Date post: | 10-Apr-2018 |
Category: |
Documents |
Upload: | neuroactive |
View: | 216 times |
Download: | 0 times |
of 12
8/8/2019 Noble Indian Infrastructure Preview 2009-02-13
1/12
Page 1 of 12www.noblegp.com
Clear thinking from
We do not see the Indian infrastructure sector getting out of the
doldrums for the next six months despite the governments back-to-back
stimulus packages. In light of the structural problems facing the
infrastructure sector, we prefer EPC companies to developers. Amongst
developers, we prefer companies with operating assets and assets with
lower dependence on real estate.
The Governments stimulus packages, for jump-starting private infrastructure
investments will be unsuccessful in injecting life into the sector because:
of the private sectors reduced appetite for risk. Multiple data sources point tosharply reduced private participation in infrastructure projects in 2008-09.
Hence, investment is expected to fall sharply from the US$22 bn invested in
each of 2006 and 2007 as reality dawns and bidders start considering
economic risks, fluctuating interest rates and restricted credit availability.
the Governments measures lack speed and efficacy. Monetary measures maynot drive disbursals as banks start pricing risks higher and face limits on sector
and group exposures. Moreover, lack of availability of affordable international
funds will make the External Commercial Borrowings (ECBs) relaxations
ineffective. Finally, the amplification of IIFCLs refinancing capacities by
US$850 mn seems like a stopgap measure in a long haul (XI th plan estimates
the private sector debt requirement for infrastructure to be US$90 bn).
lack of project planning deters private capital. We believe that during the past2-3 years, even ill-conceived projects managed to get funding. International
experience and industry sources stress the importance of properly planned
projects using a life-cycle approach along with policies/procedures for
adequate risk sharing and implementation. Lack of adequate project-planning
and an overly narrow focus on the specific transaction will continue to result in
a lack of private sector interest.
PREFER EPC COMPANIES WITH LIMITED DEVELOPER ROLE
In the current scenario, where inadequate project planning may keep economic
risks high and flexibility low in concession agreements, we prefer EPC companies
over developers. However, most of the EPC companies have become part
developer. Hence, we prefer EPC companies with: (a) a large proportion of cash
contracts in their order books, (b) minimal equity investment needs in infra
SPVs/subsidiaries; and (c) low leverage. Firms that meet these criteria are IVRCL,
Punj Lloyd and Simplex Infrastructure.
PREFER DEVELOPERS WITH LOW DEPENDENCE ON EXTERNAL
ASSETS
Amongst the developers, we prefer companies with operating assets and assets
with the least dependence on external real estate. We prefer roads under
operation and regulated assets such as utilities to airports and toll roads under
development. Developers owning operating toll-roads (eg: GVK, IRB) should be
preferred to Greenfield toll-road developers with toll-roads under development (eg:
Nagarjuna, Madhucon and HCC). Over the next two months we will initiatecoverage on GVK and IRB amongst the developers and Punj Lloyd and IVRCL
amongst the EPC firms.
India Infrastructure
Research preview
13 February 2009
Indian infrastructureExit the developer, enter the builder
Historical movement of the infra index
Source: Bloomberg
Table 1 Coming soon from our stable
Company Comment
IVRCL EPC/developer
Simplex Infrastructure EPC
GVK Power & Infrastructure Developer
IRB Infrastructure Developer
Nagarjuna Construction EPC/developer
Punj Lloyd EPC
Source: Noble research
Analyst
Nitin Bhasin+91 (0) 22 4211 [email protected]
Sales
Pramod Gubbi
+91 22 4211 [email protected] Ramachandran
+44 (0) 20 7763 [email protected]
0
20
40
60
80
100
120
CNX500 Inde x C NX Infra Inde x
8/8/2019 Noble Indian Infrastructure Preview 2009-02-13
2/12
Indian infrastructure
Page 2 of 12
Clear thinking from
THE WELL PUBLICISED TARGETS OF THE XITH
PLAN
In order to close the increasing deficit in Indian infrastructure, the Government of
India (GoI) increased the XIth plan (FY07-12) outlay by 1.4X over the Xth plan (FY02-
07) (see Table 2). Recognising the limits of public resources and the increasing
success of public-private partnerships (PPPs) in infrastructure, the GoI increased
share of private investment to 30% in the XIth plan from 20% in the Xth plan; in
absolute terms to Rs6.2 tn, 2.6X growth from the X
th
plan. However, the relativerole of public and private sectors will vary with some sectors such as airports and
telecommunication attracting a larger share of private investment, whereas roads
and power have a lower share of private participation.
