NON-STORE CLOSURE RENOVATION
Pre Construction Due Diligence Meet with town to discuss expectations and
pre-schedule inspections. Have Permits in hand
Meet with landlord to discuss dumpster & storage locations and to see if they have any site specific regulations This is especially important in mall locations
Complete the detailed construction schedule Cross reference the Material Schedules on plan
to the FFE Plan to the Items Ordered Sheet to look for discrepancies
Conduct pre-construction meeting with the SM, DM, CM and GC to alleviate apprehensions and go over expectations
Freehold, NJ Before & After
Typical Closing Schedule Day 1; Monday; 12:00 noon until 5:00 am (16 hours) Day 2; Tuesday; 12:00 noon until 5:00 am (16 hours) Day 3; Wednesday; 12:00 noon until 5:00 am (16 hours) Day 4; Thursday; 12:00 noon until 5:00 am (16 hours)
Not needed if floor is not being done Day 5; Friday; 6:00 pm close until 5:00 am (11 hours) Days 6 & 7; No work over the weekend (OPTIONAL) Day 8; Monday; 6:00 pm close until 5:00 am (11 hours) Day 9; Tuesday; 8:00 pm until 5:00 am (9 hours) Day 10; Wednesday; 8:00 pm until 5:00 am (9 hours) Thursday; Store is back to normal hours
Monday Day 1- Backline
Demo of back line/int. walls Rework electric & plumbing Build new walls/rock 1 side Blocking/install wall cubbies Set backline cabinets & counters
Re-set equipment Power and plumbing hook ups Clean and re-set store for a normal morning opening
Tuesday Day 2 - Frontline
Demo frontline, save pastry case Saw cutting for floor sink relo Re-work electric and plumbing Set new bar, POS, & pastry case Re-set all equipment Power and plumbing hook ups Seam Corian counters at the BL
Demo floor tiles to be replaced Scarify floor of thinset Prep for back splash wall tile Begin wall prep for paint Demo and set panels at 1st R. R. Clean and re-set this store for a normal morning opening
Wednesday Day 3 – Lighting/Ceiling
Rough framing inspection Re-locate/add wood soffit panels Install new ceiling lighting Finish first R.R. install Fixtures Install Banquette seating Continue wall prep
Demo existing chair rail Replace all damaged ceiling tiles Install R.R. accessories Clean and re-set store for a normal morning opening
Thursday Day 4 - Flooring
Install floor tile, base and grout Install backsplash tile and grout Continue wall prep Demo and set panels at 2nd R. R. Install under counter lights at cubbies Install FRP at the wet cabinets
Final ceiling prep for Friday paint Prep and install wall cladding at the accent wall Install custom wood trim at hallway door Clean and re-set this store for a normal morning opening
Friday Day 5 – Ceiling Paint Protection for ceiling paint Install BOH Eliason door Finish 2nd R.R. install fixtures Install R.R. accessories
Finish and sand all spackle Clean and re-set this store for a normal morning opening
Sat/Sun DAY 6 &7 No Work Over The Weekend
Monday Day 8 Install free-standing merchandise bays Build and set new condiment cart Begin wall paint, paint R.R. Install chair rail
Install new walk-off mat Install FRP & re-set BOH as per plan Install vinyl wainscoting Clean and re-set this store for a normal morning opening
Tuesday Day 9
Finish all wall painting Install custom shelving unit Install artwork/mural trim Install metal corner guards
Install mural Install artwork Silicone throughout Clean and re-set this store for a normal morning opening
Wednesday Day 10
Final electrical inspection Final plumbing inspection Build and set furniture General punch list Professional cleaning service
window cleaning mechanical floor
cleaning high dusting general cleaning
After today, the store is back to normal hours Final building and health inspections are done during the day on Thursday
Florham Park, NJ Store Expansion
BEFORE AFTER
OBJECTIVES: add Clover, claimed 500 square feet of unused square footage which increased customer seating from (18) to (32) seats, open-space feel with updated palette.
Before and After Floor Plans
Phasing Plan
Mercer Mall Ten Year Reno with a Restroom Relocation &
BOH Expansion, BEFORE AFTER
OBJECTIVES; enlarge BOH and Managers area, get the full size refrigerator into the back of house, open up space, while increasing seating from (11) to (20) seats , we also replaced floor tile (tile over tile).
Before & After Floor Plans
Phasing Plan
Glen Rock, NJ Reno Using The Temporary Trailer
KEEPING THE CUSTOMER HAPPY WHILE INSIDE….
Setting Trailer Utility Hookups General Guide Lines
Trailer must fit the location Get prior approval from the town Safe & separate egress for customers and workers Plan on minimum 4 days to set trailer with inspections (NJ) Prior arrangements for ice delivery and bulk milk storage Prior coordination of data runs for POS and brewing equipment Temporary dry storage will be required We were able to open store and then remove trailer in one day
This store was completed in 11 days working thru the weekend, turn over on Friday. We installed new floor tiles and did a full bar reversal. There were only a few hours of interrupted business.
Click icon to add picture
QUESTIONS