GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University 0722.00 Utility Development Plan June 16, 2009 Stage Two Report NMSU ELECTRICAL DISTRIBUTION SYSTEM OVERVIEW NMSU takes power from El Paso Electric Company at 13,800/23,900 volts (25 kV) at two locations; the Tortugas Substation at the southeast corner of Locust Street and Standley Drive and the Geothermal Substation on Geothermal Drive on the east side of Interstate 25. The Tortugas Substation splits the service into six feeders (numbered 1 through 6) which distribute power through the bulk of the campus. The Geothermal Substation distributes power as Circuit 7 to the east side of I25 and the area around the Aggie Memorial Stadium. The older facilities on campus are served at 4160 volts (5 kV). The original service was located at the Central Heating and Cooling Plant. Starting in the 1980s, 25 kV circuits were extended from the Tortugas Substation to portions of the campus. At several locations, substations consisting of a 23,900 to 4160-volt stepdown transformer and sectionalizing switches provided connections to portions of the older 5 kV distribution system. Portions of the 4160-volt distribution system utilize old technology oil switches and pole-type transformers that are at the end of their typically expected useful life. The Central Heating and Cooling Plant contains two 5 kV distribution sections connected to redundant transformers and 25 kV feeders. If one feeder or transformer fails, the redundant set can be energized to feed the Central Heating and Cooling Plant loads. At several locations sectionalizing switches provide a means for circuits to be backfed by a different circuit in the event of an equipment failure or maintenance outage. To utilize this feature, circuits have to be kept lightly loaded such that a circuit can carry its normal load plus the load of the backfed circuit. Approximately 90% of the 5 kV cable (in the “backbone”) is 500 MCM copper with an ampacity of 475 amps. Where there are taps off the backbone, the cable is stepped down to #4/0, #2/0 or #2. In the older installation, the 5kV cable is run in Orangeberg conduit located in the concrete pour of the utility tunnel floors. All of the 25 kV cable is #4/0 aluminum with an ampacity of 230 amps. GAS TURBINE OPERATION A natural gas fired turbine provides a source of on-site power generation. This turbine is typically connected to Central Heating and Cooling Plant loads, a few classroom and administration buildings, and Computer Center loads. If excess generated power is available, the distribution system can be configured to deliver that on-site generated power to the Tortugas Substation for distribution on the NMSU grid. Controls at the Tortugas Substation prohibit NMSU-generated power from entering the El Paso Electric Company system. The turbine is connected to Central Plant Distribution Board Feeder EG. Turbine loads are varied to keep the turbine running economically. Connected loads may vary during the year. Feeders EFM & EFW in the Central Plant distribution board are utilized to connect “essential” building loads to the turbine.
Transcript
Page 1: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University 0722.00 Utility Development Plan

June 16, 2009 Stage Two Report

NMSU ELECTRICAL DISTRIBUTION SYSTEM OVERVIEW

NMSU takes power from El Paso Electric Company at 13,800/23,900 volts (25 kV) at two locations; the Tortugas Substation at the southeast corner of Locust Street and Standley Drive and the Geothermal Substation on Geothermal Drive on the east side of Interstate 25. The Tortugas Substation splits the service into six feeders (numbered 1 through 6) which distribute power through the bulk of the campus. The Geothermal Substation distributes power as Circuit 7 to the east side of I25 and the area around the Aggie Memorial Stadium.

The older facilities on campus are served at 4160 volts (5 kV). The original service was located at the Central Heating and Cooling Plant. Starting in the 1980s, 25 kV circuits were extended from the Tortugas Substation to portions of the campus. At several locations, substations consisting of a 23,900 to 4160-volt stepdown transformer and sectionalizing switches provided connections to portions of the older 5 kV distribution system. Portions of the 4160-volt distribution system utilize old technology oil switches and pole-type transformers that are at the end of their typically expected useful life.

The Central Heating and Cooling Plant contains two 5 kV distribution sections connected to redundant transformers and 25 kV feeders. If one feeder or transformer fails, the redundant set can be energized to feed the Central Heating and Cooling Plant loads.

At several locations sectionalizing switches provide a means for circuits to be backfed by a different circuit in the event of an equipment failure or maintenance outage. To utilize this feature, circuits have to be kept lightly loaded such that a circuit can carry its normal load plus the load of the backfed circuit.

Approximately 90% of the 5 kV cable (in the “backbone”) is 500 MCM copper with an ampacity of 475 amps. Where there are taps off the backbone, the cable is stepped down to #4/0, #2/0 or #2. In the older installation, the 5kV cable is run in Orangeberg conduit located in the concrete pour of the utility tunnel floors.

All of the 25 kV cable is #4/0 aluminum with an ampacity of 230 amps.

GAS TURBINE OPERATION A natural gas fired turbine provides a source of on-site power generation. This turbine is typically connected to Central Heating and Cooling Plant loads, a few classroom and administration buildings, and Computer Center loads. If excess generated power is available, the distribution system can be configured to deliver that on-site generated power to the Tortugas Substation for distribution on the NMSU grid. Controls at the Tortugas Substation prohibit NMSU-generated power from entering the El Paso Electric Company system.

The turbine is connected to Central Plant Distribution Board Feeder EG. Turbine loads are varied to keep the turbine running economically. Connected loads may vary during the year. Feeders EFM & EFW in the Central Plant distribution board are utilized to connect “essential” building loads to the turbine.

Page 2: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University 0722.00 Utility Development Plan

June 16, 2009 Stage Two Report

Central Plant Distribution Board tie breaker EBT is closed when there is excess generating capacity. That takes power back to Tortugas Substation via feeder #4 (transformers T25-385 and T25-390). That excess power is connected to the general NMSU grid and is metered as negative power at Tortugas Substation breaker TF4.

If the Tortugas Substation detects an El Paso Electric outage, the Central Plant Distribution Board tie breaker EBT is opened so that only the Computer Center and Feeders EFM & EFW (NMSU Central Plant calls those Essential Loads) are connected to the turbine (to keep from overloading the turbine).

ELECTRICAL DISTRIBUTION SYSTEM DEFICIENCIES

FEEDER 3 & 4 REPLACEMENT Installation of 25 kV circuits started in the 1 980s. The initial installation was “designed” by the installing contractor. Installed pullboxes do not have concrete floors and some only have dirt (not even gravel). There are no cable racks on the inside walls of the pullboxes. In some cases 4 x 4 redwood timber is on the pullbox floor, but in some boxes there is nothing but dirt. Cables lay on the dirt floor or on top of 4x4 timbers on the dirt floor. In some areas, the installation allows water and sand to wash into the pullboxes and then raceways. Some of the 25 kV cable is non-jacketed with an exposed concentric neutral. The moisture and sand abrasion causes the concentric neutral to corrode and become damaged, necessitating replacement. This is especially true in the duct banks for feeders #3 and 4 north out of the Tortugas Substation. Replacement of the ductbanks and pullboxes in a fashion to minimize water and debris entrance is desirable. Some projects in the Master Plan may require a new feeder from the Tortugas Substation north towards University Avenue. Part of that new feeder project could include replacement of the existing Feeders #3 & 4 (where the routing is parallel).

The single-line diagram shows Circuits 3 & 4 routed through the same pullboxes as they run north out of the Tortugas Substation. Where the circuit routing splits, the Electric Shop requests a switch to provide selection capability for maintenance or outages etc.

MORE THAN ONE SERVICE TO A BUILDING Where building additions incorporated adding primary voltage transformers (additional services), there is a National Electrical Code (NEC) code issue regarding more than one electric service to a “building.” Examples include Williams Hall Annex, Gerald Thomas Hall (Ag), Jett, Corbett, Garcia, the Activities Center and Foster.

For example, the pole-type transformers in the Williams Hall Annex vault could be removed and that load tied to the newer padmount transformer feeding the main Williams Hall (assuming sufficient transformer capacity). That would eliminate the exposed live electrical terminations inside the Williams Hall Annex vault and combine the two services eliminating a NEC violation and hazardous condition. A new raintight distribution section with two mains for the Annex and main building could be installed adjacent to the padmount transformer.

Page 3: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University 0722.00 Utility Development Plan

June 16, 2009 Stage Two Report

FEEDER #7 REVISIONS On the east side of the I25 freeway, NMSU has a second 25 kV service from El Paso Electric (Geothermal Substation). A 25kV to 5kV stepdown transformer at the substation distributes power to loads in the area. An old overhead power line feeding the Greenhouses, Rodeo Grounds, Chemical Storage and the PSL Antenna farm is connected to this service. This overhead power line needs maintenance/repair. El Paso Electric has overhead distribution in this area and an option to repair is to have El Paso Electric serve these loads directly.

Feeder #7 runs from the Geothermal Substation under the freeway to the Stadium area. This feeder utilizes 25 kV #4/0 aluminum conductors (operated at 5kV) to the NW Stadium vault where it transitions to 5kV 500 MCM copper. (#4/0 Aluminum does not carry much load at 5 kV). Feeder #7 could be reconfigured to operate at 25 kV providing more load capacity) and connected to additional loads in the northeast corner of the campus.

PAN AM CENTER REDUNDANT FEED There is concern that an outage to the Pan Am Center could have adverse financial impacts and that therefore a redundant feed (25 kV) should be provided. One option to provide a redundant feed is to rework feeder #7 from the Geothermal Substation. Feeder #7 runs through the Field House Vault (north of the football stadium) which is just south of the Pan Am Center. The feeder could be configured to operate at 25 kV (revising feeds to the 5 kV loads now connected to Feeder #7). A switch would be required to select feeder #7 or #5 to feed the Pan Am Center. Operating this feeder at 25 kV may also provide capacity to pick up other loads in the area, reducing the loading on the existing feeders serving that portion of campus.

FEEDER #5 TO ED SERVICES The Electric Shop is concerned about the old Feeder #5 cable between the EL Vault through the Garcia tunnel to the Educational Services Center Vault. The existing cable was installed in 1978 as part of the original building construction. The cable is inside orangeberg raceway in the concrete pour for the tunnel floor. The Educational Services Center is at the end of a long radial feeder. There is concern that an outage of this building’s functions would adversely affect NMSU operations. The existing cable could be replaced. An option is to disconnect Educational Services from Feeder 5 (freeing capacity for a new building) and connect it to Feeder #7 (Geothermal Sub) which runs close to this vault and could easily be extended and connected to this load.

FEEDER #5 LOADING The Master Plan calls for several new buildings in the areas served by Feeder #5. An option to reduce load is to revise the normal switching configuration at the Locust Substation. At switch S25-140, open the feed to switch S25-145 which disconnects 2000 kVA transformer T25-440 from Circuit #5. In switch S25-145, the switch for Feeder #2 could be closed connecting transformer T25-440 to Circuit #2. Refer to Master Plan Issues later in this report.

TORTUGAS SUB ISOLATING SWITCHES

The Electric Shop requests that isolating switches be installed on Tortugas Substation circuits 1, 2, 3, 4, & 5. This will allow the substation switches to be isolated from back feeds during maintenance at the Tortugas Substation.

Page 4: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University 0722.00 Utility Development Plan

June 16, 2009 Stage Two Report

REPLACEMENT OF OLD EQUIPMENT Portions of the 5 kV distribution system still in use date from the original building construction, which in some cases far exceeds the typically accepted useful life for that equipment. Old technology oil switches and pole-type transformers are installed in some electrical vaults. In some vaults, the installed equipment arrangement is difficult to maintain or is potentially hazardous. Each year, the Electric Shop typically renovates two of the old transformer vaults, so many of the high priority ones have been modified as available funding allows. The electrical distribution system (switches, transformers, cabling, etc) in the following buildings should be considered for upgrading/replacement.

Buildings 79 & 80. Rhodes-Garrett-Hamiel Hall was originally built in 1941. The two 500 kVA transformers and switches are old (end of typical life), but in serviceable condition.

Building 82. The Biology annex was originally built in 1941. The 500 kVA transformer and switches are old (end of typical life), but in serviceable condition.

Building 154 Garcia Annex was originally built in 1949. Replace primary and 112.5 kVA transformer.

Building 187 Chemistry was originally built in 1957. Replacement of primary switches and 500 kVA, 225 kVA & 150 kVA transformers is presently planned by the Electric Shop.

Building 189 Jett Hall was originally built in 1956. The Jett high-voltage vault needs to be reworked. Replace oil-filled switches and one 500 kVA, two 300 kVA and two 225 kVA transformers. The present installation is crowded creating a maintenance hazard.

Building 244 Gerald Thomas Hall (Ag Bldg) was originally built in 1963. High voltage distribution needs to be revised. One 75 kVA and one 225 kVA transformers are on the roof. Replace 300 kVA pole-type transformers. Refeed one 75 kVA and two 225 kVA transformers. Revise/replace switching and provide a single main disconnect for the building.

Building 245 Tejada Building was originally built in 1962. Replace switches and a 150 kVA transformer.

Building 260 Monagle Residence Hall originally built in 1965. The ten-year Master Plan indicates this building is to be demolished. If the building is to remain in use, the switches and transformer need to be replaced.

Building 276 Walden Hall was originally built in 1966. The 500 kVA transformer needs to be replaced.

Building 278 Branson Library was originally built in 1951. The 1500 kVA transformer needs to be replaced.

Page 5: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University 0722.00 Utility Development Plan

June 16, 2009 Stage Two Report

Building 285 Corbett Center was originally built 1968. Rework two primary vaults and replace 1500 kVA and 300 kVA transformers. Corbett Center has two 5kV and one 25kV services.

Building 288 Guthrie Hall was originally built in 1968. Replace a 500 kVA dry-type transformer.

Building 301 Thomas & Brown Hall was originally built in 1972. Replace the 500 kVA pole- type transformers. The building configuration includes a plumbing chase vertically over the electrical vault which is a potential hazard. Plumbing drains are directly over transformers and debris on floor indicates there has been water leakage into the vault in the past. Refer to the Appendix for photos.

Building 321 James B Delameter Activity Center was originally built in 1973. Replace the 500 kVA pole-type transformers. There is one 5kV feeder to the pole-type transformers and one 25 kV service to this facility. Rework the two feeds to a single service to the building.

Building 338 Educational Services was originally built in 1978. Replace the 300 kVA pole-type transformers.

Building 371 Wind Tunnel Research was originally built in 1981. Replace the 300 kVA pole- type transformers.

Building 386 Business Complex was originally built in 1983. Replace the 25 kV non-jacketed primary cable and three 167 kVA pole-type transformers.

ISSUES REQUIRING ADDITIONAL STUDY

EMERGENCY POWER Two generators at the Central Plant generate emergency lighting power during a power outage. A 300 kVA step up transformer at the Central Plant distributes emergency lighting power through the utility tunnels to some of the older buildings in the heart of the campus at 5kV. Where the feeders leave the Central Plant, they are #2 awg, but as the circuits get farther away, they are tapped down to #6. Small stepdown transformers with circuit breaker load centers are located in the tunnel for distribution of 120-volt circuits to emergency lighting and exit signs in selected buildings. Over the years, telephone equipment has been added to these circuits. This emergency lighting power distribution system is probably overloaded and experiencing voltage drop problems.

Some buildings incorporate backup generators for emergency loads. Buildings with generators include USDA, Police, Foster, Biology Annex, Pan Am Center, Chemistry. Some of the existing generators are diesel and some are natural gas. Natural gas does not meet the National Electrical Code requirement for an on-site fuel supply.

Most campus buildings utilize individual battery packs for emergency lighting. Providing an individual battery pack at each luminaire and exit sign leads to a large quantity of battery packs that require periodic testing and replacement. Current codes require documented periodic testing of egress lighting battery systems leading to high maintenance costs.

Page 6: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University 0722.00 Utility Development Plan

June 16, 2009 Stage Two Report

Emergency power issues should be reviewed and a coherent policy developed for implementation in all campus facilities.

MASTER PLAN DEFICIENCIES

The most pressing issue is how to feed the proposed Arts Complex now under preliminary design. It is to be located near the southeast corner of Espina and University Avenue. Feeders #5 & 6 are in the general area. The loading of individual feeders needs to provide spare capacity to carry the additional load of another feeder when feeder tie breakers are closed for maintenance or repair. The existing and proposed future feeder loading and the long distance from the Tortugas Substation require additional study. El Paso Electric has an overhead power line running along Espina that could perhaps provide a new metered service if serving the Arts Complex becomes problematic.

Plans call for some of the family housing along the I10 freeway is to be relocated and the Academic Research District expanded into that space. That area is presently served by 25kV circuit #1. This circuit presently only feeds student housing loads and power is metered at the Tortugas substation (separate accounting from academics). The system will have to be reconfigured if the Academic Research district is to be separately metered.

The 60,000 square-foot Tech Lab/Classroom facility in the 5-year plan is to be built at the site of Hardman and Jacobs halls which are served by circuit 2 out of the Chiller Plant which is utilized to load the turbine. Desired turbine loading will have to be considered when selecting a power source for new facilities in areas served by feeders connected to the turbine.

The 263, 250 square-foot New Academic Buildings in the 10-year plan is to be built at the present site of the Ag facility which is served by circuit 2 out of the Chiller Plant which is utilized to load the turbine.

Any load changes to circuit 2 will have to be coordinated with desired turbine loading, or another power source extended to the area.

The1 10,850 square-foot Zuhl Library expansion and the 233,250 square-foot Research/Lab Building in the 15-year plan adds load to circuit 3. Circuit 3 is presently the heaviest loaded circuit on campus.

The 218,190 square-foot Academic Lab Building in the 15-year plan adds load to circuit 6. The building location may require that circuit 6 be relocated.

The 81,900 square-foot Greek or Family Housing Phase 1 in the 15-year plan will add load to circuit 2.

Page 7: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University 0722.00 Utility Development Plan

June 16, 2009 Stage Two Report

NORTH CAMPUS ISSUES Feeders #5 and #6 run near the proposed building site for the Arts Complex. From a metered maximum demand standpoint, either feeder appears to have capacity for this one project. However, due to the length of feeders from the Tortugas Substation and the fact that much of that routing is run at 4160 volts, the two circuits should be analyzed further.

Many of the building projects in the NMSU Master Plan are sited in areas presently served by Feeder #5. The existing metered maximum demand on Feeder #5 is 2882 kW. Based on watts per square foot and the proposed building areas in the master Plan, an additional electrical load of 3238 kW is planned for that area (refer to the end of the electrical loading spread sheet). That does not include any load for a chilled water plant to serve the proposed buildings.

Future loads in the area now served by circuit 5: 5-year Plan: Arts Complex, 234,000 sf

Jordan Street Entrance Housing, 225,000 sf Student Services Phase 1 (Near Speech English), 37,500 sf

10-year Plan Student Services Phase 2, 37,500 sf Chamisa Dorms Phase 2, 55,628 sf East Mixed Use/Graduate Housing, Ph. 1, 116,100 sf New Undergraduate Housing (near Monagle Hall), 56,520 sf Student Activities Expansion, 87,160 sf

15-year Plan East Mixed Use/Grad Housing Phase 2 (near Chi Omega Sorority), 117,720 sf

The Master Plan contains other proposed facilities but does not indicate the proposed locations.

Options to provide additional power capacity for the area along the south side of University Avenue include the following:

NEW EPE SERVICE: El Paso Electric has an existing underground power line running along Locust Street. There is an existing pullbox between the southeast corner of Corbett Center and the Chamisa Dorms. EPE may be able to provide a new service at that location.

NEW 25 KV FEEDER FROM TORTUGAS SUBSTATION: A new feeder could be added to the Tortugas Substation and run north to a new chilled water plant that would also contain a distribution substation. New loads could be fed from the new feeder/substation. Existing buildings nearby could be re-fed from the new feeder, unloading existing feeders for other new loads more remote from the new chiller plant/substation. Installation of this new feeder may provide an opportunity (in a common ductbank) to replace portions of Feeders #3 & #4 which are damaged due to improper initial installation (refer to Feeder #3 & 4 Replacement).

If further analysis of Feeders #5 and #6 determine that neither is suitable to feed the Arts Complex, and there is not sufficient time or money available to implement either of the above

Page 8: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University 0722.00 Utility Development Plan

June 16, 2009 Stage Two Report

options, a new electric service could be provided. El Paso Electric has an overhead line along Espina that perhaps could be utilized to temporarily feed the Arts Complex.

Page 9: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University 0722.00 Utility Development Plan

June 16, 2009 Stage Two Report

STRATEGIES TO REPAIR DEFICIENCIES & ACCOMPLISH GROWTH

REPLACEMENT OF THE 25KV DISTRIBUTION SYSTEM Drawing E1 .00 shows the geographical areas currently served by the six 25kV Tortugas feeders, and the single Geothermal feeder. Drawings E1A – E1E depict the staged replacement and expansion of the 25kV underground distribution system. These drawings generally show the rearrangement of the areas served by 25kV feeders; each area contains a single radial feeder, loaded and arranged so that each feeder may be backed up by an adjacent feeder.

Phase 1–2014 Refer to site plan drawing E1A. Construction of a new Secondary Utility Plant is an opportunity to increase electrical capacity in the north-central campus area, replace aging feeders TF-3 and TF-4, establish connections to a new El Paso Electric source north of campus, establish a tie between the Tortugas and Geothermal services (suggested switch to be controlled by El Paso Electric), and establish new 25kV feeders.

Refer to single-line drawing E5A. A new 25kV substation is suggested at the Secondary Utility Plant. The new substation may be served from a new El Paso Electric service from the north, or from a replacement Tortugas substation. Both options are shown on the drawing; a complete buildout may accomplish both options, resulting in two 25kV substations, each with a utility source, and an intertie between the two.

The feeders shown on single–line drawing E5A are depicted in the Phase 1 – 2014 planning timeframe. However, the minimal implementation of this strategy would be the construction of the new Secondary Utility Plant substation, and either the new El Paso Electric service to the north, or the replacement of the Tortugas Substation and the installation of the interconnect between the Tortugas Substation and the Secondary Utility Plant Substation. There are no spare switch positions in the existing Tortugas Substation, so any new feeder or interconnect cabling will occasion the replacement of the Tortugas Substation switchgear; however, as previously mentioned in this report, this switchgear is beyond useful lifespan and its replacement would be a reliability benefit to NMSU. The possible interconnect between a new Secondary Utility Plant Substation and a new Tortugas Substation is shown routed north on Locust Avenue; this is also the routing of existing 25kV Feeders 3 & 4, so this project would also replace those feeders with new.

Phase 1 – 2014 also includes the connection of 13 new buildings to the 25kV system, either on a new 25kV feeder or an existing nearby 25kV feeder (to be replaced in a future timeframe).

The present value of these improvements is estimated at:

Phase 1 -2014 $11.1M

Refer to the following cost opinions. The suggested new switchgear at both the Secondary Utility Plant and the Tortugas Substation is vacuum-circuit-breaker type, enclosed in a manufactured switchgear building. The underground 25kV feeders are single-conductor #4/0 aluminum, to match the feeders currently used at NMSU. Feeders costs carry burdens for

Page 10: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University 0722.00 Utility Development Plan

June 16, 2009 Stage Two Report

excavation, concrete encasement, backfill and surface repair, a manhole every 500’, and a padmounted sectionalizing switch every 1,000’.

Phase 2-5 –2019, 2024, 2029, 2034 Refer to site plan drawings E1B - E1E, and single-line drawing E-5A. Phases 2-5 of this strategy will expand the replacement 25kV system begun in Phase 1. The system is envisioned as radial feeders, each less than 50% loaded, which by switching may be back up buildings in an adjacent area.

The present value of these improvements is estimated at:

Phase 2– 2019 $1.27M

Phase 3–2024 $1.96M Phase 4–2029 $1.94M

Phase 5–2034 $1.37M

(Refer to Phase 1 – 2014 for estimating assumptions used.)

REPAIR OF DEFICIENCIES The strategy detailed above will correct the deficiencies of age and condition in the 25kV electrical distribution system by replacing switchgear and replacing underground cabling. Refer to Electrical Distribution System Deficiencies and Master Plan Deficiencies.

