+ All Categories
Home > Documents > Noble Indian Infrastructure Preview 2009-02-13

Noble Indian Infrastructure Preview 2009-02-13

Date post: 10-Apr-2018
Category:
Upload: neuroactive
View: 216 times
Download: 0 times
Share this document with a friend

of 12

Transcript
  • 8/8/2019 Noble Indian Infrastructure Preview 2009-02-13

    1/12

    Page 1 of 12www.noblegp.com

    Clear thinking from

    We do not see the Indian infrastructure sector getting out of the

    doldrums for the next six months despite the governments back-to-back

    stimulus packages. In light of the structural problems facing the

    infrastructure sector, we prefer EPC companies to developers. Amongst

    developers, we prefer companies with operating assets and assets with

    lower dependence on real estate.

    The Governments stimulus packages, for jump-starting private infrastructure

    investments will be unsuccessful in injecting life into the sector because:

    of the private sectors reduced appetite for risk. Multiple data sources point tosharply reduced private participation in infrastructure projects in 2008-09.

    Hence, investment is expected to fall sharply from the US$22 bn invested in

    each of 2006 and 2007 as reality dawns and bidders start considering

    economic risks, fluctuating interest rates and restricted credit availability.

    the Governments measures lack speed and efficacy. Monetary measures maynot drive disbursals as banks start pricing risks higher and face limits on sector

    and group exposures. Moreover, lack of availability of affordable international

    funds will make the External Commercial Borrowings (ECBs) relaxations

    ineffective. Finally, the amplification of IIFCLs refinancing capacities by

    US$850 mn seems like a stopgap measure in a long haul (XI th plan estimates

    the private sector debt requirement for infrastructure to be US$90 bn).

    lack of project planning deters private capital. We believe that during the past2-3 years, even ill-conceived projects managed to get funding. International

    experience and industry sources stress the importance of properly planned

    projects using a life-cycle approach along with policies/procedures for

    adequate risk sharing and implementation. Lack of adequate project-planning

    and an overly narrow focus on the specific transaction will continue to result in

    a lack of private sector interest.

    PREFER EPC COMPANIES WITH LIMITED DEVELOPER ROLE

    In the current scenario, where inadequate project planning may keep economic

    risks high and flexibility low in concession agreements, we prefer EPC companies

    over developers. However, most of the EPC companies have become part

    developer. Hence, we prefer EPC companies with: (a) a large proportion of cash

    contracts in their order books, (b) minimal equity investment needs in infra

    SPVs/subsidiaries; and (c) low leverage. Firms that meet these criteria are IVRCL,

    Punj Lloyd and Simplex Infrastructure.

    PREFER DEVELOPERS WITH LOW DEPENDENCE ON EXTERNAL

    ASSETS

    Amongst the developers, we prefer companies with operating assets and assets

    with the least dependence on external real estate. We prefer roads under

    operation and regulated assets such as utilities to airports and toll roads under

    development. Developers owning operating toll-roads (eg: GVK, IRB) should be

    preferred to Greenfield toll-road developers with toll-roads under development (eg:

    Nagarjuna, Madhucon and HCC). Over the next two months we will initiatecoverage on GVK and IRB amongst the developers and Punj Lloyd and IVRCL

    amongst the EPC firms.

    India Infrastructure

    Research preview

    13 February 2009

    Indian infrastructureExit the developer, enter the builder

    Historical movement of the infra index

    Source: Bloomberg

    Table 1 Coming soon from our stable

    Company Comment

    IVRCL EPC/developer

    Simplex Infrastructure EPC

    GVK Power & Infrastructure Developer

    IRB Infrastructure Developer

    Nagarjuna Construction EPC/developer

    Punj Lloyd EPC

    Source: Noble research

    Analyst

    Nitin Bhasin+91 (0) 22 4211 [email protected]

    Sales

    Pramod Gubbi

    +91 22 4211 [email protected] Ramachandran

    +44 (0) 20 7763 [email protected]

    0

    20

    40

    60

    80

    100

    120

    CNX500 Inde x C NX Infra Inde x

  • 8/8/2019 Noble Indian Infrastructure Preview 2009-02-13

    2/12

    Indian infrastructure

    Page 2 of 12

    Clear thinking from

    THE WELL PUBLICISED TARGETS OF THE XITH

    PLAN

    In order to close the increasing deficit in Indian infrastructure, the Government of

    India (GoI) increased the XIth plan (FY07-12) outlay by 1.4X over the Xth plan (FY02-

    07) (see Table 2). Recognising the limits of public resources and the increasing

    success of public-private partnerships (PPPs) in infrastructure, the GoI increased

    share of private investment to 30% in the XIth plan from 20% in the Xth plan; in

    absolute terms to Rs6.2 tn, 2.6X growth from the X

    th

    plan. However, the relativerole of public and private sectors will vary with some sectors such as airports and

    telecommunication attracting a larger share of private investment, whereas roads

    and power have a lower share of private participation.

