+ All Categories
Home > Documents > Nov 2005 Kursk Project Report Mhc

Nov 2005 Kursk Project Report Mhc

Date post: 14-Apr-2018
Category:
Upload: klumerx
View: 218 times
Download: 0 times
Share this document with a friend

of 33

Transcript
  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    1/33

    Report

    Measurement of Leak Rates at Kursk Natural Gas Regulator Stations

    Kursk, Russia

    November 1 - 10, 2005

    Submitted to:

    Alexandre Okmianski

    DirectorAddGlobe LLC

    Phone: (650) 357-7735 ext. 25

    Fax: (650) 357-7342

    [email protected]

    Submitted by:

    Milton W. Heath III

    Heath Consultants Incorporated9030 Monroe Road

    Houston, TX 77061

    713-844-1304

    [email protected]

    November 22, 2005

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    2/33

    2

    1.0 Summary and Introduction

    This report describes a leak measurement program conducted in Kursk, Russia at Kursk Natural

    Gas Distribution Company regulator stations. The survey was conducted from November 1st

    through November 10th, 2005. During this program all standardized components, including

    flanges, pipe thread connectors, block valves, regulators, plug valves and pressure relief valves in

    natural gas service were surveyed for leaks. Any leaks found were tagged and measured using the

    Hi Flow Sampler. These leak rate measurements were then entered into a database, where they

    can be sorted both by the leak size and tag number, so that the leak rate of any individual leak can

    be determined and the most significant leaks targeted for cost effective repair. These average leak

    rates, known as emission factors, allow the leakage to be compared to industry averages.

    2.0 Site Description

    Table 1 details specific facility characteristics for the Kursk Regulator Stations.

    Table 1: Site Description of Kursk Leak Measurement Sites

    Site Visits Facility Type System AgeOperating

    Pressures

    47Regulator Stations

    (above ground)47 years

    0.3 MPa and 0.003

    MPa

    The Kursk natural gas distribution system has been operating since 1958 with approximately

    8000 Kilometers of pipeline in the region. Roughly 3700 kilometers of this pipeline is situated

    within the city limits of Kursk. Approximately one sixth (1/6) of this system is designed

    aboveground where low pressure gas serves the residential and business communities. The vast

    majority of the system (5/6) is belowground and travels along the roadways.

    Within Kursk, there are reported to be 138 regulator stations, which regulate the higher pressures

    (0.3 MPa) down to lower pressures (0.003 MPa) for residential service. During our eight days of

    surveying from November 1st through November 10th, we were able to survey 47 of these

    stations for leak detection and measurement.

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    3/33

    3

    3.0 Field Program Description

    During this leak survey, leak detection at the facilities was conducted using catalyticoxidation/thermal conductivity detectors (Heath Gasurveyors 6-500). The Heath Gasurveyor

    instruments were calibrated in Houston, Texas on Friday October 28 th, 2005 using both 2.5%

    methane in air and 99% methane in air. All identified leaks (those that screened above 0.5%

    methane in air) were tagged and numbered.

    Once leaks were identified, leak rate measurements were made using the Hi-Flow Sampler. The

    Hi-Flow Sampler makes leak rate measurements with the same accuracy as enclosure

    measurements but at a speed approaching that of leak detection screening instruments (Howard et

    al., 1994; Lott et al., 1995 Howard, 1995). The Hi-Flow Sampler uses a high flow rate of air to

    completely capture the gas leaking from the component. A catalytic oxidation/thermal

    conductivity sensor is used to measure the sample concentration in the air stream of the high flow

    system. The Hi-Flow Sampler essentially performs an enclosure measurement using the flow

    regime induced by the sampler instead of a physical enclosure. A description of the Hi-Flow

    Sampler and its advantages over typical screening and enclosure measurements is provided in

    Appendix I.

    The Hi Flow Sampler was calibrated in Houston, Texas on October 28th and then calibrated in

    Kursk, Russia on November 2ndand November 10th. Verification of calibration took place in theKursk Gas engineering office and field on November 3rdand November 7th.

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    4/33

    4

    4.0 Field Measurement Results

    Individual leak rates for all leaks are presented in the appendices. Leak rates sorted by leakidentification number are presented in Appendix II. Leak rates sorted by component category

    with emission factors are presented in Appendix III. Leaks sorted by leak rate are presented in

    Appendix IV. All yearly values are based on continuous leakage throughout the year. Figures 1-6

    are illustrative pictures of the work site with Hi Flow Sampling device.

