of 28
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
1/28
Northgate Station Area Update
Sound Transit Board Briefing
May 24, 2012
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
2/28
Todays Briefing
Report on good progress made on Northgate issues
Discuss context of Northgate today and vision for Northgateas Urban Center in the future
Northgate Station Integrated Access Plan Northgate Executive Steering Committee reached consensus
on several issues
Next steps ST Board action on North Link Project baselining in June
North Link groundbreaking in August
2
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
3/28
North Link Timeline
2003 -2006
April2006
Oct.2010
July2011
Nov.2011
June2012
Aug.2012 2021
PE
FSEIS
Complete
Boardapprovesfinal route& stations
North Linkfinal design
begins
NorthgateStation15%
design
NorthgateStation30%
design
BaselineNorth LinkProject
North Link
constructionbegins
Northgate60% design
NorthLinkopens
333
3
ST2 PassesNovember 2008
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
4/28
Northgate Executive Steering Committee
Committee of senior managers from KCM, City of Seattle, andST formed last year to offer guidance on Northgate issues:
ST station design and construction issues
KCM Transit Center redesign plans
HUD Sustainable Communities grant activities including urbandesign study and KCM TOD plans
Goals of Committee:
Fully integrated inter-modal transit facilities timely implementation of TOD plans
Maintain & achieve ridership goals during and after LRT/TODdevelopment
4
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
5/28
Ridership at Northgate Transit Facilities
70%
30%
2012 Access Modes
Bus/Ped/Bike
Park&Ride
5,000
5
15,000
2030 Ridership
5,000 daily boardings
15,000 daily boardings
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
6/28
Northgate Station Integrated Access Plan
Goal: improve access to Northgate Station by all modes Integrated access modes include:
Link light rail system
pedestrian and bike access Metro and ST bus service
future TOD projects
passenger drop-off and pick-up zones park-and-ride facilities
6
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
7/28
Northgate StationKey features:
Elevated station spans NE 103rd with
escalators, elevators and stairs Accommodates landing for a future ped.
bridge over I-5
Two entrances for easy connections to:
Residences/businesses Bus transfers/P&R
Future TOD
Bicycle parking/access
Accommodates Citys sidewalk/bike access
improvement plans
7
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
8/28
Northgate StationPerspective Looking Northeast
8
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
9/28
1b
51
Pedestrian and Bike
Access Improvements
City of Seattle has identified sidewalkimprovements for Northgate area
SDOT bike improvements include cycle-track proposed along 1st Ave NE and
sharrows on NE 100th and NE 103rd KCM completed I-5 pedestrian bridge
feasibility study CMAQ grant request by ST/KCM/City
includes $1.5 million for pedestrian and
bike improvements
9
Sidewalk ImprovementsBike ImprovementsI-5 Pedestrian Bridge
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
10/28
Future Northgate
Northgate is designated Urban Center
Citys 2024 growth targets: + 2,500 households (+ 66%)
+ 4,200 jobs (+ 40%)
City of Seattle Northgate area planning:
1993 Northgate Neighborhood Plan HUD Sustainable Communities
grant funded urban design
study for Northgate (began in
2011)
10
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
11/28
Metro Northgate Objectives
Excellent Transit Facility emphasizing Bus to Bus andBus to Train connections. Priority for walk, bike andtransit access.
During construction: Ridership losses need to bemitigated. No loss of ridership or revenue.
After construction: Mixed use transit orientedenvironment with affordable housing. Maximize Metrovalue including ridership.
Integrate the local bus network with Link.
11
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
12/28
Future Transit Center and TOD
12
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
13/28
Thornton Place Development
13
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
14/28
TOD: Near Term
14
85 Height414 Units9,300 SF Retail
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
15/28
Long Term at Northgate?
15
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
16/28
Metro Strategic
Plan Policy Reinvestment
Opportunity Begin Planning
RestructureProcess 2019
Metro TransitService
Restructure2021
16
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
17/28
Northgate Mall
SPG Garage280 Spaces
Thornton Place350 Spaces
West Parcel289 Spaces
East Parcel
464 Spaces
WSDOT Lots139 Spaces
North SeattleCommunity College
Northgate Existing Conditions(Park-and-Ride Facilities: 1,522 stalls)
17
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
18/28
ST Construction Impacts on Parking(Draft 1/10/12)
18
428 P&R Stalls
451 Northgate
Mall Stalls
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
19/28
Northgate Steering Committee Consensus
1. Fully mitigate construction impacts on P&R parking2. Preferred mitigation approach is to build replacement garage
between 600 to 900 stalls
3. Preferred site for new garage is on Northgate Mall property
near station; West Parcel site remains an option
4. Strong support for phasing in KCM TOD sites (currently usedfor parking) following completion of garage; beginning as
early as 2015
19
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
20/28
Northgate Parking Garage Preferred Site
2020
20
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
21/28
Garage at Northgate Mall Project Benefits
Shared use parking already proven successful at Northgate Help maintain ridership during construction
Shared use parking agreement could reduce STs total costs
Mitigates adverse impacts to businesses Avoids displacement of P&R stalls during garage construction
Site is close to station; improves connections to the inter-
modal facility
21
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
22/28
Garage at Northgate Mall Land Use Benefits
Locates parking activities close to station and freeway
More efficient land use than surface parking
Accommodates KCMs future TOD plans
West Parcel site remains unencumbered
allows flexibility in re-design of Transit Center
allows conversion of KCMs surface P&R lots to TOD sites
Garage would allow future development of other Mall property
without more parking (maintains tenant lease parking ratios)
22
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
23/28
Northgate Surface vs. Garage Parking
1.1 acres
KCM West Parcel: 3.1 acres
Affected Parking AreasMall Garage Site: 1.1 acres
vs.Surface area of displaced parking: 7.2 acres
SPG Staging Area 2.8 acres
23
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
24/28
Northgate Future TOD Sites
1.1 acres
KCM West Parcel: 2.1acres
KCM East Parcel: 3.8 acres
KCM Future TOD SitesWest Parcel (Remainder): 2.1 acres
East Parcel: 3.8 acresTotal: 5.9 acres
24
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
25/28
Northgate Park & Ride Facility Capacity
Current
(2012)
During ST
Construction
with New
Garage
After Northgate
Station Opens*
(2021)
Total P&R Stalls 1522 1544 1219
* Assumes full build-out of KCMs East and West Parcel TOD Sites
25
SPG lease (280 stalls) renewal: 2026
Thornton Place lease (350 stalls) ends: 2046
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
26/28
Northgate Station Area - Future
26
10%
90%
2030 Access Modes (Daily)
Park & Ride
Bus/Walk/Bike
Based on 2030 ridership forecast atNorthgate Station of 15,000 dailyboardings
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
27/28
Northgate Station Area - Future
2%
43%
7%
18%
30%
2030 PM Peak Access Modes
Bike
Bus
Drop-off/pick-up
Park & Ride
Walk
Based on 2030 ridership forecast atNorthgate Station PM peak periodaccess data (5,400)
27
7/31/2019 Northgate - Board Briefing 5-24-12 FINAL_uncut
28/28
Northgate Next Steps
Northgate construction update public meeting on June 4th
Olympic View Elementary School, 6-8pm
North Link project baselining briefing for ST Capital Committeeon June 14th
ST Board action on North Link project baselining on June 28th
North Link ground breaking event August 2012
28