+ All Categories
Home > Documents > Nodal Program Update

Nodal Program Update

Date post: 15-Mar-2016
Category:
Upload: drake-garner
View: 48 times
Download: 0 times
Share this document with a friend
Description:
Nodal Program Update. Jason Iacobucci Nodal Program Manager Technical Advisory Committee 6 May 2010. Agenda. Program Status Issue Escalation Policy LFC Overview Cut-Over Overview Market Readiness Follow-Up Discussion. 180 Days to Go-Live. Phase 5: Full Functionality - PowerPoint PPT Presentation
50
Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 6 May 2010
Transcript
Page 1: Nodal Program Update

Nodal Program Update

Jason IacobucciNodal Program Manager

Technical Advisory Committee6 May 2010

Page 2: Nodal Program Update

2 Technical Advisory Committee3 June 2010

Agenda

• Program Status

• Issue Escalation Policy

• LFC Overview

• Cut-Over Overview

• Market Readiness

• Follow-Up Discussion

Page 3: Nodal Program Update

3

180 Days to Go-Live

Technical Advisory Committee3 June 2010

Phase 5: Full Functionality0 Items Impacting Go-Live Date

263 Possible QSEs

81 QSEs with Resources

182 QSEs without

Resources

78 Qualified

3 Non-Qualified

176 Qualified

6 Non-Qualified

Day Ahead Market

Real Time Market

99.9 % of System Generation

.1% of System Generation

97% of all QSEs have qualified

6 Non-Qualified4 New (30 day grace period)1 Working with ERCOT Scurry County Wind LP1 Unresponsive UBS AG London Branch

3 Non-Qualified1 New (30 day grace period)2 Working with ERCOT Invenergy Turkey Track (SQ5) Xtend Energy LLP

Page 4: Nodal Program Update

4

180 Days to Go-Live

Achievements within Market Trials: • CRR

• Four monthly CRR auctions and one Balance of the Year auction have been completed and invoiced• Real Time Markets

• SCED• Real Time settlements

• DAM / RUC• DRUC has been running in conjunction with DAM for 5 weeks• DAM Settlements are being completed in conjunction with the DAM• Settlement and extraction data has been available since Mid-May• Continual strong participation from the Market Participants (Averaged 180 QSEs / DAM run)• DAM / RUC 5 times per wk

• Ancillary Services• SASM

– Will run as needed with Ancillary Services • Closed Loop LFC

• 2 hour test will occurred last month

• Credit• Credit Module went into effect on May 14th

Technical Advisory Committee3 June 2010

Market Trials has been running for 16 weeks Market Quality Testing and Operational Readiness

Page 5: Nodal Program Update

5

180 Days to Go-Live

Technical Advisory Committee3 June 2010

Market Trials has been running for 16 weeks Market Quality Testing and Operational Readiness

Upcoming Milestones for Market Trials:

• Closed Loop LFC

• 8 hour will occur in mid June

• Reporting support for DAM/RUC/SASM continues to be upgraded

• CMM Module for NPRR 206

• 168 HR Test

• System Cut-Over

• Go-Live

Page 6: Nodal Program Update

6

Integrated Nodal Timeline – Go-Live December 1st, 2010

Technical Advisory Committee3 June 2010

Page 7: Nodal Program Update

7

2010 Market Trials Timeline – Go-Live December 1st, 2010

Technical Advisory Committee3 June 2010

Page 8: Nodal Program Update

8

180 Days to Go-Live

Technical Advisory Committee3 June 2010

DAM Summary

Page 9: Nodal Program Update

9

Test Activities CRRRTM DAMOSEMS COMSNMMS CMM REG REPORTS

Functional Stability

System Stability

Business Stability

Go-Live

Functional Completeness

Solution/ Data Completeness

Solution/ Data Quality

FA/SA TEST

INTEGRATION TEST

BUSINESS PROCESS TEST

PERFORMANCE & LOAD TEST

Model Load /Validation Processes

MARKET TEST

UI Performance

Improvements

Contingencies

ICCP Quality

SE Quality

DRUC

DAM

DAMRTM

CRR INVOICES

HRUCSASM

SCED

Model Baseline

ICCP Point Checkout

Technical Advisory Committee3 June 2010

Business Quality

Integration

1 Day Dual Entry

Testing May Auction

Integrated Credit

Management

Integration

Phase 5:Full Functionality

Phase 4: DAM/RUC

Phase 5:Full Functionality

RARF

SEM MT 2.1

MT 3.0MT 4.0 MT 5.0

Page 10: Nodal Program Update

10

Nodal Defects Trends - High Priority (Must Fix Before Go-Live)

Technical Advisory Committee3 June 2010

• Defect counts decreased due to planned defect migrations into Nodal ITest. •Primary source for Open defect counts are EIP, EMS, MMS, and NMMS.

