1 NORTHSIDE REDEVELOPMENT GENERAL AVIATION HANGAR DEVELOPMENT PHASE II January 20 th , 2016 Public Notice Item Matt Hoffman, A.A.E. Senior Manager, Aviation Real Estate
Transcript
Page 1: NORTHSIDE REDEVELOPMENT GENERAL AVIATION ... CAC Business...January 20 th, 2016 Public Notice Item Matt Hoffman, A.A.E. Senior Manager, Aviation Real Estate 2 Overview • Airport

1

NORTHSIDE REDEVELOPMENT GENERAL AVIATION HANGAR DEVELOPMENT PHASE II

January 20th, 2016

Public Notice Item

Matt Hoffman, A.A.E.

Senior Manager, Aviation Real Estate

Page 2: NORTHSIDE REDEVELOPMENT GENERAL AVIATION ... CAC Business...January 20 th, 2016 Public Notice Item Matt Hoffman, A.A.E. Senior Manager, Aviation Real Estate 2 Overview • Airport

2

Overview

• Airport Futures identified GA as priority • Northside Redevelopment Strategy

– 2013 committee presentation/review – 2014 Phase I implementation, Terminal Balancing/Atlantic Aviation

• 2016 Phase II hangar development – Existing tenant – Adjacent to Atlantic Aviation project – Maximize use of remaining portion of Zone 2

Page 3: NORTHSIDE REDEVELOPMENT GENERAL AVIATION ... CAC Business...January 20 th, 2016 Public Notice Item Matt Hoffman, A.A.E. Senior Manager, Aviation Real Estate 2 Overview • Airport

3

Northside Vicinity Map

= Atlantic Aviation New

= New Hangar

= Atlantic Aviation Existing

Page 4: NORTHSIDE REDEVELOPMENT GENERAL AVIATION ... CAC Business...January 20 th, 2016 Public Notice Item Matt Hoffman, A.A.E. Senior Manager, Aviation Real Estate 2 Overview • Airport

4

N.E. Airport Way

ZONE 1 AIR CARRIER

RESERVE

ZONE 2 AVIATION REDEVELOPMENT

ZONE 3 EXISTING LONG TERM HOTELS

ZONE 4 AVIATION

REDEVELOPMENT

Atlantic Aviation

NEW

H

ANG

ARS

Page 5: NORTHSIDE REDEVELOPMENT GENERAL AVIATION ... CAC Business...January 20 th, 2016 Public Notice Item Matt Hoffman, A.A.E. Senior Manager, Aviation Real Estate 2 Overview • Airport

5

CONCEPTUAL RENDERING

ATLANTIC AVIATION UNDER CONSTRUCTION

Page 6: NORTHSIDE REDEVELOPMENT GENERAL AVIATION ... CAC Business...January 20 th, 2016 Public Notice Item Matt Hoffman, A.A.E. Senior Manager, Aviation Real Estate 2 Overview • Airport

6 CONCEPTUAL RENDERING

Page 7: NORTHSIDE REDEVELOPMENT GENERAL AVIATION ... CAC Business...January 20 th, 2016 Public Notice Item Matt Hoffman, A.A.E. Senior Manager, Aviation Real Estate 2 Overview • Airport

7

CONCEPTUAL RENDERING

Page 8: NORTHSIDE REDEVELOPMENT GENERAL AVIATION ... CAC Business...January 20 th, 2016 Public Notice Item Matt Hoffman, A.A.E. Senior Manager, Aviation Real Estate 2 Overview • Airport

8

Timeline

2016 2017 Commission Approval

Demolition

Site Preparation

Construction

Completion

Page 9: NORTHSIDE REDEVELOPMENT GENERAL AVIATION ... CAC Business...January 20 th, 2016 Public Notice Item Matt Hoffman, A.A.E. Senior Manager, Aviation Real Estate 2 Overview • Airport

9

Sustainability GUIDING PRINCIPLES

1. Long-term preservation of commercial air carrier facilities & assets.

2. Through financial principles of cost control, prudent capital investment, and as appropriate, alternative development, sustain & grow Airport revenue.

3. Contribute to regional economic development, provide short term construction jobs, & through growth of business aviation, long term business aviation-related jobs.

4. Ensure Airport meets aviation obligations, development is compatible with the Master Plan, & land resources are used efficiently.

Page 10: NORTHSIDE REDEVELOPMENT GENERAL AVIATION ... CAC Business...January 20 th, 2016 Public Notice Item Matt Hoffman, A.A.E. Senior Manager, Aviation Real Estate 2 Overview • Airport

10

Clarifying Questions and

Public Comment


Recommended