    A total of 47 regulator stations were inspected between November 1st and November 10th, 2005.

    A total of 94 leaks were identified and measured amounting to a total leak rate of 918,591m3/yr.

    Table 2 provides a summary of the results from the measurement program.

    Table 2: Summary of Leak Rates at 24 Kursk Regulator Stations

    Component CategoryLeak

    Rate

    (LPM)

    Leak

    Rate

    (LPH)

    Leak Rate

    M3/Yr

    Leak Rate from Valve Stem Packings (90leaks out of 244 valves surveyed)

    1,614 96,828 848,213

    Leak Rate from Flanges (1 leak out of 727flanges surveyed)

    1.5 90 788

    Leak Rate from Pressure Relief Valve (3

    leaks out of 36 PRVs surveyed)132 7,944 69,589

    Figure 1 - Nykoli, Chief of Gas Regulator Service Department, Assisting the project.

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    5/33

    5

    Figure 2 - Verification Team from DNV and United Nations Inspects stations and reviews

    methodology.

    Figure 3 - Russian Carbon Fund, Kursk Gas, DNV, United Nations, Rosgasification and Heath

    Consultants Inc. inspecting sites.

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    6/33

    6

    Figure 4 - Max, Lead Specialist from "Center Gas Service Opt" assists with leak measurements

    along with Nykoli of Kursk Gas.

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    7/33

    7

    5.0 Repair and Measurement of Emission Reductions

    As part of this pilot program, an effort was made to repair a few of the identified leaks using

    Gore-Tex sealing materials manufactured in the USA. Once the leaks were tagged and measured,

    gas crews attempted to repair seven valve packing stem leaks. Leak rate measurements were once

    again taken at each of the seven valves where complete repairs were validated and emission

    reductions were verified. Table 3 provides a summary of the results from the emission reduction

    efforts employed. Figures 1 and 2 are pictures of the engineering technicians making the repairs

    on the valves.

    Table 3: Summary of Valve Stem Packing Repairs Conducted during Pilot Program

    Description and

    Location

    Leak Rate (LPM)

    BEFORE

    Leak Rate

    (LPM)

    AFTER

    Site 12, Leak 1 18 0

    Site 36, Leak 1 35.8 0

    Site 36, Leak 2 227.7 0Site 36, Leak 3 4.7 0

    Site 36, Leak 4 64.1 0

    Site 36, Leak 5 13.5 0

    Site 36, Leak 6 1.7 0

    Total Reductions 365.5

    Figure 5 Nykoli and Alex of Kursk Gaz repair leaking valve with new Gore-Tex sealants.

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    8/33

    8

    Figure 6

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    9/33

    9

    6.0 Emission Factors

    Emission factors are the average leakage for a particular component category. They are calculated

    by finding the total leak rate for each component category and dividing by the total number of

    components surveyed in that category. A total of 1007 components were surveyed from

    November 1st through November 10th, 2005. Out of this total, there were 244 valves screened for

    at the regulator stations, of which 90 leaks were found, equating to a leak frequency of

    approximately 36.8%. This is at the high end of the leak frequency range compared to similar

    studies at regulator stations in the United States natural gas industry. The emission factors for the

    valves and other two component categories surveyed at the Kursk regulator stations are displayed

    in Table 4 and are based on measurements prior to any repairs attempted.

    Table 4. Kursk Valve Emission Factors (Assumes Continuous Leakage)

    Kursk Regulator Stations

    Component

    Category

    Number of

    Components

    Surveyed

    Emission Factor

    (Liters Per Minute)

    Kursk Valve Emission

    Factor (m3/Component/Yr)

    Regulator Valves 244 6.61 3,476Pressure Relief

    Valves36 3.68 1,933

    Flanges 727 .002 1.08

    7.0 References

    CMA, 1989. Improving Air Quality: Guidance for Estimating Fugitive Emissions from

    Equipment. Chemical Manufacturer's Association, Washington, DC 20037.

    EPA, 2000. Seventh Annual Natural Gas STAR Implementation Workshop, October 11 13,2000. Houston, TX. US Environmental Protection Agency, Washington, DC.

    Lott, B., T. Howard, and M. Webb, 1995. New Techniques Developed for Measuring Fugitive

    Emissions. Pipe Line & Gas Industry, Vol. 78, No. 10., Oct. 1995.