Page 11: Nodal Program Update

11

Nodal Program Risks & Issues

Technical Advisory Committee3 June 2010

Risk/Issue Impacted Milestone

Target Category Probability Severity Status

Market Interaction Operating Level Agreements (OLAs)

Need to determine operating level agreements associated with market interactions to assist ERCOT in establishing operational thresholds:

-Network Model Management

-CRR sizing

-Reporting

Program April/May 2010

Scope / Budget

High Low • Phase 4 OLA definitions complete

• Phase 5 OLA definitions drafted, pending approval

• Update given at NATF on 06/01

• 200,000 submissions total; NATF to discuss on 06/01

• Reports continue to become available as Market Trials activities ramp-up. Performance monitoring continues

Market Design AssessmentRisk around the protocol traceability project and the market results as each phase of market trials becomes active.

Program August2010

Scope / Budget

Low High • Building experienced market design team to review and assess design and protocol alignment with market trials results

Operational ReadinessOperational readiness of the Nodal systems and business processes are an increasing risk at this point in the program

Program September2010

Scope / Schedule/

Budget

Med High • Organizational capability assessments and improvement recommendations are under review by executive management

• The PMO has and will continue to identify critical deficiencies and implement mitigation strategies to ensure delivery

Page 12: Nodal Program Update

12

Issue Escalation Policy For Market Participants

• ERCOT Nodal personnel are pulling back from non-Go-Live interaction within subcommittees and task forces

• Avenues for Question Resolution and Issue Escalation– Question Resolution

• Current Market Trials Calls• Email to [email protected]

– Issue Escalation• Issue brought up at Subcommittee, Working Group, or Task Force

– Discussed without ERCOT involvement• Issue is brought before NATF for overall market discussion and ERCOT

opinion– NATF follows up on issue– NATF brings issue forward before TAC

• Voting Items are brought before TAC

Technical Advisory Committee3 June 2010

Page 13: Nodal Program Update

13

Reminder of Nodal Offer Caps and Prices

Technical Advisory Committee3 June 2010

•Prices higher than the $2,250 offer cap were observed in the Real-Time Market in the past month- Per PUCT rule and Protocols (4.4.11), there are offer caps from resources, but not price caps- Also described in protocols are shift factors and power balance penalties that can result in prices

above offer caps • On May 5, from 3-6pm there was a scenario that created prices up to $3,759:

-  Transmission constraints were active in nodal  - Group of resources were lost in a data loading process resulted in under-generation

•   Resulted in a simulated under-generation situation with active constraints   • As designed, the Real-Time market invoked penalty factors for both:

-  Under-generation (power-balance) penalty of $3,001 -  Constraints/congestion added on top based on shift factor times penalty factor

•    345 kV: $4,500/MW•   138 kV: $3,500/MW•    69 kV: $2,800/MW

-  Penalty values for market trials set in Congestion Management Working group with ERCOT, Market, and IMM - Price spikes may be only local and may not dramatically increase Load Zone price that Load is settled on - Final penalty factors to be set through ERCOT and stakeholder process and brought to TAC/Board of Directors prior to go-live.

• Even with NPRR091 of $180 or 18 heat rate x GasIndex, prices can be as high as $3,000

Page 14: Nodal Program Update

Scott MiddletonMarket Trials

LFC Test Overview

Page 15: Nodal Program Update

15 Technical Advisory Committee

2-Hour LFC Test Update

2-Hour LFC Test Update

Test Activities Approx Timeline

Market WebEx start 8:00 AM

ERCOT - MP pre-test troubleshooting period 8:00 AM - 11:15 AM

Test start 11:15 AM

Zonal-Nodal cutover 11:15 AM - 11:55 AM

System frequency controlled by nodal systems 11:55 AM - 12:25 PM

Nodal-Zonal cutover 12:25 PM - 1:00 PM

Test end 1:00 PM

Market WebEx end 1:15 PM

3 June 2010

Page 16: Nodal Program Update

16 Technical Advisory Committee

2-Hour LFC Test Update

2-Hour LFC Test Update (continued)

Constraints (activated in both Nodal and Zonal) Start Time

Garrott - Midtown OC3 Loss of Greens Bayou  - Gable and Hardy - Crocket 138KV overloads Midtown - Garrott 138KV - 102% of 317 MVA rating.