    Table 2 Share of private investment in the XIth

    plan to be about 30% versus 20% in

    Xth

    plan

    Figure 1 Electricity and roads to account

    for larger share of private funding

    (Rs bn) Xth plan XIth plan

    Total Public Private Total Public Private

    Electricity 2,919 69% 31% 6,665 72% 28%

    Roads and Bridges 1,449 95% 5% 3,142 66% 34%

    Telecommunications 1,034 47% 53% 2,584 31% 69%

    Railways 1,197 100% 0% 2,618 81% 19%

    Irrigation 1,115 100% 0% 2,533 100% 0%

    Water Supply & Sanitation 648 98% 2% 1,437 96% 4%Ports 141 26% 74% 880 38% 62%

    Airports 68 57% 43% 310 30% 70%

    Storage 48 30% 70% 224 50% 50%

    Gas 97 90% 10% 169 61% 39%

    Total 8,714 80% 20% 20,562 70% 30%

    Source: Planning Commission, Noble research Source: Planning Commission, Noble research

    However, execution of the planned expenditure is lagging due to various

    regulatory, financing and procedural constraints and we expect the overall

    investments by 2012 to miss the stated targets by 30-35%. In this note we examine:

    The reasons behind this expenditure shortfall The implications of this shortfall for investors in this sector Some of the steps that might be taken post elections to address the shortfallTHE DRIVERS OF THE EXPENDITURE SHORTFALL

    We see the following three drivers of the shortfall:

    1. The private sectors reduced appetite for risk2. The governments flawed attempts to improve financing for infrastructure3. Lack of proper project planning

    1. Falling appetite for riskAfter witnessing heavy investment in 2006 and 2007, private participation in public

    infrastructure is expected to be much lower in 2008 and 2009 relative to the

    US$22 bn invested in each of those previous years. In 2006-07, as capital became

    plentiful, the risk premium for these greenfield projects all but disappeared, even as

    nominal rates and interest rate volatility were increasing. However, now with the

    emerging economic risks, rising interest rates and concerns about credit

    availability, private interest is waning in infrastructure investment, a fact that can be

    inferred from media reports on the dismal level of bidding activity in state and

    central projects. For example, recent media reports indicate that just one company

    each had bid in five road tenders opened recently to develop the 6,500km

    highways and that too with Viability Gap Funding (VGF) of 37-39% of the total

    project cost

    We believe that Indian PPP projects have been assuming more interest rate risk

    over 2006-08 with senior debt funding rising and equity participation dropping.

    The tenor of debt at 7-10 years continues to remain relatively short by the

    standards of this industry, with a trend towards shorter reset periods. PwCs

    30 %

    17%9%

    8%

    1%9% 3%

    2%1%

    Electricity

    Roads and Bridges

    Telecommunications

    Railways

    Irrigation

    Water Supply &SanitationPorts

    Airports

    Storage

    Gas

    Figure 2 Rising private investments in

    Indian infra

    Source: PPIAF, Noble research

    52

    43

    46

    3

    9

    8 22

    22

    -

    5

    10

    15

    20

    25

    1996

    1997

    1998

    1999

    2000

    2001

    2002

    2003

    2004

    2005

    2006

    2007

    (US$ bn)

    Water and sewage

    Transport

    Telecom

    Energy

  • 8/8/2019 Noble Indian Infrastructure Preview 2009-02-13

    3/12

    Indian infrastructure

    Page 3 of 12

    Clear thinking from

    research highlights that for select PPP projects, spreads dropped in 2006 and 2007

    to reach levels below AAA and AA rated corporate bonds (thus suggesting minimal

    economic risk in Indian infrastructure investment!).

    Figure 3 Debt-equity ratios rising for Indias PPPs Figure 4 PPP spreads fell sharply over the period 2004-07

    Source: PricewaterhouseCoopers, Noble research Source: Bloomberg, PricewaterhouseCoopers, Noble research

    Early evidence for 2009 suggests a reconnection between lending rates and

    project risk fundamentals. The apparent underpricing of project risk during the

    2006-2007 period suggests potential difficulties for a number of project loans as

    they reach their first interest reset period (every two to three years on average), or

    worse, as some projects recapitalise in their transition from construction to

    operations.

    Whilst some of the reasons for the private sectors heightened risk aversion are

    linked to the credit crisis and the re-pricing of risk globally, there are some sector

    specific issues in India as well such as poor project planning (discussed

    subsequently) and political uncertainty with the looming elections.