There are approximately 145 5kV transformers at NMSU, with accompanying aging 5kV distribution. While in-building secondary-voltage projects are not addressed within this Utility

Development Plan, it would be prudent to begin replacing these transformers with 25kV transformers connected to the suggested new 25kV electrical distribution system, and simultaneously correcting the multiple building services, feeders and switches in the tunnel system, and other deficiencies noted in Electrical Distribution System Deficiencies.

The costs to replace and expand the 25kV electrical distribution system are described above. However, these improvements will not repair or replace the 5kV system, which is fed by a number of 25-5kV transformer substations located around the NMSU campus. The present value of a building transformer replacement is approximately $90,000 per building; this includes costs similar to those detailed for a building connection in the following cost opinions. The present value of the conversion of all 5kV buildings to 25kV services might cost approximately $9.5M.

Page 11: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

OPINION OF PROBABLE CONSTRUCTION COST BASIS FOR ESTIMATE

E K I CODE A ( No design

completed) o CODE B

(Preliminary design)

CODE C (Finished design)

COMPUTED BY: TCM New Mexico State University Proj. No. 0874.00

CHECKED BY: TAE Utility Development Plan Dept. Electrical

6 / 1 6 / 0 9 2014 Electrical Capital Costs - Substations Sheet No.

SUMMARY QUANTITY MATERIAL LABOR EQUIP TOTAL COST

No.

UNITS

UNIT

MEAS.

PER

UNIT

TOTAL PER

UNIT

TOTAL PER

UNIT

Secondary Utility Plant Substation Outdoor enclosure 1 ls $75,000.00 $75,000.00 $75,000

Utility compartment 1 ls $30,000.00 $30,000.00 $30,000

Main breakers 2 ea $30,000.00 $60,000.00 $60,000

Feeder breakers 17 ea $30,000.00 $510,000.00 $510,000

Cubicles 10 ea $10,000.00 $100,000.00 $100,000

Site work 1 ls $25,000.00 $25,000.00 $25,000

Tortugas Substation Outdoor enclosure 1 ls $75,000.00 $75,000.00 $75,000

Utility compartment 1 ls $30,000.00 $30,000.00 $30,000

Main breakers 2 ea $30,000.00 $60,000.00 $60,000

Feeder breakers 17 ea $30,000.00 $510,000.00 $510,000

Cubicles 10 ea $10,000.00 $100,000.00 $100,000

Site work 1 ls $25,000.00 $25,000.00 $25,000

El Paso Electric reconnection 1 ls $50,000.00 $50,000.00 $50,000

Relay interconnect to SUPS 1 ls $20,000.00 $20,000.00 $20,000

Subtotal $1,670,000

Subcontractor Overhead, 10% $167,000

Subcontractor Profit, 10% $183,700

Subtotal $2,020,700

General Contractor Overhead, 10% $202,070

General Contractor Profit, 5% $111,139

Subtotal $2,333,909

General Contractor Liability, 1.5% $35,009

General Contractor Bond, 2.5% $58,348

General Contractor Tax, 5.5% $133,500

General Contractor Total $2,560,764

Soft Costs, 30% $768,229

Escalation, 3% per year yrs Total $3,328,994

Page 12: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

OPINION OF PROBABLE CONSTRUCTION COST BASIS FOR ESTIMATE

E K I CODE A ( No design

completed) o CODE B

(Preliminary design)

CODE C (Finished design)

COMPUTED BY: TCM New Mexico State University Proj. No. 0874.00

CHECKED BY: TAE Utility Development Plan Dept. Electrical

6 / 1 6 / 0 9 2014 Electrical Capital Costs - Feeders Sheet No.

SUMMARY QUANTITY MATERIAL LABOR EQUIP TOTAL COST

No.

UNITS

UNIT

MEAS.

PER

UNIT

TOTAL PER

UNIT

TOTAL PER

UNIT

El Paso Electric service (north) (2) 4" conduit, incl. sitework 1400 lf $3.59 $5,026.00 $6.15 $8,610.00 $0.50 $14,336

25kV cable, two sets #4/0 84 clf $820.00 $68,880.00 $251.00 $21,084.00 $89,964

Feeder TF2/JM1 (2) 4" conduit, incl. sitework 5700 lf $3.59 $20,463.00 $6.15 $35,055.00 $0.50 $58,368

25kV cable, two sets #4/0 342 clf $820.00 $280,440.00 $251.00 $85,842.00 $366,282

Feeder TF3/JF16 (2) 4" conduit, incl. sitework 6000 lf $3.59 $21,540.00 $6.15 $36,900.00 $0.50 $61,440

25kV cable, one set #4/0 180 clf $820.00 $147,600.00 $251.00 $45,180.00 $192,780

Feeder TF9/JF6 (2) 4" conduit, incl. sitework 9000 lf $3.59 $32,310.00 $6.15 $55,350.00 $0.50 $92,160

25kV cable, one set #4/0 270 clf $820.00 $221,400.00 $251.00 $67,770.00 $289,170

Feeder TF14/JF5 (2) 4" conduit, incl. sitework 6000 lf $3.59 $21,540.00 $6.15 $36,900.00 $0.50 $61,440

25kV cable, one set #4/0 180 clf $820.00 $147,600.00 $251.00 $45,180.00 $192,780

Padmounted Switch 28 ea $15,000.00 $421,500.00 $3,550.00 99,755.00 $521,255

Manhole 56 ea $5,000.00 $281,000.00 $1,000.00 56,200.00 $337,200

Subtotal $2,277,175

Subcontractor Overhead, 10% $227,718

Subcontractor Profit, 10% $250,489

Subtotal $2,755,382

General Contractor Overhead, 10% $275,538

General Contractor Profit, 5% $151,546

Subtotal $3,182,466

General Contractor Liability, 1.5% $47,737

General Contractor Bond, 2.5% $79,562

General Contractor Tax, 5.5% $182,037

General Contractor Total $3,491,802

Soft Costs, 30% $1,047,540

Escalation, 3% per year yrs Total $4,539,342

Page 13: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

OPINION OF PROBABLE CONSTRUCTION COST BASIS FOR ESTIMATE

E K I CODE A ( No design

completed) o CODE B

(Preliminary design)

CODE C (Finished design)

COMPUTED BY: TCM New Mexico State University Proj. No. 0874.00

CHECKED BY: TAE Utility Development Plan Dept. Electrical

6 / 1 6 / 0 9 2014 Electrical Capital Costs - Feeders cont'd Sheet No.

SUMMARY QUANTITY MATERIAL LABOR EQUIP TOTAL COST

No.

UNITS

UNIT

MEAS.

PER

UNIT

TOTAL PER

UNIT

TOTAL PER

UNIT

Feeder TF15/JF3 (2) 4" conduit, incl. sitework 5700 lf $3.59 $20,463.00 $6.15 $35,055.00 $0.50 $58,368

25kV cable, one set #4/0 171 clf $820.00 $140,220.00 $251.00 $42,921.00 $183,141

Feeder TF16/JF4 (2) 4" conduit, incl. sitework 8700 lf $3.59 $31,233.00 $6.15 $53,505.00 $0.50 $89,088

25kV cable, one set #4/0 261 clf $820.00 $214,020.00 $251.00 $65,511.00 $279,531

Feeder TF3/JF16 (2) 4" conduit, incl. sitework 6000 lf $3.59 $21,540.00 $6.15 $36,900.00 $0.50 $61,440

25kV cable, one set #4/0 180 clf $820.00 $147,600.00 $251.00 $45,180.00 $192,780

Building Connections Buildings to be connected 13 ea (2) 4" conduit, incl. sitework 2600 lf $3.59 $9,334.00 $6.15 $15,990.00 $0.50 $26,624

25kV cable, one set #4/0 78 clf $820.00 $63,960.00 $251.00 $19,578.00 $83,538

Padmounted switch 13 ea $15,. 000 00 $195,. 000 00 $3,550.00 $46,. 150 00 $241,150

Padmounted xfmr, averaged sizing 13 ea $10,000.00 $130,000.00 $3,550.00 $46,150.00 $176,150

Subtotal $1,391,810

Subcontractor Overhead, 10% $139,181

Subcontractor Profit, 10% $153,099

Subtotal $1,684,090

General Contractor Overhead, 10% $168,409

General Contractor Profit, 5% $92,625

Subtotal $1,945,124

General Contractor Liability, 1.5% $29,177

General Contractor Bond, 2.5% $48,628

General Contractor Tax, 5.5% $111,261

General Contractor Total $2,134,190

Soft Costs, 30% $640,257

Escalation, 3% per year yrs Total $2,774,447

Page 14: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

OPINION OF PROBABLE CONSTRUCTION COST BASIS FOR ESTIMATE

E K I CODE A ( No design

completed) o CODE B

(Preliminary design)

CODE C (Finished design)

COMPUTED BY: TCM New Mexico State University Proj. No. 0874.00

CHECKED BY: TAE Utility Development Plan Dept. Electrical

6 / 1 6 / 0 9 2019 Electrical Capital Costs - Feeders cont'd Sheet No.

SUMMARY QUANTITY MATERIAL LABOR EQUIP TOTAL COST

No.

UNITS

UNIT

MEAS.

PER

UNIT

TOTAL PER

UNIT

TOTAL PER

UNIT

Feeders, Areas TF8 & TJF10 (2) 4" conduit, incl. sitework 3500 lf $3.59 $12,565.00 $6.15 $21,525.00 $0.50 $35,840

25kV cable, one set #4/0 105 clf $820.00 $86,100.00 $251.00 $26,355.00 $112,455

Building Connections Buildings to be connected 12 ea (2) 4" conduit, incl. sitework 2400 lf $3.59 $8,616.00 $6.15 $14,760.00 $0.50 $24,576

25kV cable, one set #4/0 72 clf $820.00 $59,040.00 $251.00 $18,072.00 $77,112

Padmounted switch 12 ea $15,. 000 00 $180,. 000 00 $3,550.00 $42,. 600 00 $222,600

Padmounted xfmr, averaged sizing 12 ea $10,000.00 $120,000.00 $3,550.00 $42,600.00 $162,600

Subtotal $635,183

Subcontractor Overhead, 10% $63,518

Subcontractor Profit, 10% $69,870

Subtotal $768,571

General Contractor Overhead, 10% $76,857

General Contractor Profit, 5% $42,271

Subtotal $887,700

General Contractor Liability, 1.5% $13,316

General Contractor Bond, 2.5% $22,193

General Contractor Tax, 5.5% $50,776

General Contractor Total $973,984

Soft Costs, 30% $292,195

Escalation, 3% per year yrs Total $1,266,180

Page 15: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

OPINION OF PROBABLE CONSTRUCTION COST BASIS FOR ESTIMATE

E K I CODE A ( No design

completed) o CODE B

(Preliminary design)

CODE C (Finished design)

COMPUTED BY: TCM New Mexico State University Proj. No. 0874.00

CHECKED BY: TAE Utility Development Plan Dept. Electrical

6 / 1 6 / 0 9 2024 Electrical Capital Costs - Feeders Sheet No.

SUMMARY QUANTITY MATERIAL LABOR EQUIP TOTAL COST

No.

UNITS

UNIT

MEAS.

PER

UNIT

TOTAL PER

UNIT

TOTAL PER

UNIT

Feeders, Areas JF4 & JF10 (2) 4" conduit, incl. sitework 4000 lf $3.59 $14,360.00 $6.15 $24,600.00 $0.50 $40,960

25kV cable, one set #4/0 120 clf $820.00 $98,400.00 $251.00 $30,120.00 $128,520

Feeder, Area JF14 (2) 4" conduit, incl. sitework 1000 lf $3.59 $3,590.00 $6.15 $6,150.00 $0.50 $10,240

25kV cable, one set #4/0 30 clf $820.00 $24,600.00 $251.00 $7,530.00 $32,130

Building Connections Buildings to be connected 19 ea (2) 4" conduit, incl. sitework 3800 lf $3.59 $13,642.00 $6.15 $23,370.00 $0.50 $38,912

25kV cable, one set #4/0 114 clf $820.00 $93,480.00 $251.00 $28,614.00 $122,094

Padmounted switch 19 ea $15,000.00 $285,000.00 $3,550.00 $67,450.00 $352,450

Padmounted xfmr, averaged sizing 19 ea $10,000.00 $190,000.00 $3,550.00 $67,450.00 $257,450

Subtotal $982,756

Subcontractor Overhead, 10% $98,276

Subcontractor Profit, 10% $108,103

Subtotal $1,189,135

General Contractor Overhead, 10% $118,913

General Contractor Profit, 5% $65,402

Subtotal $1,373,451

General Contractor Liability, 1.5% $20,602

General Contractor Bond, 2.5% $34,336

General Contractor Tax, 5.5% $78,561

General Contractor Total $1,506,950

Soft Costs, 30% $452,085

Escalation, 3% per year yrs Total $1,959,035

Page 16: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

OPINION OF PROBABLE CONSTRUCTION COST BASIS FOR ESTIMATE

E K I CODE A ( No design

completed) o CODE B

(Preliminary design)

CODE C (Finished design)

COMPUTED BY: TCM New Mexico State University Proj. No. 0874.00

CHECKED BY: TAE Utility Development Plan Dept. Electrical

6 / 1 6 / 0 9 2029 Electrical Capital Costs - Feeders Sheet No.

SUMMARY QUANTITY MATERIAL LABOR EQUIP TOTAL COST

No.

UNITS

UNIT

MEAS.

PER

UNIT

TOTAL PER

UNIT

TOTAL PER

UNIT

Building Connections Buildings to be connected 24 ea (2) 4" conduit, incl. sitework 4800 lf $3.59 $17,232.00 $6.15 $29,520.00 $46,752

25kV cable, one set #4/0 144 clf $820.00 $118,080.00 $251.00 $36,144.00 $154,224

Padmounted switch 24 ea $15,000.00 $360,000.00 $3,550.00 $85,200.00 $445,200

Padmounted xfmr, averaged sizing 24 ea $10,000.00 $240,000.00 $3,550.00 $85,200.00 $325,200

Subtotal $971,376

Subcontractor Overhead, 10% $97,138

Subcontractor Profit, 10% $106,851

Subtotal $1,175,365

General Contractor Overhead, 10% $117,536

General Contractor Profit, 5% $64,645

Subtotal $1,357,547

General Contractor Liability, 1.5% $20,363

General Contractor Bond, 2.5% $33,939

General Contractor Tax, 5.5% $77,652

General Contractor Total $1,489,500

Soft Costs, 30% $446,850

Escalation, 3% per year yrs Total $1,936,350

Page 17: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

OPINION OF PROBABLE CONSTRUCTION COST BASIS FOR ESTIMATE

E K I CODE A ( No design

completed) o CODE B

(Preliminary design)

CODE C (Finished design)

COMPUTED BY: TCM New Mexico State University Proj. No. 0874.00

CHECKED BY: TAE Utility Development Plan Dept. Electrical

6 / 1 6 / 0 9 2034 Electrical Capital Costs - Feeders Sheet No.

SUMMARY QUANTITY MATERIAL LABOR EQUIP TOTAL COST

No.

UNITS

UNIT

MEAS.

PER

UNIT

TOTAL PER

UNIT

TOTAL PER

UNIT

Building Connections Buildings to be connected 17 ea (2) 4" conduit, incl. sitework 3400 lf $3.59 $12,206.00 $6.15 $20,910.00 $33,116

25kV cable, one set #4/0 102 clf $820.00 $83,640.00 $251.00 $25,602.00 $109,242

Padmounted switch 17 ea $15,000.00 $255,000.00 $3,550.00 $60,350.00 $315,350

Padmounted xfmr, averaged sizing 17 ea $10,000.00 $170,000.00 $3,550.00 $60,350.00 $230,350

Subtotal $688,058

Subcontractor Overhead, 10% $68,806

Subcontractor Profit, 10% $75,686

Subtotal $832,550

General Contractor Overhead, 10% $83,255

General Contractor Profit, 5% $45,790

Subtotal $961,595

General Contractor Liability, 1.5% $14,424

General Contractor Bond, 2.5% $24,040

General Contractor Tax, 5.5% $55,003

General Contractor Total $1,055,063

Soft Costs, 30% $316,519

Escalation, 3% per year yrs Total $1,371,581

Page 18: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University 0722.00

June 16, 2009 Stage Two Report

APPENDIX A

METERED POWER READINGS FROM THE “POWER RICH” EMCS THAT IS PART

OF THE TURBINE INSTALLATION

Central Plant 5kV Gear Connected to Turbine Circuit Max kW Calculated Amps + Date of Max kW Time of Max kW

EFCP 1517 226 8/12/08 8:30pm

EFW 1342 200 2/11/09 3:13pm EG2 4583 684 2/3/09 9:17am

EG1 4582 684

EF4A 1300 194 12/28/08 6:32am

ENT 1266 189 6/16/07 11:24am

EFCC 304 45 4/9/08 6:20 pm

EFM 907 135 4/8/08 9:21 am

EF4B (non- essential)

1293 193 12/28/08 6:32am

EF4C 0

Tortugas Substation 25 kV gear Circuit Max kW Calculated Amps + Date of Max kW Time of Max kW

TF1 862 23.1 8/24/07 4:35 am

TF2 820 22.0 8/24/07 TF3 3783 98.3 6/18/08 8:52pm

TF4 +2442 63.4 5/14/08 3:06am

TF4 (Turbine) * -2566 -66.7 12/29/08 3:32 pm TF5 2882 74.9 11/16/07 12:21 am

TF6 2187 56.8 8/22/07 7”56 pm * Power from Turbine backfeeds through this breaker to feed portions of the campus load.

A negative number indicates power generated by the turbine is being fed into the NMSU grid.

+ Based on average power factor of 93% metered by El Paso Electric

The NMSU electrical distribution system incorporates several locations were one feeder can be connected to another through a normally open switch. This allows a main feeder breaker to be taken off line for maintenance or to re-feed portions of the system if a part fails. Adding new loads to feeders should consider not just the normal load on the feeder, but the potential of the full load from an adjacent feeder if the feeder tie is closed.

Examples of feeders that can be tied together include: Feeders 5 & 6 Feeders 3 & 5 Feeders 1 & 6 Feeders 2 & 5 Feeders 2 & 3 Feeders 3 & 6 Feeders 3 & 4 Feeders 4 & 6 Feeders 2 & 7

Page 19: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University 0722.00

June 16, 2009 Stage Two Report

SUMMARY OF NMSU FEEDER TABULATION SPREAD SHEET

Feeder # kW (W/SqFt Calc) Metered Max kW Notes

1 9934 862 1

2 1772

3 7655 3783

4 6139 2442

5 8267 2882

6 3798 2352

7 1487 2

Notes: A spread sheet was developed to analyze loading of the 25 kV and 5 kV feeders on campus. The spread sheet listed the buildings connected to each feeder along with an estimated load based on typical watts per square foot for the type of facility. The table above compares the estimated load from that spread sheet with actual metered maximum demand loads at the Tortugas Substation.

1. Square footage of married student housing was not available for the calc, so installed transformer kVA is listed as a calculated load.

2. The turbine EMCS does not monitor the meter for Feeder #7. The watts/sq. ft. for feeder #7 are not accurate because building areas, types of loads and well pump horsepowers were not available. GLHN used 50% of installed transformer kVA as a load in many cases.

Page 20: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University 0722.00

June 16, 2009 Stage Two Report

APPENDIX B – PHOTOGRAPHS

NMSU Central Plant has 2 generators for emergency lighting power in central campus buildings. Voltage is stepped up to 5 kV at central plant and fed through tunnels to disconnects and dry- type transformers for lighting circuit to nearby buildings. This disconnect and transformer are in the utility tunnel near Jett Hall.

Page 21: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University 0722.00

June 16, 2009 Stage Two Report

Jett Hall vault. Maintenance space above the 5 kV oil switches was so tight that the Electric Shop had to chip voids in the vault roof to allow sufficient space to dismantle the switches for maintenance.

Page 22: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University 0722.00

June 16, 2009 Stage Two Report

Thomas & Brown Hall electric vault. The electric vault ceiling is open to a plumbing chase. Plumbing drains with corrosion indicating leakage are above electrical equipment.

Thomas & Brown Vault. Debris on floor indicated water has been ponding on the floor. Note live electrical terminations on transformers.

Page 23: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University 0722.00

June 16, 2009 Stage Two Report

Thomas & Brown Vault. An electrical bus duct and transformers with exposed live electrical terminations is directly below the plumbing chase. Water could run into bust duct causing failure. Tools or piping could be dropped down the chase contacting live electrical parts causing arcing.

Page 24: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University 0722.00

June 16, 2009 Stage Two Report

Williams Hall Electrical Vault. Old technology 5 kV porcelain cutouts are utilized for transformer primary disconnects. Exposed live terminations on transformer secondary are directly opposite the electrical switchboard. Personnel facing the electrical switchboard have their backs exposed to live terminations.

Williams Hall Electrical Vault.