Table 2 Share of private investment in the XIth
plan to be about 30% versus 20% in
Xth
plan
Figure 1 Electricity and roads to account
for larger share of private funding
(Rs bn) Xth plan XIth plan
Total Public Private Total Public Private
Electricity 2,919 69% 31% 6,665 72% 28%
Roads and Bridges 1,449 95% 5% 3,142 66% 34%
Telecommunications 1,034 47% 53% 2,584 31% 69%
Railways 1,197 100% 0% 2,618 81% 19%
Irrigation 1,115 100% 0% 2,533 100% 0%
Water Supply & Sanitation 648 98% 2% 1,437 96% 4%Ports 141 26% 74% 880 38% 62%
Airports 68 57% 43% 310 30% 70%
Storage 48 30% 70% 224 50% 50%
Gas 97 90% 10% 169 61% 39%
Total 8,714 80% 20% 20,562 70% 30%
Source: Planning Commission, Noble research Source: Planning Commission, Noble research
However, execution of the planned expenditure is lagging due to various
regulatory, financing and procedural constraints and we expect the overall
investments by 2012 to miss the stated targets by 30-35%. In this note we examine:
The reasons behind this expenditure shortfall The implications of this shortfall for investors in this sector Some of the steps that might be taken post elections to address the shortfallTHE DRIVERS OF THE EXPENDITURE SHORTFALL
We see the following three drivers of the shortfall:
1. The private sectors reduced appetite for risk2. The governments flawed attempts to improve financing for infrastructure3. Lack of proper project planning
1. Falling appetite for riskAfter witnessing heavy investment in 2006 and 2007, private participation in public
infrastructure is expected to be much lower in 2008 and 2009 relative to the
US$22 bn invested in each of those previous years. In 2006-07, as capital became
plentiful, the risk premium for these greenfield projects all but disappeared, even as
nominal rates and interest rate volatility were increasing. However, now with the
emerging economic risks, rising interest rates and concerns about credit
availability, private interest is waning in infrastructure investment, a fact that can be
inferred from media reports on the dismal level of bidding activity in state and
central projects. For example, recent media reports indicate that just one company
each had bid in five road tenders opened recently to develop the 6,500km
highways and that too with Viability Gap Funding (VGF) of 37-39% of the total
project cost
We believe that Indian PPP projects have been assuming more interest rate risk
over 2006-08 with senior debt funding rising and equity participation dropping.
The tenor of debt at 7-10 years continues to remain relatively short by the
standards of this industry, with a trend towards shorter reset periods. PwCs
30 %
17%9%
8%
1%9% 3%
2%1%
Electricity
Roads and Bridges
Telecommunications
Railways
Irrigation
Water Supply &SanitationPorts
Airports
Storage
Gas
Figure 2 Rising private investments in
Indian infra
Source: PPIAF, Noble research
52
43
46
3
9
8 22
22
-
5
10
15
20
25
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
(US$ bn)
Water and sewage
Transport
Telecom
Energy
8/8/2019 Noble Indian Infrastructure Preview 2009-02-13
3/12
Indian infrastructure
Page 3 of 12
Clear thinking from
research highlights that for select PPP projects, spreads dropped in 2006 and 2007
to reach levels below AAA and AA rated corporate bonds (thus suggesting minimal
economic risk in Indian infrastructure investment!).
Figure 3 Debt-equity ratios rising for Indias PPPs Figure 4 PPP spreads fell sharply over the period 2004-07
Source: PricewaterhouseCoopers, Noble research Source: Bloomberg, PricewaterhouseCoopers, Noble research
Early evidence for 2009 suggests a reconnection between lending rates and
project risk fundamentals. The apparent underpricing of project risk during the
2006-2007 period suggests potential difficulties for a number of project loans as
they reach their first interest reset period (every two to three years on average), or
worse, as some projects recapitalise in their transition from construction to
operations.
Whilst some of the reasons for the private sectors heightened risk aversion are
linked to the credit crisis and the re-pricing of risk globally, there are some sector
specific issues in India as well such as poor project planning (discussed
subsequently) and political uncertainty with the looming elections.
2. Government measures to improve funding lack speed andefficacy
Through its two stimulus packages in Dec-08 and Jan-09, the GoI has sought to
improve the infrastructure sectors access to finance by:
Allowing IIFCL to raise tax-free bonds for re-financing banks loans toinfrastructure companies at lower cost,
Relaxing ECB regulations for NBFCs focusing on infrastructure lending andborrowings by infrastructure companies,
Reduction in banks cash reserve requirements, cuts in repo and reverse reporate, upward revision of credit targets (for Public Sector Banks), and
Increase in the FII investment limit in rupee denominated corporate bonds inIndia to US$15 bn from US$6 bn.