    2. Government measures to improve funding lack speed andefficacy

    Through its two stimulus packages in Dec-08 and Jan-09, the GoI has sought to

    improve the infrastructure sectors access to finance by:

    Allowing IIFCL to raise tax-free bonds for re-financing banks loans toinfrastructure companies at lower cost,

    Relaxing ECB regulations for NBFCs focusing on infrastructure lending andborrowings by infrastructure companies,

    Reduction in banks cash reserve requirements, cuts in repo and reverse reporate, upward revision of credit targets (for Public Sector Banks), and

    Increase in the FII investment limit in rupee denominated corporate bonds inIndia to US$15 bn from US$6 bn.

    We do not see these measures as being particularly effective for the reasons

    highlighted in this section.

    Banksrisk pricing and regulatory issues to keep the impact of monetary

    measures muted

    Pricing of project risks by banks has in the past depended more on sponsor-bank

    relationships than on a broader and more rigorous evaluation of project

    fundamentals. The importance of pricing project risk, and its reflection in the

    interest rate charged by Indian banks has varied over time with little attention torisk analysis. This has lead to declining PPP spreads over 2004-07 (see figure 4).

    However, as concerns about economic growth have come to the fore, banks are

    now waking up to the risks such as inflexible concession agreements, cost overruns

    0

    10

    20

    30

    40

    50

    60

    70

    80

    1998 1999 2000 2001 2002 2003 2004 2005 2006 2007

    %ageoftotal

    Senior debt Equity

    Subordinated debt Government grants

    0

    100

    200

    300

    400

    500

    600

    2002 2003 2004 2005 2006 2007

    Basispoints

    Selected PPP projects AAA bonds

    AA bonds BBB bonds

    Table 3 The Governments measures

    may not have the desired impact

    Impactedentity

    Comments

    NBFCs Relaxed ECB regulations butwhere is the foreign money?

    ECBs Lack of money internationally toinvest in India on account ofincreasing spreads

    Commercialbanks

    Exposure at high levels withsome banks at limit levels;

    heightened risk perceptionIIFCL Disbursals of Rs30 bn in FY09,one-third below the targeteddisbursal

    Source: Noble research

  • 8/8/2019 Noble Indian Infrastructure Preview 2009-02-13

    4/12

    Indian infrastructure

    Page 4 of 12

    Clear thinking from

    and user charge revenues. Not only are banks increasing risk analysis, they are also

    not abiding by the earlier loan documents and are now negotiating rates on

    account of the increased risk perception of the infrastructure sector. Industry

    sources (NBFCs and rating agencies) highlight that banks are constrained not so

    much because of liquidity concerns but because of their fear that the projects they

    finance may turn out to be non-performing assets.

    Bankstoo small to provide a solutionAlthough the government is increasing the credit available to the banking system,

    Indian banks are relatively small. Only 11 banks had equity above US$1 bn (Rs49 bn)

    in March 2007 of which two were private sector banks. Even Indias largest bank,

    State Bank of India (SBI) had just over US$7 bn of capital in March 2007. The total

    equity of the 82 scheduled commercial banks (including 29 foreign banks) was

    US$50 bn.

    Group exposure guidelines of the Reserve Bank of India (RBI) also limit a banks

    exposure to any group, to 50% of its capital funds. This ceiling can be breached

    very quickly for companies specialising in infrastructure projects. For instance, a

    group company with two Ultra Mega Power Plants (UMPPs) of US$4 bn each, and a

    US$500 mn road project executed through separate special purpose vehicles

    (SPVs) can require debt funds to the tune of US$5.8bn.

    IIFCL a stopgap measure at best

    Amplification of IIFCLs refinancing capacities by US$850 mn (Rs400 bn) over the

    next 12-15 months seems like a stopgap measure in a long haul given the large

    US$90 bn private sector debt requirements over the XIth plan (see figure 5). Also,

    IIFCLs refinancing of bank loans through the issue of 5-year tax-free bonds does

    not address the issue of lack of long-tenor funds for the infrastructure sector.

    Though the new funds raised will increase IIFCLs disbursal capabilities, we believe

    it could be another 5-6 months before these new funds are disbursed to new

    projects as appraisal and sanctions take time. Moreover, the increase in exposure

    limits for IIFCL and heightened risk perception amongst banks could mean banks

    increasingly opt for maximum refinancing (through IIFCL) and minimum exposure

    (to their balance sheet), leading to a lower-than-expected impetus.

    IIFCLs participation in the overall project cost for sanctioned proposals has

    hitherto not been more than 10-15% and its disbursals have not been very

    meaningful in the overall scheme of things. Although, IIFCL expects disbursals to

    increase to Rs30 bn in FY09 from Rs15 bn in FY08, these disbursals will still be

    insignificant in terms of the overall debt requirements of the projects. IIFCL says

    that it will disburse Rs50 bn by March 2010.