Page 25: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

F1E

New Mexico State UniversityUtility Development Plan

2009-2034+ Existing Building Electrical Load Projections - List 16-Jun-09 T5 Quantity: None T25 Quantity: 60

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+

FEEDER TF1 - RED/EXISTING - TORTUGAS SUBSTATION 13800/23900

1 270

COLE VILLAGE - FOLLOWING NEXT (7) TRANSFORMER LOADS ARE WITH-IN THE COLE VILLAGE - SUBTOTALS 1966 Individually addressed units Housing 168,040 168,040 168,040 168,040 168,040 0 9 x Trenches 1.5 252.06 1169 252.06 252.06 252.06 252.06 252.06 0.00

4 167 T25-100

4 167 T25-105

4 167 T25-110

4 167 T25-115

4 167 T25-120

4 167 T25-125

4 167 T25-180

1 214

TOM COURT VILLAGE/COLE VILLAGE - FOLLOWING NEXT (11) TRANSFORMER LOADS ARE WITH-IN THE TOM COURT VILLAGE - SUBTOTALS 1959 Individually addressed units Housing 71,200 71,200 71,200 71,200 71,200 0 9, 10 x Trenches 1.5 106.80 1895 106.80 106.80 106.80 106.80 106.80 0.00

4 167 T25-210

4 167 T25-215

4 167 T25-220

4 167 T25-225

4 167 T25-230

4 167 T25-235

4 167 T25-240

4 100 T25-245

4 167 T25-250

4 25 T25-255

4 167 T25-260

4 167 T25-265

4 100 T25-300

1 NA WELL # 9 /TOM FORT VILLAGE NA Tom Fort Village/Williams Ave Well #9 10 1 x Trenches 90.00 300 T25-360

1 206

SUTHERLAND VILLAGE - FOLLOWING NEXT (18) TRANSFORMER LOADS ARE WITH-IN THE SUTHERLAND VILLAGE - SUBTOTALS 1958 Individually addressed units Housing 142,400 142,400 142,400 142,400 0 0 6, 9 x Trenches 1.5 213.60 2805 213.60 213.60 213.60 213.60 0.00 0.00

4 100 T25-130

4 167 T25-135

4 167 T25-140

4 167 T25-145

4 167 T25-165

4 100 T25-170

4 167 T25-175

4 167 T25-185

4 100 T25-190

4 167 T25-195

4 167 T25-200

4 167 T25-205

4 167 T25-270

4 167 T25-275

4 167 T25-280

4 167 T25-285

4 167 T25-290

4 167 T25-295

1 462K VISTA del MONTE APARTMENT COMPLEX 1992 1435 Stanley Dr Housing 4,650 4,650 4,650 4,650 4,650 4,650 10 4 x Trenches 1.5 6.98 167 T25-315 6.98 6.98 6.98 6.98 6.98 6.98

1 462M VISTA del MONTE APARTMENT COMPLEX 1992 1415 Stanley Dr Housing 7,079 7,079 7,079 7,079 7,079 7,079 10 4 x Trenches 1.5 10.62 167 T25-310 10.62 10.62 10.62 10.62 10.62 10.62

1 462N VISTA del MONTE APARTMENT COMPLEX 1992 3551 Williams Ave Housing 7,079 7,079 7,079 7,079 7,079 7,079 10 x Trenches 1.5 10.62 T25-310 10.62 10.62 10.62 10.62 10.62 10.62

1 462P VISTA del MONTE APARTMENT COMPLEX 1992 3553 Williams Ave Housing 9,278 9,278 9,278 9,278 9,278 9,278 10 x Trenches 1.5 13.92 T25-310 13.92 13.92 13.92 13.92 13.92 13.92

1 526Q VISTA del MONTE APARTMENT COMPLEX 1995 1435 N Stanley Dr Housing 7,070 7,070 7,070 7,070 7,070 7,070 10 x Trenches 1.5 10.61 T25-315 10.61 10.61 10.61 10.61 10.61 10.61

1 526R VISTA del MONTE APARTMENT COMPLEX 1995 3560 Research Dr Housing 7,070 7,070 7,070 7,070 7,070 7,070 10 x Trenches 1.5 10.61 T25-315 10.61 10.61 10.61 10.61 10.61 10.61

1 526S VISTA del MONTE APARTMENT COMPLEX 1995 1455 N Stanley Dr Housing 7,483 7,483 7,483 7,483 7,483 7,483 10 x Trenches 1.5 11.22 T25-320 11.22 11.22 11.22 11.22 11.22 11.22

1 526T VISTA del MONTE APARTMENT COMPLEX 1995 3548 Research Dr Housing 7,070 7,070 7,070 7,070 7,070 7,070 10 4 x Trenches 1.5 10.61 100 T25-320 T25-325 10.61 10.61 10.61 10.61 10.61 10.61

1 526U VISTA del MONTE APARTMENT COMPLEX 1995 3540 Research Dr Housing 7,070 7,070 7,070 7,070 7,070 7,070 10 x Trenches 1.5 10.61 T25-320 10.61 10.61 10.61 10.61 10.61 10.61

1 526V VISTA del MONTE APARTMENT COMPLEX 1995 3546 Research Dr Housing 7,070 7,070 7,070 7,070 7,070 7,070 10 4 x Trenches 1.5 10.61 100 T25-325 10.61 10.61 10.61 10.61 10.61 10.61

1 526W VISTA del MONTE APARTMENT COMPLEX 1995 3547 Williams Ave Housing 7,070 7,070 7,070 7,070 7,070 7,070 10 4 x Trenches 1.5 10.61 100 T25-300 10.61 10.61 10.61 10.61 10.61 10.61

1 526X VISTA del MONTE APARTMENT COMPLEX 1995 3545 Williams Ave Housing 7,256 7,256 7,256 7,256 7,256 7,256 10 x Trenches 1.5 10.88 T25-300 10.88 10.88 10.88 10.88 10.88 10.88

1 471 AGGIE EXPRESS CONVIENIENCE STORE & LAUNDRY 1992 3555 Williams Ave Services Students, Families 7,423 7,423 7,423 7,423 7,423 7,423 10 2 x Trenches 2 14.85 150 T25-305 14.85 14.85 14.85 14.85 14.85 14.85

Feeder # Bldg. # Building Name Year Built Address CategoryGSF

Dwg Area Notes Fed From Electricity Utility Corridor Watts/SF

Estimated Load KVA

Xformer KVA

Xformer ID Tag

Page 1

Page 26: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

F1E

New Mexico State UniversityUtility Development Plan

2009-2034+ Existing Building Electrical Load Projections - List 16-Jun-09 T5 Quantity: None T25 Quantity: 60

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+

FEEDER TF1 - RED/EXISTING - TORTUGAS SUBSTATION 13800/23900

Feeder # Bldg. # Building Name Year Built Address CategoryGSF

Dwg Area Notes Fed From Electricity Utility Corridor Watts/SF

Estimated Load KVA

Xformer KVA

Xformer ID Tag

1 387B CERVANTES VILLAGE APARTMENT COMPLEX 1983 1390 Stanley Dr Housing 15,968 15,968 15,968 15,968 15,968 0 9, 10, 12 4 x Trenches 1.5 23.95 167 T25-355 23.95 23.95 23.95 23.95 23.95 0.00

1 387D CERVANTES VILLAGE APARTMENT COMPLEX 1983 1400 Stanley Dr Housing 17,964 17,964 17,964 17,964 17,964 0 9, 10, 12 4 x Trenches 1.5 26.95 167 T25-340 26.95 26.95 26.95 26.95 26.95 0.00

1 387D CERVANTES VILLAGE APARTMENT COMPLEX 1983 1400 Stanley Dr Housing 9, 10, 12 4 x Trenches 167 T25-350

1 387E CERVANTES VILLAGE APARTMENT COMPLEX 1983 3650 Research Way Housing 17,964 17,964 17,964 17,964 17,964 0 9, 10, 12 4 x Trenches 1.5 26.95 167 T25-335 26.95 26.95 26.95 26.95 26.95 0.00

1 413F CERVANTES VILLAGE APARTMENT COMPLEX 1989 1500 Center Way Housing 15,968 15,968 15,968 15,968 15,968 0 9, 10, 12 4 x Trenches 1.5 23.95 167 T25-373 23.95 23.95 23.95 23.95 23.95 0.00

1 413G CERVANTES VILLAGE APARTMENT COMPLEX 1989 4201 Sam Steele Way Housing 15,968 15,968 15,968 15,968 15,968 0 9, 10, 12 4 x Trenches 1.5 23.95 167 T25-371 23.95 23.95 23.95 23.95 23.95 0.00

1 415H CERVANTES VILLAGE APARTMENT COMPLEX 1991 4301 Sam Steele Way Housing 16,768 16,768 16,768 16,768 16,768 0 9, 10, 12 4 x Trenches 1.5 25.15 167 T25-372 25.15 25.15 25.15 25.15 25.15 0.00

1 415H CERVANTES VILLAGE APARTMENT COMPLEX 1991 4301 Sam Steele Way Housing 9, 10, 12 4 x Trenches 167 T25-374

1 415H CERVANTES VILLAGE APARTMENT COMPLEX 1991 4301 Sam Steele Way Housing 9, 10, 12 4 x Trenches 167 T25-378

1 415J CERVANTES VILLAGE APARTMENT COMPLEX 1991 4401 Sam Steele Way Housing 16,768 16,768 16,768 16,768 16,768 0 9, 10, 12 4 x Trenches 1.5 25.15 167 T25-375 25.15 25.15 25.15 25.15 25.15 0.00

1 415J CERVANTES VILLAGE APARTMENT COMPLEX 1991 4401 Sam Steele Way Housing 9, 10, 12 4 x Trenches 167 T25-376

1 415J CERVANTES VILLAGE APARTMENT COMPLEX 1991 4401 Sam Steele Way Housing 9, 10, 12 4 x Trenches 167 T25-377

1 387A CERVANTES VILLAGE BLDG A (CHILDREN'S VILLAGE) 1983 4101 Sam Steele Way Services Students, Families 15,968 15,968 15,968 15,968 15,968 0 9, 10, 12 4 x Trenches 2 31.94 167 T25-365 31.94 31.94 31.94 31.94 31.94 0.00

1 387C CERVANTES VILLAGE BLDG C (CHILDREN'S VILLAGE) 1983 4121 Sam Steele Way Services Students, Families 15,968 15,968 15,968 15,968 15,968 0 9, 10, 12 4 x Trenches 2 31.94 167 T25-370 31.94 31.94 31.94 31.94 31.94 0.00

1 388 VISTA del MONTE COMMUNITY CENTER 1984 1410 Center Dr Services Students, Families 3,393 3,393 3,393 3,393 3,393 3,393 10 3 x Trenches 2 6.79 300 T25-345 6.79 6.79 6.79 6.79 6.79 6.79

PROJECTED EXISTING FEEDER TF1 TOTALS 627,005 627,005 627,005 627,005 484,605 96,061 962 9591 962 962 962 962 748 149

VA/SQFT TOTAL 1.53 1.53 1.53 1.53 1.54 1.56

AMPERE TOTAL 25 249 25 25 25 25 19 4

MAXIMUM DEMAND kW 890 890

CALCULATED AMPS 23 23

EXISTING FEEDER TF1 NMSU 'POWER RICH' TURBINE READINGS: MINIMUM 427kW (11A), MAXIMUM DEMAND 890kW (23A), AVERAGE 620kW (15A). DATE OF MAXIMUM kW READING AUGUST 24, 2007 @ 4:35AM. CALCULATED AMPS BASED ON AN AVERAGE POWER FACTOR OF 95% METERED BY EL PASO ELECTRIC.

GENERAL NOTES

A Refer to New Mexico State University Utility Development Plan Campus Building and Utility Master List for existing and future planned building numbers and square footage.

B New Mexico State University provided site utility plans indicating locations of existing electrical utilities such as feeder circuits, transformer locations, substations, switches and the like with some assumptions being made.

C New Mexico State University provided Campus Electrical Switching for NMSU last updated February 25, 2008 and data sheets received May 27, 2009.

D New Mexico State University provided and obtained metered power readings from the 'Power Rich' EMCS that is part of the the turbine installation.

E New Mexico State University provided and obtained metered power readings from the Niagara system.

F Where building, site data is not availed NA (Not Available/Not Applicable) has been indicated.

G Where building GSF was not available or feeder loads indicate items such as street lights, sports fields and the like the transformer kVA was used as a load at 30% of kVA rating.

NOTES

1 ������������ �� ���������������� ��������� ������������� ������������� ����� ��������������������� ����������� ����� !"#�������� ���$�!##%����!��%� &'#�$�!(��� ���������� ���������������)��������� �* �����+�� �������� ��� � ���� ���������� ��������� ���� ���������%������������+�� ���������������

2 Building 471 Aggie Express Convenience Store & Laundry, transformer T25-305, 150KVA-120/208V, 3Phase pad mounted outdoor unit.

3 Building 388 Vista Del Monte Community Center, transformer T25-345, 300KVA-120/208V, 3P pad mounted outdoor unit.

4 All transformers are identified as 13.8KV -120/240V, single phase pad mounted outdoor unit.

Building Category Watts/SQFT

Academic 2.15

Academic Classroom (Acad - Classroom(s)) 2.3

Academic Classroom Laboratory (Acad - Classroom/Lab) 2.5

Academic Laboratory (Acad - Lab) 3

Administration 2

Auxiliary (AUX) 1.75

Auxiliary/Housing (Aux/Housing) 1.5

Housing Dormitory 1.5

Housing Single Family Residence 1.5

Independent Operations (IO) 2.25

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 2.75

Productions and Operations Management (POM) 5

Productions and Operations Management (POM) 6

Productions and Operations Management (POM) 8

Productions and Operations Management (POM) 12

Services - Family, Student 2

Page 2

Page 27: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

F2E

New Mexico State UniversityUtility Development Plan

2009-2034+ Existing Building Electrical Load Projections - List 16-Jun-09 T5 Quantity: 25 T25 Quantity: 2

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+

FEEDER TF2 - YELLOW/EXISTING - TORTUGAS SUBSTATION 13800/23900

2LOCUST AND STEWART SUBSTATION - FOLLOWING NEXT (10) LOADS ON T25-450

2 NA STREET LIGHTS NA GREGG/WILLIAMS-AVE Housing -Site 7 x Trenches 33.75 112.5 T5-385 T25-450 33.75 33.75 33.75 33.75 33.75 33.752 211 RENTFROW GYM 1958 3165 Williams Ave Acad-Gymnasium 13,622 13,622 0 0 0 0 7 x Trenches 2.3 31.33 225 T5-390 T25-450 31.33 31.33 0.00 0.00 0.00 0.00

2 248 REGENTS ROW 1962 3034 McFle Circle Administration 82,386 82,386 82,386 82,386 0 0 7 x Trenches 2 164.77 500 T5-395 T25-450 164.77 164.77 164.77 164.77 0.00 0.00

2 248 REGENTS ROW 1962 3034 McFle Circle Administration 7 x Trenches 22.50 45 T5-400 T25-450 22.50 22.50 22.50 22.50 0.00 0.00

2 248 REGENTS ROW 1962 3034 McFle Circle Administration 7 x Trenches 22.50 45 T5-405 T25-450 22.50 22.50 22.50 22.50 0.00 0.00

2 248 REGENTS ROW 1962 3034 McFle Circle Administration 7 x Trenches 37.50 75 T5-410 T25-450 37.50 37.50 37.50 37.50 0.00 0.00

2 261 STUDENT HEALTH SERVICE 1965 3080 Breland Auxiliary 16,456 16,456 16,456 16,456 16,456 16,456 7 x Trenches 1.75 28.80 225 T5-415 T25-450 28.80 28.80 28.80 28.80 28.80 28.80

2 184 BRELAND HALL 1954 1525 Steward St Acad- Laboratory 95,313 95,313 95,313 95,313 95,313 95,313 7 x Trenches 3 285.94 500 T5-420 T25-450 285.94 285.94 285.94 285.94 285.94 285.94

2 251 NATATORIUM 1962 1520 Steward St Auxiliary 15,421 15,421 15,421 15,421 15,421 15,421 7 x Trenches 1.75 26.99 150 T5-420 T25-450 26.99 26.99 26.99 26.99 26.99 26.99

2 321 JAMES B. DELAMATER ACITIVITY CENTER 1973 1600 Steward St Acad- Gymnasium 57,055 57,055 57,055 57,055 57,055 57,055 7 1 x Trenches 2.3 131.23 500 T5-430 T25-450 131.23 131.23 131.23 131.23 131.23 131.23LOCUST AND STEWART SUBSTATION T25-450 - SUBTOTAL 280,253 280,253 266,631 266,631 184,245 184,245 785.30 2500 T25-450 785.30 785.30 753.97 753.97 506.70 506.70

2WELLS AND LOCUST SUBSTATION - FOLLOWING NEXT (31) LOADS ON T25-465

2 347 ANIMAL CARE FACILITY 1978 3520 Research Dr. Acad- Laboratory 4,058 4,058 4,058 4,058 4,058 4,058 10 3 x Trenches 3 12.17 500 T5-165 T25-465 12.17 12.17 12.17 12.17 12.17 12.17

2 221 OFS OFFICE 1960 1530 Well St POM 6,461 6,461 6,461 6,461 0 0 10 3 x Trenches 1.5 9.69 T5-165 T25-465 9.69 9.69 9.69 9.69 0.00 0.00

2 NA SOCCER FIELD RESTROOMS NA NA Site 10 3 x Trenches 5.00 T5-165 T25-465 5.00 5.00 5.00 5.00 5.00 5.002 267 FIRE STATION (OFS) 1965 1510 Wells St. POM 9,476 9,476 9,476 9,476 0 0 10 4 x Trenches 1.5 14.21 75 T5-170 T25-465 14.21 14.21 14.21 14.21 0.00 0.00

2 373 OFS MOTOR POOL 1981 3535 Research Dr POM 3,636 3,636 3,636 3,636 0 0 10 4 x Trenches 2.75 10.00 T5-170 T25-465 10.00 10.00 10.00 10.00 0.00 0.00

2 369 PHOTOVOLTAIC EXPERTIMENTAL STATION/CENTER 1980 3705 Research Dr. Acad- Laboratory 3,002 3,002 3,002 3,002 3,002 3,002 12 5 x Trenches 3 9.01 50 T5-175 T25-465 9.01 9.01 9.01 9.01 9.01 9.01

2 514 PHOTOVOLTAIC EXPERTIMENTAL STATION/LABS 1980 3705 Research Dr. Acad- Laboratory 8,951 8,951 8,951 8,951 8,951 8,951 12 5 x Trenches 3 26.85 T5-175 T25-465 26.85 26.85 26.85 26.85 26.85 26.85

2 343 AIR TEST FACILITY/WIND TUNNEL 1977 1625 Standley Dr Acad-Classroom 1,630 1,630 1,630 1,630 1,630 1,630 10 x Trenches 90.00 300 T5-180 T25-465 90.00 90.00 90.00 90.00 90.00 90.002 381 DEPARTMENTAL STORAGE NA NA Auxiliary 13,517 13,517 13,517 13,517 0 0 10 x Trenches 7.50 25 T5-185 T25-465 7.50 7.50 7.50 7.50 0.00 0.00

2 382 DEPARTMENTAL STORAGE NA NA Auxiliary 13,517 13,517 13,517 13,517 0 0 10 T5-185 T25-4652 384 DEPARTMENTAL STORAGE NA NA Auxiliary 18,293 18,293 18,293 18,293 0 0 10 T5-185 T25-4652 371 WIND TUNNEL/RESEARCH BUILDING 1981 1635 Standley Dr. Acad- Laboratory 10,031 10,031 10,031 10,031 0 0 10 x Trenches 3 30.09 50 T5-190 T25-465 30.09 30.09 30.09 30.09 0.00 0.00

2 371 WIND TUNNEL/RESEARCH BUILDING 1981 1635 Standley Dr. Acad- Laboratory 10 6 50 T5-195 T25-4652 371 WIND TUNNEL/RESEARCH BUILDING 1981 1635 Standley Dr. Acad- Laboratory 10 6 50 T5-200 T25-4652 355 WELLS HALL 1978 1720 Wells St. Acad- Laboratory 20,049 20,049 20,049 0 0 0 10 x Trenches 3 60.15 112.5 T5-205 T25-465 60.15 60.15 60.15 0.00 0.00 0.00

2 223 OFS GROUNDS SHOP 1959 1530 Wells St. POM 7,687 7,687 7,687 7,687 0 0 10 x Trenches 2.75 21.14 112.5 T5-210 T25-465 21.14 21.14 21.14 21.14 0.00 0.00

2 398 COSMEDIC RAY LAB 1989 3515 Locust St. Acad- Laboratory 917 917 917 0 0 0 10 x Trenches 3 26.41 112.5 T5-215 T25-465 26.41 26.41 26.41 0.00 0.00 0.002 385 THEATRE SCENE SHOP 1983 3525 Locust St. Acad- Laboratory 7,886 7,886 7,886 0 0 0 10 7 T5-215 T25-4652 467 HOUSING/BOOKSTORE WAREHOUSE 1992 3533 Locust St. Housing 14,885 14,885 14,885 0 0 0 10 x Trenches 1.5 22.60 500 T5-220 T25-465 22.60 22.60 22.60 0.00 0.00 0.002 417 ANTENNA FARM 1990 3615 Locust Ave. Acad-Classroom/Site 180 180 180 180 180 180 10 x Trenches 22.50 75 T5-225 T25-465 22.50 22.50 22.50 22.50 22.50 22.502 271 GREEK COMPLEX (FRATERNITY HOUSES) 1966 1745 Wells St. Housing 7,653 7,653 7,653 0 0 0 7/10 x Trenches 1.5 45.92 300 T5-230 T25-465 45.92 45.92 45.92 0.00 0.00 0.002 272 GREEK COMPLEX 1966 1745 Wells St. Housing 7,653 7,653 7,653 0 0 0 7/10 8 T5-230 T25-4652 273 GREEK COMPLEX 1966 1745 Wells St. Housing 7,653 7,653 7,653 0 0 0 7/10 8 T5-230 T25-4652 274 GREEK COMPLEX 1966 1745 Wells St. Housing 7,653 7,653 7,653 0 0 0 7/10 8 T5-230 T25-4652 414 GREEK COMPLEX 1990 1775 Wells St. Housing 36,908 36,908 36,908 0 0 0 7/10 x Trenches 1.5 55.36 225 T5-235 T25-465 55.36 55.36 55.36 55.36 0.00 0.00

2 222 OFS WAREHOUSE/WELL 8 1960 1600 Wells St. POM 25,306 25,306 25,306 25,306 0 0 10 x Trenches 2.75 139.67 500 T5-440 T25-465 139.67 139.67 139.67 139.67 0.00 0.002 152 OFS CUSTODIAL QUONSET (HOUSING) 1948 1710 Wells St. POM 5,307 5,307 5,307 5,307 0 0 10 9 T5-440 T25-465

2 153OFS STORAGE QUONSET ENTTOMOLOGY LAB (EPPWS) 1949 1620 Well St. POM 5,095 5,095 5,095 5,095 0 0 10 9 T5-440 T25-465

2 220 OFS CARPENTER SHOP 1960 1530 Wells St. POM 6,372 6,372 6,372 6,372 0 0 10 9 T5-440 T25-4652 223 OFS GROUNDS 1959 1530 Wells St. POM 7,687 7,687 7,687 7,687 0 0 10 9 T5-440 T25-4652 455 OFS MASONARY SHOP 1989 1530 Wells St. POM 1,022 1,022 1,022 1,022 0 0 10 9 T5-440 T25-465

WELLS AND LOCAUST SUBSTATION T25-465 - SUBSTOTAL 262,485 262,485 262,485 151,228 17,821 17,821 608.27 2500 T25-465 608.27 608.27 608.27 453.20 165.53 165.53

Feeder # Bldg. # Building Name Year Built Address CategoryGSF

Dwg Area

Notes Fed From Electricity Utility Corridor Watts/SFEstimated Load KVA

Xformer KVA

Xformer ID Tag

Page 1

Page 28: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

F2E

New Mexico State UniversityUtility Development Plan

2009-2034+ Existing Building Electrical Load Projections - List 16-Jun-09 T5 Quantity: 25 T25 Quantity: 2

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+

FEEDER TF2 - YELLOW/EXISTING - TORTUGAS SUBSTATION 13800/23900

Feeder # Bldg. # Building Name Year Built Address CategoryGSF

Dwg Area

Notes Fed From Electricity Utility Corridor Watts/SFEstimated Load KVA

Xformer KVA

Xformer ID Tag

2LOCUST AND STEWART SUBSTATION T25-450 SUBTOTAL 280,253 280,253 266,631 266,631 184,245 184,245 785.30 2500 T25-450 785.30 785.30 753.97 753.97 506.70 506.70

2WELLS ANS LOCAUST SUBSTATION T25-460 SUBTOTAL 262,485 262,485 262,485 151,228 17,821 17,821 608.27 2500 T25-465 608.27 608.27 608.27 453.20 165.53 165.53

PROJECTED EXISTING FEEDER TF2 TOTALS 542,738 542,738 529,116 417,859 202,066 202,066 1394 5000 1394 1394 1362 1207 672 672

VA/SQFT TOTAL 3 3 3 3 3 3

AMPERE TOTAL 36 130 36 36 35 31 17 17

MAXIMUM DEMAND kW 822 822

CALCULATED AMPS 21 21

EXISTING FEEDER TF2 NMSU 'POWER RICH' TURBINE READINGS: MINIMUM 359kW (9A), MAXIMUM DEMAND 822kW (22A), AVERAGE 580kW (15A). DATE OF MAXIMUM kW READING AUGUST 24, 2007, NO TIME AVAIABLE. CALCULATED AMPS BASED ON AN AVERAGE POWER FACTOR OF 95% METERED BY EL PASO ELECTRIC.

GENERAL NOTES

A Refer to New Mexico State University Utility Development Plan Campus Building and Utility Master List for existing and future planned building numbers and square footage.

B New Mexico State University provided site utility plans indicating locations of existing electrical utilities such as feeder circuits, transformer locations, substations, switches and the like with some assumptions being made.

C New Mexico State University provided Campus Electrical Switching for NMSU last updated February 25, 2008 and data sheets received May 27, 2009.

D New Mexico State University provided and obtained metered power readings from the 'Power Rich' EMCS that is part of the the turbine installation.

E New Mexico State University provided and obtained metered power readings from the Niagara system.

F Where building, site data is not availed NA (Not Available/Not Applicable) has been indicated.

G Where building GSF was not available or feeder loads indicate items such as street lights, sports fields and the like the transformer kVA was used as a load at 30% of kVA rating.

