    Northgate Station Area Update

    Sound Transit Board Briefing

    May 24, 2012

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    2/28

    Todays Briefing

    Report on good progress made on Northgate issues

    Discuss context of Northgate today and vision for Northgateas Urban Center in the future

    Northgate Station Integrated Access Plan Northgate Executive Steering Committee reached consensus

    on several issues

    Next steps ST Board action on North Link Project baselining in June

    North Link groundbreaking in August

    2

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    3/28

    North Link Timeline

    2003 -2006

    April2006

    Oct.2010

    July2011

    Nov.2011

    June2012

    Aug.2012 2021

    PE

    FSEIS

    Complete

    Boardapprovesfinal route& stations

    North Linkfinal design

    begins

    NorthgateStation15%

    design

    NorthgateStation30%

    design

    BaselineNorth LinkProject

    North Link

    constructionbegins

    Northgate60% design

    NorthLinkopens

    333

    3

    ST2 PassesNovember 2008

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    4/28

    Northgate Executive Steering Committee

    Committee of senior managers from KCM, City of Seattle, andST formed last year to offer guidance on Northgate issues:

    ST station design and construction issues

    KCM Transit Center redesign plans

    HUD Sustainable Communities grant activities including urbandesign study and KCM TOD plans

    Goals of Committee:

    Fully integrated inter-modal transit facilities timely implementation of TOD plans

    Maintain & achieve ridership goals during and after LRT/TODdevelopment

    4

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    5/28

    Ridership at Northgate Transit Facilities

    70%

    30%

    2012 Access Modes

    Bus/Ped/Bike

    Park&Ride

    5,000

    5

    15,000

    2030 Ridership

    5,000 daily boardings

    15,000 daily boardings

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    6/28

    Northgate Station Integrated Access Plan

    Goal: improve access to Northgate Station by all modes Integrated access modes include:

    Link light rail system

    pedestrian and bike access Metro and ST bus service

    future TOD projects

    passenger drop-off and pick-up zones park-and-ride facilities

    6

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    7/28

    Northgate StationKey features:

    Elevated station spans NE 103rd with

    escalators, elevators and stairs Accommodates landing for a future ped.

    bridge over I-5

    Two entrances for easy connections to:

    Residences/businesses Bus transfers/P&R

    Future TOD

    Bicycle parking/access

    Accommodates Citys sidewalk/bike access

    improvement plans

    7

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    8/28

    Northgate StationPerspective Looking Northeast

    8

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    9/28

    1b

    51

    Pedestrian and Bike

    Access Improvements

    City of Seattle has identified sidewalkimprovements for Northgate area

    SDOT bike improvements include cycle-track proposed along 1st Ave NE and

    sharrows on NE 100th and NE 103rd KCM completed I-5 pedestrian bridge

    feasibility study CMAQ grant request by ST/KCM/City

    includes $1.5 million for pedestrian and

    bike improvements

    9

    Sidewalk ImprovementsBike ImprovementsI-5 Pedestrian Bridge

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    10/28

    Future Northgate

    Northgate is designated Urban Center

    Citys 2024 growth targets: + 2,500 households (+ 66%)

    + 4,200 jobs (+ 40%)

    City of Seattle Northgate area planning:

    1993 Northgate Neighborhood Plan HUD Sustainable Communities

    grant funded urban design

    study for Northgate (began in

    2011)

    10

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    11/28

    Metro Northgate Objectives

    Excellent Transit Facility emphasizing Bus to Bus andBus to Train connections. Priority for walk, bike andtransit access.

    During construction: Ridership losses need to bemitigated. No loss of ridership or revenue.

    After construction: Mixed use transit orientedenvironment with affordable housing. Maximize Metrovalue including ridership.

    Integrate the local bus network with Link.

    11

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    12/28

    Future Transit Center and TOD

    12

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    13/28

    Thornton Place Development

    13

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    14/28

    TOD: Near Term

    14

    85 Height414 Units9,300 SF Retail

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    15/28

    Long Term at Northgate?