    Banks are now waking up to the

    economic and project-related risks

    Table 4 The RBIs norms for banks

    and FI lending impose company and

    group restrictions

    Single company Group

    20% of the capitalfunds for infrastructureprojects*

    20% of the capitalfunds for infrastructureprojects*

    *25% with Boards approval

    **55% with Boards approval

    Capital funds include Tier I & II capital

    Source: RBI, Noble research

    Figure 5 XIth

    plan projects 70% of

    private investment to be met through

    borrowings

    Source: Planning Commission, Noble research

    IIFCL disbursals will still be insignificant

    in terms of overall private sector debt

    requirement

    Table 5 IIFCLs exposure for projects which have achieved financial closure

    (Rs bn) No. of projects Project cost Loan sanctioned Amount allocated

    Road 46 248 46 32

    Port 4 28 4 3

    Power 18 674 85 75Airport 2 147 22 8

    Urban infrastructure 1 1 0 0

    Total 71 1,097 156 119

    Source: IIFCL, Noble research

    16 2024

    3138

    129

    -

    20

    40

    60

    80

    100

    120

    140

    US$

    bn

    Borrowings Private

  • 8/8/2019 Noble Indian Infrastructure Preview 2009-02-13

    5/12

    Indian infrastructure

    Page 5 of 12

    Clear thinking from

    ECBsunavailable but also not the best option

    The relaxation in ECB regulations for infrastructure investment may be a positive

    move. However, past financial crises leave us less sanguine of this source as a

    steady long-term funding option. Moreover, given the scarcity of credit and wide

    spreads prevailing in global markets, we do not see increasing ECB flows to either

    NBFCs or corporates within the infrastructure segment (it is highly unlikely that

    ECBs can provide finance at sub-12% cost and that too for borrowers with weak or

    non-existent credit ratings).

    Moreover, raising money internationally can create problems when macro concerns

    increase. For example during the financial crises in Asia in 1997 and in Argentina in

    2002, many projects broke under the severe stress of such crises, as the local

    currency revenues of such projects could no longer service foreign currency debt

    made more expensive by steep currency devaluations.

    NBFCs

    There is a large chunk of infrastructure financing that comes from NBFCs, but it is

    concentrated in few large NBFCs such as IDFC. Currently, the only mode of

    financing for these NBFCs is, directly or indirectly, are the banks. Opening the ECB

    window for these NBFCs will not serve any purpose as there is hardly any

    international money on the ECB front ready to come to India (and whatever moneyis willing to come to India will not come at sub-12% interest rates).

    Equity capital to match debt capital may remain in short supply

    We expect increasing risk perception amongst the debt providers to increase the

    share of equity in infrastructure projects from 25% to a significantly higher

    proportion. However, as is well known, equity is in short-supply due to the state of

    capital markets. Moreover, hitherto equity sources for Indian infrastructure have

    been largely domestic (more than 80% came from project developers, with the

    next largest contributor being the public sector). With the large order book

    additions and ongoing infrastructure projects, the balance sheets of many private

    promoters are stretched and their ability to bring in further equity is doubtful.

    Participation by foreign players, particularly strategic investors, has been low eventhough PPP projects in many of the sectors are allowed to have 100% FDI. FDI

    accounted for only 11% (~US$300-400 mn) of the total investment in the Indian

    projects studied by Public-Private Infrastructure Advisory Facility (PPIAF) over

    1995-2007. The port sector had the largest share (51%) of this foreign investment,

    followed by airports (32%) and roads (16%). Only nine projects were reported to

    have strategic investor participation totalling a mere US$167 mn: four in ports,

    three in airports, and one each in water supply and railways.

    Figure 7 FDI flow in sectors like power is already declining

    Source: DIPP, Noble research

    2822

    51

    89

    7

    44

    70 74

    2

    21

    87

    78

    47

    39

    24

    14

    57

    9

    -

    10

    20

    30

    40

    50

    60

    7080

    90

    100

    2005-06 2006-07 2007-08 2008

    (Apr-Oct)

    Rsbn

    Telecommuni

    cations

    Construction

    Real estate

    Power

    Oil & gas

    Figure 6 ECB availability has been

    declining since the beginning of 2008

    Source: Bloomberg, Noble research

    Domestic companies and developers are

    reluctant to part with equity at current

    valuations

    0

    500

    1,000

    1,500

    2,000

    2,500

    3,000

    ECB/FCCB moving

    average last 12months (US$ mn)

  • 8/8/2019 Noble Indian Infrastructure Preview 2009-02-13

    6/12

    Indian infrastructure

    Page 6 of 12

    Clear thinking from

    3. Lack of planning and policies deters private capitalPrivate investment in infrastructure is not only being held back due to inadequate

    funding but also due to a shortage of well-conceptualised projects.