    Howard, T., R. Kantamaneni, and G. Jones, 1999. Cost Effective Leak Mitigation at Natural Gas

    Transmission Compressor Stations. Report prepared for the Compressor Research Supervisory

    Committee of PRC International; Gas Research Institute; and U.S. Environmental Protection

    Agency Natural Gas Star Program. PRCI Report No. PR-246-9526.

    Kantamaneni, R., G. Jones, M. Barna, P. Cooper, and T. Howard, 1997. Trends in Leak Rates atMetering and Regulating Facilities and the Effectiveness of Leak Detection and Repair (LDAR)

    Programs. Report prepared for the Compressor Research Supervisory Committee of PRC

    International; Gas Research Institute; and U.S. Environmental Protection Agency Natural GasStar Program (510 Third Street, 5th Floor, Washington, DC 2001).

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    10/33

    10

    Appendix I

    Leak Measurement Techniques

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    11/33

    11

    A.1.1 Screening Techniques, Correlation Equations, and Bagging Measurements

    Screening techniques, correlation equations, and enclosure (bagging) measurements have long

    been the standard techniques to measure fugitive emissions from leaking process components

    such as valves, flanges, and open-ended lines. Screening techniques originally started as a leak

    detection method only. Correlations were then developed to relate the concentration measured

    using a leak detection instrument to the leak rate. These correlations compare leak rates

    measured using enclosure methods to the maximum concentrations measured either 1 cm or 1

    mm from the components using a leak detector such as organic vapor analyzer (OVA) (CMA,

    1989; Webb and Martino, 1992). Although these correlations make it easy to estimate leak rates,

    the inaccuracies are unacceptable for true leak measurements. For any given leak, the estimated

    leak rate can vary from the actual leak rate by as much as a factor of 1,000. With these

    uncertainties, it is impossible to use screening techniques to determine which leaks are large

    enough to justify repair on a cost-effective basis.

    The most serious drawback of using screening concentrations and correlation equations is their

    inability to accurately characterize leaks that are beyond the scale of typical leak detectors

    ("pegged sources"). The most common leak detector used when correlations are applied is the

    Foxboro OVA-108 (and a recent version, the TVA-1000), which uses a flame ionization detector.

    The sampling flow rate of the OVA-108 is approximately 1,000 ml/min, so if as little as 10

    ml/min of methane is captured, the resulting concentration will be 10,000 ppm (1%) which is the

    upper limit of the instrument. Wind speed, distance of the probe from the leak, and

    characteristics of the leak such as exit velocity affect how much of the leak actually is captured

    by the sample probe. These uncertainties explain the large scatter in estimating leak rates using

    screening concentrations.

    It is the pegged sources that contribute most to the facility emissions and losses. In our

    experience, 3% - 6% of the components in a natural gas transmission facility will leak and

    approximately 0.5 % will exceed the range of the leak detection instrument. One approach would

    be to repair all of the pegged source leaks, or repair a percentage of these leaks that is equal to the

    percent reduction of emissions that has been set as a goal. Unfortunately, this can be a costly and

    ineffective strategy. Because of their inaccuracy, screening measurements cannot be used to

    determine which leaks should be fixed first or what the leak reduction would result.

    Bagging measurements are accurate but are too expensive and time consuming to measure every

    leak at a facility. In this method, the leaking component is wrapped with a nonpermeable

    material (such as Tedlar or Mylar) and a clean purge gas (such as nitrogen) sweeps through the

    enclosure at a measured flow rate. Vacuum bagging may also be performed. For the case of

    methane (CH4) the leak rate from the component can be calculated from the purge flow rate

    through the enclosure and the concentration of methane in the outlet stream as follows:

    QCH4 = Fpurge x CCH4 (1)

    where:

    QCH4 = leak rate of methane from the enclosed component (cfm),

    Fpurge = the purge flow rate of the clean air or nitrogen (cfm), and

    CCH4 = the measured concentration of methane in the exit flow (percent).

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    12/33

    12

    Besides screening with a flame ionization detector, other leak detection methods are available and

    are often more economical. A soap bubble solution can provide a visual leak detection method

    for many natural gas facility components. Although not appropriate for liquid process streams,very hot components, OELs, and flanges with deep crevices, the use of soap can increase the

    speed of leak detection by a factor of two to three times that of screening with an organic vapor

    analyzer. If leak rate measurements using Indaco sampling are performed, then any effective leak

    detection method can be used to find leaks.