10:45 AM

Bellaire Autotransformer OC3 Loss of Bellaire 345/138KV autotransformer 2 overloads Bellaire 345/138KV autotransformer 4 - 101% of 600 MVA rating.

11:45 AM

3 June 2010

Page 17: Nodal Program Update

17 Technical Advisory Committee

2-Hour LFC Test Update

2-Hour LFC Test Update (continued)

Common ICCP Issues Identified/Solved During the Test   On/Off status incorrect for LBST/RBST points   Resource Status Codes (RSTs) coming in as SUSPECT   OFF RST being sent for units that were online and generating MW RST of ON instead of ONREG being sent for units with REG Responsibilities RST of ONREG being sent for units in hours where they had no REG

Responsibility Non-zero LSLs being sent for WGRs   HSLs for WGRS being set to capacity rather than un-curtailed MW output MPs updating REG Responsibilities slowly  

RegUp & RegDown Responsibilities switched for one another

 

AS Responsibilities not lining up between Nodal and Zonal (i.e., wrong AS Type or wrong MW value)

3 June 2010

Page 18: Nodal Program Update

Lisa HooverCut-Over Lead

Cut-Over Kick-Off Overview

Page 19: Nodal Program Update

19http://nodal.ercot.com 19

Page 20: Nodal Program Update

20

• How Time Frame Was Defined– First triggering event necessary to support Cut-Over; includes both business and

technical aspectso Pre Go-Live Activities currently ~120 days out (August)o Post Go-Live Activities related to Nodal currently ~180 days after go-live (June 2011)

• Scope of Cut-Over for ERCOT– Cut-Over Planning Activities– Training on System and Business Processes– Security and Compliance– Data Preparation, Migration and Reconciliation– Contingency / Fall-Back Plans– Organization and Support Structure– Communication

Technical Advisory Committee

Cut Over ScopeNodal Market Readiness

3 June 2010

Page 21: Nodal Program Update

21 Technical Advisory Committee

Timeline DevelopmentNodal Market Readiness

• How We Worked Through the Development Process:- Started with Timeline of Business Applications with Earliest Go-Live Dates- Looked at Predecessors and Successors Applications- Incorporated Mid-Stream Dependency Applications- Captured Outstanding Questions

o Developed List of Decisions, Proposed Assumptions and Implications

• Example of Artifacts Taken into Account:- Texas Nodal Market Go-Live Procedure- Texas Nodal Market 168-Hour Test Procedure- Market Trials Real-Time Market Testing Market Participant Handbook

3 June 2010

Page 22: Nodal Program Update

22 Technical Advisory Committee

Key Cut-Over ActivitiesNodal Market Readiness

October NovemberSeptember2010 December

3 June 2010

Key Cut-Over Activities

Page 23: Nodal Program Update

23 Technical Advisory Committee

Cut-Over TimelineNodal Market Readiness

3 June 2010

Page 24: Nodal Program Update

24 Technical Advisory Committee

Market Participant Role and Responsibilities and ResponsibilitiesNodal Market Readiness

A Glance at Market Participant Roles and Responsibilities

Network Model

Nodal Protocol Section 3.10 goes into effect (Sept. 1)• TAC Approval – July 1st • Board Approval – July 20th

• Market Notice – July 30th

September 1st Deadline to Submit Changes for the December Network Model

October 15th Market Validation of the December Network Model

December 1st December Network Model in Effect*

* load date tbd

3 June 2010

Page 25: Nodal Program Update

25 Technical Advisory Committee

Market Participant Role and ResponsibilitiesNodal Market Readiness

A Glance at Market Participant Roles and Responsibilities

Outage Scheduler

Nodal Protocol Section 3.1 goes into effect (Sept. 1)• TAC Approval – July 1st • Board Approval – July 20th

• Market Notice – July 30th

September 1st Market Participants to Enter Production Outages for December and Beyond

September 15th Market Participants Having Outages Occurring in December and Beyond Should Be Synchronized Between Zonal and Nodal

September 15th ERCOT to Begin Approving/Rejecting Outages in Production using Both Zonal and Nodal Systems

3 June 2010

Page 26: Nodal Program Update

26 Technical Advisory Committee

Market Participant Role and ResponsibilitiesNodal Market Readiness

A Glance at Market Participant Roles and ResponsibilitiesCredit, CRR and Settlements