    Lot of projects lack in project evaluation methodology

    In India, Centre and states suffer from a lack of project preparation capacity. As per

    the Comptroller and Auditor General (CAG) of India more than two-thirds of the

    National Highways Development Project (NHDP) Phase I projects were delayed

    because of preparation of faulty detailed project reports (DPRs). As India

    transitions from procuring and bidding out a large portfolio of PPPs, to managing

    and overseeing this portfolio and spreading the program to other sectors, it needs

    a robust evaluation mechanism. Industry sources point out that during the last 2-3

    years even ill-conceived projects with improper sharing of risk also received private

    investments and bank funding (example: Noida Toll Bridge, which went through

    restructuring in its early days of operations). CAGs report also points to lack of

    evaluations: it states that if the National Highways Authority (NHAI) had fixed toll

    rates and concession periods on the basis of sound evaluation, the concession

    period of the Jaipur-Kishangarh and Delhi-Gurgaon projects could have been

    restricted to 12 and 14 years, respectively (as opposed to the actual 18 years and 20

    years, respectively, for which those concessions have been granted).

    International experience also suggests that poor or incomplete project evaluations

    were the primary reason that many PPP projects around the world in the 1990s

    were halted due to stakeholder disputes. A 2002 study found that, on average, in

    nine out of ten transport infrastructure projects (generally among the most

    expensive PPP projects), costs are underestimated, in some sectors such as rail, by

    much as 45% on average.

    IMPLICATIONS FOR INVESTORS

    Given that the policy and the process shortfalls highlighted in the previous sections

    are not going to disappear in the short-medium term and given that private

    capitals risk appetite will not return to FY07/FY08 levels for some time to come,

    we prefer EPC companies to developer companies. Given the lack of private

    capital, we expect governments (central and state) to increase outlay on

    infrastructure activities as announced in the recent stimulus package. This should

    result in the continuing business for EPC players.

    We prefer EPC companies over developers

    Our research indicates that about 50% of the overall infrastructure expenditure in

    the Xth plan will be the construction component i.e about Rs10 tn (US$200 bn)

    over FY07-12. In the current scenario, where inadequate project planning may keep

    economic risks high and flexibility low in concession agreements, we prefer EPC

    companies over developers. Where developers face uncertainties with regards tohigher interest rates and the changing economic scenario, EPC companies cash

    contracts are relatively insulated (barring the rising working capital costs and

    barring a complete standstill in the construction activity). We further expect EPC

    players to benefit from additional government spending in Indian infrastructure.

    Limited pure EPC players... developer role creating incentive problems

    Though we prefer EPC companies in the current scenario compared to the

    developers, we highlight that most of the EPC companies have become part

    developers creating efficiency problems and incentive compatibility challenges.

    GMRs woes in DIAL is a model case ofimproper evaluation wherein GMR has

    sought support from government early

    on for traffic and revenue shortfall and

    inability to raise funds by trumpeting the

    possibilities of halting of work due to

    running out of financial resources. The

    recent levy of Airport Development Fee

    (ADF) has also come after Indian Law

    Ministry had rejected the same in

    December 2008 citing agreements

    signed in 2006

    During the last 2-3 years even ill-

    conceived projects received private

    investments and bank funding

    We prefer EPC player over developers;

    within the sector we prefer power and

    roads to airports

    Table 6 Near-term coverage

    Company Comment

    IVRCL EPC/developer

    GVK Power & Infrastructure Developer

    IRB Infrastructure Developer

    Nagarjuna Construction EPC/developer

    Punj Lloyd EPC

    Source: Noble research

  • 8/8/2019 Noble Indian Infrastructure Preview 2009-02-13

    7/12

    Indian infrastructure

    Page 7 of 12

    Clear thinking from

    Table 7 EPC players increasingly assuming developer role

    Companies Toll-roads Captive power Real estate Airports Ports

    HCC Gammon IVRCL Patel Engineering Simplex

    Nagarjuna Construction Lanco Infratech Source: Company data, Noble research

    Many construction firms have formed project companies to bid on big projects,

    because they cannot afford the opportunity cost of missing out on the construction

    contracts that are embedded in them. Companies have been increasingly willing to

    bet their balance sheets on concessions or greenfield construction projects that

    ostensibly tie them to a bankable revenue stream (from tolls, tariffs or government

    transfers). This enables them to raise project financing (or did when the going was

    good). However, this creates a risk for construction companies in so far as they can

    get stuck in low margin businesses as in the case of Gammon. That being said,

    academic research suggests that EPC companies have good reason to become

    developers.

    Sirtaine, Pinglo, Guasch and Fosters (2005) find that for Latin American

    developers the IRR is below the weighted average cost of capital (WACC) (see

    figure 8). However, after making standard accounting adjustments (for example, to

    add to the utilities the high rates of management fees and transfers to subsidiaries

    through purchases) mainly for the EPC companies assuming a developer role, the

    rate of return surpasses the costs of capital.