We do not see these measures as being particularly effective for the reasons
highlighted in this section.
Banksrisk pricing and regulatory issues to keep the impact of monetary
measures muted
Pricing of project risks by banks has in the past depended more on sponsor-bank
relationships than on a broader and more rigorous evaluation of project
fundamentals. The importance of pricing project risk, and its reflection in the
interest rate charged by Indian banks has varied over time with little attention torisk analysis. This has lead to declining PPP spreads over 2004-07 (see figure 4).
However, as concerns about economic growth have come to the fore, banks are
now waking up to the risks such as inflexible concession agreements, cost overruns
0
10
20
30
40
50
60
70
80
1998 1999 2000 2001 2002 2003 2004 2005 2006 2007
%ageoftotal
Senior debt Equity
Subordinated debt Government grants
0
100
200
300
400
500
600
2002 2003 2004 2005 2006 2007
Basispoints
Selected PPP projects AAA bonds
AA bonds BBB bonds
Table 3 The Governments measures
may not have the desired impact
Impactedentity
Comments
NBFCs Relaxed ECB regulations butwhere is the foreign money?
ECBs Lack of money internationally toinvest in India on account ofincreasing spreads
Commercialbanks
Exposure at high levels withsome banks at limit levels;
heightened risk perceptionIIFCL Disbursals of Rs30 bn in FY09,one-third below the targeteddisbursal
Source: Noble research
8/8/2019 Noble Indian Infrastructure Preview 2009-02-13
4/12
Indian infrastructure
Page 4 of 12
Clear thinking from
and user charge revenues. Not only are banks increasing risk analysis, they are also
not abiding by the earlier loan documents and are now negotiating rates on
account of the increased risk perception of the infrastructure sector. Industry
sources (NBFCs and rating agencies) highlight that banks are constrained not so
much because of liquidity concerns but because of their fear that the projects they
finance may turn out to be non-performing assets.
Bankstoo small to provide a solutionAlthough the government is increasing the credit available to the banking system,
Indian banks are relatively small. Only 11 banks had equity above US$1 bn (Rs49 bn)
in March 2007 of which two were private sector banks. Even Indias largest bank,
State Bank of India (SBI) had just over US$7 bn of capital in March 2007. The total
equity of the 82 scheduled commercial banks (including 29 foreign banks) was
US$50 bn.
Group exposure guidelines of the Reserve Bank of India (RBI) also limit a banks
exposure to any group, to 50% of its capital funds. This ceiling can be breached
very quickly for companies specialising in infrastructure projects. For instance, a
group company with two Ultra Mega Power Plants (UMPPs) of US$4 bn each, and a
US$500 mn road project executed through separate special purpose vehicles
(SPVs) can require debt funds to the tune of US$5.8bn.
IIFCL a stopgap measure at best
Amplification of IIFCLs refinancing capacities by US$850 mn (Rs400 bn) over the
next 12-15 months seems like a stopgap measure in a long haul given the large
US$90 bn private sector debt requirements over the XIth plan (see figure 5). Also,
IIFCLs refinancing of bank loans through the issue of 5-year tax-free bonds does
not address the issue of lack of long-tenor funds for the infrastructure sector.
Though the new funds raised will increase IIFCLs disbursal capabilities, we believe
it could be another 5-6 months before these new funds are disbursed to new
projects as appraisal and sanctions take time. Moreover, the increase in exposure
limits for IIFCL and heightened risk perception amongst banks could mean banks
increasingly opt for maximum refinancing (through IIFCL) and minimum exposure
(to their balance sheet), leading to a lower-than-expected impetus.
IIFCLs participation in the overall project cost for sanctioned proposals has
hitherto not been more than 10-15% and its disbursals have not been very
meaningful in the overall scheme of things. Although, IIFCL expects disbursals to
increase to Rs30 bn in FY09 from Rs15 bn in FY08, these disbursals will still be
insignificant in terms of the overall debt requirements of the projects. IIFCL says
that it will disburse Rs50 bn by March 2010.