NOTES

1 James B. Delamater Activity Center Building 321 (1973) and James B. Delamater Activity Center 96 Addition (1996) GSF as indicated in the Master Building Matrix was divided between the 5kV (Circuit 2) and 25kV (Circuit 5) feeders.

2 Wind Tunnel/Research Building 371 GSF as indicated in the Master Building Matrix was divided between the 5kV (Circuit 2) and the 25kV (Circuit 5) feeders.

3 Animal Care Facility Building 347, OFS Office Building 221 and Soccer Field Restroom are fed from transformer T5-165.

4 Fire Station (OFS) Building 267 and OFS Motor Pool Building 373 are fed from transformer T5-170.

5 Photovoltaic Experimental Station/Center Building 369 and Photovoltaic Experimental Station/Lab Building 514 are fed from transformer T5-175.

6 Wind Tunnel Research Building 371 10,031 GSF and all estimated loads included on line above.

7 Cosmic Ray Lab Building 398 and Theater Scene Shop Building 385 are fed from transformer T5-215.

8 Greek Complex Building 271, 272, 273, 273 are fed from transformer T5-230 and all estimated loads included on line above.

9 OFS Warehouse , Well 8 Building 222, OFS Custodial Quonset (Housing) Building 152, OFS Storage Quonset Entomology Lab (EPPWS) Building 153, OFS Grounds Building 223,

OFS Carpenter Shop Building 220, OFS Masonry Shop Building 455 are fed from transformer T5-455 and all estimated loads included on line above.

Building Category Watts/SQFT

Academic 2.15

Academic Classroom (Acad - Classroom(s)) 2.3

Academic Classroom Laboratory (Acad - Classroom/Lab) 2.5

Academic Laboratory (Acad - Lab) 3

Administration 2

Auxiliary (AUX) 1.75

Auxiliary/Housing (Aux/Housing) 1.5

Housing Dormitory 1.5

Housing Single Family Residence 1.5

Independent Operations (IO) 2.25

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 2.75

Productions and Operations Management (POM) 5

Productions and Operations Management (POM) 6

Productions and Operations Management (POM) 8

Productions and Operations Management (POM) 12

Services - Family, Student 2

Page 2

Page 29: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

F2E

Page 3

Page 30: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

F2E

Page 4

Page 31: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

F3E

New Mexico State UniversityUtility Development Plan

2009-2034+ Existing Building Electrical Load Projections - List 16-Jun-09 T5 Quantity: 17 T25 Quantity: 8

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+

FEEDER TF3 - GREEN/EXISTING - TORTUGAS SUBSTATION 13800/23900

3

COLLEGE SUBSTATION (NES) CENTRAL PLANT - FOLLOWING NEXT (3) LOADS ON T25-395 AND T25-400 REDUNDANT TRANSFORMERS/FEEDERS

3 NA CHILLER #1 ( 116 RLA @ 4.16kV) NA Central Plant Building #269 Mechanical Equipment 6 x 836.00 T25-395/400 836.00 836.00 836.00 836.00 836.00 836.00

3 NA CHILLER #2 ( 116 RLA @ 4.16kV) NA Central Plant Building #269 Mechanical Equipment 6 x 836.00 T25-395/400 836.00 836.00 836.00 836.00 836.00 836.00

3 NA CHILLER #3 ( 116 RLA @ 4.16kV) NA Central Plant Building #269 Mechanical Equipment 6 x 836.00 T25-395/400 836.00 836.00 836.00 836.00 836.00 836.00

3 541 ED AND HAROLD FOREMAN ENGINEERING COMPLEX 1997 1060 Frenger Mall Acad- Laboratory 84,526 84,526 84,526 84,526 84,526 84,526 6 x Trenches 3 253.58 1500 T5 -845 T25-395/400 253.58 253.58 253.58 253.58 253.58 253.58COLLEGE SUBSTATION REDUNDANT TRANSFORMERS/FEEDERS T25-395 AND OR T25-400 SUBTOTAL 84,526 84,526 84,526 84,526 84,526 84,526 2761.58 2500 T25-395/400 2761.58 2761.58 2761.58 2761.58 2761.58 2761.58

3

PHYSICAL SCIENCE LAB (PSL) SUBSTATION - FOLLOWING NEXT (9) LOADS ON T25-405 (H3T4 TRANSFORMER)

3 330 NEW MEXICO DEPARTMENT OF AGRICULTURE 1975 3190 South Espina St. IO 28,288 28,288 28,288 28,288 28,288 28,288 6 x Trenches 2.25 63.65 500 T5-100 T25-405 63.65 63.65 63.65 63.65 63.65 63.65

3 282 STUCKY HALL 1970 3170 South Espina St. IO- Laboratory 5,234 5,234 5,234 0 0 0 6 x Trenches 2.25 11.78 75 T5-105 T25-405 11.78 11.78 11.78 0.00 0.00 0.00

3 263PHYSICAL SCIENCE LAB (PSL) CLINTON P. ANDERSON HALL 1965 1050 Stewart St. Acad- Laboratory 135,847 135,847 135,847 135,847 135,847 135,847 6 x Trenches 3 268.98 750 T5-130 T25-405 268.98 268.98 268.98 268.98 268.98 268.98

3 263PHYSICAL SCIENCE LAB (PSL) CLINTON P. ANDERSON HALL 1965 1050 Stewart St. Acad- Laboratory 1 x Trenches 3 134.49 300 T5-135 T25-405 134.49 134.49 134.49 134.49 134.49 134.49

3 279PHYSICAL SCIENCE LAB (PSL) GARAGE/CARPENTRY/PAINT SHOP 1966 1050 Stewart St. Acad-Classroom 6,800 6,800 6,800 0 0 0 6 x Trenches 2.3 15.64 500 T5-140 T25-405 15.64 15.64 15.64 0.00 0.00 0.00

3 472PHYSICAL SCIENCE LAB (PSL) ENVIRONMENTAL TEST FACILITY 1992 1050 Stewart St. Acad-Laboratory 1,200 1,200 1,200 1,200 1,200 1,200 6 x Trenches 3 4.36 500 T5-145 T25-405 4.36 4.36 4.36 4.36 4.36 4.36

3 242 PHYSICAL SCIENCE LAB (PSL) SOLAR BUILDING 1969 1050 Stewart St. Acad-Laboratory 152 152 152 152 152 152 6 2 T5-145 T25-405

3 523 PHYSICAL SCIENCE LAB (PSL) ASTRO HUT 1969 1050 Stewart St. Acad-Laboratory 100 100 100 100 100 100 6 2 T5-145 T25-405

3 280PHYSICAL SCIENCE LAB (PSL) FABRICATION SHOP (WEST) 1966 1050 Stewart St. Acad-Classroom 6,856 6,856 6,856 0 0 0 6 x Trenches 2.3 15.77 300 T5-150 T25-405 15.77 15.77 15.77 0.00 0.00 0.00

3 216 PHYSICAL SCIENCE LAB (PSL) MACHINE SHOP (EAST) 1959 1050 Stewart St. Acad-Classroom 7,570 7,570 7,570 0 0 0 6 x Trenches 2.3 17.41 112.5 T5-155 T25-405 17.41 17.41 17.41 0.00 0.00 0.00

3 243 PHYSICAL SCIENCE LAB (PSL) ANNEX 1961 1050 Stewart St. Acad-Classroom 6,288 6,288 6,288 0 0 0 6 x Trenches 2.3 14.46 112.5 T5-160 T25-405 14.46 14.46 14.46 0.00 0.00 0.00PHYSICAL SCIENCE LAB (PSL) SUBSTATION T25-405 (H3T4) SUBTOTAL 198,335 198,335 198,335 165,587 165,587 165,587 546.53 2000 T25-405 546.53 546.53 546.53 471.47 471.47 471.47

3HARDMAN SUBSTATION FOLLOWING NEXT (7) LOADS ON T25-420

3 276 WALDEN HALL 1966 1200 Frenger Mall Acad- Laboratory 36,259 36,259 36,259 36,259 36,259 36,259 6 x Trenches 3 108.78 500 T5-600 T25-420 108.78 108.78 108.78 108.78 108.78 108.78

3 278 BRANSON LIBRARY/HALL 1951 1305 Frenger Mall Acad 159,696 159,696 159,696 159,696 159,696 159,696 6 x Trenches 2.15 343.35 1500 T5-605 T25-420 343.35 343.35 343.35 343.35 343.35 343.35

3 32 YOUNG HALL 1928 1300 South Horseshoe Acad-Classroom 12,713 12,713 12,713 12,713 12,713 12,713 2 x Trenches 2.3 29.24 300 T5-610 T25-420 29.24 29.24 29.24 29.24 29.24 29.24

3 461 ZUHL LIBRARY (NEW) 1992 2911 McFie Circle Acad 95,952 95,952 95,952 95,952 95,952 95,952 7 x Trenches 2.15 206.30 750 T5-615 T25-420 206.30 206.30 206.30 206.30 206.30 206.30

3 225 ASTRONOMY BUILDING 1959 1320 Frenger Mall Acad- Laboratory 15,486 15,486 15,486 15,486 15,486 15,486 7 x Trenches 3 46.46 300 T5-620 T25-420 46.46 46.46 46.46 46.46 46.46 46.46

3 82 BIOLOGY ANNEX 1941 3080 Williams Ave. Acad- Laboratory 11,280 11,280 11,280 11,280 11,280 11,280 7 x Trenches 3 33.84 500 T5-625 T25-420 33.84 33.84 33.84 33.84 33.84 33.84

3 262 FRENGER FOOD COURT 1965 1420 Frenger Mall Auxiliary 6,678 6,678 6,678 6,678 6,678 6,678 7 x Trenches 1.75 11.69 300 T5-630 T25-420 11.69 11.69 11.69 11.69 11.69 11.69

HARDMAN SUBSTATION T25-420 SUBTOTAL 338,064 338,064 338,064 338,064 338,064 338,064 779.64 2500 T25-420 779.64 779.64 779.64 779.64 779.64 779.64

Feeder # Bldg. # Building Name Year Built Address CategoryGSF

Dwg Area Notes Fed From Electricity Utility Corridor Watts/SF

Estimated Load KVA

Xformer KVA

Xformer ID Tag

Page 1

Page 32: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

F3E

New Mexico State UniversityUtility Development Plan

2009-2034+ Existing Building Electrical Load Projections - List 16-Jun-09 T5 Quantity: 17 T25 Quantity: 8

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+

FEEDER TF3 - GREEN/EXISTING - TORTUGAS SUBSTATION 13800/23900

Feeder # Bldg. # Building Name Year Built Address CategoryGSF

Dwg Area Notes Fed From Electricity Utility Corridor Watts/SF

Estimated Load KVA

Xformer KVA

Xformer ID Tag

3

COLLEGE SUBSTATION REDUNDANT TRANSFORMERS/FEEDERS T25-395 AND OR T25-400 SUBTOTAL 84,526 84,526 84,526 84,526 84,526 84,526 2,761.58 2500 T25-395/400 2761.58 2761.58 2761.58 2761.58 2761.58 2761.58

3PHYSICAL SCIENCE LAB (PSL) SUBSTATION T25-405 (H3T4) SUBTOTAL 198,335 198,335 198,335 165,587 165,587 165,587 546.53 2000 T25-405 546.53 546.53 546.53 471.47 471.47 471.47

3 HARDMAN SUBSTATION T25-420 SUBTOTAL 338,064 338,064 338,064 338,064 338,064 338,064 779.64 2500 T25-420 779.64 779.64 779.64 779.64 779.64 779.643 126 COMPUTER CENTER 1966 1275 Stewart St. Acad- Laboratory 40,288 40,288 40,288 40,288 40,288 40,288 6 x Trenches 3 120.86 2000 T25-410 120.86 120.86 120.86 120.86 120.86 120.86

3 287 O'DONNELL HALL 1968 1220 Stewart St. Acad- Laboratory 93,858 93,858 93,858 93,858 93,858 93,858 6 x Trenches 3 281.57 750 T25-412 281.57 281.57 281.57 281.57 281.57 281.57

3 391 SCIENCE HALL (NEW) 1987 1290 Frenger Mall Acad- Laboratory 114,918 114,918 114,918 114,918 114,918 114,918 6 x Trenches 3 344.75 1500 T25-415 344.75 344.75 344.75 344.75 344.75 344.75

3 126 COMPUTER CENTER 1966 1275 Stewart St. Acad- Laboratory 40,288 40,288 40,288 40,288 40,288 40,288 6 3 x Trenches 3 120.86 2000 T25-410 120.86 120.86 120.86 120.86 120.86 120.86

PROJECTED EXISTING FEEDER TF3 TOTALS 869,989 869,989 869,989 837,241 837,241 837,241 4835 11250 4835 4835 4835 4760 4760 4760

VA/SQFT TOTAL 6 6 6 6 6 6

AMPERE TOTAL 126 292 126 126 126 124 124 124

MAXIMUM DEMAND kW 3982 3982

CALCULATED AMPS 103 103

EXISTING FEEDER TF3 NMSU 'POWER RICH' TURBINE READINGS: MINIMUM 845kW (22A), MAXIMUM DEMAND 3982kW (104A), AVERAGE 2264kW (59A). DATE OF MAXIMUM kW READING JUNE 18, 2008 @ 8:52PM. CALCULATED AMPS BASED ON AN AVERAGE POWER FACTOR OF 95% METERED BY EL PASO ELECTRIC.

GENERAL NOTES

A Refer to New Mexico State University Utility Development Plan Campus Building and Utility Master List for existing and future planned building numbers and square footage.

B New Mexico State University provided site utility plans indicating locations of existing electrical utilities such as feeder circuits, transformer locations, substations, switches and the like with some assumptions being made.

C New Mexico State University provided Campus Electrical Switching for NMSU last updated February 25, 2008 and data sheets received May 27, 2009.

D New Mexico State University provided and obtained metered power readings from the 'Power Rich' EMCS that is part of the turbine installation.

E New Mexico State University provided and obtained metered power readings from the Niagara system.

F Where building, site data is not availed NA (Not Available/Not Applicable) has been indicated.

G Where building GSF was not available or feeder loads indicate items such as street lights, sports fields and the like the transformer kVA was used as a load at 30% of kVA rating.

NOTES

1 Physical Science Lab Building #263 loads is shared with transformers T5-130 and T51-35.

2 Physical Science Lab Buildings #472, 242, 523 loads are shared with transformer T5-145.

3 Computer Center Building 126 GSF, loads and the like have not been included because feeder #3 is an alternate feeder.

Building Category Watts/SQFT

Academic 2.15

Academic Classroom (Acad - Classroom(s)) 2.3

Academic Classroom Laboratory (Acad - Classroom/Lab) 2.5

Academic Laboratory (Acad - Lab) 3

Administration 2

Auxiliary (AUX) 1.75

Auxiliary/Housing (Aux/Housing) 1.5

Housing Dormitory 1.5

Housing Single Family Residence 1.5

Independent Operations (IO) 2.25

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 2.75

Productions and Operations Management (POM) 5

Productions and Operations Management (POM) 6

Productions and Operations Management (POM) 8

Productions and Operations Management (POM) 12

Services - Family, Student 2

Page 2

Page 33: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

F4E

New Mexico State UniversityUtility Development Plan

2009-2034+ Existing Building Electrical Load Projections - List 16-Jun-09 T5 Quantity: 47 T25 Quantity: 2

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+

*FEEDER TF4 - BLUE/EXISTING - TORTUGAS SUBSTATION 13800/23900

4

CENTRAL PLANT FEEDER 'EFCC' - FOLLOWING NEXT (4) LOADS ON T25-385 AND T25-390 REDUNDANT TRANSFORMERS/FEEDERS

4 126 COMPUTER CENTER 1966 1275 Stewart St. Acad-Laboratory 40,288 40,288 40,288 40,288 40,288 40,288 6 x Trenches 3 120.86 1000 T5-820 T25-385/390 120.86 120.86 120.86 120.86 120.86 120.864 126 COMPUTER CENTER 1966 1275 Stewart St. Acad-Laboratory 40,288 40,288 40,288 40,288 40,288 40,288 6 1 x Pole/Overhead 3 120.86 500 T5-825 T25-385/390 120.86 120.86 120.86 120.86 120.86 120.864 126 COMPUTER CENTER 1966 1275 Stewart St. Acad-Laboratory 40,288 40,288 40,288 40,288 40,288 40,288 6 1 x Trenches 3 120.86 112.5 T5-830 T25-385/390 120.86 120.86 120.86 120.86 120.86 120.864 126 COMPUTER CENTER 1966 1275 Stewart St. Acad-Laboratory 40,288 40,288 40,288 40,288 40,288 40,288 6 1 x Trenches 3 120.86 500 T5-840 T25-385/390 120.86 120.86 120.86 120.86 120.86 120.86

CENTRAL PLANT FEEDER 'EPCC' - SUBTOTAL 40,288 40,288 40,288 40,288 40,288 40,288 483.46 2112.5 483.46 483.46 483.46 483.46 483.46 483.46

4

CENTRAL PLANT FEEDER 'EFCP' - FOLLOWING NEXT (2) LOADS ON T25-385 AND T25-390 REDUNDANT TRANSFORMERS/FEEDERS

4 269 OFS CENTRAL HEATING PLANT - 'TCB' 1966 3060 Sweet St POM 21,071 21,071 21,071 21,071 21,071 21,071 6 x Trenches 6 126.43 1500 T5-875 T25-385/390 126.43 126.43 126.43 126.43 126.43 126.434 269 OFS CENTRAL HEATING PLANT - 'TCP' 1966 3060 Sweet St POM 21,071 21,071 21,071 21,071 21,071 21,071 6 2 x Trenches 6 126.43 2000 T5-880 T25-385/390 126.43 126.43 126.43 126.43 126.43 126.43

CENTRAL PLANT FEEDER 'EPCP' - SUBTOTAL 21,071 21,071 21,071 21,071 21,071 21,071 252.85 3500 252.85 252.85 252.85 252.85 252.85 252.85

4

CENTRAL PLANT FEEDER 'EFM' - FOLLOWING NEXT (18) LOADS ON T25-385 AND T25-390 REDUNDANT TRANSFORMER FEEDERS

4 172 HADLEY HALL 1953 2855 Weddell St. Administration 38,199 38,199 38,199 38,199 38,199 38,199 2 x Trenches 2 103.35 450 T5-675 T25-385/390 103.35 103.35 103.35 103.35 103.35 103.354 56 DOVE HALL 1936 1305 North Horseshoe Administration 13,476 13,476 13,476 13,476 13,476 13,476 2 3 x Trenches 2 T5-675 T25-385/3904 288 GUTHRIE HALL 1968 1325 International Mall Acad-Classroom 41,531 41,531 41,531 41,531 41,531 41,531 3 x Trenches 2.3 95.52 500 T5-680 T25-385/390 95.52 95.52 95.52 95.52 95.52 95.524 365 ENGLISH/SPEECH BUILDING 1981 1405 International Mall Acad-Classroom 28,322 28,322 28,322 28,322 28,322 28,322 3 x Trenches 2.3 65.14 500 T5-685 T25-385/390 65.14 65.14 65.14 65.14 65.14 65.144 323 HARDMAN HALL 1974 2902 McFie Circle Acad-Classroom 30,370 0 0 0 0 0 3 x Trenches 2.3 69.85 150 T5-690 T25-385/390 69.85 0.00 0.00 0.00 0.00 0.004 250 JACOBS HALL 1963 2908 McFie Circle Acad-Laboratory 22,433 0 0 0 0 0 3 x Trenches 3 67.30 112.5 T5-695 T25-385/390 67.30 0.00 0.00 0.00 0.00 0.004 250 JACOBS HALL 1963 2908 McFie Circle Acad-Laboratory 0 0 0 0 0 0 3 4 x Trenches 3 67.30 500 T5-700 T25-385/390 67.30 0.00 0.00 0.00 0.00 0.004 249 HERSCHELL ZOHN (HZ) THEATRE 1963 3014 McFie Circle Acad-Classroom 23,572 0 0 0 0 0 7 x Trenches 2.3 54.22 750 T5-705 T25-385/390 54.22 0.00 0.00 0.00 0.00 0.004 389 MUSIC CENTER 1983 1075 North Horseshoe Acad-Classroom 56,153 56,153 56,153 56,153 56,153 56,153 2 x Trenches 2.3 129.15 750 T5-715 T25-385/390 129.15 129.15 129.15 129.15 129.15 129.154 187 CHEMISTRY BUILDING 1957 1175 North Horseshoe Acad-Laboratory 115,878 115,878 115,878 115,878 115,878 115,878 2 x Trenches 3 114.72 500 T5-770 T25-385/390 114.72 114.72 114.72 114.72 114.72 114.724 187 CHEMISTRY BUILDING 1957 1175 North Horseshoe Acad-Laboratory 0 0 0 0 0 0 2 5 x Trenches 3 114.72 225 T5-775 T25-385/390 114.72 114.72 114.72 114.72 114.72 114.724 187 CHEMISTRY BUILDING 1957 1175 North Horseshoe Acad-Laboratory 0 0 0 0 0 0 2 5 x Trenches 3 114.72 150 T5-780 T25-385/390 114.72 114.72 114.72 114.72 114.72 114.724 188 GARDINER HALL 1957 1255 North Horseshoe Acad-Laboratory 63,224 63,224 63,224 63,224 63,224 63,224 2 x Trenches 3 62.59 500 T5-785 T25-385/390 62.59 62.59 62.59 62.59 62.59 62.594 188 GARDINER HALL 1957 1255 North Horseshoe Acad-Laboratory 0 0 0 0 0 0 2 6 x Trenches 3 62.59 225 T5-790 T25-385/390 62.59 62.59 62.59 62.59 62.59 62.594 188 GARDINER HALL 1957 1255 North Horseshoe Acad-Laboratory 0 0 0 0 0 0 2 6 x Trenches 3 62.59 300 T5-795 T25-385/390 62.59 62.59 62.59 62.59 62.59 62.594 33 KENT HALL 1929 1280 E. University Ave. Acad-Classroom 20,473 20,473 20,473 20,473 20,473 20,473 2 x Trenches 2.3 47.09 112.5 T5-800 T25-385/390 47.09 47.09 47.09 47.09 47.09 47.094 386 BUSINESS ADMINISTRATION 1983 1320 University Ave. Acad-Classroom 54,992 54,992 54,992 54,992 54,992 54,992 3 x Trenches 2.3 126.48 501 T5-805 T25-385/390 126.48 126.48 126.48 126.48 126.48 126.484 60 DAN W. WILLIAMS/WILLIAMS HALL 1938 1390 E. University Ave. Acad-Laboratory 36,857 36,857 0 0 0 0 3 x Trenches 3 110.57 150 T5-815 T25-385/390 110.57 110.57 0.00 0.00 0.00 0.004 60A DAN W. WILLIAMS/WILLIAMS HALL ANNEX 1984 1390 E. University Ave. Acad-Laboratory 11,928 11,928 0 0 0 0 3 x Trenches 3 37.56 300 T5-810 T25-385/390 37.56 37.56 0.00 0.00 0.00 0.004 517 WILLIAMS HALL SCULPTURE SHEED 1995 1390 E. University Ave. Acad-Laboratory 592 592 0 0 0 0 3 11 x Trenches

CENTRAL PLANT FEEDER 'EFM' - SUBTOTAL 557,408 481,033 432,248 432,248 432,248 432,248 1505.46 6676 1505.46 1246.80 1098.67 1098.67 1098.67 1098.67