Nodal Protocol Section 7 goes into effect (Oct. 13)• TAC Approval – August 5th • Board Approval – August 17th • Market Notice – September 13th

October 2nd ERCOT to Pull Network Model and Outage Data

October 12th – 20th ERCOT to Determine Creditworthiness

October 13th ERCOT to Begin Accepting PCRR Nominations for the December 2010 Monthly CRR Auction

October 20th ERCOT to allocate PCRRs for NOIEs for the December 2010 Monthly CRR AuctionNetwork Model for the December 2010 Monthly CRR Auction Posted

October 20th Model Posted for December 2010 Monthly CRR per Nodal Protocol 3.10.1

October 21st ERCOT to Post ACLs

October 24th ERCOT to Post the December 2010 Monthly CRR Auction Notice

November 3rd ACLs Posted via MIS

3 June 2010

Page 27: Nodal Program Update

27 Technical Advisory Committee

Market Participant Role and Responsibilities Nodal Market Readiness

A Glance at Market Participant Roles and Responsibilities

Credit, CRR and Settlements (continued)

November 4th – 10th Start of the Bid/Offer Submission Window for December 2010 Monthly CRR Auction

November 7th CRR Locks Credit

November 9th Can Post Additional Collateral for December 2010 Monthly Auction

November 11th Run the December 2010 Monthly CRR Auction

November 16th Publication of the December 2010 Monthly CRR Auction Results

November 17th Publication of the December 2010 Monthly CRR Invoice

November 22nd Payment Due for December 2010 Monthly CRR Auction

November 23rd ERCOT to Pay CRR Account Holders Owed from December 2010 Monthly CRR Auction

3 June 2010

Page 28: Nodal Program Update

28 Technical Advisory Committee

Market Participant Role and Responsibilities and ResponsibilitiesNodal Market Readiness

A Glance at Market Participant Roles and Responsibilities

Markets, Operations and Remaining Protocol Sections

November 23rd

Nodal Protocol Sections 3, 4, 5 and 6 go into effect as well as all other unimplemented Protocol Sections (Nov. 23)

•TAC Approval – October 7th • Board Approval – October 19th • Market Notice – October 23rd

November 23rd Market Submission Opens (7 Day Operational Window)

November 30th

ERCOT Grid Operations to Switch to Nodal Control and Execute a Binding DA Market--

o 10:00 Run DAM for Dec.1o 14:00 Initiate LFC Control of Systemo 14:30 Run DRUCo 18:00 Adjustment Period for Dec. 1, and run HRUC hourlyo 24:00 Settle Market on Nodal Real-Time Prices and Dispatch

3 June 2010

Page 29: Nodal Program Update

29

• Assess Your Readiness

• Continue to Actively Engage in Market Trials

• Cut-Over 60-Day Outlook Updates Through Board of Directors, NATF, and TAC

• ERCOT to Communicate Network Model Transition Plan (June)

• Update on Cut-Over to be released on a market call or seminar (July)• Additional Cut-Over Details

Technical Advisory Committee

Next StepsNodal Market Readiness

3 June 2010

Page 30: Nodal Program Update

30

• Update on Cut-Over and Retirement to be released on a market call or seminar (September)

• End Dates of Parallel Support• Decommissioning of Systems

• Market Launch Plan (September)

• Update on Cut-Over and Contingency Plans to be released on a market call or seminar (October)

• What Do We Do If xyz fails? • How Long Would It Take To Fail Back to Zonal if We Had to?

• Be Aware of Nodal Protocol Dates and Actions Requested

Technical Advisory Committee

Next StepsNodal Market Readiness

3 June 2010

Next Steps

Page 31: Nodal Program Update

Vikki GatesReadiness & Transformation

Market Readiness

Page 32: Nodal Program Update

32

2010

Participant Readiness Touch Points

Technical Advisory Committee3 June 2010

Meetings

Training

Outreach

Market trials

AugustJulyJuneMay

• NATF 5/4

• Nodal 101• Transmission 101• Generation 101, 201• CRR – instructor-led• NMMS• Economics of LMP• NOIE QSE Operations

• Standby site visits• Metrics monitoring• Bi-weekly TSP calls• MRS #4 Cutover

• Weekly Trials calls• 2 hr system-wide LFC

test• Phase 5 Market Trials

initiates

• NATF 6/1 and 6/29

• Nodal 101• LSE 201• Generation 101, 201• Economics of LMP• CC Workshop• VC Workshop• AS Workshop• Retail Workshop• TSP Outage