Banks are now waking up to the
economic and project-related risks
Table 4 The RBIs norms for banks
and FI lending impose company and
group restrictions
Single company Group
20% of the capitalfunds for infrastructureprojects*
20% of the capitalfunds for infrastructureprojects*
*25% with Boards approval
**55% with Boards approval
Capital funds include Tier I & II capital
Source: RBI, Noble research
Figure 5 XIth
plan projects 70% of
private investment to be met through
borrowings
Source: Planning Commission, Noble research
IIFCL disbursals will still be insignificant
in terms of overall private sector debt
requirement
Table 5 IIFCLs exposure for projects which have achieved financial closure
(Rs bn) No. of projects Project cost Loan sanctioned Amount allocated
Road 46 248 46 32
Port 4 28 4 3
Power 18 674 85 75Airport 2 147 22 8
Urban infrastructure 1 1 0 0
Total 71 1,097 156 119
Source: IIFCL, Noble research
16 2024
3138
129
-
20
40
60
80
100
120
140
US$
bn
Borrowings Private
8/8/2019 Noble Indian Infrastructure Preview 2009-02-13
5/12
Indian infrastructure
Page 5 of 12
Clear thinking from
ECBsunavailable but also not the best option
The relaxation in ECB regulations for infrastructure investment may be a positive
move. However, past financial crises leave us less sanguine of this source as a
steady long-term funding option. Moreover, given the scarcity of credit and wide
spreads prevailing in global markets, we do not see increasing ECB flows to either
NBFCs or corporates within the infrastructure segment (it is highly unlikely that
ECBs can provide finance at sub-12% cost and that too for borrowers with weak or
non-existent credit ratings).
Moreover, raising money internationally can create problems when macro concerns
increase. For example during the financial crises in Asia in 1997 and in Argentina in
2002, many projects broke under the severe stress of such crises, as the local
currency revenues of such projects could no longer service foreign currency debt
made more expensive by steep currency devaluations.
NBFCs
There is a large chunk of infrastructure financing that comes from NBFCs, but it is
concentrated in few large NBFCs such as IDFC. Currently, the only mode of
financing for these NBFCs is, directly or indirectly, are the banks. Opening the ECB
window for these NBFCs will not serve any purpose as there is hardly any
international money on the ECB front ready to come to India (and whatever moneyis willing to come to India will not come at sub-12% interest rates).
Equity capital to match debt capital may remain in short supply
We expect increasing risk perception amongst the debt providers to increase the
share of equity in infrastructure projects from 25% to a significantly higher
proportion. However, as is well known, equity is in short-supply due to the state of
capital markets. Moreover, hitherto equity sources for Indian infrastructure have
been largely domestic (more than 80% came from project developers, with the
next largest contributor being the public sector). With the large order book
additions and ongoing infrastructure projects, the balance sheets of many private
promoters are stretched and their ability to bring in further equity is doubtful.
Participation by foreign players, particularly strategic investors, has been low eventhough PPP projects in many of the sectors are allowed to have 100% FDI. FDI
accounted for only 11% (~US$300-400 mn) of the total investment in the Indian
projects studied by Public-Private Infrastructure Advisory Facility (PPIAF) over
1995-2007. The port sector had the largest share (51%) of this foreign investment,
followed by airports (32%) and roads (16%). Only nine projects were reported to
have strategic investor participation totalling a mere US$167 mn: four in ports,
three in airports, and one each in water supply and railways.
Figure 7 FDI flow in sectors like power is already declining
Source: DIPP, Noble research
2822
51
89
7
44
70 74
2
21
87
78
47
39
24
14
57
9
-
10
20
30
40
50
60
7080
90
100
2005-06 2006-07 2007-08 2008
(Apr-Oct)
Rsbn
Telecommuni
cations
Construction
Real estate
Power
Oil & gas
Figure 6 ECB availability has been
declining since the beginning of 2008
Source: Bloomberg, Noble research
Domestic companies and developers are
reluctant to part with equity at current
valuations
0
500
1,000
1,500
2,000
2,500
3,000
ECB/FCCB moving
average last 12months (US$ mn)
8/8/2019 Noble Indian Infrastructure Preview 2009-02-13
6/12
Indian infrastructure
Page 6 of 12
Clear thinking from
3. Lack of planning and policies deters private capitalPrivate investment in infrastructure is not only being held back due to inadequate
funding but also due to a shortage of well-conceptualised projects.