4

CENTRAL PLANT FEEDER 'EFW' - FOLLOWING NEXT (23) LOADS ON T25-385 AND T25-390 REDUNDANT TRANSFORMER FEEDERS

4 245 TEJADA BUILDING EXTENSION ANNEX 1962 3005 Knox St. Acad-Laboratory 11,182 11,182 0 0 0 0 6 x Trenches 3 33.55 150 T5-490 T25-385/390 33.55 33.55 0.00 0.00 0.00 0.004 199 HERDERS RESIDENCE/FARM RESIDENCE 1953 3140 Espina St. Acad-Classroom 1,045 1,045 1,045 0 0 0 6 x Trenches 2.3 2.40 15 T5-495 T25-385/390 2.40 2.40 2.40 0.00 0.00 0.004 164 NEALE HALL 1951 3080 South Espina St. Acad-Laboratory 15,868 15,868 0 0 0 0 6 x Trenches 3 47.60 500 T5-500 T25-385/390 47.60 47.60 0.00 0.00 0.00 0.004 NA AG BUILDING NA NA NA/SITE 0 0 0 0 0 0 6 7 x Trenches/Overhead 90.00 300 T5-505 T25-385/390 90.00 90.00 90.00 90.00 90.00 90.004 NA AG BUILDING NA NA NA/SITE 0 0 0 0 0 0 6 7 x Trenches/Overhead 22.50 75 T5-510 T25-385/390 22.50 22.50 22.50 22.50 22.50 22.504 NA AG BUILDING NA NA NA/SITE 0 0 0 0 0 0 6 7 x Trenches/Overhead 22.50 75 T5-515 T25-385/390 22.50 22.50 22.50 22.50 22.50 22.504 NA AG BUILDING NA NA NA/SITE 0 0 0 0 0 0 6 7 x Trenches/Overhead 67.50 225 T5-520 T25-385/390 67.50 67.50 67.50 67.50 67.50 67.504 NA AG BUILDING NA NA NA/SITE 0 0 0 0 0 0 6 7 x Trenches/Overhead 67.50 225 T5-525 T25-385/390 67.50 67.50 67.50 67.50 67.50 67.504 NA AG BUILDING NA NA NA/SITE 0 0 0 0 0 0 6 7 x Trenches/Overhead 90.00 300 T5-530 T25-385/390 90.00 90.00 90.00 90.00 90.00 90.004 NA AG BUILDING NA NA NA/SITE 0 0 0 0 0 0 6 7 x Trenches/Overhead 225.00 750 T5-535 T25-385/390 225.00 225.00 225.00 225.00 225.00 225.004 363 ENGINEER COMPLEX 1980 1025 Stewart St. Acad-Laboratory 55,585 55,585 55,585 55,585 55,585 55,585 6 x Trenches 3 300.00 1000 T5-540 T25-385/390 300.00 300.00 300.00 300.00 300.00 300.004 363 ENGINEER COMPLEX 1980 1025 Stewart St. Acad-Laboratory 0 0 0 0 0 0 6 8 x Trenches 3 55.03 300 T5-545 T25-385/390 55.03 55.03 55.03 55.03 55.03 55.034 363 ENGINEER COMPLEX 1980 1025 Stewart St. Acad-Laboratory 0 0 0 0 0 0 6 8 x Trenches 3 55.03 300 T5-550 T25-385/390 55.03 55.03 55.03 55.03 55.03 55.034 190 JETT ENGINEERING HALL/ANNEX 1957 1025 Frenger Mall Acad-Laboratory 6,529 6,529 6,529 6,529 6,529 6,529 6 x Trenches 3 19.59 500 T5-555 T25-385/390 19.59 19.59 19.59 19.59 19.59 19.594 189 JETT ENGINEERING HALL 1956 1040 South Horseshoe Acad-Laboratory 84,901 84,901 84,901 84,901 84,901 84,901 6 x Trenches 3 63.68 225 T5-560 T25-385/390 63.68 63.68 63.68 63.68 63.68 63.684 189 JETT ENGINEERING HALL 1956 1040 South Horseshoe Acad-Laboratory 0 0 0 0 0 0 6 9 x Trenches 3 63.68 225 T5-565 T25-385/390 63.68 63.68 63.68 63.68 63.68 63.684 189 JETT ENGINEERING HALL 1956 1040 South Horseshoe Acad-Laboratory 0 0 0 0 0 0 6 9 x Trenches 3 63.68 300 T5570 T25-385/390 63.68 63.68 63.68 63.68 63.68 63.684 189 JETT ENGINEERING HALL 1956 1040 South Horseshoe Acad-Laboratory 0 0 0 0 0 0 6 9 x Trenches 3 63.68 300 T5-575 T25-385/390 63.68 63.68 63.68 63.68 63.68 63.684 301 THOMAS AND BROWN HALL 1972 1125 Frenger Mall Acad-Laboratory 49,711 49,711 49,711 49,711 49,711 49,711 6 x Trenches 3 149.13 500 T5-585 T25-385/390 149.13 149.13 149.13 149.13 149.13 149.134 10 GODDARD HALL 1913 1100 South Horseshoe Acad-Laboratory 31,942 31,942 31,942 31,942 31,942 31,942 2 x Trenches 3 95.83 300 T5-587 T25-385/390 95.83 95.83 95.83 95.83 95.83 95.834 34 FOSTER HALL 1930 1200 South Horseshoe Acad-Laboratory 98,084 98,084 98,084 98,084 98,084 98,084 6 x Trenches 3 147.13 750 T5-590 T25-385/390 147.13 147.13 147.13 147.13 147.13 147.134 34 FOSTER HALL 1930 1200 South Horseshoe Acad-Laboratory 0 0 0 0 0 0 6 10 x Trenches 3 147.13 750 T5-591 T25-385/390 147.13 147.13 147.13 147.13 147.13 147.134 368 KNOX HALL 1981 2980 South Espina St. Acad-Laboratory 75,737 75,737 75,737 75,737 75,737 75,737 6 x Trenches 3 227.21 750 T5-885 T25-385/390 227.21 227.21 227.21 227.21 227.21 227.21

CENTRAL PLANT FEEDER 'EFW' - SUBTOTAL 430,584 430,584 403,534 402,489 402,489 402,489 2119.32 8815 2119.32 2119.32 2038.17 2035.77 2035.77 2035.77

Feeder # Bldg. # Building Name Year Built Address CategoryGSF

Dwg Area

Notes Fed From Electricity Utility Corridor Watts/SFEstimated Load KVA

Xformer KVA

Xformer ID Tag

Page 1

Page 34: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

F4E

New Mexico State UniversityUtility Development Plan

2009-2034+ Existing Building Electrical Load Projections - List 16-Jun-09 T5 Quantity: 47 T25 Quantity: 2

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+

*FEEDER TF4 - BLUE/EXISTING - TORTUGAS SUBSTATION 13800/23900

Feeder # Bldg. # Building Name Year Built Address CategoryGSF

Dwg Area

Notes Fed From Electricity Utility Corridor Watts/SFEstimated Load KVA

Xformer KVA

Xformer ID Tag

4 CENTRAL PLANT FEEDER 'EPCC' - SUBTOTAL 40,288 40,288 40,288 40,288 40,288 40,288 483.46 2113 T25-385/390 483.46 483.46 483.46 483.46 483.46 483.464 CENTRAL PLANT FEEDER 'EPCP' - SUBTOTAL 21,071 21,071 21,071 21,071 21,071 21,071 252.85 3500 T25-385/390 252.85 252.85 252.85 252.85 252.85 252.854 CENTRAL PLANT FEEDER 'EFM' - SUBTOTAL 557,408 481,033 432,248 432,248 432,248 432,248 1505.46 6676 T25-385/390 1505.46 1246.80 1098.67 1098.67 1098.67 1098.674 CENTRAL PLANT FEEDER 'EFW' - SUBTOTAL 430,584 430,584 403,534 402,489 402,489 402,489 2119.32 8815 T25-385/390 2119.32 2119.32 2038.17 2035.77 2035.77 2035.77

4CENTRAL PLANT T25-385 AND T25-390 REDUNDANT TANSFORMER FEEDERS - SUBTOTAL 1,049,351 972,976 897,141 896,096 896,096 896,096 4361.09 21104 T25-385/390 4361.09 4102.43 3873.15 3870.74 3870.74 3870.74

2500 T25-385/390

*PROJECTED EXISING FEEDER TF4 TOTALS 1,049,351 972,976 897,141 896,096 896,096 896,096 4361 2500 4361 4102 3873 3871 3871 3871

VA/SQFT TOTAL 4 4 4 4 4 4

AMPERE TOTAL 113 65 113 107 101 101 101 101

MAXIMUM DEMAND kW 2699 2699

CALCULATED AMPS 70 70

MAXIMUM DEMAND kW - (TURBINE/BACKFEED) -2597 -2597

CALCULATED AMPS - (TURBINE/BACKFEED) -67 -67

EXISTING FEEDER TF4 NMSU 'POWER RICH' TURBINE READINGS: MAXIMUM DEMAND +2699kW (70A), AVERAGE -1047kW (-27A). DATE OF MAXIMUM kW READING MAY 14, 2008 @ 3:06AM. CALCULATED AMPS BASED ON AN AVERAGE POWER FACTOR OF 95% METERED BY EL PASO ELECTRIC.

*TF4 FEEDER, POWER FROM TURBINE BACKFEEDS THROUGH THIS BREAKER TO FEED PORTIONS OF THE CAMPUS LOADS. NEGATIVE NUMBER INDICATES POWER GENERATED BY THE TURBINE WHICH IS BEING FED INTO THE NMSU GRID.

POWER RICH' TURBINE READINGS: MAXIMUM DEMAND -2597 (-67A). MAXIMUM kW DEMAND READING DECEMBER 29, 2009 @ 3:32PM.

GENERAL NOTES

A Refer to New Mexico State University Utility Development Plan Campus Building and Utility Master List for existing and future planned building numbers and square footage.

B New Mexico State University provided site utility plans indicating locations of existing electrical utilities such as feeder circuits, transformer locations, substations, switches and the like with some assumptions being made.

C New Mexico State University provided Campus Electrical Switching for NMSU last updated February 25, 2008 and data sheets received May 27, 2009.

D New Mexico State University provided and obtained metered power readings from the 'Power Rich' EMCS that is part of the turbine installation.

E New Mexico State University provided and obtained metered power readings from the Niagara system.

F Where building, site data is not availed NA (Not Available/Not Applicable) has been indicated.

G Where building GSF was not available or feeder loads indicate items such as street lights, sports fields and the like the transformer kVA was used as a load at 30% of kVA rating.

NOTES

1 Computer Center Building 126 GSF, has not been included. There is one (1) building with four (4) transformers, feeders.

2 OFS Central Heating Plant 'TCP' Building 269 GSF, has not been included. There is one (1) building with two (2) transformers, feeders.

3 Dove Hall Building 56 is feed from Hadley Hall Building 172 transformer and feeder.

4 Jacobs Hall Building 250 GSF, has been included in line above. There is one (1) building with two (2) transformers, feeders.

5 Chemistry Building 187 GSF, has been included in line above. There is one (1) building with three(3) transformers, feeders.

6 Gardner Hall Building 186 GSF, has been included in line above. There is one (1) building with three(3) transformers, feeders.

7 No information available as to Building #, address, GSF, and the like. The estimated load is based on transformer size @ 30% load.

8 Engineering Complex Building 363 GSF, has been included in line above. There is only one (1) building with three (3) transformers, feeders.

9 Jett Engineering Hall Building 189 GSF, has been included in the line above. There is only one (1) building with four (4) transformers, feeders.

10 Foster Hall Building 34 GSF, has been included in the line above. There is only one (1) building with two (2) transformers, feeders.

11 Williams Hall Sculpture Shed Building 517 GSF has been in the line above and respective loads included in Dan W. Williams Hall Annex.

Building Category Watts/SQFT

Academic 2.15

Academic Classroom (Acad - Classroom(s)) 2.3

Academic Classroom Laboratory (Acad - Classroom/Lab) 2.5

Academic Laboratory (Acad - Lab) 3

Administration 2

Auxiliary (AUX) 1.75

Auxiliary/Housing (Aux/Housing) 1.5

Housing Dormitory 1.5

Housing Single Family Residence 1.5

Independent Operations (IO) 2.25

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 2.75

Productions and Operations Management (POM) 5

Productions and Operations Management (POM) 6

Productions and Operations Management (POM) 8

Productions and Operations Management (POM) 12

Services - Family, Student 2

Page 2

Page 35: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

F5E

New Mexico State UniversityUtility Development Plan

2009-2034+ Existing Building Electrical Load Projections - List 16-Jun-09 T5 Quantity: 16 T25 Quantity: 20

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+

FEEDER TF5 - PURPLE/EXISTING - TORTUGAS SUBSTATION 13800/23900

5GARCIA SUBSTATION - FOLLOWING NEXT (3) LOADS ON T25-430 VIA S5-320

5 268 CHI OMEGA SORORITY HOUSE NA NA Housing 6,388 6,388 6,388 0 0 0 3 x Trenches 1.5 9.58 30 T5-710 T25-430 9.58 9.58 9.58 0.00 0.00 0.005 275 GARCIA RESIDENCE HALL (FIRST FLOOR) 1968 1715 International Mall Housing 208,371 208,371 208,371 208,371 208,371 208,371 3 x Trenches 1.5 312.56 500 T5-715 T25-430 312.56 312.56 312.56 312.56 312.56 312.565 275 GARCIA RESIDENCE HALL 1968 1715 International Mall Housing 1 x Trenches 500 T5-720 T25-430

GARCIA SUBSATATION T25-430 SUBTOTAL 214,759 214,759 214,759 208,371 208,371 208,371 322.14 1000 T25-430 322.14 322.14 322.14 312.56 312.56 312.56

5LOCUST SUBSTATION - FOLLOWING NEXT (13) LOADS ON T25-435 VIA S5-285

5 285 CORBETT 1968 1600 International Mall Auxiliary 106,656 106,656 106,656 106,656 106,656 106,656 3 7 x Trenches 1.75 186.65 1500 T5-640 T25-440 186.65 186.65 186.65 186.65 186.65 186.655 285 CORBETT 1968 1600 International Mall Auxiliary 3 2,7 x Trenches 300 T5-645 T25-4405 154 GARCIA ANNEX 1949 3024locust St Administration 28,895 28,895 28,895 28,895 28,895 29,895 7 x Trenches 2 57.79 112.5 T5-650 T25-440 57.79 57.79 57.79 57.79 57.79 59.795 NA STREET LIGHTS NA Locust near Chamisa Dorms Site 7 x Trenches 50.00 100 T5-655 T25-440 50.00 50.00 50.00 50.00 50.00 50.005 338 EDUCATIONAL SERVICES CENTER 1978 1780 East University Ave Administration 50,366 50,366 50,366 50,366 50,366 50,366 4 x Trenches 2 100.73 300 T5-660 T25-440 100.73 100.73 100.73 100.73 100.73 100.73

5 250MONAGLE RESIDENCE HALL - WOMENS RESIDENCE CENTER (WRC) 1965 1525 International Mall Housing 121,457 121,457 0 0 0 0 3 x Trenches 1.5 182.19 500 T5-725 T25-440 182.19 182.19 0.00 0.00 0.00 0.00

5 250MONAGLE RESIDENCE HALL - WOMENS RESIDENCE CENTER (WRC) 1965 1525 International Mall Housing 3 3 x Trenches 150 T5-730 T25-440

5 250MONAGLE RESIDENCE HALL - WOMENS RESIDENCE CENTER (WRC) 1965 1525 International Mall Housing 3 3 x Trenches 112.5 T5-735 T25-440

5 250MONAGLE RESIDENCE HALL - WOMENS RESIDENCE CENTER (WRC) 1965 1525 International Mall Housing 3 3 x Trenches 112.5 T5--740 T25-440

5 250MONAGLE RESIDENCE HALL - WOMENS RESIDENCE CENTER (WRC) 1965 1525 International Mall Housing 3 3 x Trenches 112.5 T5-745 T25-440

5 163-213ZETA TAU ALPHA/DELTA ZETA SORORITY HOUSE (ZTA/DZ) NA NA Housing 14,502 14,502 0 0 0 0 3 3 x Trenches 1.5 21.75 75 T5--750 T25-440 21.75 21.75 0.00 0.00 0.00 0.00

5 185RHODES (185) - GARNETT (79) - HAMIEL (80) RESIDENCE HALL 1955 2735 Jordan St Housing 28,324 28,324 28,324 28,324 28,324 28,324 3 x Trenches 1.5 42.49 500 T5-755 T25-440 42.49 42.49 42.49 42.49 42.49 42.49

5 79RHODES (185) - GARNETT (79) - HAMIEL (80) RESIDENCE HALL 1941 2715 Jordan St Housing 37,511 37,511 37,511 37,511 37,511 37,511 3 4 x Trenches 1.5 56.27 500 T5-760 T25-440 56.27 56.27 56.27 56.27 56.27 56.27

5 80RHODES (185) - GARNETT (79) - HAMIEL (80) RESIDENCE HALL 1941 2725 Jordan St Housing 3 5 x Trenches LOCUST SUBSTATION T25-440 SUBTOTAL 387,711 387,711 251,752 251,752 251,752 252,752 697.86 1000 T25-440 697.86 697.86 493.92 493.92 493.92 495.92

5 GARCIA SUBSATATION T25-430 SUBTOTAL 214,759 214,759 214,759 208,371 208,371 208,371 x Trenches 322.14 1000 T25-430 322.14 322.14 322.14 312.56 312.56 312.565 LOCUST SUBSTATION T25-440 SUBTOTAL 387,711 387,711 251,752 251,752 251,752 252,752 x Trenches 697.86 1000 T25-440 697.86 697.86 493.92 493.92 493.92 495.925 590 HEALTH AND SOCIAL SERVICES 2003 1335 International Mall Acad-Housing 64,663 64,663 64,663 64,663 64,663 64,663 3 x Trenches 1.5 96.99 750 T25-423 96.99 96.99 96.99 96.99 96.99 96.995 95 NEW CHEMISTRY BUILDING 1995/1196 1995/1996 NA Acad- Laboratory 59,400 59,400 59,400 59,400 59,400 59,400 2 6 x Trenches 3 178.20 750 T25-425 178.20 178.20 178.20 178.20 178.20 178.205 83 MILTON HALL 1941 2915 McFie Circle Acad-Classroom 99,311 99,311 99,311 99,311 99,311 99,311 3 x Trenches 2.3 228.42 750 T25-426 228.42 228.42 228.42 228.42 228.42 228.425 285 96 CORBETT/ANNEX ADDITION 1996 1600 International Mall Auxiliary 106,656 106,656 106,656 106,656 106,656 106,656 3 7 x Trenches 1.75 186.65 2000 T25-435 186.65 186.65 186.65 186.65 186.65 186.65

5 321 JAMES B DELAMATER ACTIVITY CENTER 96 ADDITION 1996 1600 Steward St Acad-Gymnasium 57,055 57,055 57,055 57,055 57,055 57,055 7 8 x Trenches 2.15 122.67 225 T25-445 122.67 122.67 122.67 122.67 122.67 122.675 NA PRESLEY ASKEW FIELD AND SOFTBALL FIELD NA NA Site 7 x Trenches 150.00 500 T25-460 150.00 150.00 150.00 150.00 150.00 150.005 NA INTRAMURAL FIELDS (LIGHTS) NA NA Site 7 x Trenches 225.00 750 T25-482 225.00 225.00 225.00 225.00 225.00 225.005 NA CRICKET TOWER NA NA Site 7 x Trenches 67.50 225 T25-484 67.50 67.50 67.50 67.50 67.50 67.505 605 CHAMISA VILLAGE/DORMS - CHAMISA A 2006 1725 Steward St Housing Dormitory 114,056 114,056 114,056 114,056 114,056 114,056 7 x Trenches 1.5 171.08 500 T25-486 171.08 171.08 171.08 171.08 171.08 171.085 605 CHAMISA VILLAGE/DORMS - CHAMISA B 2006 7 9 x Trenches 500 T25-4885 605 CHAMISA VILLAGE/DORMS - CHAMISA COMMON AREA 2006 7 9 x Trenches 75 T25-4925 605 CHAMISA VILLAGE/DORMS - CHAMISA C 2006 7 9 x Trenches 500 T25-494

Feeder # Bldg. # Building Name Year Built Address CategoryGSF

Dwg Area

Notes Fed From Electricity Utility Corridor Watts/SFEstimated Load KVA

Xformer KVA

Xformer ID Tag

Page 1

Page 36: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

F5E

New Mexico State UniversityUtility Development Plan

2009-2034+ Existing Building Electrical Load Projections - List 16-Jun-09 T5 Quantity: 16 T25 Quantity: 20

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+

FEEDER TF5 - PURPLE/EXISTING - TORTUGAS SUBSTATION 13800/23900

Feeder # Bldg. # Building Name Year Built Address CategoryGSF

Dwg Area

Notes Fed From Electricity Utility Corridor Watts/SFEstimated Load KVA

Xformer KVA

Xformer ID Tag

5 371 WND TUNNEL/RESEARCH BUILDING 1981 1635 Stanley Dr Acad- Laboratory 5,016 5,016 5,016 5,016 0 0 6 10 x Trenches 3 15.05 750 T25-455 15.05 15.05 15.05 15.05 0.00 0.005 596 FULTON ATHLETIC CENTER - STADIUM ANNEX+LTGS 2004 1815 Wells St Auxiliary 37,069 37,069 37,069 37,069 37,069 37,069 8 x Trenches 1.75 64.87 1000 T25-466 64.87 64.87 64.87 64.87 64.87 64.875 601 TENNIS CENTER - 12 COURTS 2006 1800 Wells St Academic 3,888 3,888 3,888 3,888 3,888 3,888 10 x Trenches 2.15 8.36 300 T25-467 8.36 8.36 8.36 8.36 8.36 8.365 394A GENSIS AND ACADEMIC CENTER - A 1987 3655 Research Dr Independent Operations (IO) 10,000 10,000 10,000 10,000 10,000 0 10 11 x Trenches 2.25 73.15 1000 T25-470 73.15 73.15 73.15 73.15 73.15 0.005 394B GENSIS AND ACADEMIC CENTER - B 1987 3655 Research Dr Independent Operations (IO) 10,000 10,000 10,000 10,000 10,000 0 10 115 394C GENSIS AND ACADEMIC CENTER - C 1987 3655 Research Dr Independent Operations (IO) 10,011 10,011 10,011 10,011 10,011 0 10 115 395 GENSIS AND ACADEMIC CENTER OFFICE 1987 3655 Research Dr Independent Operations (IO) 2,500 2,500 2,500 2,500 2,500 0 10 11

5 604 PINION HALL 2006 1760 E University Housing Dormitory 97,395 97,395 97,395 97,395 97,395 97,395 3 x Trenches 1.5 146.09 300 T25-476 146.09 146.09 146.09 146.09 146.09 146.095 284 PAN AMERICAN CENETR 1968 1810 E University Ave Auxiliary 215,633 215,633 215,633 215,633 215,633 215,633 4/9 x Trenches 2.25 485.17 2500 T25-478 485.17 485.17 485.17 485.17 485.17 485.17

PROJECTED EXISTING FEEDER TF5 TOTALS 1,495,123 1,495,123 1,359,164 1,352,776 1,347,760 1,316,249 3239 15375 3239 3239 3035 3026 3011 2939

VA/SQFT TOTAL 2 2 2 2 2 2

AMPERE TOTAL 84 399 84 84 79 79 78 76

MAXIMUM DEMAND kW 2882 2882

CALCULATED AMPS 75 75

EXISTING FEEDER TF5 NMSU 'POWER RICH' TURBINE READINGS: MINIMUM 1354kW (35A), MAXIMUM DEMAND 2882kW (75A), AVERAGE 2020kW (52A). DATE OF MAXIMUM kW READING NOVEMBER 16, 2007 @ 12:21AM. CALCULATED AMPS BASED ON AN AVERAGE POWER FACTOR OF 95% METERED BY EL PASO ELECTRIC.

GENERAL NOTES

A Refer to New Mexico State University Utility Development Plan Campus Building and Utility Master List for existing and future planned building numbers and square footage.

B New Mexico State University provided site utility plans indicating locations of existing electrical utilities such as feeder circuits, transformer locations, substations, switches and the like with some assumptions being made.