Scheduler Road Show begins

• Phase 5 Metrics launch

• Weekly Trials calls• 8 hr system-wide LFC

test• Full market trials

functionality continues

• TBD

• Qualification assessment (MP17)

• Standby site visits

• Weekly Trials calls• 48 hr system-wide

LFC test• Verifiable costs in

execution• NPRR206 in

execution

• Nodal 101• Transmission 101• Generation 101, 201• Basic Training

Program• NOIE QSE Operations• Settlements 301

• Weekly Trials calls• Prepare for 168 hr

test

• NATF 8/3 and 8/31

• Nodal 101• Transmission 101• Generation 101, 201• Basic Training

Program• NOIE QSE Operations• Settlements 301

• Standby site visits

Page 33: Nodal Program Update

33

Next 60-days of Workshops

Technical Advisory Committee3 June 2010

Course Start Date LocationTransmission 101 June 1 ERCOT Met Center (Austin)

Combined Cycle Workshop June 2 Suez Energy (Houston)

Verifiable Cost Workshop June 3 Suez Energy (Houston)

Generation 101 June 8 LCRA (Austin)

Market Settlements 301 June 9 Suez Energy (Houston)

Generation 201 June 17 LCRA (Austin)

Basic Training Program June 21 ERCOT Met Center (Austin)

Credit Workshop June 17 ERCOT Met Center (Austin)

Load Serving Entity 201 June 23 Austin Energy Town Lake Center (Austin)

Credit Workshop June 17 ERCOT Met Center (Austin)

ERCOT 101 for Wind Generation June 28 ERCOT Met Center (Austin)

Transmission 101 June 29 Energy Plaza (Dallas)

Transmission 101 July 13 CenterPoint Energy (Houston)

Enrollment at: http://nodal.ercot.com/training/courses/index.html

Page 34: Nodal Program Update

34 Technical Advisory Committee

Metrics Roadmap PURPLE

ORANGE

Timing and Design Confirmed

Timing subject to change, design in progress

MP15A

MP16

MP20

MP3

MP6

MP11

MP14CE9

E1

N2EMO9(B)

CRR3

EMO6

MO4 MO5

CO1

CO2

CO3

CO4

CO5

CO6 CO7

CO8 CO9

C10

E7

E11

E12

EMO2

EMO3

C1-C10

EMO13

MO7

CRR4

E5

IMM1

R0

R2

R3

MP15B

MP3

N1

E3

E10

R1

MP17

EMO9(D)

EMO1

MO9

MO8 MO3

MO10

EMO10 EMO9(C) EMO7EMO9(A)

EMO8

New Metric

MP23

3 June 2010

Page 35: Nodal Program Update

35

CRR Metrics

Technical Advisory Committee

Metric Name Current Score

Applies to Weight Green % Yellow % Red % Not

Scored % Primary Criteria Notes

Market Participant MetricsMP15(B) CRR Connectivity Qualification

Green CRRAHs Even weighting 91.4% 0.0% 4.3% 4.3% Successful submission

CRR transactions64/70 CRRAHs

qualified.

CRR3 Operation of CRR Auctions and

AllocationsGreen CRRAHs Even

weighting 93.8% 0% 0% 6.2%

Participation in at least one of the last two

auctions or allocations. AMBER/RED scores

light up 5/5/2010.

60/64 CRRAHs with adequate participation in May or Balance of Year

auction or allocation

ERCOT Metrics

CRR3 Operation of CRR Auctions and

Allocations

Amber ERCOT N/A N/A N/A N/A N/A

Auction results distributed to

participants per schedule in CRR

Handbook

5/2 “2010 Balance of year auction results” moved to 5/5 due to Nexant resources

onsite.

5/6/2010 ERCOT N/A N/A N/A N/A N/A

Allocated Revenue Rights in statistical

sample = 100% accurate

Results of Source/Sink prices / CRR Clearing

prices report (avail 5/6)

CO8 Verify CRR Auction Invoices

Green ERCOT N/A N/A N/A N/A N/ACRR Auction Result for MP(n) – CRR Auction

Invoices for MP(n) = 0$

S&B validated that auction invoices

reflected awards per CRRAH for March, April,

and May auctions, .