Lot of projects lack in project evaluation methodology
In India, Centre and states suffer from a lack of project preparation capacity. As per
the Comptroller and Auditor General (CAG) of India more than two-thirds of the
National Highways Development Project (NHDP) Phase I projects were delayed
because of preparation of faulty detailed project reports (DPRs). As India
transitions from procuring and bidding out a large portfolio of PPPs, to managing
and overseeing this portfolio and spreading the program to other sectors, it needs
a robust evaluation mechanism. Industry sources point out that during the last 2-3
years even ill-conceived projects with improper sharing of risk also received private
investments and bank funding (example: Noida Toll Bridge, which went through
restructuring in its early days of operations). CAGs report also points to lack of
evaluations: it states that if the National Highways Authority (NHAI) had fixed toll
rates and concession periods on the basis of sound evaluation, the concession
period of the Jaipur-Kishangarh and Delhi-Gurgaon projects could have been
restricted to 12 and 14 years, respectively (as opposed to the actual 18 years and 20
years, respectively, for which those concessions have been granted).
International experience also suggests that poor or incomplete project evaluations
were the primary reason that many PPP projects around the world in the 1990s
were halted due to stakeholder disputes. A 2002 study found that, on average, in
nine out of ten transport infrastructure projects (generally among the most
expensive PPP projects), costs are underestimated, in some sectors such as rail, by
much as 45% on average.
IMPLICATIONS FOR INVESTORS
Given that the policy and the process shortfalls highlighted in the previous sections
are not going to disappear in the short-medium term and given that private
capitals risk appetite will not return to FY07/FY08 levels for some time to come,
we prefer EPC companies to developer companies. Given the lack of private
capital, we expect governments (central and state) to increase outlay on
infrastructure activities as announced in the recent stimulus package. This should
result in the continuing business for EPC players.
We prefer EPC companies over developers
Our research indicates that about 50% of the overall infrastructure expenditure in
the Xth plan will be the construction component i.e about Rs10 tn (US$200 bn)
over FY07-12. In the current scenario, where inadequate project planning may keep
economic risks high and flexibility low in concession agreements, we prefer EPC
companies over developers. Where developers face uncertainties with regards tohigher interest rates and the changing economic scenario, EPC companies cash
contracts are relatively insulated (barring the rising working capital costs and
barring a complete standstill in the construction activity). We further expect EPC
players to benefit from additional government spending in Indian infrastructure.
Limited pure EPC players... developer role creating incentive problems
Though we prefer EPC companies in the current scenario compared to the
developers, we highlight that most of the EPC companies have become part
developers creating efficiency problems and incentive compatibility challenges.
GMRs woes in DIAL is a model case ofimproper evaluation wherein GMR has
sought support from government early
on for traffic and revenue shortfall and
inability to raise funds by trumpeting the
possibilities of halting of work due to
running out of financial resources. The
recent levy of Airport Development Fee
(ADF) has also come after Indian Law
Ministry had rejected the same in
December 2008 citing agreements
signed in 2006
During the last 2-3 years even ill-
conceived projects received private
investments and bank funding
We prefer EPC player over developers;
within the sector we prefer power and
roads to airports
Table 6 Near-term coverage
Company Comment
IVRCL EPC/developer
GVK Power & Infrastructure Developer
IRB Infrastructure Developer
Nagarjuna Construction EPC/developer
Punj Lloyd EPC
Source: Noble research
8/8/2019 Noble Indian Infrastructure Preview 2009-02-13
7/12
Indian infrastructure
Page 7 of 12
Clear thinking from
Table 7 EPC players increasingly assuming developer role
Companies Toll-roads Captive power Real estate Airports Ports
HCC Gammon IVRCL Patel Engineering Simplex
Nagarjuna Construction Lanco Infratech Source: Company data, Noble research
Many construction firms have formed project companies to bid on big projects,
because they cannot afford the opportunity cost of missing out on the construction
contracts that are embedded in them. Companies have been increasingly willing to
bet their balance sheets on concessions or greenfield construction projects that
ostensibly tie them to a bankable revenue stream (from tolls, tariffs or government
transfers). This enables them to raise project financing (or did when the going was
good). However, this creates a risk for construction companies in so far as they can
get stuck in low margin businesses as in the case of Gammon. That being said,
academic research suggests that EPC companies have good reason to become
developers.
Sirtaine, Pinglo, Guasch and Fosters (2005) find that for Latin American
developers the IRR is below the weighted average cost of capital (WACC) (see
figure 8). However, after making standard accounting adjustments (for example, to
add to the utilities the high rates of management fees and transfers to subsidiaries
through purchases) mainly for the EPC companies assuming a developer role, the
rate of return surpasses the costs of capital.
Be that as it may, within the EPC sub-sector, we prefer EPC companies with: (a)
large proportion of cash contracts in their order books, (b) minimal equity
investment needs in infra SPVs/subsidiaries, and (c) low leverage. Firms that meet
these criteria are IVRCL, Punj Lloyd and Simplex Infrastructure.