    Be that as it may, within the EPC sub-sector, we prefer EPC companies with: (a)

    large proportion of cash contracts in their order books, (b) minimal equity

    investment needs in infra SPVs/subsidiaries, and (c) low leverage. Firms that meet

    these criteria are IVRCL, Punj Lloyd and Simplex Infrastructure.

    Over the next 2 months we will initiate coverage on the following EPC firms:

    - Punj Lloyd (PUNJ.IN, market cap US$590 mn) is a pure Engineering &Construction (E&C) major catering to the hydrocarbons and civil construction

    sectors across India, Asia and the Middle East. The recent acquisition of

    Sembawang has helped it scale up its expertise in large scale urban

    infrastructure in Asia and Africa.

    - IVRCL (IVRC.IN, market cap US$327 mn) is the leading water-segmentengineering procurement, construction and commissioning (EPCC) player with

    minimal developer (one road and Chennai water desalination project) role.

    IVRCL through its subsidiary IVR Prime has exposure to real estate

    development.

    - Simplex Infrastructure (SINF.IN, US$152 mn) is a pure EPC company withbusiness experience spanning across industrial, infrastructure and residential

    projects in India and the Middle East. The company has recently forayed intoonshore oil drilling.

    Amongst developers, we prefer power and roads to airports

    Within the infrastructure developer segment, we prefer developer companies with

    projects with economic profiles which are the least dependent on external assets

    such as the attached real estate. We believe airport assets to be the riskiest as

    these projects are heavily dependent on the adjoining real estate (examples: Delhi

    (GMR) and Mumbai (GVK)). Developers owning operating toll-roads (eg: GVK,

    IRB) should be preferred to Greenfield toll-road developers with toll-roads under

    development (eg: Nagarjuna, Madhucon and HCC). Within utilities, although new

    generation capacities may find financial closure difficult, regulation assures returns

    with comparably lower risk profile for new generation companies; however, some

    level of merchant power capacity can improve the economic profile of powergeneration projects.

    Figure 8 EPC companies can improve

    IRRs through captive contracts (Latin

    American data)

    Source: Sirtaine, Pinglo, Guasch and Foster2005 (Latin America: 34 concessions)

    0%

    2%

    4%

    6%

    8%

    10%

    12%

    14%

    16%

    18%

    20%

    Transport Water Telecom Energy

    WACC Adjusted IRR Unadjusted IRR

  • 8/8/2019 Noble Indian Infrastructure Preview 2009-02-13

    8/12

    Indian infrastructure

    Page 8 of 12

    Clear thinking from

    Table 8 Risks and rewards of infrastructure segments

    Asset segment Risk Avg cash yield(yrs 1-5)*

    Averageleveraged IRR**

    Capitalappreciation

    potential

    Toll roads (operating) Low 4-8% 8-12% Limited

    Regulated assets Low-med 6-10% 10-15% Limited

    Rail Medium 8-12% 14-18% Yes

    Airports/ seaports Medium 5-10% 15-18% YesToll roads (development) Med-high 3-5% 12-20% Yes

    Note: * Cash distribution to equity holders as a percentage of equity investment** Assumes debt of50% to 85% and investment periods of not less than five to seven years

    Source: Larry W. Beeferman, Noble research

    Over the next two months we will initiate coverage on the following developers:

    - GVK Power and Infrastructure (GVKP.IN, market cap US$610 mn) is one of theleading infrastructure developers in India with a portfolio of assets spanning

    power, roads, SEZ and airport (Mumbai International airport).

    - IRB Infrastructure (IRB.IN, market cap US$786 mn) is Indias leading toll-roadoperator on a build-operate-transfer (BOT) basis with 11 operational roads, one

    under construction and two at financial closure stage.

    Developers face multiple risks

    While actual economic growth in recent years has exceeded the expectations of

    some of the project feasibility studies, none anticipated the current economic

    slowdown. As a result, developers project cash flows and asset values are highly

    susceptible to construction delays, the current economic slowdown and interest

    rate risk (the latter due to the frequent interest reset periods of the loans). Though

    infrastructure assets are long-term in nature and their intrinsic value should not be

    significantly affected by short-term movements in the changing economic

    landscape, many assets in India do not have any operating track record and may

    face risks not factored during aggressive bidding for these assets in 2006-07.

    We expect developer companies to face serious challenges as most of the

    infrastructure developers projections for cash flows from projects did not involve

    stress testing. For projects with full market exposure, and aggressive debt

    amortisation, a sudden economic downturn could push debt service coverage

    levels dangerously near the loans covenant, requiring a restructuring of project

    debt. Rating agencies such as Fitch expect a large amount of loan restructuring to

    take place over the next few years, as a wave of projects exit the construction

    phase and enter operations.

    Good examples of projects beset by these challenges are the Noida Toll Bridge

    and the Delhi International Airport (DIAL) being developed by GMR Infrastructure.