Green ERCOT N/A 100% 0% 0% 0%System Generated

CRR Auction Invoices not posted = 0

March 2010 Monthly = 40 of 40April 2010 Monthly = 38 of 38May 2010 Monthly = 48 of 48

Active Phase 3 Metric

Notes:1. Added CRR3 participation threshold (market segment) - >= 80% participation (GREEN), >= 50% and < 80% (AMBER), < 50% (RED)

3 June 2010

Page 36: Nodal Program Update

36

Real-Time Metrics

Technical Advisory Committee

Metric Name Current Score

Applies to Weight Green % Yellow % Red % Not

Scored % Primary Criteria Notes

Market Participant Metrics

MP3 Market Submissions Connectivity Qualification

Green QSERs Generation Ratio Share 99.0% 1.0% 0.0% 0.0%

Successful submission of RT and DAM

transactions

81/84 QSERS Qualified (includes QSEs with Load Resources).

Green QSEs Even weighting 96.7% .06% .05% 2.2%

176/182 QSEs qualified. Below 95% threshold for

overall GREEN.

MP15-A Real-time Market Participation Green QSERs Generation

Ratio Share 99.0% 1.0% 0.0% 0.0%Weekly average of

daily SCED submissions

77/79 QSERs above 95% weekly average for

SCED submissions.

EMO6 Individual LFC Testing Green QSERs Generation

Ratio Share 91% 0% 0% 9%

80% of system-wide generation has

completed individual QSE tests for LFC

56/76 QSERs completed their individual LFC test

ERCOT Metrics

MO4 Verify SCED Execution Quality Green ERCOT N/A 100% 0% 0% 0%

All successful SCED executions passed the post-execution price

validations.

4/6-4/19 period - 4,030 Price Validation runs with no rule violations

MO5 Generate 6 Months of LMPs Green ERCOT N/A 98.1%. 0% 1.9% 0%

95% of SCED executions completed with LMPs posted on

MIS.

4/6-4/19 period, 3,985 out of 4,063 SCED runs

with LMPs posted.

Active Phase 3 and 4 Metrics

Notes:1. ERCOT Criteria added to MP3 and MP15(B) – “ERCOT scores in connectivity will mirror the MP scores.”

3 June 2010

Page 37: Nodal Program Update

37

Day-Ahead Market Metrics

Technical Advisory Committee

Metric Name Current Score

Applies to Weight Green % Yellow % Red % Not

Scored % Primary Criteria Notes

Market Participant Metrics

MP16 DAM Participation

Green QSERs Generation Ratio Share 98.9% 0.0% 1.1% 0%

Participation in 50% of the Day-Ahead Market

runs

76/79 Rolling Average QSEs with Resources,

70/79 Regular

Amber QSEs Even Weighting 79.1% 6.0% 12.1% 2.8% 144/182 Rolling Average

QSEs w/o Resources

ERCOT Metrics

MO8 Verify DAM Execution Quality 5/19/2010 ERCOT N/A N/A N/A N/A Red

DAM executions pass the post-execution price validations

Report in progress

MO9 Generate DAM LMPs 5/19/2010 ERCOT N/A N/A N/A N/A N/A

95 percent Day-Ahead Market execution as evidenced by Day-

Ahead LMP postings

Report in progress

MO10 DRUC Execution 6/2/2010 ERCOT N/A N/A N/A N/A N/A 95 percent DRUC

execution Report in progress

Notes:1.MP16 – 10 DAM runs (as of the 5/4/2010 run)2.MP16 – Metric is based on a 2 week rolling average. 3.MP16 – 96.5% Load participating.

3 June 2010

Page 38: Nodal Program Update

38

Outage Scheduler Metrics

Technical Advisory Committee

Metric Name Current Score

Applies to Weight Green % Yellow % Red % Not Scored % Primary Criteria Notes

Market Participant Metrics

MP20 Outage Scheduler

Connectivity Qualification

Green QSERs Generation Ratio Share 98.1% 0.0% 0.0% 1.9%

Successful submission of OS

transactions

74/78 QSERS qualified.

Green TSPs Ownership Ratio Share 99.8% 0% 0% .02% 23/25 TSPs qualified.

ERCOT Metrics

EMO3 Verify Outage Evaluation System

Functionality6/2/2010 ERCOT N/A N/A N/A N/A N/A

A test of the Outage

Management Process is completed

Will be reviewed at 6/1 NATF

Active Phase 3 Metric

3 June 2010

Page 39: Nodal Program Update

39

Network Modeling Metrics

Technical Advisory Committee

Metric Name Current Score

Applies to Weight Green % Yellow % Red % Not

Scored % Primary Criteria Notes

Market Participant Metrics

MP14-C TSP Model Validation Green TSPs Ownership

Ratio Share 99.9% .1% 0.0% 0.0% Network Model data validated by TSP

24/28 TSPs have submitted model

validation e-mail to ERCOT.