Over the next 2 months we will initiate coverage on the following EPC firms:
- Punj Lloyd (PUNJ.IN, market cap US$590 mn) is a pure Engineering &Construction (E&C) major catering to the hydrocarbons and civil construction
sectors across India, Asia and the Middle East. The recent acquisition of
Sembawang has helped it scale up its expertise in large scale urban
infrastructure in Asia and Africa.
- IVRCL (IVRC.IN, market cap US$327 mn) is the leading water-segmentengineering procurement, construction and commissioning (EPCC) player with
minimal developer (one road and Chennai water desalination project) role.
IVRCL through its subsidiary IVR Prime has exposure to real estate
development.
- Simplex Infrastructure (SINF.IN, US$152 mn) is a pure EPC company withbusiness experience spanning across industrial, infrastructure and residential
projects in India and the Middle East. The company has recently forayed intoonshore oil drilling.
Amongst developers, we prefer power and roads to airports
Within the infrastructure developer segment, we prefer developer companies with
projects with economic profiles which are the least dependent on external assets
such as the attached real estate. We believe airport assets to be the riskiest as
these projects are heavily dependent on the adjoining real estate (examples: Delhi
(GMR) and Mumbai (GVK)). Developers owning operating toll-roads (eg: GVK,
IRB) should be preferred to Greenfield toll-road developers with toll-roads under
development (eg: Nagarjuna, Madhucon and HCC). Within utilities, although new
generation capacities may find financial closure difficult, regulation assures returns
with comparably lower risk profile for new generation companies; however, some
level of merchant power capacity can improve the economic profile of powergeneration projects.
Figure 8 EPC companies can improve
IRRs through captive contracts (Latin
American data)
Source: Sirtaine, Pinglo, Guasch and Foster2005 (Latin America: 34 concessions)
0%
2%
4%
6%
8%
10%
12%
14%
16%
18%
20%
Transport Water Telecom Energy
WACC Adjusted IRR Unadjusted IRR
8/8/2019 Noble Indian Infrastructure Preview 2009-02-13
8/12
Indian infrastructure
Page 8 of 12
Clear thinking from
Table 8 Risks and rewards of infrastructure segments
Asset segment Risk Avg cash yield(yrs 1-5)*
Averageleveraged IRR**
Capitalappreciation
potential
Toll roads (operating) Low 4-8% 8-12% Limited
Regulated assets Low-med 6-10% 10-15% Limited
Rail Medium 8-12% 14-18% Yes
Airports/ seaports Medium 5-10% 15-18% YesToll roads (development) Med-high 3-5% 12-20% Yes
Note: * Cash distribution to equity holders as a percentage of equity investment** Assumes debt of50% to 85% and investment periods of not less than five to seven years
Source: Larry W. Beeferman, Noble research
Over the next two months we will initiate coverage on the following developers:
- GVK Power and Infrastructure (GVKP.IN, market cap US$610 mn) is one of theleading infrastructure developers in India with a portfolio of assets spanning
power, roads, SEZ and airport (Mumbai International airport).
- IRB Infrastructure (IRB.IN, market cap US$786 mn) is Indias leading toll-roadoperator on a build-operate-transfer (BOT) basis with 11 operational roads, one
under construction and two at financial closure stage.
Developers face multiple risks
While actual economic growth in recent years has exceeded the expectations of
some of the project feasibility studies, none anticipated the current economic
slowdown. As a result, developers project cash flows and asset values are highly
susceptible to construction delays, the current economic slowdown and interest
rate risk (the latter due to the frequent interest reset periods of the loans). Though
infrastructure assets are long-term in nature and their intrinsic value should not be
significantly affected by short-term movements in the changing economic
landscape, many assets in India do not have any operating track record and may
face risks not factored during aggressive bidding for these assets in 2006-07.
We expect developer companies to face serious challenges as most of the
infrastructure developers projections for cash flows from projects did not involve
stress testing. For projects with full market exposure, and aggressive debt
amortisation, a sudden economic downturn could push debt service coverage
levels dangerously near the loans covenant, requiring a restructuring of project
debt. Rating agencies such as Fitch expect a large amount of loan restructuring to
take place over the next few years, as a wave of projects exit the construction
phase and enter operations.
Good examples of projects beset by these challenges are the Noida Toll Bridge
and the Delhi International Airport (DIAL) being developed by GMR Infrastructure.