    15

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    16/28

    Metro Strategic

    Plan Policy Reinvestment

    Opportunity Begin Planning

    RestructureProcess 2019

    Metro TransitService

    Restructure2021

    16

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    17/28

    Northgate Mall

    SPG Garage280 Spaces

    Thornton Place350 Spaces

    West Parcel289 Spaces

    East Parcel

    464 Spaces

    WSDOT Lots139 Spaces

    North SeattleCommunity College

    Northgate Existing Conditions(Park-and-Ride Facilities: 1,522 stalls)

    17

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    18/28

    ST Construction Impacts on Parking(Draft 1/10/12)

    18

    428 P&R Stalls

    451 Northgate

    Mall Stalls

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    19/28

    Northgate Steering Committee Consensus

    1. Fully mitigate construction impacts on P&R parking2. Preferred mitigation approach is to build replacement garage

    between 600 to 900 stalls

    3. Preferred site for new garage is on Northgate Mall property

    near station; West Parcel site remains an option

    4. Strong support for phasing in KCM TOD sites (currently usedfor parking) following completion of garage; beginning as

    early as 2015

    19

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    20/28

    Northgate Parking Garage Preferred Site

    2020

    20

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    21/28

    Garage at Northgate Mall Project Benefits

    Shared use parking already proven successful at Northgate Help maintain ridership during construction

    Shared use parking agreement could reduce STs total costs

    Mitigates adverse impacts to businesses Avoids displacement of P&R stalls during garage construction

    Site is close to station; improves connections to the inter-

    modal facility

    21

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    22/28

    Garage at Northgate Mall Land Use Benefits

    Locates parking activities close to station and freeway

    More efficient land use than surface parking

    Accommodates KCMs future TOD plans

    West Parcel site remains unencumbered

    allows flexibility in re-design of Transit Center

    allows conversion of KCMs surface P&R lots to TOD sites

    Garage would allow future development of other Mall property

    without more parking (maintains tenant lease parking ratios)

    22

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    23/28

    Northgate Surface vs. Garage Parking

    1.1 acres

    KCM West Parcel: 3.1 acres

    Affected Parking AreasMall Garage Site: 1.1 acres

    vs.Surface area of displaced parking: 7.2 acres

    SPG Staging Area 2.8 acres

    23

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    24/28

    Northgate Future TOD Sites

    1.1 acres

    KCM West Parcel: 2.1acres

    KCM East Parcel: 3.8 acres

    KCM Future TOD SitesWest Parcel (Remainder): 2.1 acres

    East Parcel: 3.8 acresTotal: 5.9 acres

    24

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    25/28

    Northgate Park & Ride Facility Capacity

    Current

    (2012)

    During ST

    Construction

    with New

    Garage

    After Northgate

    Station Opens*

    (2021)

    Total P&R Stalls 1522 1544 1219

    * Assumes full build-out of KCMs East and West Parcel TOD Sites

    25

    SPG lease (280 stalls) renewal: 2026

    Thornton Place lease (350 stalls) ends: 2046

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    26/28

    Northgate Station Area - Future

    26

    10%

    90%

    2030 Access Modes (Daily)

    Park & Ride

    Bus/Walk/Bike

    Based on 2030 ridership forecast atNorthgate Station of 15,000 dailyboardings

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    27/28

    Northgate Station Area - Future

    2%

    43%

    7%

    18%

    30%

    2030 PM Peak Access Modes

    Bike

    Bus

    Drop-off/pick-up

    Park & Ride

    Walk

    Based on 2030 ridership forecast atNorthgate Station PM peak periodaccess data (5,400)

    27

  • 7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut

    28/28

    Northgate Next Steps

    Northgate construction update public meeting on June 4th

    Olympic View Elementary School, 6-8pm

    North Link project baselining briefing for ST Capital Committeeon June 14th

    ST Board action on North Link project baselining on June 28th

    North Link ground breaking event August 2012

    28