 application program file copied above. Logon screen will appear and login using, name ‘MANAGER’ and Password

‘PASSWORD’. Connect the TRICON, using ‘Control Panel’ menu. Ensure the Tristation network

node is 192.168.1.1. Modify the application software (latest PT2 file) as required to implement the changes

wrt new project. Switch ‘TRICON’ to ‘Program’ mode. Download the program using ‘Download all’. Switch ‘TRICON’ to run mode.

Note the project file version is _______________ (after downloading) (The number before the decimal point represents the number of Download All’s, the number following the decimal point is the number of Download Changes since the last Download All command.) 7.6.2. Tricon Hardware Check

All Tricon modules to display ACTIVE and PASS LED ‘ON”. Check TRICON configuration against ESD System Architecture Drawing.

Tricon Start-up Checks – Test Complete

YME/SA Date IME Date

Page 31: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 31 of 43

NMR 602.10 Rev. B

7.7. TRICON SOE RETRIEVAL UTILITY CHECKS

Existing Tristation / SOE PC with the software installed will be used for the expansion Project.

7.7.1. Running SOE

Copy the latest SOE configuration file from Engineering Station C:\Programfiles\Triconex\ TriStation1131ver4.1\Programs\XXX.SOE to SOE Station C:\Programfiles\Triconex\tr1soe\.

Open new dummy file using SOE Retrieval Utility. Trinode address will be indicated as 192.168.1.1, if the SOE and TRICON

communication is OK. Run the SOE retrieval to begin collecting the event.

Tricon SOE Retieval Startup Checks – Test Complete

YME/SA Date IME Date

Page 32: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 32 of 43

NMR 602.10 Rev. B

7.8. ESD CONFIGURATION AND SPARES CHECKS WRT NEWLY SUPPLIED HARDWARE

The following section details the functional check required for TRICON system configuration.

Verify existence of control program. Check the module configuration as per ‘Rack Assignment & IO Details’ in DLD. Check the TRIOCN I/O addressing for the hardware points randomly. Check the TRICON I/O addressing for the software points randomly. Check the SOE block configuration.

Following table details the table for IO quantity to identify the spare coverage. Module Used Pts /

moduleQty of

ModulesInstalled Points

Installed spares

Installed spares %

Analog Inputs, TMR 3700A 9 32 1 32 23 71.88%

Digital Inputs, 24VDCTMR 3503E 10 32 2 64 54 84.38%

Digital Outputs 24VDC, TMR 3604E 10 16 2 32 22 68.75%

Analog Outputs, TMR 3805E 0 8 1 8 8 100.00%

Overall 29 6 136 107 78.68% Configuration and Spares Checks – Test Complete

YME/SA Date IME Date

Page 33: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 33 of 43

NMR 602.10 Rev. B

7.9. FAILURE MODE AND DIAGNOSTIC CHECKS

7.9.1. Tricon Power Supply Failure

Remove chassis#10 upper power supply A Check TS1131 diagnostic display shows Chassis power supply A is faulted. Ensure proper operation of the system, by actuating any one digital input. Re-insert chassis#10 upper power supply A Ensure diagnostic displays return to normal status Repeat this procedure with chassis#10 lower power supply B

7.9.2. Input Feed Failure 110VAC UPS

Switch OFF 110VAC Primary Input Power Supply-1 (MCB 11). Check chassis # 10 primary power supplyis OFF. Check Main chassis shows alarm. Ensure proper operation of the system, by actuating any one digital input. Switch ON 110VAC Primary Input Power Supply-1 (MCB 11). Check chassis # 10 primary power supply is ON. Check Main chassis shows Normal. Ensure proper operation of the system, by actuating any one digital input. Repeat this procedure for Secondary Input Power Supply-2 (MCB 12).

7.9.3. Complete Power Failure & Battery Backup Checks

Switch OFF complete power to the ESD Tricon modules with all modules inserted in place.

Switch ON and check program running from battery backup. Failure Mode Tests – Test Complete

YME/SA Date IME Date

Page 34: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 34 of 43

NMR 602.10 Rev. B

7.10. PERFORMANCE CHECKS

7.10.1. Hardware

Check that the LED on all the TRICON chassis, power supplies and the IO Modules are showing normal.

7.10.2. Application Program: The version and the dates on the application program shall be recorded. Sl.No Application File Name Version Date

1 TS1131 Project File 2 SOE Configuration file

Note: Version Number of TS1131 project file indicates as - The number before the decimal point represents the number of Download All’s, & the number following the decimal point is the number of Download Changes since the last Download All command. 7.10.3. Scan Time Verification Using the Tricon Diagnostics Panel, note down the scan time for the Application Program, Scan Time set _____________mS Excess Scan time ____________mS Note: Acceptance Criteria for the Scan Time is lower than 100ms. 7.10.4. Tricon IO & Memory Point Allocation Verification Print the Project Memory Allocation Listing Report using the TS1131 Print Report function.

Check the % spare memory allocated for each variable type. Acceptance Criteria: 20% Spare memory allocated for each variable type. Performance Tests – Test Complete

YME/SA Date IME Date

Page 35: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 35 of 43

NMR 602.10 Rev. B

8. COMPLETION OF SAT CERTIFICATE

System Name: SAT Details SAT Location: SAT Start Date SAT Completion Date: Upon completion of SAT.