Back-ended revenue profile coupled with high interest rates not only led torestructuring of Noida Toll Bridges but also for extension of the concession
period.
Early into its operations DIAL has witnessed traffic declines and debt hasbecome scarce. This has lead to repeated requests for levy of additional fees
for making the revenue shortfall. Waning interest in the adjoining real estate
has also impacted the funding for the airport.
Interest reset periods for outstanding project loans are aggressive, occurring every
two to three years, and in some cases, even annually. Most projects have reset
periods that coincide with projects entering their operating phase. While project
concession agreements contain annual tariff adjustment clauses that are usually
tied to inflation, this natural hedge is not perfect. Moreover, regulatory hurdles such
as the new Model Concession Agreement (MCA) capping overall project returns by
linking traffic growth with the concession period can be a dampener for investment
returns for developers.
While actual economic growth in recent
years has exceeded the expectations of
some of the project feasibility studies,
none anticipated the current economic
slowdown
Cash flows for most of the projects were
built as annuities and did not involve
stress testing
8/8/2019 Noble Indian Infrastructure Preview 2009-02-13
9/12
Indian infrastructure
Page 9 of 12
Clear thinking from
THE WAY FORWARD FOR INDIAN INFRASTRUCTURE
In order to improve debt and long-term funding availability and concurrently
increase private participation in the infrastructure sector, the GoI needs to push for
structural changes in the financial system, increase participation of financial
investors and follow a life-cycle approach to planning infrastructure projects.
1. Development of long-term bond marketsThe creation of a deep and robust debt capital market can increase the flow of
long-term funds and reduce reliance on banks. The Indian corporate bond market,
though one of the largest in Asia, is still at an early stage of development, and its
growth is hampered by institutional, legal, and regulatory constraints that make
bonds a more expensive way of financing debt. The domestic bond market
continues to be dominated by public borrowingNational Thermal Power
Corporation (NTPC), NHAI and Power Finance Corporation (PFC)and does not
address the needs of the corporate market.
Moreover, to increase the efficiency of the private placement market for debt, the
GoI needs to reduce the regulatory asymmetry between loans and bonds. The
regulations relating to investments in bonds are far more restrictive compared to
granting of loans(i) Banks cannot invest in unrated debt instruments but can
invest in unrated loans, and (ii) Banks grant loans with no mark-to-market
implications, but their bond investments are subject to mark-to-market regulations.
2. Increased investment by pension/insurance fundsThe projected growth of pension funds and life insurance assets and their natural
synergy with infrastructure can support long-term infra financing with tenors of 10-
20 years. The Insurance Regulatory and Development Authoritys (IRDA) recent
move to increase the exposure limit of insurance companies to a single
infrastructure company to 20% from the present ceiling of 10% is a step in the right
direction.
Table 10 More room for insurance sectors exposure to infrastructure
Investment in infrastructure andsocial sectors (Rs bn)
Investment in infrastructure andsocial sectors as a proportion to
total investment by insurancecompanies (%)
Life insurers
2006-07 698 13.0
2005-06 496 12.5
2004-05 455 12.4
Non-life insurers
2006-07 61 12.1
2005-06 50 12.7
2004-05 44 12.6
Source: IRDA, Noble research
However, we believe there is more to be done as IRDAs current guidelines call for
project ratings of not less than AA for debt securities. Generally, infrastructure
projects that depend on, say, toll collections or airport traffic get a BBB rating.
Therefore, important road or national highway projects may not be able to get
investment from the insurance sector unless regulations are amended.
3. Dominance of certain developers can make matters worseGovernment regulations and policies are restrictive for bidding of projects in roads,
ports and airports. Clauses in the Request for Quotation (RFQ) allow a fixed
number of tenders to enter the final phase of price bids. This has not affected roads
only but also airports and ports. Another bottleneck is assigning marks on the
basis of experience at the pre-qualification stage, which automatically disqualifies
new companies wanting to enter the infrastructure development space. Industry
sources say that these clauses should apply to larger projects rather than the
smaller ones. Since Dec-07, as many as 60 tenders under NHDP III have been on
hold because of restrictive clauses.
