+ All Categories
Home > Documents > Non-Store Closure Renovation

Non-Store Closure Renovation

Date post: 25-Feb-2016
Category:
Upload: vera
View: 30 times
Download: 0 times
Share this document with a friend
Description:
Non-Store Closure Renovation. Pre Construction Due Diligence. Meet with town to discuss expectations and pre-schedule inspections. Have Permits in hand Meet with landlord to discuss dumpster & storage locations and to see if they have any site specific regulations - PowerPoint PPT Presentation
Popular Tags:
23
NON-STORE CLOSURE RENOVATION
Transcript
Page 1: Non-Store Closure Renovation

NON-STORE CLOSURE RENOVATION

Page 2: Non-Store Closure Renovation

Pre Construction Due Diligence Meet with town to discuss expectations and

pre-schedule inspections. Have Permits in hand

Meet with landlord to discuss dumpster & storage locations and to see if they have any site specific regulations This is especially important in mall locations

Complete the detailed construction schedule Cross reference the Material Schedules on plan

to the FFE Plan to the Items Ordered Sheet to look for discrepancies

Conduct pre-construction meeting with the SM, DM, CM and GC to alleviate apprehensions and go over expectations

Page 3: Non-Store Closure Renovation

Freehold, NJ Before & After

Page 4: Non-Store Closure Renovation

Typical Closing Schedule Day 1; Monday; 12:00 noon until 5:00 am (16 hours) Day 2; Tuesday; 12:00 noon until 5:00 am (16 hours) Day 3; Wednesday; 12:00 noon until 5:00 am (16 hours) Day 4; Thursday; 12:00 noon until 5:00 am (16 hours)

Not needed if floor is not being done Day 5; Friday; 6:00 pm close until 5:00 am (11 hours) Days 6 & 7; No work over the weekend (OPTIONAL) Day 8; Monday; 6:00 pm close until 5:00 am (11 hours) Day 9; Tuesday; 8:00 pm until 5:00 am (9 hours) Day 10; Wednesday; 8:00 pm until 5:00 am (9 hours) Thursday; Store is back to normal hours

Page 5: Non-Store Closure Renovation

Monday Day 1- Backline

Demo of back line/int. walls Rework electric & plumbing Build new walls/rock 1 side Blocking/install wall cubbies Set backline cabinets & counters

Re-set equipment Power and plumbing hook ups Clean and re-set store for a normal morning opening

Page 6: Non-Store Closure Renovation

Tuesday Day 2 - Frontline

Demo frontline, save pastry case Saw cutting for floor sink relo Re-work electric and plumbing Set new bar, POS, & pastry case Re-set all equipment Power and plumbing hook ups Seam Corian counters at the BL

Demo floor tiles to be replaced Scarify floor of thinset Prep for back splash wall tile Begin wall prep for paint Demo and set panels at 1st R. R. Clean and re-set this store for a normal morning opening

Page 7: Non-Store Closure Renovation

Wednesday Day 3 – Lighting/Ceiling

Rough framing inspection Re-locate/add wood soffit panels Install new ceiling lighting Finish first R.R. install Fixtures Install Banquette seating Continue wall prep

Demo existing chair rail Replace all damaged ceiling tiles Install R.R. accessories Clean and re-set store for a normal morning opening

Page 8: Non-Store Closure Renovation

Thursday Day 4 - Flooring

Install floor tile, base and grout Install backsplash tile and grout Continue wall prep Demo and set panels at 2nd R. R. Install under counter lights at cubbies Install FRP at the wet cabinets

Final ceiling prep for Friday paint Prep and install wall cladding at the accent wall Install custom wood trim at hallway door Clean and re-set this store for a normal morning opening

Page 9: Non-Store Closure Renovation

Friday Day 5 – Ceiling Paint Protection for ceiling paint Install BOH Eliason door Finish 2nd R.R. install fixtures Install R.R. accessories

Finish and sand all spackle Clean and re-set this store for a normal morning opening

Page 10: Non-Store Closure Renovation

Sat/Sun DAY 6 &7 No Work Over The Weekend

Page 11: Non-Store Closure Renovation

Monday Day 8 Install free-standing merchandise bays Build and set new condiment cart Begin wall paint, paint R.R. Install chair rail

Install new walk-off mat Install FRP & re-set BOH as per plan Install vinyl wainscoting Clean and re-set this store for a normal morning opening

Page 12: Non-Store Closure Renovation

Tuesday Day 9

Finish all wall painting Install custom shelving unit Install artwork/mural trim Install metal corner guards

Install mural Install artwork Silicone throughout Clean and re-set this store for a normal morning opening

Page 13: Non-Store Closure Renovation

Wednesday Day 10

Final electrical inspection Final plumbing inspection Build and set furniture General punch list Professional cleaning service

window cleaning mechanical floor

cleaning high dusting general cleaning

After today, the store is back to normal hours Final building and health inspections are done during the day on Thursday

Page 14: Non-Store Closure Renovation

Florham Park, NJ Store Expansion

BEFORE AFTER

OBJECTIVES: add Clover, claimed 500 square feet of unused square footage which increased customer seating from (18) to (32) seats, open-space feel with updated palette.

Page 15: Non-Store Closure Renovation

Before and After Floor Plans

Page 16: Non-Store Closure Renovation

Phasing Plan

Page 17: Non-Store Closure Renovation

Mercer Mall Ten Year Reno with a Restroom Relocation &

BOH Expansion, BEFORE AFTER

OBJECTIVES; enlarge BOH and Managers area, get the full size refrigerator into the back of house, open up space, while increasing seating from (11) to (20) seats , we also replaced floor tile (tile over tile).

Page 18: Non-Store Closure Renovation

Before & After Floor Plans

Page 19: Non-Store Closure Renovation

Phasing Plan

Page 20: Non-Store Closure Renovation

Glen Rock, NJ Reno Using The Temporary Trailer

KEEPING THE CUSTOMER HAPPY WHILE INSIDE….

Page 21: Non-Store Closure Renovation

Setting Trailer Utility Hookups General Guide Lines

Trailer must fit the location Get prior approval from the town Safe & separate egress for customers and workers Plan on minimum 4 days to set trailer with inspections (NJ) Prior arrangements for ice delivery and bulk milk storage Prior coordination of data runs for POS and brewing equipment Temporary dry storage will be required We were able to open store and then remove trailer in one day

Page 22: Non-Store Closure Renovation

This store was completed in 11 days working thru the weekend, turn over on Friday. We installed new floor tiles and did a full bar reversal. There were only a few hours of interrupted business.

Click icon to add picture

Page 23: Non-Store Closure Renovation

QUESTIONS


Recommended