NOTICE OF CONSTRUCTION MCI/VERIZON FIBER CABLE INSTALLATION PROJECT BOLLINGER CANYON ROAD FROM SAN RAMON VALLEY BOULEVARD TO NORRIS CANYON ROAD Planned construction period: July to October 2019 Staff issued an Encroachment Permit to MCI/Verizon’s contractor, Golden State Utility Company (GSUC), for the installation of new fiber cable along Bollinger Canyon Road from San Ramon Valley Boulevard to Norris Canyon Road. This project is necessary to maintain the MCI/Verizon fiber cable system as well as upgrade the services for digital cable television, digital telephone, and high-speed data. Details of the permit issued are as follows: Bollinger Canyon Road from San Ramon Valley Boulevard to Norris Canyon Road o Scope of the project: potholing of existing utilities; five 4’x4’ bore pits; seven new vault installation; approximately 5,200 feet directional bore behind the curb; placement of approximately 16,000 feet of conduit for fiber installation; and approximately 5,200 feet of shadow duct per the Reimbursement Agreement for Duct Construction. o Limits of work: will start at the southeast corner of Bollinger Canyon Road and Norris Canyon Road approximately 100 feet east from Bollinger Canyon Road, and continues south along the west side on Bollinger Canyon Road to San Ramon Valley Boulevard, as shown on Exhibit B. o Project Schedule – July to October 2019 Contact Information: City of San Ramon Verizon Roy Shields – Sr. Engineering Inspector Sammy Truong – OSP Engineer Cell: (925) 570-1867 Cell: (408) 332-9480 Email: [email protected] Email: [email protected] Eric Ramos – Engineering Specialist Golden State Utility Co. Direct: (925) 973-2698 Richard Santos – Area Manager Email: [email protected] Cell: (415) 716-9351 Email: [email protected]
Transcript
Page 1: NOTICE OF CONSTRUCTION MCI/VERIZON FIBER CABLE ...

NOTICE OF CONSTRUCTION

MCI/VERIZON FIBER CABLE INSTALLATION PROJECT BOLLINGER CANYON ROAD FROM SAN RAMON VALLEY BOULEVARD

TO NORRIS CANYON ROAD

Planned construction period: July to October 2019

Staff issued an Encroachment Permit to MCI/Verizon’s contractor, Golden State Utility Company (GSUC), for the installation of new fiber cable along Bollinger Canyon Road from San Ramon Valley Boulevard to Norris Canyon Road. This project is necessary to maintain the MCI/Verizon fiber cable system as well as upgrade the services for digital cable television, digital telephone, and high-speed data. Details of the permit issued are as follows:

• Bollinger Canyon Road from San Ramon Valley Boulevard to Norris Canyon Roado Scope of the project: potholing of existing utilities; five 4’x4’ bore pits; seven

new vault installation; approximately 5,200 feet directional bore behind thecurb; placement of approximately 16,000 feet of conduit for fiber installation;and approximately 5,200 feet of shadow duct per the ReimbursementAgreement for Duct Construction.

o Limits of work: will start at the southeast corner of Bollinger Canyon Road andNorris Canyon Road approximately 100 feet east from Bollinger Canyon Road,and continues south along the west side on Bollinger Canyon Road to SanRamon Valley Boulevard, as shown on Exhibit B.

o Project Schedule – July to October 2019

Contact Information:

City of San Ramon Verizon Roy Shields – Sr. Engineering Inspector Sammy Truong – OSP Engineer Cell: (925) 570-1867 Cell: (408) 332-9480 Email: [email protected] Email: [email protected]

Eric Ramos – Engineering Specialist Golden State Utility Co. Direct: (925) 973-2698 Richard Santos – Area Manager Email: [email protected] Cell: (415) 716-9351

Email: [email protected]

Page 2: NOTICE OF CONSTRUCTION MCI/VERIZON FIBER CABLE ...

Sources: Esri, HERE, Garmin, USGS, Intermap, INCREMENT P, NRCan, Esri Japan, METI, Esri China (Hong Kong), Esri Korea, Esri (Thailand), NGCC, ©OpenStreetMap contributors, and the GIS User Community

CITY OF SAN RAMON2401 Crow Canyon Rd, San Ramon, CA 94583ENGINEERING SERVICES

MCI/Verizon Underground Fiber Conduit Installation Project

±Exhibit A

PROPOSED VAULT

CONDUITEXISTING VAULT

BORE PIT

NORRIS CANYON RD

SAN RAMON VALLEY BLVD

BOLLINGER CANYON RD


Recommended