C New Mexico State University provided Campus Electrical Switching for NMSU last updated February 25, 2008 and data sheets received May 27, 2009.

D New Mexico State University provided and obtained metered power readings from the 'Power Rich' EMCS that is part of the turbine installation.

E New Mexico State University provided and obtained metered power readings from the Niagara system.

F Where building, site data is not availed NA (Not Available/Not Applicable) has been indicated.

G Where building GSF was not available or feeder loads indicate items such as street lights, sports fields and the like the transformer kVA was used as a load at 30% of kVA rating.

NOTES

1 Garcia Residence Hall Building 275 GSF and all estimated loads indicated on line above.

2 Corbett Building 285 GSF and all estimated loads indicated on line above.

3 Monagle Residence Hall/Women's Residence Center (WRC) Building GSF and all estimated loads indicated on line(s) above.

4 Rhodes Building 185 GSF (18,522) and half of Garnett Building 79 GSF (19,804) and all estimated loads indicated on line above.

5 Hamiel Building 80 GSF (27,709) and half of Garnett Building 79 GSF (19,804) and all estimated loads indicated on line above.

6 New Chemistry Building 95 GSF of 59,400 which will be subtracted from Chemistry Building 187 GSF of 115,878 (115,878-59,400= 56,478) feeder #3.

7 Corbett Building 285 (1968) and Corbett Building 285 Annex addition (1996) GSF as indicated in the Master Building Matrix was divided between the 5kV and 25kV loads.

8 James B. Delamater Activity Center Building 321 (1973) and James B. Delamater Activity Center 96 Addition (1996) GSF as indicated in the Master Building Matrix was divided between the 5kV (Circuit 2) and 25kV (Circuit 5) feeders.

9 Chamisa Village/Dorms Building 605 GSF and all estimated loads indicated on the line above.

10 Wind Tunnel/Research Building 371 GSF as indicated in the Master Building Matrix was divided between the 5kV (Circuit 2) and the 25kV (Circuit 5) feeders.

Building Category Watts/SQFT

Academic 2.15

Academic Classroom (Acad - Classroom(s)) 2.3

Academic Classroom Laboratory (Acad - Classroom/Lab) 2.5

Academic Laboratory (Acad - Lab) 3

Administration 2

Auxiliary (AUX) 1.75

Auxiliary/Housing (Aux/Housing) 1.5

Housing Dormitory 1.5

Housing Single Family Residence 1.5

Independent Operations (IO) 2.25

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 2.75

Productions and Operations Management (POM) 5

Productions and Operations Management (POM) 6

Productions and Operations Management (POM) 8

Productions and Operations Management (POM) 12

Services - Family, Student 2

Page 2

Page 37: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

F6E

New Mexico State UniversityUtility Development Plan

2009-2034+ Existing Building Electrical Load Projections - List 16-Jun-09 T5 Quantity: 15 T25 Quantity: 12

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+

FEEDER TF6 - MAGENTA/EXISTING - TORTUGAS SUBSTATION 13800/23900

6

DONA ANA BRANCH (DAB) COMMUNITY COLLEGE SUBSTATION - FOLLOWING NEXT (4) LOADS ON T25-150

6 357 DAB COMMUNITY COLLEGE NA NA Academic Classroom Lab 42,850 42,850 42,850 42,850 42,850 42,850 6 x Trench 2.5 107.13 1500 T5-110 107.13 107.13 107.13 107.13 107.13 107.136 479 DAB SHOP NA NA Academic Laboratory 23,500 23,500 23,500 23,500 23,500 23,500 6 x Trench 3 70.50 1000 T5-115 70.50 70.50 70.50 70.50 70.50 70.506 480 DAB SHOP (NORTH) NA NA Academic Laboratory 20,500 20,500 20,500 20,500 20,500 20,500 6 x Trench 3 61.50 1000 T5-120 61.50 61.50 61.50 61.50 61.50 61.506 540 HEALTH AND PUBLIC SERVICES (ALLIED) NA NA Administration 41,737 41,737 41,737 41,737 41,737 41,737 9 x Trench 2 83.47 500 T5-125 83.47 83.47 83.47 83.47 83.47 83.47

DONA ANA BRANCH SUBSTATION T25-150 SUBTOTAL 128,587 128,587 128,587 128,587 128,587 128,587 322.60 2000 T25-150 322.60 322.60 322.60 322.60 322.60 322.60

6EL PASEO/COLLEGE DR SUBSTATION - FOLLOWING NEXT (6) LOADS ON T25-475

6 RANGE CATERPILLAR 5,043 5,043 5,043 5,043 5,043 5,043 x Trench 3 15.13 150 T5-455 15.13 15.13 15.13 15.13 15.13 15.136 361 J. GORDON WATTS ENTOMOLOGY LAB, EAST 1978 650 College Dr. Acad- Laboratory 1,681 1,681 1,681 1,681 1,681 1,681 1 36 360 J. GORDON WATTS ENTOMOLOGY LAB, MIDDLE 1978 650 College Dr. Acad- Laboratory 1,681 1,681 1,681 1,681 1,681 1,681 1 36 359 J. GORDON WATTS ENTOMOLOGY LAB, WEST 1978 650 College Dr. Acad- Laboratory 1,681 1,681 1,681 1,681 1,681 1,681 1 36 432 J. GORDON WATTS LAB SHOP 1980 650 College Dr. Acad- Classroom 500 500 500 500 500 500 1 x Trench6 NA WELL #14 NA NA Site x Trench 250.00 500 T5-460 250.00 250.00 250.00 250.00 250.00 250.006 2 NEMATOLOGY LAB/USDA 1890 655 College Dr Acad- Laboratory 5,420 5,420 5,420 5,420 5,420 5,420 1 4 x Trench/Overhead 3 16.26 67 T5-465 16.26 16.26 16.26 16.26 16.26 16.266 NA MILLER FIELD NA NA Site 2 x Overhead 11.25 37.5 T5-475 11.25 11.25 11.25 11.25 11.25 11.256 44 ALUMNI AND VISITORS CENTER/NEW MUSEUM 1928 775 College Dr Administration 7,588 7,588 7,588 7,588 7,588 7,588 1/2 x Trench 2 15.18 150 T5-480 15.18 15.18 15.18 15.18 15.18 15.186 30 CAMPUS POLICE DEPARTMENT/AG INSTITUTE 1930 725 College Dr. Administration 19,310 19,310 19,310 19,310 19,310 19,310 1 x Trench 2 38.62 300 T5-485 38.62 38.62 38.62 38.62 38.62 38.62

EL PASEO/COLLEGE DR SUBSTATION T25-475 SUBTOTAL 42,904 42,904 42,904 42,904 42,904 42,904 346.44 1500 T25-475 346.44 346.44 346.44 346.44 346.44 346.44

6KNOX/FRENGER ST SUBSTATION - FOLLOWING NEXT (5) LOADS ON T25-495

6 372 ANIMAL MET & HOG BARN/PHYSIOLOGY LAB 1981 3020 Knox St. Acad- Laboratory 6,677 6,677 0 0 0 0 6 x Trench 3 20.03 225 T5-850 20.03 20.03 0.00 0.00 0.00 0.006 NA SILO NA NA Site 6 x Trench 15.00 50 T5-855 15.00 15.00 15.00 15.00 15.00 15.00

6 166 MILKING PARLOR/LIVESTOCK OFFICE/FEED STORAGE 1952 3170 Knox St. Acad- Laboratory 7,713 7,713 7,713 7,713 7,713 7,713 6 x Trench 3 23.14 75 T5-860 23.14 23.14 23.14 23.14 23.14 23.14

6 SANR ENGINEERING LAB AND POULTRY SCIENCE 12,648 12,648 0 0 0 0 x Trench 3 37.94 112.5 T5-865 37.94 37.94 0.00 0.00 0.00 0.00

6 212 SUGARMAN SPACE GRANT BUILDING 1958 3050 Knox St. Acad-Classroom 2,402 2,402 0 0 0 0 6 5

6 329 BIOLOGICAL CONTROL INSECTARY 1973 3080 Knox St. Acad- Laboratory 7,224 7,224 0 0 0 0 6 5

6 375 ANIMAL SCIENCE SHOP NA NA Academic 3,022 3,022 0 0 0 0 6 56 390 PGEL GREENHOUSES 1985 2990 Knox St. Academic 10,086 10,086 0 0 0 0 6 x Trench 3 30.26 300 T5-870 30.26 30.26 0.00 0.00 0.00 0.006 426 PGEL HEADHOUSE/LAB 2989 2990 Knox St. Acad- Laboratory 0 0 0 0 0 0 6 6

KNOX/FRENGER ST SUBSTATION T25-495 SUBTOTAL 49,772 49,772 7,713 7,713 7,713 7,713 126.37 2000 T25-495 126.37 126.37 38.14 38.14 38.14 38.14

6 585 WOOTEN HALL (JORNADA Hall) T25-487 2002 NA Acad- Laboratory 29,600 29,600 29,600 29,600 29,600 29,600 6 x Trench 3 88.80 300 T25-487 88.80 88.80 88.80 88.80 88.80 88.80

6DONA ANA BRANCH (DBA) SUBSTATION T25-150 SUBTOTAL 128,587 128,587 128,587 128,587 128,587 128,587 x Trench 323 2000 T25-150 322.60 322.60 322.60 322.60 322.60 322.60

6EL PASEO/COLLEGE DR SUBSTATION T25-475 SUBTOTAL 42,904 42,904 42,904 42,904 42,904 42,904 x Trench 346.44 1500 T25-475 346.44 346.44 346.44 346.44 346.44 346.44

6 KNOX/FRENGER ST SUBSTATION T25-495 SUBTOTAL 49,772 49,772 7,713 7,713 7,713 7,713 126.37 2000 T25-495 126.37 126.37 38.14 38.14 38.14 38.14

Feeder # Bldg. # Building Name Year Built Address CategoryGSF

Dwg Area

Notes Fed From Electricity Utility Corridor Watts/SFEstimated Load KVA

Xformer KVA

Xformer ID Tag

Page 1

Page 38: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

F6E

New Mexico State UniversityUtility Development Plan

2009-2034+ Existing Building Electrical Load Projections - List 16-Jun-09 T5 Quantity: 15 T25 Quantity: 12

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+

FEEDER TF6 - MAGENTA/EXISTING - TORTUGAS SUBSTATION 13800/23900

Feeder # Bldg. # Building Name Year Built Address CategoryGSF

Dwg Area

Notes Fed From Electricity Utility Corridor Watts/SFEstimated Load KVA

Xformer KVA

Xformer ID Tag

6 341 DONA ANA BRANCH (DBA) NORTH NA NA Academic 54,000 54,000 54,000 54,000 54,000 54,000 6 2 x Trench 3 162.00 2000 T25-150 162.00 162.00 162.00 162.00 162.00 162.006 NA WELL #17 NA NA Site x Trench 90.00 300 T25-151 90.00 90.00 90.00 90.00 90.00 90.006 465 EQUESTRIAN CENTER NA NA Academic 10,800 10,800 10,800 10,800 10,800 10,800 6 7 x Trench 2.15 23.22 75 T25-152 23.22 23.22 23.22 23.22 23.22 23.226 341 DONA ANA BRANCH (DBA) SOUTHEAST CORNER NA NA Academic Laboratory 54,000 54,000 54,000 54,000 54,000 54,000 6 2 x Trench 2.15 116.10 500 T25-155 116.10 116.10 116.10 116.10 116.10 116.106 NA WELL # 10 NA NA Site x Trench 150.00 500 T25-160 150.00 150.00 150.00 150.00 150.00 150.006 551 SKEEN HALL - CSDAL 1999 945 College Dr Acad- Laboratory 135,896 135,896 135,896 135,896 135,896 135,896 2 x Trench 3 407.69 750 T25-480 407.69 407.69 407.69 407.69 407.69 407.696 551 SKEEN HALL - CSDAL 1999 945 College Dr Acad- Laboratory 2 1 x Trench 750 T25-4856 551 SKEEN HALL - CSDAL 1999 945 College Dr Acad- Laboratory 2 1 x Trench 1000 T25-490

PROJECTED EXISTING FEEDER TF6 TOTALS 505,559 505,559 463,500 463,500 463,500 463,500 1,833 11,675 1,833 1,833 1,745 1,745 1,745 1,745

VA/SQFT TOTAL 4 4 4 4 4 4

AMPERE TOTAL 48 303 48 48 45 45 45 45

MAXIMUM DEMAND kW 2630 2630

CALCULATED AMPS 68 68

EXISTING FEEDER TF6 NMSU 'POWER RICH' TURBINE READINGS: MINIMUM 721kW (18A), MAXIMUM DEMAND 2630kW (68A), AVERAGE 1280kW (33A). DATE OF MAXIMUM kW READING AUGUST 22, 2007 @ 7:56PM. CALCULATED AMPS BASED ON AN AVERAGE POWER FACTOR OF 95% METERED BY EL PASO ELECTRIC.

GENERAL NOTES

A Refer to New Mexico State University Utility Development Plan Campus Building and Utility Master List for existing and future planned building numbers and square footage.

B New Mexico State University provided site utility plans indicating locations of existing electrical utilities such as feeder circuits, transformer locations, substations, switches and the like with some assumptions being made.

C New Mexico State University provided Campus Electrical Switching for NMSU last updated February 25, 2008 and data sheets received May 27, 2009.

D New Mexico State University provided and obtained metered power readings from the 'Power Rich' EMCS that is part of the turbine installation.

E New Mexico State University provided and obtained metered power readings from the Niagara system.

F Where building, site data is not availed NA (Not Available/Not Applicable) has been indicated.

G Where building GSF was not available or feeder loads indicate items such as street lights, sports fields and the like the transformer kVA was used as a load at 30% of kVA rating.

NOTES

1 Skeen Hall - CSDAL Building 551 GSF and all estimated loads indicated on line(s) above.

2 Dona Ana Branch (DBA) Building 341 North and Southeast corner GSF was divided between the two (2) transformers (North and Southeast units).

3 Buildings 359, 360 and 361 total GSF and all estimated loads indicated on line above for Range Caterpillar.

4 No information available for USDA. Estimated load is for both Nematology Lab Building 2 and USDA.

5 Buildings 212, 329 and 375 total GSF and all estimated loads indicated on line above for Sanr Engineering Lab and Poultry Science.

6 PGEL Head house/Lab Building 426, GSF of 4,104 included in line above PGEL Greenhouse Building 390 GSF total (Building 390 GSF 5,982).

7 Equestrian Building 465 GSF is based on measured square footage from site plan and will not match Official Building Master List.

Building Category Watts/SQFT

Academic 2.15

Academic 2.3

Academic Classroom (Acad - Classroom(s)) 2.5

Academic Classroom Laboratory (Acad - Classroom/Lab) 3

Academic Laboratory (Acad - Lab) 2

Administration 1.75

Auxiliary (AUX) 1.5

Auxiliary/Housing (Aux/Housing) 1.5

Housing Dormitory 1.5

Housing Single Family Residence 2.25

Independent Operations (IO) 1.5

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 2.75

Productions and Operations Management (POM) 5

Productions and Operations Management (POM) 6

Productions and Operations Management (POM) 8

Productions and Operations Management (POM) 12

Productions and Operations Management (POM) 2

Services - Family, Student

Page 2

Page 39: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

F7E

New Mexico State UniversityUtility Development Plan

2009-2034+ Existing Building Electrical Load Projections - List 16-Jun-09 T5 Quantity: 23 T25 Quantity: 1

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+

FEEDER GF7 - LIGHT PURPLE/EXISTING - GEOTHERMAL SUBSTATION 13800/23900

7GEOTHERMAL SUBSTATION - FOLLOWING NEXT (22) LOADS ON T25-261

7 NA GEOTHERMAL RD BORDER HEALTH TIGRE NA NA Site NA x Trenches/Overhead 15.00 50 T5-240 T25-261 15.00 15.00 15.00 15.00 15.00 15.007 NA TANK - 4 MILLION GALLON TANK NA NA Site NA x Trenches 33.75 112.5 T5-245 T25-261 33.75 33.75 33.75 33.75 33.75 33.757 366 PRESIDENTS RESIDENCE 1979 4501 Geothermal Dr. Administration 6,558 6,568 6,568 6,568 6,568 6,568 NA x Trenches/Overhead 2 13.12 75 T5250 T25-261 13.12 13.14 13.14 13.14 13.14 13.147 582 GOLF DRIVING RANGE FACILITY 1997 3895 Herb Wimbley Dr. Auxiliary 919 919 919 919 919 919 NA x Trenches 1.75 1.61 30 T5255 T25-261 1.61 1.61 1.61 1.61 1.61 1.617 464 OLD GEOTHERMAL PUMP HOUSE 1985 3490 Aggie Rodeo Dr. IO 2,412 2,412 2,412 2,412 2,412 2,412 NA x Trenches 2.25 5.43 112.5 T5-260 T25-261 5.43 5.43 5.43 5.43 5.43 5.437 NA FS5 7W1 NA NA Site NA 1 x Trenches/Overhead 22.50 75 T5-265 T25-261 22.50 22.50 22.50 22.50 22.50 22.507 392 GEOTHERMAL GREENHOUSES/ALDERSHOT 1985 3490 Aggie Rodeo Dr. IO 6,000 6,000 6,000 6,000 6,000 6,000 NA x Trenches/Overhead 2.25 27.00 112.5 T5-270 T25-261 27.00 27.00 27.00 27.00 27.00 27.007 393 GEOTHERMAL GREENHOUSES/ALDERSHOT 1985 3490 Aggie Rodeo Dr. IO 6,000 6,000 6,000 6,000 6,000 6,000 NA 2 112.5 T5-270 T25-2617 NA RODEO GROUNDS NA NA Site NA x Trenches/Overhead 15.00 50 T5-275 T25-261 15.00 15.00 15.00 15.00 15.00 15.007 NA FLYFARM NA NA Site NA 3 x Trenches/Overhead 7.50 25 T5-280 T25-261 7.50 7.50 7.50 7.50 7.50 7.507 NA CHEMICAL STORAGE NA NA Site NA x Trenches/Overhead 7.50 25 T5-285 T25-261 7.50 7.50 7.50 7.50 7.50 7.507 NA GS7 7E10 NA NA Site NA 4 x Trenches/Overhead 7.50 25 T5-290 T25-261 7.50 7.50 7.50 7.50 7.50 7.507 NA PHYSICAL SCIENCE LAB (PSL) ANTENNA FARM NA NA Site NA x Trenches 67.50 225 T5-295 T25-261 67.50 67.50 67.50 67.50 67.50 67.507 378 GOLF COURSE PUMP HOUSE 1982 4225 Geothermal Dr. Auxiliary/Site 302 302 302 302 302 302 NA x Trenches 150.00 500 T5-300 T25-261 150.00 150.00 150.00 150.00 150.00 150.007 NA UNKNOWN NA NA Site NA x Trenches 90.00 300 T5-340 T25-261 90.00 90.00 90.00 90.00 90.00 90.007 NA GOLF COURSE RESTROOM NA NA Site NA 5 x Trenches/Overhead 7.50 25 T5-350 T25-261 7.50 7.50 7.50 7.50 7.50 7.507 NA STADIUM WEST NA NA Site NA x Trenches 150.00 500 T5-355 T25-261 150.00 150.00 150.00 150.00 150.00 150.007 NA STADIUM EAST NA NA Site NA x Trenches 90.00 300 T5360 T25-261 90.00 90.00 90.00 90.00 90.00 90.007 NA STADIUM PUMP/WEIGHT ROOM NA NA Site NA x Trenches 90.00 300 T5-365 T25-261 90.00 90.00 90.00 90.00 90.00 90.007 NA STADIUM DRESSING ROOM NA NA Site NA x Trenches 37.50 75 T5-370 T25-261 37.50 37.50 37.50 37.50 37.50 37.507 NA OUTDOOR ACTIVITIES NA NA Site NA x Trenches 22.50 75 T5-375 T25-261 22.50 22.50 22.50 22.50 22.50 22.507 NA TEAM ROOM AND SCOREBOARD NA NA Site NA 6 x Trenches 90.00 300 T5-??? T25-261 90.00 90.00 90.00 90.00 90.00 90.007 NA STREET LIGHTING NA NA Site NA x Trenches 45.00 150 T5-445 T25-261 45.00 45.00 45.00 45.00 45.00 45.007 NA SOCCER FIELD WELL NA NA Site NA 7 x Trenches 90.00 300 T5??? T25-261 90.00 90.00 90.00 90.00 90.00 90.00

7 GEOTHERMAL SUBSTATION T25-261 - SUBTOTAL 22,191 22,201 22,201 22,201 22,201 22,201 1085.90 3855 1085.90 1085.92 1085.92 1085.92 1085.92 1085.92

7 GEOTHERMAL SUBSTATION T25-261 SUBTOTAL 22,191 22,201 22,201 22,201 22,201 22,201 1,085.90 3855.00 1,085.90 1,085.92 1,085.92 1,085.92 1,085.92 1,085.922000 T25-261

Fed From Electricity Utility Corridor Watts/SFEstimated Load KVA

Xformer KVA

Xformer ID Tag

GSFDwg Area

NotesFeeder # Bldg. # Building Name Year Built Address Category

Page 1

Page 40: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

F7E

New Mexico State UniversityUtility Development Plan

2009-2034+ Existing Building Electrical Load Projections - List 16-Jun-09 T5 Quantity: 23 T25 Quantity: 1

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+

FEEDER GF7 - LIGHT PURPLE/EXISTING - GEOTHERMAL SUBSTATION 13800/23900

Fed From Electricity Utility Corridor Watts/SFEstimated Load KVA

Xformer KVA

Xformer ID Tag

GSFDwg Area

NotesFeeder # Bldg. # Building Name Year Built Address Category

PROJECTED EXISTING FEEDER GF7 TOTALS 22,191 22,201 22,201 22,201 22,201 22,201 1,086 2000 1086 1086 1086 1086 1086 1086

VA/SQFT TOTAL 49 49 49 49 49 49

AMPERE TOTAL 28 52 28 28 28 28 28 28

EXISTING FEEDER GF7 NMSU 'POWER RICH' TURBINE READINGS ARE NOT AVAIABLE. CALCULATED AMPS BASED ON AN AVERAGE POWER FACTOR OF 95% METERED BY EL PASO ELECTRIC.

GENERAL NOTES

A Refer to New Mexico State University Utility Development Plan Campus Building and Utility Master List for existing and future planned building numbers and square footage.

B New Mexico State University provided site utility plans indicating locations of existing electrical utilities such as feeder circuits, transformer locations, substations, switches and the like with some assumptions being made.

C New Mexico State University provided Campus Electrical Switching for NMSU last updated February 25, 2008 and data sheets received May 27, 2009.

D New Mexico State University provided and obtained metered power readings from the 'Power Rich' EMCS that is part of the turbine installation.

E New Mexico State University provided and obtained metered power readings from the Niagara system.

F Where building, site data is not availed NA (Not Available/Not Applicable) has been indicated.

G Where building GSF was not available or feeder loads indicate items such as street lights, sports fields and the like the transformer kVA was used as a load at 30% of kVA rating.

NOTES

1 FS5 7W1 transformer kVA is unknown and is estimated as three (3) 25 kVA single phase pole mounted transformers.

2 Geothermal Greenhouse /Aldershot Building 393 GSF, has been included in the line above. There are multiple greenhouse buildings with one (1) transformer, feeder.

3 Fly Farm transformer kVA is unknown and is estimated as one (1) 25 kVA single phase pole mounted transformer.

4 GS7 7E10 transformer kVA is unknown and is estimated as one (1) 25kVA single phase pole mounted transformer.

5 Golf Course Restroom transformer kVA is unknown and is estimated as one (1) 25kVA single phase pole mounted transformer.