Table 9 Public borrowings dominate
domestic debt securities in India
(%)Public Private
FIsCorporate
entities
All issuers 49 40 12
Argentina 72 9 19
Brazil 78 21 1
PRC 56 42 2
India 96 3 1
Mexico 82 3 15
South Korea 48 21 31
Thailand 34 42 23
Source: BIS (2006), Noble research
Same set of developers that do other
EPC jobs for govt/non-govt could limit
the overall execution capabilities in the
country
8/8/2019 Noble Indian Infrastructure Preview 2009-02-13
10/12
Indian infrastructure
Page 10 of 12
Clear thinking from
4. Life-cycle approach towards projectsWe believe in order to attract increasing private investments the government
should follow a full life-cycle approach (e.g., a clear framework) for partnerships
that confers adequate attention to all phases of a PPPfrom policy and planning, to
the transaction phase, and then to managing the concession. Such an approach can
help avoid problems of poor setup, lack of clarity about outcomes, inadequate
internal capacity, lack of interest from the private sector, and an overly narrow
focus on the transaction.
Figure 9 Life-cycle approach to project planning increases bankable projects
Source: ADB
Government budget
Int. Long-term Fund Providers
Project Revenue
Commercial Banks
Infrastructure Funds
Capital Markets
Bankable projects
Increasing pool
of funds
Easing Financing
ConstraintsDeveloping long-termbond marketsEncouraging pensionand mutualfunds, insurancecompaniesand financialinstitutions to invest in
infrastructureDedicated long-termfinancing institutionsRating of projects
8/8/2019 Noble Indian Infrastructure Preview 2009-02-13
11/12
Indian infrastructure
Page 11 of 12
Clear thinking from
CONTACT DETAILS
Saurabh Mukherjea, Head of Indian Equitiest. +91 22 4211 0901 e: [email protected]
SALES
Pramod Gubbi t +91 22 4211 0902; e: [email protected]
Sarojini Ramachandran t: +44 20 7763 2329 e: [email protected]
LEAD ANALYSTS BY SECTOR
Banks and Financial Services:
Aditi Thapliyal t +9122 4211 0904; [email protected]
Consumer:
Jaibir Singh Sethi t +91 22 4211 0905; [email protected]
Infrastructure:
Nitin Bhasin t +91 22 4211 0909; [email protected]
Power:
Bhargav Buddhadev t 91 22 4211 0910; [email protected]
Technology:
Ankur Rudra t +91 22 4211 0906; [email protected]
Economy and Country Research:
Dipankar Mitra t +91 22 4211 0920; [email protected]
701 Powai Plaza 120 Old Broad StreetHiranandani Gardens LondonMumbai 400076 EC2N 1AR
t: +91 22 4211 0999 t: +44 020 7763 2200f: +91 22 25701154 f: +44 020 7763 2397
8/8/2019 Noble Indian Infrastructure Preview 2009-02-13
12/12
Indian infrastructure
Clear thinking from
Disclaimer - Important Information
This report has been issued by Clear Capital Limited which is part of Noble, the UK investment banking group. Clear Capital
Limited is authorised and regulated by the Financial Services Authority.
Noble is committed to producing research of the highest quality and integrity, to protecting its analysts autonomy, maintainingthe culture of impartiality following its acquisition of Clear Capital and providing transparent disclosure of any potential
conflicts. However, for the purpose of UK regulation, Noble produces non-independent research which is deemed to be a
marketing communication under the FSA Conduct of Business rules and is not prepared in accordance with the legal
requirements to promote independence of investment research. It is also not subject to the prohibition on dealing ahead of the
dissemination of investment research. Noble has rigorous procedures in place to manage any conflicts in research and limits
dealing ahead, which are explained in more detail on our website http://www.noblegp.com/regulatory
The contents are based upon sources of information believed to be reliable but no warranty or representation, expressed or
implied, is given as to their accuracy or completeness. Any opinion reflects Nobles judgement at the date of publication and
neither Noble nor its directors or employees accepts any responsibility in respect of the information or recommendations
contained herein which, moreover, are subject to change without notice. This is neither an offer, nor a solicitation, to buy or sell
any investment referred to in this document. The material is general information intended for recipients who understand the
risks associated with investment. It does not take account of whether an investment, course of action, or associated risks are
suitable for the recipient.
Noble may provide services (including corporate finance advice) where the flow of information is restricted by a Chinese Wall.
Accordingly, information may be available to Noble that is not reflected in this document.
This document is intended to be used by market professionals (eligible counterparties and professional clients but not retail
clients). Retail clients must not rely on this document and should note that Nobles advisory services are not available to them.
The document must not be copied or re-distributed to another person / organisation without Nobles prior written consent.
This document is approved for communication by Noble to market professionals who have registered with Noble to receive
such information.
Clear Capital Limited is registered in England & Wales No.4637166. Registered office: 120 Old Broad Street, London EC2N 1AR.
Tel +44 (0)20 7763 2200