MP6 Telemetry Compliance with Nodal

Protocols 3.10.7.5

Green QSERs Generation Ratio Share 100% 0.0% 0.0% 0.0%

Expected State Estimator telemetry

submitted.

78/78 complete. 3502 total SE points provided

Green QSERs Generation Ratio Share 100% 0.0% 0.0% 0.0% Expected SCED

telemetry submitted.78/78 complete. 7629 SCED points provided

Green TSPs Ownership Ratio Share 99.3% 0.0% 0.0% .7%

Expected TSP telemetry per ICCP

Handbook submitted

16/17 TSPs above 95% threshold for GREEN. 357 points outstanding

N2 Telemetry ICCP System Failover

Green/White only QSERs Generation

Ratio Share 11.8% 0% 0% 88.2%

ICCP Failover test completed successfully prior to the 8-hour LFC 

test.

18/78 QSERs completed ICCP telemetry failover

test

MP18 Mapping of Resources and Loads

in Private Use Networks

6/2/2010 QSERs Generation Ratio Share N/A N/A N/A N/A

# of QSE(n) PUN Points Provided / # of QSE(n) PUN Points

Expected

306 points across 7 QSEs with Resources. 15 points still assigned

to TDSP.

MP23 Telemetry Quality (MP to ICCP

server)

7/14/2010 TSPsOwnership Ratio Share N/A N/A N/A N/A

# of TSP(n) Suspect/Bad points

provided / # of TSP(n) points total

1356 Suspect/Bad points (97.9% good

quality).

7/14/2010 QSERs Generation Ratio Share N/A N/A N/A N/A

# of QSER(n) Suspect/Bad points

provides / # of QSER(n) points total

871 Suspect/Bad points (94.9% good quality)

Active 4 Metric

Notes:1.MP6 does not include 405 QSE CB and DSC points from TSP outreach. ERCOT is determining whether these rollback into the QSER MP6 measurement

3 June 2010

Page 40: Nodal Program Update

40

Network Model Metrics

Technical Advisory Committee

Network Modeling Metrics

Metric Name0 Current Score

Applies to Weight Green % Yellow % Red % Not

Scored % Primary Criteria Notes

ERCOT MetricsEMO9(A) State

Estimator Standards Performance

5/19/2010 ERCOT N/A N/A N/A N/A N/AState Estimator

converges 97% during monthly test period

March 91.4% convergence

EMO9(B) RTCA Modeling Differences 5/19/2010 ERCOT N/A N/A N/A N/A N/A

95% of values matched between Zonal and

Nodal Network Models- Impedances

- Dynamically and Non-dynamically Rated

Lines- Load Tap Settings

Measurement excludes pseudo switches and

multi-section lines

EMO9(C) RTCA CSC Comparison 7/14/2010 ERCOT N/A N/A N/A N/A N/A

CSC Pre-contingency SE Flows within 5% (Hourly snapshot)

Measurement establishes baseline flows on Commercial lines to indicate the

significance of Psuedo modeling and multi-

section lines on the SE flows.

EMO9(D) Validate Zonal and Nodal Security Analysis

Results

9/8/2010 ERCOT N/A N/A N/A N/A N/A

90% of active constraints in Zonal

RTCA are also detected in Nodal

RTCA

To be determined

EMO10 Anomalous / Auto-Disabled

Telemetered Points6/2/2010 ERCOT N/A N/A N/A N/A N/A

The % of Anomalous and Auto-Disabled

Measurements is less than 2% of Total Measurements

April Nodal 2.58%March Nodal 3.17%Zonal hovers ~ 1.7%

Notes:1. SE performance requirements in EMO12 moved to EMO9(A)

3 June 2010

Page 41: Nodal Program Update

41

Resource Entity Metrics

Technical Advisory Committee

Metric Name Current Score Applies to Weight Green % Yellow % Red % Not Scored % Primary Criteria Notes

Market Participant Metrics

MP11 Resource Registration Green REs

Registered MW

Capacity Ratio Share

97.7% 1.82% .5% 0.0%

Decision Making Authority form submitted, and

GENMAP validated

151/157 Resources completed.