6 Team Room and Scoreboard transformer ID tag is not known.

7 Soccer field well transformer kVA and ID tag is unknown with transformer estimated at one (1) 300kVA three phase pad mounted transformer.

Building Category Watts/SQFT

Academic 2.15

Academic Classroom (Acad - Classroom(s)) 2.3

Academic Classroom Laboratory (Acad - Classroom/Lab) 2.5

Academic Laboratory (Acad - Lab) 3

Administration 2

Auxiliary (AUX) 1.75

Auxiliary/Housing (Aux/Housing) 1.5

Housing Dormitory 1.5

Housing Single Family Residence 1.5

Independent Operations (IO) 2.25

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 2.75

Productions and Operations Management (POM) 5

Productions and Operations Management (POM) 6

Productions and Operations Management (POM) 8

Productions and Operations Management (POM) 12

Services - Family, Student 2

Page 2

Page 41: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

TFGFE SUM

New Mexico State UniversityUtility Development Plan

2009-2034+ Summary - Existing Building Electrical Load Projections 16-Jun-09 EXISTING SITE TOTAL T5 Quantity: 143 (TOTUGAS 120) 23 (GEOTHERMAL 23) EXISTING SITE TOTAL T25 Quantity: 105 (TORTUGAS 104) (GOTHERMAL 1)

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+

TORTUGAS SUBSTATION 13800/23900 FEEDERS TF1-TF6

TF1(E) PROJECTED EXISTING FEEDER TF1 SUBTOTAL 627,005 627,005 627,005 627,005 484,605 96,061 961.88 9591 961.88 961.88 961.88 961.88 748.28 149.50VA/SQFT SUB-TOTAL 1.53 1.53 1.53 1.53 1.54 1.56AMPERE SUB-TOTAL 24.99 249.16 24.99 24.99 24.99 24.99 19.44 3.88MAXIMUM DEMAND 890kW 890.00 890.00CALCULATED AMPS 23.12 23.12

TF2(E) PROJECTED EXISTING FEEDER TF2 SUBTOTAL 542,738 542,738 529,116 417,859 202,066 202,066 1393.58 5000 1393.58 1393.58 1362.25 1207.17 672.23 672.23VA/SQFT SUB-TOTAL 2.57 2.57 2.57 2.89 3.33 3.33AMPERE SUB-TOTAL 36.20 129.89 36.20 36.20 35.39 31.36 17.46 17.46MAXIMUM DEMAND 822kW 822.00 822.00CALCULATED AMPS 21.35 21.35

TF3(E) PROJECTED EXISTING FEEDER TF3 SUBTOTAL 869,989 869,989 869,989 837,241 837,241 837,241 4834.94 11250 4834.94 4834.94 4834.94 4759.88 4759.88 4759.88VA/SQFT SUB-TOTAL 5.56 5.56 5.56 5.69 5.69 5.69AMPERE SUB-TOTAL 125.61 292.26 125.61 125.61 125.61 123.66 123.66 123.66MAXIMUM DEMAND 3982kW 3982.00 3982.00CALCULATED AMPS 103.45 103.45

TF4(E) PROJECTED EXISTING FEEDER TF4 TOTALS 1,049,351 972,976 897,141 896,096 896,096 896,096 4361.09 2500 4361.09 4102.43 3873.15 3870.74 3870.74 3870.74VA/SQFT SUB-TOTAL 4.16 4.22 4.32 4.32 4.32 4.32AMPERE SUB-TOTAL 113.30 64.95 113.30 106.58 100.62 100.56 100.56 100.56MAXIMUM DEMAND 2699kW 2699.00 2699.00CALCULATED AMPS 70.12 70.12MAXIMUM DEMAND -2566kW (TURBINE) -2597 -2597CALCULATED AMPS -66.66 (TURBINE) -67.47 -67.47

*Feeder # Building NameGSF

Estimated Load KVA

Xformer KVA

Page 1

Page 42: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

TFGFE SUM

New Mexico State UniversityUtility Development Plan

2009-2034+ Summary - Existing Building Electrical Load Projections 16-Jun-09 EXISTING SITE TOTAL T5 Quantity: 143 (TOTUGAS 120) 23 (GEOTHERMAL 23) EXISTING SITE TOTAL T25 Quantity: 105 (TORTUGAS 104) (GOTHERMAL 1)

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+*Feeder # Building Name

GSFEstimated Load KVA

Xformer KVA

TF5(E) PROJECTED EXISTING FEEDER TF5 TOTALS 1,495,123 1,495,123 1,359,164 1,352,776 1,347,760 1,316,249 3239.20 15375 3239.20 3239.20 3035.27 3025.68 3010.64 2939.49VA/SQFT SUB-TOTAL 2.17 2.17 2.23 2.24 2.23 2.23AMPERE SUB-TOTAL 84.15 399.43 84.15 84.15 78.85 78.60 78.21 76.36MAXIMUM DEMAND 2882kW 2882.00 2882.00CALCULATED AMPS 74.87 74.87

TF6(E) PROJECTED EXISTING FEEDER TF6 TOTALS 505,559 505,559 463,500 463,500 463,500 463,500 1833.21 11,675 1833.21 1833.21 1744.98 1744.98 1744.98 1744.98VA/SQFT SUB-TOTAL 3.63 3.63 3.76 3.76 3.76 3.76AMPERE SUB-TOTAL 47.62 303.30 47.62 47.62 45.33 45.33 45.33 45.33MAXIMUM DEMAND 2630 (64A) 2630.00 2630.00CALCULATED AMPS 68.32 68.32

TF1-TF6(E) TORTUGAS SUBSTATION TOTALS 5,089,765 5,013,390 4,745,915 4,594,477 4,231,268 3,811,213 16,624 55,391 16,624 16,365 15,812 15,570 14,807 14,137VA/SQFT TOTAL 20 20 20 20 21 21AMPERE TOTAL 432 1,439 432 48 45 45 45 45MAXIMUM DEMAND kW 13,905 13,905CALCULATED AMPS 361 361

GEOTHERMAL SUBSTATION 13800/23900 FEEDERS TF1-TF6GF7(E) PROJECTED EXISTING FEEDER GF7 TOTALS 22,191 22,201 22,201 22,201 22,201 22,201 1085.90 2000.00 1085.90 1085.92 1085.92 1085.92 1085.92 1085.92

VBA/SQFT TOTAL 48.93 48.91 48.91 48.91 48.91 48.91AMPERE TOTAL 28.21 51.96 28.21 47.62 28.21 28.21 28.21 28.21MAXIMUM DEMAND kW NOT AVAIABLE 0.00 0.00 0.00

GENERAL NOTES

A Refer to New Mexico State University Utility Development Plan Campus Building and Utility Master List for existing and future planned building numbers and square footage.

B New Mexico State University provided site utility plans indicating locations of existing electrical utilities such as feeder circuits, transformer locations, substations, switches and the like with some assumptions being made.

C New Mexico State University provided Campus Electrical Switching for NMSU last updated February 25, 2008 and data sheets received May 27, 2009.

D New Mexico State University provided and obtained metered power readings from the 'Power Rich' EMCS that is part of the turbine installation.

E New Mexico State University provided ad obtained metered power readings from the Niagara system.

NOTES

* (E) Indicates an existing feeder. TF1 (Tortugas Substation Feeder 1) and GF7 (Geothermal Substation Feeder 7).

Page 2

Page 43: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

2014

New Mexico State UniversityUtility Development Plan

2014-2034+ New Building Electrical Load Projections - List 16-Jun-09 Estimated T5 Quantity: 3 Estimated T25 Quantity: 15

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+

FIVE YEAR ADDITION 2014 (2009 - 2014) AND BEYOND 2034+ - SECONDARY AND TORTUGAS NEW SUBSTATION 13800/23900 ADDITIONAL LOADS 05-01 ART COMPLEX - PHASE 1 2014 Acad-Classroom 0 234,000 234,000 234,000 234,000 234,000 2 x Trenches 2.3 538.20 T25-XXX 0.00 538.20 538.20 538.20 538.20 538.20

05-02 INSTITUTE FOR PUBLIC POLICY (DOMENICI CENTER) 2014 Acad-Classroom 0 55,980 55,980 55,980 55,980 55,980 3 x Trenches 2.3 128.75 T25-XXX 0.00 128.75 128.75 128.75 128.75 128.75

05-03 STUDENT SERVICES FACILITY - PHASE 1 2014 Administration 0 37,500 37,500 37,500 37,500 37,500 3 x Trenches 2 75.00 T25-XXX 0.00 75.00 75.00 75.00 75.00 75.00

05-04 NATIVE AMERICAN CULTURAL CENTER 2014 Acad-Classroom 0 26,900 26,900 26,900 26,900 26,900 7 x Trenches 2.3 61.87 T25-XXX 0.00 61.87 61.87 61.87 61.87 61.87

05-05 TECHNICAL LAB/CLASSROOM FACILITY 2014 Acad-Classroom/Lab 0 60,000 60,000 60,000 60,000 60,000 3 1 x Trenches 2.5 150.00 T25-XXX 0.00 150.00 150.00 150.00 150.00 150.00

05-06ARROWHEAD CENTER EXPANSION - PHASE 1 (4 BUILDINGS) 2014 IO 61,302 61,302 61,302 61,302 61,302 12 2, 4

05-07 PARKING LOTS 2014 Auxiliary/Site 0 0 0 0 0 0 11 x 0.00 0.00 0.00 0.00 0.00 0.00 0.00

05-08 BOOKSTORE 2014 Auxiliary 0 35,000 35,000 35,000 35,000 35,000 3 x Trenches 1.75 61.25 T25-XXX 0.00 61.25 61.25 61.25 61.25 61.25

05-09 NMDA BUILDING RENOVATIONS AND ADITIONS 2014 IO 0 60,000 60,000 60,000 60,000 60,000 6 x Trenches 2.25 135.00 T25-XXX 0.00 135.00 135.00 135.00 135.00 135.00

05-10ADDITIONS TO THE HEALTH ANS SOCIAL SERVICES BUILDING ` Acad-Classroom 0 7,387 7,387 7,387 7,387 7,387 3 x Trenches 2.3 16.99 T25-XXX 0.00 16.99 16.99 16.99 16.99 16.99

05-11 FOOTBALL OFFICES (STADIUM PHASE 2) 2014 Auxiliary 0 6,749 6,749 6,749 6,749 6,749 8 x Trenches 1.75 11.81 T25-XXX 0.00 11.81 11.81 11.81 11.81 11.81

05-12 SOCCER FACILITY 2014 Auxiliary 0 10,000 10,000 10,000 10,000 10,000 8 x Trenches 1.75 17.50 T25-XXX 0.00 17.50 17.50 17.50 17.50 17.50

05-13 CHAMISA DORMITORITIES - PHASE 2 2014 Housing 0 55,628 55,628 55,628 55,628 55,628 7 3, 4 Trenches 1.5 83.44 T25-XXX 0.00 83.44 83.44 83.44 83.44 83.44

05-14DUAL - CREDIT LAS CRUSES HIGH SCHOOL (ARROWHEAD) 2014 IO 242,510 242,510 242,510 242,510 242,510 11

05-15SECONDARY UTILITY CENTER - ESTIMATED SQFT 2 LEVELS 2014 POM 0 15,000 15,000 15,000 15,000 15,000 3 x Trenches 6 90.00 T25-XXX 0.00 90.00 90.00 90.00 90.00 90.00

05-15 NEW 2000 TON CHILLER CH1 (1100kW EST) 2014 POM 0 0 0 0 0 0 3 x 1100.00 T5-XXX T25-XXX 0.00 1100.00 1100.00 1100.00 1100.00 1100.00

05-15 NEW 2000 TON CHILLER JCH2 (1100kW EST) 2014 POM 0 0 0 0 0 0 3 x 1100.00 T5-XXX T25-XXX 0.00 1100.00 1100.00 1100.00 1100.00 1100.00

05-15 NEW 2000 TON CHILLER CH3 (1100kW EST) 2014 POM 0 0 0 0 0 0 3 x 1100.00 T5-XXX T25-XXX 0.00 1100.00 1100.00 1100.00 1100.00 1100.00

FIVE YEAR ADDITION 2014 -2034+ SUBTOTAL 0 604,144 604,144 604,144 604,144 604,144 4,669.82 0.00 4,669.82 4,669.82 4,669.82 4,669.82 4,669.82

PROJECTED FIVE YEAR LOAD ADDITION TOTALS 2014 ( 20014-2034+) 0 604,144 604,144 604,144 604,144 604,144 4,670 0 4670 4670 4670 4670 4670

VA/SQFT TOTAL 0 8 8 8 8 8

AMPERE TOTAL 121 0 121 121 121 121 121

GENERAL NOTES

A Refer to New Mexico State University Utility Development Plan Campus Building and Utility Master List for existing and future planned building numbers and square footage.

B New Mexico State University provided site utility plans indicating locations of existing electrical utilities such as feeder circuits, transformer locations, substations, switches and the like with some assumptions being made.

C New Mexico State University provided Campus Electrical Switching for NMSU last updated February 25, 2008 and data sheets received May 27, 2009.

NOTES

1 Following demolition of Hardman Hall (323), Jacobs Hall (250), and the Herschell Zohn Theatre (249).

2 SF based on a single story building footprint.

3 SF based on the assumption that Ph. 2 will double the size of the facility.

4 Arrowhead Research Park/Center electrical utilities will not be provide from NMSU existing or new Secondary or Tortugas Substations.

Building Category Watts/SQFT

Academic 2.15

Academic Classroom (Acad - Classroom(s)) 2.3

Academic Classroom Laboratory (Acad - Classroom/Lab) 2.5

Administration 2

Auxiliary (AUX) 1.75

Auxiliary/Housing (Aux/Housing) 1.5

Housing Dormitory 1.5

Housing Single Family Residence 1.5

Independent Operations (IO) 2.25

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 2.75

Productions and Operations Management (POM) 5

Productions and Operations Management (POM) 6

Productions and Operations Management (POM) 8

Productions and Operations Management (POM) 12

Services - Family, Student 2

Fed From Electricity Utility Corridor Watts/SFEstimated Load KVA

Xformer KVA

Xformer ID Tag

GSFDwg Area NotesFeeder # Bldg. # Building Name Year Built Address Category

Page 1

Page 44: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

2019

New Mexico State UniversityUtility Development Plan

2014-2034+ New Building Electrical Load Projections - List 16-Jun-09 Estimated T5 Quantity: 1 Estimated T25 Quantity: 15

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+

TEN YEAR ADDITION 2019 (2014-2019) AND BEYOND 2034 + - SECONDARY AND TORTUGAS NEW SUBSTATION 13800/23900 ADDITIONAL LOADS 10-01 WEST MIXED USE/GRADUATE HOUSING 2019 Housing 0 0 64,800 64,800 64,800 64,800 3 1 x Trenches 1.5 97.20 T25-XXX 0.00 0.00 97.20 97.20 97.20 97.2010-02 EASTMIXED USE/GRADUATE HOUSING PHASE 1 2019 Housing 0 0 116,100 116,100 116,100 116,100 3 1,2 x Trenches 1.5 174.15 T25-XXX 0.00 0.00 174.15 174.15 174.15 174.1510-03 STUDENT SERVICES FACILITY - PHASE 2 2019 Administration 0 0 37,500 37,500 37,500 37,500 3 3,4 x Trenches 2.15 80.63 T25-XXX 0.00 0.00 80.63 80.63 80.63 80.6310-04 NEW UNDERGRADUATE HOUSING 2019 Housing 0 0 56,520 56,520 56,520 56,520 3 3,5 x Trenches 1.5 84.78 T25-XXX 0.00 0.00 84.78 84.78 84.78 84.7810-05 PLAZA (OFF CAMPUS) 2019 Auxiliary/Site 0 0 0 0 0 0 3 13 x 0.00 0.00 0.00 0.00 0.00 0.00 0.0010-06 NEW MARRIED STUDENT HOUSING 2019 Housing 0 0 165,660 165,660 165,660 165,660 7 5 x Trenches 1.5 248.49 T25-XXX 0.00 0.00 248.49 248.49 248.49 248.4910-07 STUDENT ACTIVITIES EXPANSION 2019 Auxiliary 0 0 87,160 87,160 87,160 87,160 7 6,10 x Trenches 1.75 152.53 T25-XXX 0.00 0.00 152.53 152.53 152.53 152.5310-08 NEW ACADEMIC BUILDINGS 2019 Acad-Classroom 0 0 263,250 263,250 263,250 263,250 6 1,7 x Trenches 2.3 605.48 T25-XXX 0.00 0.00 605.48 605.48 605.48 605.4810-09 PARKING LOTS 2019 Auxiliary 0 0 0 0 0 0 6 8 x 1.5 0.00 T25-XXX 0.00 0.00 0.00 0.00 0.00 0.0010-10 NEW METABOLISM AND SURGEY BUILDING 2019 Acad- Laboratory 0 0 8,000 8,000 8,000 8,000 6 x Trenches 3 24.00 T25-XXX 0.00 0.00 24.00 24.00 24.00 24.00

10-11NEW PROCESSING LAB BUILDING WITH ADJACENT ANIMAL PENS 2019 Acad- Laboratory 0 0 10,000 10,000 10,000 10,000 6 x Trenches 3 30.00 T25-XXX 0.00 0.00 30.00 30.00 30.00 30.00

10-12 ARROWHEAD EXPANSION PHASE 2 (7 Buildings) 2019 IO 0 0 216,443 216,443 216,443 216,443 13 13 0.00 0.00 0.00 0.00 0.00 0.00 0.0010-13 REGENT'S LAWN LANDSCAPE IMPROVEMENTS 2019 Auxiliary/Site 0 0 0 0 0 0 3 x 0.00 0.00 0.00 0.00 0.00 0.00 0.0010-14 JORDAN STREET GATEWAY 2019 Auxiliary/Housing 0 0 190,000 190,000 190,000 190,000 3 9 x Trenches 1.5 285.00 T25-XXX 0.00 0.00 285.00 285.00 285.00 285.0010-15 EQUESTRIAN CENTER 2019 Acad-Classroom 0 0 72,280 72,280 72,280 72,280 6 10,11 x Trenches 2.3 166.24 T25-XXX 0.00 0.00 166.24 166.24 166.24 166.2410-16 ARTS COMPLEX - PHASE 2 (VISUAL ARTS) 2019 Acad-Classroom 0 0 71,500 71,500 71,500 71,500 2 x Trenches 2.3 164.45 T25-XXX 0.00 0.00 164.45 164.45 164.45 164.4510-17 JORDAN STREET PARKING GARAGE (4 LEVELS) 2019 Auxiliary 0 0 239,400 239,400 239,400 239,400 3 12 x Trenches 1.5 359.10 T25-XXX 0.00 0.00 359.10 359.10 359.10 359.1010-18 NEW 2000 TON CHILLER CH4 (1100kW EST) 2019 POM 0 0 0 0 0 0 3 14 x 1100.00 T5-XXX T25-XXX 0.00 0.00 1100.00 1100.00 1100.00 1100.00

TEN YEAR ADDITION 2019 -2034+ SUBTOTAL 0 0 1,382,170 1,382,170 1,382,170 1,382,170 3572.04 0.00 0.00 3572.04 3572.04 3572.04 3572.04

PROJECTED TEN YEAR LOAD ADDITION TOTALS 2019 ( 2019-2034+) 0 0 1,382,170 1,382,170 1,382,170 1,382,170 3,572 0 0 3572 3572 3572 3572

VA/SQFT TOTAL 0 0 3 3 3 3

AMPERE TOTAL 93 0 0 93 93 93 93

GENERAL NOTES

A Refer to New Mexico State University Utility Development Plan Campus Building and Utility Master List for existing and future planned building numbers and square footage.

B New Mexico State University provided site utility plans indicating locations of existing electrical utilities such as feeder circuits, transformer locations, substations, switches and the like with some assumptions being made.

C New Mexico State University provided Campus Electrical Switching for NMSU last updated February 25, 2008 and data sheets received May 27, 2009.

NOTES

1 SF based on a three story building footprint.

2 Following demolition of Delta Zeta and Zeta Tau Alpha sorority houses (213, 163)

3 Following demolition of Monagle Hall (260).

4 SF based on assumption that Ph. 2 will double the size of the facility

5 SF based on a three story building footprint.

6 Following demolition of Rentfrow Gymnasium (211).

7

8

9 Following demolition of D.W. Williams Hall and Annex (60, 60A).

10 SF based on a single story building footprint.

11 Following demolition of Dairy Farm/Feed Storage and the Commodity Barn Facilities (170, 166, 434) (465 stays).

12 SF based on a four story building footprint .

13 Arrowhead Research Park/Center electrical utilities will not be provide from NMSU existing or Secondary or Tortugas Substations.

14 New 2000 Ton Chiller installed in Secondary Utility Plant.

Building Category Watts/SQFT

Academic 2.15

Academic Classroom (Acad - Classroom(s)) 2.3

Academic Classroom Laboratory (Acad - Classroom/Lab) 2.5

Academic Laboratory (Acad - Lab) 3

Administration 2

Auxiliary (AUX) 1.75

Auxiliary/Housing (Aux/Housing) 1.5

Housing Dormitory 1.5

Housing Single Family Residence 1.5

Independent Operations (IO) 2.25

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 2.75

Productions and Operations Management (POM) 5

Productions and Operations Management (POM) 6

Productions and Operations Management (POM) 8

Productions and Operations Management (POM) 12

Services - Family, Student 2

Following demolition of Biological Control Insectary (329), Metabolism and Physiology Lab (372), PGEL Greenhouse and Lab (390, 426), Animal Science Shop (375), Swine Barn (196), Sugerman Space Grant Building (212), West Sheep Unit (512, 466) and Sheep Shearing/Lambing Barn (513).

Following demolition of Animal Science (376, 241, 198), Tejada Extension Annex (245), Animal Husbandry Barn (162), Sheep Barns (194), Cattle Feed Barn (240), Small Animal Lab (246), Livestock Judging Pavilion (195) and Neale Hall (164).