    Back-ended revenue profile coupled with high interest rates not only led torestructuring of Noida Toll Bridges but also for extension of the concession

    period.

    Early into its operations DIAL has witnessed traffic declines and debt hasbecome scarce. This has lead to repeated requests for levy of additional fees

    for making the revenue shortfall. Waning interest in the adjoining real estate

    has also impacted the funding for the airport.

    Interest reset periods for outstanding project loans are aggressive, occurring every

    two to three years, and in some cases, even annually. Most projects have reset

    periods that coincide with projects entering their operating phase. While project

    concession agreements contain annual tariff adjustment clauses that are usually

    tied to inflation, this natural hedge is not perfect. Moreover, regulatory hurdles such

    as the new Model Concession Agreement (MCA) capping overall project returns by

    linking traffic growth with the concession period can be a dampener for investment

    returns for developers.

    While actual economic growth in recent

    years has exceeded the expectations of

    some of the project feasibility studies,

    none anticipated the current economic

    slowdown

    Cash flows for most of the projects were

    built as annuities and did not involve

    stress testing

  • 8/8/2019 Noble Indian Infrastructure Preview 2009-02-13

    9/12

    Indian infrastructure

    Page 9 of 12

    Clear thinking from

    THE WAY FORWARD FOR INDIAN INFRASTRUCTURE

    In order to improve debt and long-term funding availability and concurrently

    increase private participation in the infrastructure sector, the GoI needs to push for

    structural changes in the financial system, increase participation of financial

    investors and follow a life-cycle approach to planning infrastructure projects.

    1. Development of long-term bond marketsThe creation of a deep and robust debt capital market can increase the flow of

    long-term funds and reduce reliance on banks. The Indian corporate bond market,

    though one of the largest in Asia, is still at an early stage of development, and its

    growth is hampered by institutional, legal, and regulatory constraints that make

    bonds a more expensive way of financing debt. The domestic bond market

    continues to be dominated by public borrowingNational Thermal Power

    Corporation (NTPC), NHAI and Power Finance Corporation (PFC)and does not

    address the needs of the corporate market.

    Moreover, to increase the efficiency of the private placement market for debt, the

    GoI needs to reduce the regulatory asymmetry between loans and bonds. The

    regulations relating to investments in bonds are far more restrictive compared to

    granting of loans(i) Banks cannot invest in unrated debt instruments but can

    invest in unrated loans, and (ii) Banks grant loans with no mark-to-market

    implications, but their bond investments are subject to mark-to-market regulations.

    2. Increased investment by pension/insurance fundsThe projected growth of pension funds and life insurance assets and their natural

    synergy with infrastructure can support long-term infra financing with tenors of 10-

    20 years. The Insurance Regulatory and Development Authoritys (IRDA) recent

    move to increase the exposure limit of insurance companies to a single

    infrastructure company to 20% from the present ceiling of 10% is a step in the right

    direction.

    Table 10 More room for insurance sectors exposure to infrastructure

    Investment in infrastructure andsocial sectors (Rs bn)

    Investment in infrastructure andsocial sectors as a proportion to

    total investment by insurancecompanies (%)

    Life insurers

    2006-07 698 13.0

    2005-06 496 12.5

    2004-05 455 12.4

    Non-life insurers

    2006-07 61 12.1

    2005-06 50 12.7

    2004-05 44 12.6

    Source: IRDA, Noble research

    However, we believe there is more to be done as IRDAs current guidelines call for

    project ratings of not less than AA for debt securities. Generally, infrastructure

    projects that depend on, say, toll collections or airport traffic get a BBB rating.

    Therefore, important road or national highway projects may not be able to get

    investment from the insurance sector unless regulations are amended.

    3. Dominance of certain developers can make matters worseGovernment regulations and policies are restrictive for bidding of projects in roads,

    ports and airports. Clauses in the Request for Quotation (RFQ) allow a fixed

    number of tenders to enter the final phase of price bids. This has not affected roads

    only but also airports and ports. Another bottleneck is assigning marks on the

    basis of experience at the pre-qualification stage, which automatically disqualifies

    new companies wanting to enter the infrastructure development space. Industry

    sources say that these clauses should apply to larger projects rather than the

    smaller ones. Since Dec-07, as many as 60 tenders under NHDP III have been on

    hold because of restrictive clauses.