3 June 2010

Page 42: Nodal Program Update

42

Readiness Metrics

Technical Advisory Committee

Metric Name Current Score Applies to

Percentage (if applicable) Primary Criteria Notes

ERCOT Metrics

E1 ERCOT Staff Completes Training Green ERCOT 100% Training plans must be adhered to for

highly impacted departments15 out of 15 highly impacted departments

are up to date with their training plans.

E9 Develop Nodal Procedures Green ERCOT 100%

Procedures developed 1 month prior an exercised in the appropriate Market

Trials Phase

All MT4 and MT5 are now developed and the MT3 procedures were exercised during

MT3 as scheduled.  MT4 procedures on target to be exercised by the end of MT4.

3 June 2010

Page 43: Nodal Program Update

43

Questions ?

Page 44: Nodal Program Update

44

Appendix

Page 45: Nodal Program Update

45

Nodal Program Risks & Issues: Definitions

3 June 2010 Technical Advisory Committee

Definitions for Category, Probability and Severity of Risks & Issues:

• Category– Scope : Will require a scope change– Schedule: Will require a schedule change– Budget: Will require a budget change

• Probability– High : Probability to occur is ≥ 90%; perceived impact would require a Change

Request over the next 1-3 months– Medium: Probability to occur is between 31 – 89%; perceived impact would

require a Change Request over the next 4 -10 months– Low: Probability to occur is ≤ 30 %; not expected to require a Change Request

• Severity – High: Milestone impact, or budget impact >$250,000 – Medium: Milestone impact - but expected to be mitigated, or budget impact

between $0 - $250,000 – Low: No milestone impact, or no budget impact

Page 46: Nodal Program Update

463 June 2010

04/24/23

120 Day OutlookWhat’s On The Horizon?

Technical Advisory Committee

Page 47: Nodal Program Update

47

120 Day Outlook : May Market Activities

Functional Area Real-Time Market

Congestion Revenue Rights

Day-Ahead Market

Reliability Unit Commitment

Outage Scheduler

COMS/Settlements

Network Modeling

Nodal Reports

Credit

Full Integration

Targeted Activities for May 2010• ERCOT ramps to DAM / DRUC 5x /

weekly• 2hr LFC closed loop test executed• ERCOT completes Balance of Year

auction• ERCOT executes June Monthly CRR

Auction• ERCOT releases credit integration• SASM executed as needed• ERCOT executes limited HRUC• ERCOT ramps to reflect protocol

timelines on a best effort basis

Jan Feb Mar Apr May June July Aug

Technical Advisory Committee3 June 2010

Page 48: Nodal Program Update

48

120 Day Outlook : June Market Activities

Functional Area Real-Time Market

Congestion Revenue Rights

Day-Ahead Market

Reliability Unit Commitment

Outage Scheduler

COMS/Settlements

Network Modeling

Nodal Reports

Credit

Full Integration

Targeted Activities for June 2010• Operational scenarios executed• 8hr LFC closed loop test executed• ERCOT executes July Monthly CRR

Auction• DAM / DRUC Continues 5x / weekly• SASM executed as needed• ERCOT executes limited HRUC• Protocol timelines on a best effort basis

Jan Feb Mar Apr May June July Aug

Technical Advisory Committee3 June 2010

Page 49: Nodal Program Update

49

120 Day Outlook : July Market Activities

Functional Area Real-Time Market

Congestion Revenue Rights

Day-Ahead Market

Reliability Unit Commitment

Outage Scheduler

COMS/Settlements

Network Modeling

Nodal Reports

Credit

Full Integration

Targeted Activities for July 2010• Exercise ‘Normal State’ processes

and procedures, including weekends• 48hr LFC closed loop test executed• DAM / DRUC executes 7x / weekly for

two weeks• ERCOT executes HRUC 7x24 during 7

day weeks• Protocol timelines during 7 day

weeks• ERCOT executes August Monthly CRR

Auction• SASM executed as needed

Jan Feb Mar Apr May June July Aug

3 June 2010 Technical Advisory Committee

Page 50: Nodal Program Update

50

120 Day Outlook : August Market Activities

Functional Area Real-Time Market

Congestion Revenue Rights

Day-Ahead Market

Reliability Unit Commitment

Outage Scheduler

COMS/Settlements

Network Modeling

Nodal Reports

Credit

Full Integration

Targeted Activities for August 2010• August is reserved for focusing on

any issues or scenarios encountered in the first 3 months of Phase 5

• Real time submission continue• ERCOT executes August Monthly CRR

Auction• SASM executed as needed

Jan Feb Mar Apr May June July Aug

Technical Advisory Committee3 June 2010


Recommended