Fed From Electricity Utility Corridor Watts/SFEstimated Load KVA

Xformer KVA

Xformer ID Tag

GSFDwg Area

NotesFeeder # Bldg. # Building Name Year Built Address Category

Page 1

Page 45: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

2024

New Mexico State UniversityUtility Development Plan

2014-2034+ New Building Electrical Load Projections - List 16-Jun-09 Estimated T5 Quantity: 2 Estimated T25 Quantity: 16T25 Quantity: 1 6

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+

FIFTEEN YEAR ADDITION 2024 (2019 - 2024) AND BEYOND 2034+ - SECONDARY AND TORTUGAS NEW SUBSTATION 13800/23900 ADDITIONAL LOADS 15-01 EAST MIXED USEGRADUATE HOUSING PHASE 2 2024 Housing 0 0 0 117,720 117,720 117,720 3 1,2 x Trenches 1.5 176.58 T25-XXX 0.00 0.00 0.00 176.58 176.58 176.5815-02 ZUHL LIBRARY EXPANSION 2024 Acad 0 0 0 110,850 110,850 110,850 7 1,3 x Trenches 2.15 238.33 T25-XXX 0.00 0.00 0.00 238.33 238.33 238.3315-03 ACADEMIC/KAB BUILDING 2024 Acad- Laboratory 0 0 0 26,220 26,220 26,220 6 1 x Trenches 3 78.66 T25-XXX 0.00 0.00 0.00 78.66 78.66 78.6615-04 ACADEMIC BUILDING 2024 Acad-Classroom 0 0 0 117,600 117,600 117,600 7 1 x Trenches 2.3 270.48 T25-XXX 0.00 0.00 0.00 270.48 270.48 270.4815-05 ACADEMIC/LAB BUILDING 2024 Acad- Laboratory 0 0 0 218,190 218,190 218,190 6 1,4 x Trenches 3 654.57 T25-XXX 0.00 0.00 0.00 654.57 654.57 654.5715-06 RESEARCH/LAB BUILDING 2024 Acad- Laboratory 0 0 0 233,250 233,250 233,250 6 1,5 x Trenches 3 699.75 T25-XXX 0.00 0.00 0.00 699.75 699.75 699.7515-07 ACADEMIC LAB BUILDING 2024 Acad- Laboratory 0 0 0 90,930 90,930 90,930 7 1 x Trenches 3 272.79 T25-XXX 0.00 0.00 0.00 272.79 272.79 272.7915-08 ATHLETIC PROGHRAM EXPANSION NORTH 2024 Auxiliary 0 0 0 65,760 65,760 65,760 8 1 x Trenches 1.75 115.08 T25-XXX 0.00 0.00 0.00 115.08 115.08 115.0815-09 GREEK OR FAMILY HOUSING - PHASE 1 2024 Housing 0 0 0 81,900 81,900 81,900 10 6 x Trenches 1.5 122.85 T25-XXX 0.00 0.00 0.00 122.85 122.85 122.8515-10 ATHLETICPROGRAM EXPANSIOPN SOUTH 2024 Auxiliary 0 0 0 65,760 65,760 65,760 11 1 x Trenches 1.75 115.08 T25-XXX 0.00 0.00 0.00 115.08 115.08 115.0815-11 SOFTBALL AND SOCCER COMPLEX 2024 Auxiliary 0 0 0 17,600 17,600 17,600 8 7 x Trenches 1.75 30.80 T25-XXX 0.00 0.00 0.00 30.80 30.80 30.8015-12 BASEBALL COMPLEX 2024 Auxiliary 0 0 0 177,560 177,560 177,560 11 7 x Trenches 1.75 310.73 T25-XXX 0.00 0.00 0.00 310.73 310.73 310.73

15-13 ARROWHEAD EXPANSION - PHASE 3 (8 BUILDINGS) 2024 IO 0 0 0 278,220 278,220 278,220 14 8 x 0.00 0.00 0.00 0.00 0.00 0.0015-14 O'DONNELL HALL - PHASE 2 2024 Acad-Classroom 0 0 0 35,000 35,000 35,000 6 x Trenches 2.3 80.50 T25-XXX 0.00 0.00 0.00 80.50 80.50 80.5015-15 ARTS COMPLEX - PHASE 3 (PERFORMANCE HALL) 2024 Acad-Classroom 0 0 0 76,500 76,500 76,500 2 x Trenches 2.3 175.95 T25-XXX 0.00 0.00 0.00 175.95 175.95 175.9515-16 JEC - NEW 2000 TON CHILLER JCH4 (1100kW EST) 2024 POM 0 0 0 0 0 0 3 9 x 1100.00 T5-XXX T25-XXX 0.00 0.00 0.00 1100.00 1100.00 1100.0015-16 NEW 2000 TON CHILLER CH4 (1100kW EST) 2024 POM 0 0 0 0 0 0 3 9 x 1100.00 T5-XXX T25-XXX 0.00 0.00 0.00 1100.00 1100.00 1100.00

FIFTEEN YEAR ADDITION 2014 -2034+ SUBTOTAL 0 0 0 1,713,060 1,713,060 1,713,060 5,542.15 0.00 0.00 0.00 5,542.15 5,542.15 5,542.15

PROJECTED FIFTEEN YEAR LOAD ADDITION TOTALS 2024 (2024-2034+) 0 0 0 1,713,060 1,713,060 1,713,060 5,542 0 0 0 5542 5542 5542

VA/SQFT TOTAL 0 0 0 3 3 3

AMPERE TOTAL 144 0 0 0 144 144 144

GENERAL NOTES

A Refer to New Mexico State University Utility Development Plan Campus Building and Utility Master List for existing and future planned building numbers and square footage.

B New Mexico State University provided site utility plans indicating locations of existing electrical utilities such as feeder circuits, transformer locations, substations, switches and the like with some assumptions being made.

C New Mexico State University provided Campus Electrical Switching for NMSU last updated February 25, 2008 and data sheets received May 27, 2009.

NOTES

1 SF based on a three story building footprint.

2 Following demolition of Chi Omega sorority houses (268).

3 Following demolition of Breland Hall Addition (north part of 184).

4 Following demolition of Bull Barn (193), Heardsmen Residence (199), Stucky Hall (282), Animal Husbandry (290), and the Feeding Research Building (303).

5 Following demolition of PSL West Shop (280), Guardhouse (281), Machine Shop (216), Rocket Shop (243) and East Shop (279).

6

7

8

9 New 2000 Ton Chiller installed in Secondary Utility Plant.

Building Category Watts/SQFT

Academic 2.15

Academic Classroom (Acad - Classroom(s)) 2.3

Academic Classroom Laboratory (Acad - Classroom/Lab) 2.5

Academic Laboratory (Acad - Lab) 3

Administration 2

Auxiliary (AUX) 1.75

Auxiliary/Housing (Aux/Housing) 1.5

Housing Dormitory 1.5

Housing Single Family Residence 1.5

Independent Operations (IO) 2.25

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 2.75

Productions and Operations Management (POM) 5

Productions and Operations Management (POM) 6

Productions and Operations Management (POM) 8

Productions and Operations Management (POM) 12

Services - Family, Student 2

Arrowhead Research Park/Center electrical utilities will not be provide from NMSU existing or new Secondary or Tortugas Substations.

Bldg. # Building Name Year Built AddressDwg Area

Xformer ID Tag

GSF

Following demolition of East and West Greek Complexes (271, 272, 273, 274, 414), Wells Hall (355), Cosmic Ray Lab (398), Theatre Scene Shop (385), Housing Warehouse (467), Ag Service Storage (316) and Flammable Storage (320), SF based on building footprint for two stories.

NotesXformer

KVA Feeder #

SF based on a two story building footprint.

Fed From Electricity Utility Corridor Watts/SFEstimated Load KVA

Category

Page 1

Page 46: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

2029

New Mexico State UniversityUtility Development Plan

2014-2034+ New Building Electrical Load Projections - List 16-Jun-09 Estimated T5 Quantity: 1 Estimated T25 Quantity: 7T25 Quantity: 7

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+

TWENTY YEAR ADDITION 2029 (2024 - 2029) AND BEYOND 2034 + - SECONDARY AND TORTUGAS NEW SUBSTATION 13800/23900 ADDITIONAL LOADS 20-01 ACADEMIC/LAB BUILDING 2029 Acad- Laboratory 0 0 0 0 118,260 118,260 7 1,2 x Trenches 3 354.78 T25-XXX 0.00 0.00 0.00 0.00 354.78 354.78

20-02 ACADEMIC/RESEARCH BUILDING 2029 Acad-Classroom 0 0 0 0 686,350 686,350 6 3,4 x Trenches 2.3 1578.61 T25-XXX 0.00 0.00 0.00 0.00 1578.61 1578.61

20-03 ACADEMIC/RESEARCH BUILDING 2029 Acad-Classroom 0 0 0 0 273,440 273,440 7 3,5 x Trenches 2.3 628.91 T25-XXX 0.00 0.00 0.00 0.00 628.91 628.91

20-04 FAMILY HOUSING - PHASE 2 2029 Housing 0 0 0 0 255,064 255,064 7 3 x Trenches 1.5 382.60 T25-XXX 0.00 0.00 0.00 0.00 382.60 382.60

20-05 ATHLETIC PROGRAM EXPANSION 2029 Auxiliary 0 0 0 0 111,420 111,420 11 1 x Trenches 1.75 194.99 T25-XXX 0.00 0.00 0.00 0.00 194.99 194.99

20-06 RECREATION FIELD EXPANSION 2029 Auxiliary/Site 0 0 0 0 0 0 10 6,8 x 0.00 0.00 0.00 0.00 0.00 0.00 0.00

20-07 ARROWHEAD EXPANSION PHASE 5 (9 Buildings) 2029 IO 0 0 0 0 203,200 203,200 13 7 0.00 0.00 0.00 0.00 0.00 0.00

20-08 ARTS COMPLEX - PHASE 4 (MUSIC, DANCE, CMI) 2029 Acad-Classroom 0 0 0 0 36,000 36,000 2 x Trenches 2.3 82.80 T25-XXX 0.00 0.00 0.00 0.00 82.80 82.80

20-09 NEW 2000 TON CHILLER CH6 (1100kW EST) 20029 POM 0 0 0 0 0 0 3 9 1100.00 T5-XXX T25-XXX 0.00 0.00 0.00 0.00 1100.00 1100.00

TWENTY YEAR ADDITION 2029 -2034+ SUBTOTAL 0 0 0 0 1,683,734 1,683,734 4,322.68 0.00 0.00 0.00 0.00 4,322.68 4,322.68

PROJECTED TWENTY YEAR LOAD ADDITION TOTALS 2029 ( 2029-2034+) 0 0 0 0 1,683,734 1,683,734 4,323 0 0 0 0 4323 4323

VA/SQFT TOTAL 0 0 0 0 3 3

AMPERE TOTAL 112 0 0 0 0 112 112

GENERAL NOTES

A Refer to New Mexico State University Utility Development Plan Campus Building and Utility Master List for existing and future planned building numbers and square footage.

B New Mexico State University provided site utility plans indicating locations of existing electrical utilities such as feeder circuits, transformer locations, substations, switches and the like with some assumptions being made.

C New Mexico State University provided Campus Electrical Switching for NMSU last updated February 25, 2008 and data sheets received May 27, 2009.

NOTES

1 SF based on a three story building footprint.

2 Following demolition of Regent's Row Dorms (248).

3 SF based on a two story building footprint.

4 Following demolition of Sutherland Village (206).

5 Following demolition of Tombaugh Observatory (317, 318, 319) and PE Restroom (314).

6

7 Following demolition of Aldershot Greenhouse.

8

9 New 2000 Ton Chiller installed in Secondary Utility Plant.

Building Category Watts/SQFT

Academic 2.15

Academic Classroom (Acad - Classroom(s)) 2.3

Academic Classroom Laboratory (Acad - Classroom/Lab) 2.5

Academic Laboratory (Acad - Lab) 3

Administration 2

Auxiliary (AUX) 1.75

Auxiliary/Housing (Aux/Housing) 1.5

Housing Dormitory 1.5

Housing Single Family Residence 1.5

Independent Operations (IO) 2.25

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 2.75

Productions and Operations Management (POM) 5

Productions and Operations Management (POM) 6

Productions and Operations Management (POM) 8

Productions and Operations Management (POM) 12

Services - Family, Student 2

Fed From Electricity Utility Corridor Watts/SFEstimated Load KVA

Dwg Area

Xformer ID Tag Feeder # Bldg. # Building Name Year Built Address Category

Following demolition of Fire Station (267), PPD Motor Pool (373), Physical Plant (221, 237, 220, 218, 223, 254, 455), PPD Warehouse (222, 153), PPD Custodial Office (152), Recycling Center 536), Storage (381, 382, 384), Air Test Facility (343) and Wind Tunnel (371).

Arrowhead Research Park/Center electrical utilities will not be provide from NMSU existing or new Secondary or Tortugas Substations.

NotesXformer

KVA

GSF

Page 1

Page 47: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

2034

New Mexico State UniversityUtility Development Plan

2014-2034+ New Building Electrical Load Projections - List 16-Jun-09 Estimated T5 Quantity: 3 Estimated T25 Quantity: 9

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+

TWENTY-FIVE YEAR ADDITION 2034 + (2029 - 2034) AND BEYOND - SECONDARY AND TORTUGAS NEW SUBSTATION 13800/23900 ADDITIONAL LOADS 25-01 ART COMPLEX - PHASE 1 2034 Acad-Classroom 0 0 0 0 0 864,366 9 1,4 x Trenches 2.3 1988.04 T25-XXX 0.00 0.00 0.00 0.00 0.00 1988.04

25-02 INSTITUTE FOR PUBLIC POLICY (DOMENICI CENTER) 2034 Acad-Classroom 0 0 0 0 0 439,110 10 2,4 x Trenches 2.3 1009.95 T25-XXX 0.00 0.00 0.00 0.00 0.00 1009.9525-03 STUDENT SERVICES FACILITY - PHASE 1 2034 Acad-Classroom 0 0 0 0 0 338,655 10 3,4 x Trenches 2.3 778.91 T25-XXX 0.00 0.00 0.00 0.00 0.00 778.9125-04 NATIVE AMERICAN CULTURAL CENTER 2034 Acad-Classroom 0 0 0 0 0 251,388 2 4 x Trenches 2.3 578.19 T25-XXX 0.00 0.00 0.00 0.00 0.00 578.1925-05 TECHNICAL LAB/CLASSROOM FACILITY 2034 Auxiliary 0 0 0 0 0 239,400 2 5 x Trenches 1.75 418.95 T25-XXX 0.00 0.00 0.00 0.00 0.00 418.95

25-06FUTURE TERTIARY CHILLED WATER PLANT - EST SQFT 2 LEVELS 2034 POM 0 0 0 0 0 10,000 10 x Trenches 6 60.00 T25-XXX 0.00 0.00 0.00 0.00 0.00 60.00

25-06 NEW 2000 TON CHILLER FCH1 (1100kW EST) 2034 POM 0 0 0 0 0 0 10 6 x 1100.00 T5-XXX T25-XXX 0.00 0.00 0.00 0.00 0.00 1100.0025-06 NEW 2000 TON CHILLER FCH2 (1100kW EST) 2034 POM 0 0 0 0 0 0 10 6 x 1100.00 T5-XXX T25-XXX 0.00 0.00 0.00 0.00 0.00 1100.0025-06 NEW 2000 TON CHILLER FCH3 (1100kW EST) 2034 POM 0 0 0 0 0 0 10 6 x 1100.00 T5-XXX T25-XXX 0.00 0.00 0.00 0.00 0.00 1100.00

TWENTY-FIVE YEAR ADDITION 2029 -2034+ SUBTOTAL 0 0 0 0 0 2,142,919 8,134.04 0.00 0.00 0.00 0.00 0.00 8,134.04

PROJECTED TWENTY-FIVE YEAR LOAD ADDITION TOTALS 2034+ ( 2029-2034+) 0 0 0 0 0 2,142,919 8,134 0 0 0 0 0 8134

VA/SQFT TOTAL 0 0 0 0 0 4

AMPERE TOTAL 211 0 0 0 0 0 211

GENERAL NOTES

A Refer to New Mexico State University Utility Development Plan Campus Building and Utility Master List for existing and future planned building numbers and square footage.

B New Mexico State University provided site utility plans indicating locations of existing electrical utilities such as feeder circuits, transformer locations, substations, switches and the like with some assumptions being made.

C New Mexico State University provided Campus Electrical Switching for NMSU last updated February 25, 2008 and data sheets received May 27, 2009.

NOTES

1 Following demolition of Tom Fort Village and Cole Village.

2 Following demolition of Cervantes Housing.

3 Following demolition of Genesis Center (394, 395) and Academic Research Center ( 412).

4 SF based on a three story building footprint.

5 SF based on a four story building footprint.

6 New 2000 Ton Chiller installed in Future Tertiary Chiller Water Plant.

Building Category Watts/SQFT

Academic 2.15

Academic Classroom (Acad - Classroom(s)) 2.3

Academic Classroom Laboratory (Acad - Classroom/Lab) 2.5

Academic Laboratory (Acad - Lab) 3

Administration 2

Auxiliary (AUX) 1.75

Auxiliary/Housing (Aux/Housing) 1.5

Housing Dormitory 1.5

Housing Single Family Residence 1.5

Independent Operations (IO) 2.25

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 1.5

Productions and Operations Management (POM) 2.75

Productions and Operations Management (POM) 5

Productions and Operations Management (POM) 6

Productions and Operations Management (POM) 8

Productions and Operations Management (POM) 12

Services - Family, Student 2

Feeder # Bldg. # Building Name Year Built Address CategoryGSF

Dwg Area

Notes Fed From Electricity Utility Corridor Watts/SFEstimated Load KVA

Xformer KVA

Xformer ID Tag

Page 1

Page 48: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

NETFGFE SUM

New Mexico State UniversityUtility Development Plan (1)

2009-2034+ Summary - Existing and New Building Electrical Load Projections 16-Jun-09

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+

TORTUGAS SUBSTATION 13800/23900 FEEDERS TF1(E)-TF6(E)

TF1(E) PROJECTED EXISTING FEEDER TF1 SUBTOTAL 627,005 627,005 627,005 627,005 484,605 96,061 961.88 961.88 961.88 961.88 961.88 748.28 149.50VA/SQFT SUB-TOTAL 1.53 1.53 1.53 1.53 1.54 1.56AMPERE SUB-TOTAL 24.99 24.99 24.99 24.99 24.99 19.44 3.88

TF2(E) PROJECTED EXISTING FEEDER TF2 SUBTOTAL 542,738 542,738 529,116 417,859 202,066 202,066 1393.58 1393.58 1393.58 1362.25 1207.17 672.23 672.23VA/SQFT SUB-TOTAL 2.57 2.57 2.57 2.89 3.33 1.56AMPERE SUB-TOTAL 36.20 36.20 36.20 35.39 31.36 17.46 17.46

TF3(E) PROJECTED EXISTING FEEDER TF3 SUBTOTAL 869,989 869,989 869,989 837,241 837,241 837,241 4834.94 4834.94 4834.94 4834.94 4759.88 4759.88 4759.88VA/SQFT SUB-TOTAL 5.56 5.56 5.56 5.69 5.69 5.69AMPERE SUB-TOTAL 125.61 125.61 125.61 125.61 123.66 123.66 123.66

TF4(E) PROJECTED EXISTING FEEDER TF4 TOTALS 1,049,351 972,976 897,141 896,096 896,096 896,096 4361.09 4361.09 4102.43 3873.15 3870.74 3870.74 3870.74VA/SQFT SUB-TOTAL 4.16 4.22 4.32 4.32 4.32 4.32AMPERE SUB-TOTAL 113.30 113.30 106.58 100.62 100.56 100.56 100.56

TF5(E) PROJECTED EXISTING FEEDER TF5 TOTALS 1,495,123 1,495,123 1,359,164 1,352,776 1,347,760 1,316,249 3239.20 3239.20 3239.20 3035.27 3025.68 3010.64 2939.49VA/SQFT SUB-TOTAL 2.17 2.17 2.23 2.24 2.23 2.23AMPERE SUB-TOTAL 84.15 84.15 84.15 78.85 78.60 78.21 76.36

TF6(E) PROJECTED EXISTING FEEDER TF6 TOTALS 505,559 505,559 463,500 463,500 463,500 463,500 1833.21 1833.21 1833.21 1744.98 1744.98 1744.98 1744.98VA/SQFT SUB-TOTAL 3.63 3.63 3.76 3.76 3.76 3.76AMPERE SUB-TOTAL 47.62 47.62 47.62 45.33 45.33 45.33 45.33

Estimated Load KVA

Xformer KVA

GSF*Feeder # Building Name

Page 1

Page 49: NMSU ELECTRICAL DISTRIBUTION SYSTEM …facilities.nmsu.edu/wp-content/uploads/sites/57/2013/09/501...GLHN Architects & Engineers, Inc. Electrical Power New Mexico State University

NETFGFE SUM

New Mexico State UniversityUtility Development Plan (1)

2009-2034+ Summary - Existing and New Building Electrical Load Projections 16-Jun-09

ESTIMATED LOAD KVA

2009 2014 2019 2024 2029 2034+ 2009 2014 2019 2024 2029 2034+Estimated Load KVA

Xformer KVA

GSF*Feeder # Building Name

JF(N)/TF(N) FIVE YEAR ADDITION 2014 PROJECTED LOADS 0.00 604,144.00 604,144.00 604,144.00 604,144.00 604,144.00 4,670 0.00 4669.82 4669.82 4669.82 4669.82 4669.82VA/SQFT SUB-TOTAL 0.00 7.73 7.73 7.73 7.73 7.73AMPERE SUB-TOTAL 121 0.00 121.32 121.32 121.32 121.32 121.32

JF(N)/TF(N) TEN YEAR ADDITION 2019 PROJECTED LOADS 0.00 0.00 1,382,170.00 1,382,170.00 1,382,170.00 1,382,170.00 3,572 0.00 0.00 3572.04 3572.04 3572.04 3572.04VA/SQFT SUB-TOTAL 0.00 0.00 2.58 2.58 2.58 2.58AMPERE SUB-TOTAL 93 0.00 0.00 92.80 92.80 92.80 92.80

JF(N)/TF(N) FIFTEEN YEAR ADDITION 2024 PROJECTED LOADS 0.00 0.00 0.00 1,713,060.00 1,713,060.00 1,713,060.00 5,542 0.00 0.00 0.00 5542.15 5542.15 5542.15VA/SQFT SUB-TOTAL 0.00 0.00 0.00 3.24 3.24 3.24AMPERE SUB-TOTAL 144 0.00 0.00 0.00 143.98 143.98 143.98

JF(N)/TF(N) TWENTY YEAR ADDITION 2019 PROJECTED LOADS 0.00 0.00 0.00 0.00 1,683,734.00 1,683,734.00 4,323 0.00 0.00 0.00 0.00 4322.68 4322.68VA/SQFT SUB-TOTAL 0.00 0.00 0.00 0.00 2.57 2.57AMPERE SUB-TOTAL 112 0.00 0.00 0.00 0.00 112.30 112.30

JF(N)/TF(N) TWENTY-FIVE YEAR ADDITION 2019 PROJECTED LOADS 0.00 0.00 0.00 0.00 0.00 2,142,919.00 8,134 0.00 0.00 0.00 0.00 0.00 8134.04VA/SQFT SUB-TOTAL 0.00 0.00 0.00 0.00 0.00 3.80AMPERE SUB-TOTAL 211 0.00 0.00 0.00 0.00 0.00 211.31

TORTUGAS/SECONDARY SUBSTATIONS 13800/23900 PROJECTED TOTALS 5,089,765 5,617,534 6,732,229 8,293,851 9,614,376 11,337,240 42,865 16,624 21,035 24,054 29,354 32,913 40,378VA/SQFT TOTAL 20 27 30 34 37 39AMPERE TOTAL 1,114 432 546 625 763 855 1,049

GF7(E) PROJECTED EXISTING FEEDER GF7 TOTALS 22,191 22,201 22,201 22,201 22,201 22,201 1086 1085.90 1085.92 1085.92 1085.92 1085.92 1085.92VA/SQFT SUB-TOTAL 48.93 48.91 48.91 48.91 48.91 48.91AMPERE SUB-TOTAL 28 28.21 28.21 28.21 28.21 28.21 28.21

GEOTHERMAL SUBSTATION 13800/23900 FEEDERS GF7(E) 22191 505559 22201 22201 22201 22201 1086 1086 1086 1086 1086 1086 1086VBA/SQFT TOTAL 49 49 49 49 49 49AMPERE TOTAL 28 28 28 28 28 28 28

GENERAL NOTES

A Refer to New Mexico State University Utility Development Plan Campus Building and Utility Master List for existing and future planned building numbers and square footage.

B New Mexico State University provided site utility plans indicating locations of existing electrical utilities such as feeder circuits, transformer locations, substations, switches and the like with some assumptions being made.

C New Mexico State University provided Campus Electrical Switching for NMSU last updated February 25, 2008 and data sheets received May 27, 2009.

NOTES

* (E) Indicates an existing feeder. TF1(E) identified as Tortugas Substation existing Feeder 1 and GF7(E) Geothermal Substation existing Feeder 7.

* (N) Indicates a new feeder JF4(N) identified as Jordan Substation (New) Feeder 4 and TF12 Tortugas Substation (New) Feeder 12 and GF7(E) Geothermal Substation existing Feeder 7.

(1) Existing and New Electrical Load Projection Summary is based on the Master Building and Utility List, building categories and assigned watts/sqft. NMSU provided maximum feeder demands were not used in the Electrical Load Projections.

SECONDARY SUBSTATION 13800/23900 FEEDERS JF(N) AND TORTAGUS SUBSTATION TF(N)

Page 2


Recommended