    Table 9 Public borrowings dominate

    domestic debt securities in India

    (%)Public Private

    FIsCorporate

    entities

    All issuers 49 40 12

    Argentina 72 9 19

    Brazil 78 21 1

    PRC 56 42 2

    India 96 3 1

    Mexico 82 3 15

    South Korea 48 21 31

    Thailand 34 42 23

    Source: BIS (2006), Noble research

    Same set of developers that do other

    EPC jobs for govt/non-govt could limit

    the overall execution capabilities in the

    country

  • 8/8/2019 Noble Indian Infrastructure Preview 2009-02-13

    10/12

    Indian infrastructure

    Page 10 of 12

    Clear thinking from

    4. Life-cycle approach towards projectsWe believe in order to attract increasing private investments the government

    should follow a full life-cycle approach (e.g., a clear framework) for partnerships

    that confers adequate attention to all phases of a PPPfrom policy and planning, to

    the transaction phase, and then to managing the concession. Such an approach can

    help avoid problems of poor setup, lack of clarity about outcomes, inadequate

    internal capacity, lack of interest from the private sector, and an overly narrow

    focus on the transaction.

    Figure 9 Life-cycle approach to project planning increases bankable projects

    Source: ADB

    Government budget

    Int. Long-term Fund Providers

    Project Revenue

    Commercial Banks

    Infrastructure Funds

    Capital Markets

    Bankable projects

    Increasing pool

    of funds

    Easing Financing

    ConstraintsDeveloping long-termbond marketsEncouraging pensionand mutualfunds, insurancecompaniesand financialinstitutions to invest in

    infrastructureDedicated long-termfinancing institutionsRating of projects

  • 8/8/2019 Noble Indian Infrastructure Preview 2009-02-13

    11/12

    Indian infrastructure

    Page 11 of 12

    Clear thinking from

    CONTACT DETAILS

    Saurabh Mukherjea, Head of Indian Equitiest. +91 22 4211 0901 e: [email protected]

    SALES

    Pramod Gubbi t +91 22 4211 0902; e: [email protected]

    Sarojini Ramachandran t: +44 20 7763 2329 e: [email protected]

    LEAD ANALYSTS BY SECTOR

    Banks and Financial Services:

    Aditi Thapliyal t +9122 4211 0904; [email protected]

    Consumer:

    Jaibir Singh Sethi t +91 22 4211 0905; [email protected]

    Infrastructure:

    Nitin Bhasin t +91 22 4211 0909; [email protected]

    Power:

    Bhargav Buddhadev t 91 22 4211 0910; [email protected]

    Technology:

    Ankur Rudra t +91 22 4211 0906; [email protected]

    Economy and Country Research:

    Dipankar Mitra t +91 22 4211 0920; [email protected]

    701 Powai Plaza 120 Old Broad StreetHiranandani Gardens LondonMumbai 400076 EC2N 1AR

    t: +91 22 4211 0999 t: +44 020 7763 2200f: +91 22 25701154 f: +44 020 7763 2397

    e: [email protected]

  • 8/8/2019 Noble Indian Infrastructure Preview 2009-02-13

    12/12

    Indian infrastructure

    Clear thinking from

    Disclaimer - Important Information

    This report has been issued by Clear Capital Limited which is part of Noble, the UK investment banking group. Clear Capital

    Limited is authorised and regulated by the Financial Services Authority.

    Noble is committed to producing research of the highest quality and integrity, to protecting its analysts autonomy, maintainingthe culture of impartiality following its acquisition of Clear Capital and providing transparent disclosure of any potential

    conflicts. However, for the purpose of UK regulation, Noble produces non-independent research which is deemed to be a

    marketing communication under the FSA Conduct of Business rules and is not prepared in accordance with the legal

    requirements to promote independence of investment research. It is also not subject to the prohibition on dealing ahead of the

    dissemination of investment research. Noble has rigorous procedures in place to manage any conflicts in research and limits

    dealing ahead, which are explained in more detail on our website http://www.noblegp.com/regulatory

    The contents are based upon sources of information believed to be reliable but no warranty or representation, expressed or

    implied, is given as to their accuracy or completeness. Any opinion reflects Nobles judgement at the date of publication and

    neither Noble nor its directors or employees accepts any responsibility in respect of the information or recommendations

    contained herein which, moreover, are subject to change without notice. This is neither an offer, nor a solicitation, to buy or sell

    any investment referred to in this document. The material is general information intended for recipients who understand the

    risks associated with investment. It does not take account of whether an investment, course of action, or associated risks are

    suitable for the recipient.

    Noble may provide services (including corporate finance advice) where the flow of information is restricted by a Chinese Wall.

    Accordingly, information may be available to Noble that is not reflected in this document.

    This document is intended to be used by market professionals (eligible counterparties and professional clients but not retail

    clients). Retail clients must not rely on this document and should note that Nobles advisory services are not available to them.

    The document must not be copied or re-distributed to another person / organisation without Nobles prior written consent.

    This document is approved for communication by Noble to market professionals who have registered with Noble to receive

    such information.

    Clear Capital Limited is registered in England & Wales No.4637166. Registered office: 120 Old Broad Street, London EC2N 1AR.

    Tel +44 (0)20 7763 2200


Recommended