Ensure all punch list items are either closed or transferred to the exception list Ensure YME/SA have signed off on punch list and SAT Test Certificates Ensure all master IME drawings / documents are marked up and are ready for

redrafting by others Completion of SAT Certificate

YME/SA Date IME Date

Page 36: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 36 of 43

NMR 602.10 Rev. B

APPENDIX B – IO LOOP CHECKSHEETS

Please refer to NMR 602.19 IO database as reference.

Page 37: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 37 of 43

NMR 602.10 Rev. B

APPENDIX C – PUNCH LIST

Find attached sample SAT Punch List Form.

SYSTEM NAME: Sheet Category (A / B)

Project Name: HARADH GOSP2 WIPS FACILITIES ESD EXP. Date: Punch List No. Originator:

Problem -

Completed Verified

Solution -

Punch List No. Originator:

Problem -

Completed Verified

Solution -

Punch List No. Originator:

Problem -

Completed Verified

Solution -

Punch List No. Originator:

Problem -

Completed Verified

Solution -

Punch List No. Originator:

Problem -

Completed Verified

Solution -

Note: 1. Category A: Critical to be completed and documented before SAT completion

Category B: To be discussed with YME/SA.

Page 38: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 38 of 43

NMR 602.10 Rev. B

APPENDIX D – CHANGE CONTROL FORM

Change Control Forms The following Change Control forms are the mechanism by which design changes are made, authorised, carried out and tested during Site Acceptance Test. As a summary the forms are: Hardware Change Register (HCR) Hardware Change Form (HCF) Software Change Register (SCR) Software Change Form (SCF)

Page 39: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 39 of 43

NMR 602.10 Rev. B

Project Number: 8SA-8-PJ-030 Project: HARADH GOSP2 WIPS FACILITIES ESD EXP.

Hardware Change – Register

HCR

Page of

HCF Number

Raised By (Initials/date)

Implemented By (Initials/date) Summary of Change Details Tested By

(Initials/date) Software version

on completion

Page 40: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 40 of 43

NMR 602.10 Rev. B

HCF Number HCF - HARDWARE CHANGE FORM Project Number: 8SA-8-PJ-030 HARADH GOSP2 WIPS FACILITIES ESD EXP.

CHANGE Details: - State here the nature of the problem, the detail of the problem, and the proposed solution. Continue on a separate sheet and attach if necessary.

Effected Doc / Drawing Number Title By (Initials)

Requested By (Name & Sign):

Position:

Date

Tested By (Name & Sign):

Position:

Date

Page 41: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 41 of 43

NMR 602.10 Rev. B

Project Number: 8SA-8-PJ-030 HARADH GOSP2 WIPS FACILITIES ESD EXP.

Software Change – Register

SCR

Page of

SCF Number

Raised By (Initials/date)

Implemented By (Initials/date) Summary of Change Details Tested By

(Initials/date) Software version

on completion

Page 42: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 42 of 43

NMR 602.10 Rev. B

SCF Number SCF - SOFTWARE CHANGE FORM Project Number: 8SA-8-PJ-030 HARADH GOSP2 WIPS FACILITIES ESD EXP.

CHANGE Details: - State here the nature of the problem, the detail of the problem, and the proposed solution. Continue on a separate sheet and attach if necessary.

Backup Taken By

Initials Date

Logic Diagram Updated By Initials

Date

I/O List Updated By

Initials Date

Requested By (Name & Sign):

Position:

Date

Tested By (Name & Sign):

Position:

Date

Tricon Software Version at Start: Software Version at Finish:

Page 43: NMR602.10 SAT Plan & Procedure

An Invensys Company

Project No: 8SA-8-PJ-030 Revision No. B

Doc. No. 8SA-8-PJ-030-SAT

PROJECT: HARADH GOSP2 WIPS FACILITIES ESD EXPANSION

SITE ACCEPTANCE TEST PLAN

Date 8th Aug 2007

Client: Yokogawa Middle East B.S.C (c) Client P.O. No. XKSS6J0004-01

Contractor: Invensys Middle East - Triconex Div. Owner P.O. No. QDCI-H14-34-C001-NA

Invensys Middle East Triconex Division P.O.Box. 31684 Al Khobar 31952 KSA Tel: +966-3-8010000 Fax: +966-3-8010199

Owner: Saudi Arabian Oil Company (S. Aramco) Sheet 43 of 43

NMR 602.10 Rev. B

APPENDIX E – Post SAT Check Sheet

System Name: The following check list covers items to prepare or correct prior to actual start-up of plant.

Remove any other links / shorts added for testing purposes

Clean cabinets

Check cabinet labels, trunk covers, cable clamps etc. are all in place

Check all TRICON modules are secured with both locking screws on each module

Close and lock all cabinet doors, remove keys and place in Triconex Accessories Box

Archive Project File to zip disk. One copy to be handed over to SA (Maintenance) and one copy to be brought back to Invensys.

Post SAT Check – Test Complete

YME/SA Date IME Date


Recommended