    A.1.2 Hi-Flow Sampling and Direct Measurements

    To overcome the shortcomings of current leak measurement methods discussed previously,

    Indaco developed a system that is able to make measurements with the same accuracy as

    enclosure measurements but at a speed approaching that of leak detection screening

    measurements. The Hi Flow Sampler uses a high flow rate of air and a modified enclosure to

    completely capture the gas leaking from the component. Catalytic oxidation and thermal

    conductivity hydrocarbon sensors are used to measure the exit concentration in the air stream of

    the system. The Hi Flow Sampler essentially makes rapid vacuum enclosure measurements so

    that emissions are calculated as follows:

    QCH4 = Fpurge x (Csample - Cback) (2)

    where:

    QCH4 = leak rate of methane from the leaking component (cfm),

    Fsampler= the sample flow rate of the sampler (cfm),

    Cmain = the concentration of methane in the sample flow (percent), and

    Cback = the concentration of methane in the background near the component (percent).

    The background concentration must be subtracted from the main sample concentration because itmay be elevated due to other leaks in the vicinity of the leak being measured. Variables such as

    wind speed and wind direction may cause the background concentration to fluctuate, so thebackground is measured simultaneously with the sample concentration.

    The Hi Flow Sampler is packaged inside a backpack, leaving the operators hands free for

    climbing ladders or descending into manholes. The instrument is controlled by a handheld LCD

    with an integral 4-key control pad, which is attached to the main unit via a 6 coiled cord. The gas

    sample is drawn into the unit via a flexible 1 I.D. hose. Various attachments connect to the

    end of the sampling hose providing the means of capturing all the gas that is leaking from the

    component under test.

    The main unit consists of an intrinsically safe, high-flow blower that pulls air from around the

    component being tested, through a flexible hose and into a manifold located inside the unit. The

    sample passes through a venturi restrictor where the measured pressure differential is used to

    calculate the samples actual flow rate. Next, a portion of the sample is drawn from the manifold

    and directed to a methane sensor that measures the samples methane concentration in the range

    of 0.05 to 100% gas by volume. A second identical methanesensor channel measures the

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    13/33

    13

    background methane level within the vicinity of the leaking component. The final element in the

    sampling system is a pump that exhausts the gas sample back into the atmosphere away from the

    sampling area.

    The measured flow rate and the measured methane levels (both leak and background levels) are

    used to calculate the leak rate of the component being tested, with all measured and calculated

    values being displayed on the hand-held control unit.

    The top flow rate of the sampler is 8 cfm. Two opposing factors influence the choice of sample

    flow rate for the system. Higher flow rates provide better leak capture especially if ambient

    winds are a factor or if the leak has significant momentum. However, higher flow rates also

    result in limits on the size of leak that can be quantified and increase the chance of interference

    from nearby leaks. For instance, at a sample flow rate of 3 cfm, a methane leak of 0.006 cfm

    would result in a concentration increase of 0.2 %. A sample flow rate of 6 cfm at the same leak

    would result in a concentration increase of only 0.1 %. When working in an area where a high

    background concentration is present, a larger net concentration increase is easier to quantify.

    A series of experiments were conducted to validate the results of the Hi Flow Sampler. A

    simulated leak was used to investigate the Hi Flow Sampler's ability to capture leaks. Laboratory

    tests were conducted by releasing methane from a compressed gas cylinder through a two-stage

    regulator and needle valve. The methane flow rate was measured using a calibrated rotameter(Cole-Parmer, Inc.) Methane flow rates were measured before and after each sampling period.

    The leak rate generator was connected to different types of components that are typically

    surveyed including a flange, valve, open ended line, and a pipe thread connector. Wind speeds of

    up to 4.5 m/s (10 mph) were generated near the leak with a fan. The results of these tests are

    shown in Table A-1. The average difference between the metered leak rate and the Hi Flow

    Sampler was 3.3% when with a maximum difference 11.1%

    Table A-1. Leak Measurement Sampler Compared to Metered Leaks (Indaco Laboratory)

    Leak Rate (l/min)Type of

    Component Rotameter Sampler

    Difference

    Rotameter - Sampler

    Difference/

    Rotameter

    Abs. Value

    Difference/

    Rotameter

    Open Ended Line 6.33 6.02 0.31 4.9% 4.9%

    Open Ended Line 61.5 61.4 0.04 0.1% 0.1%

    Open Ended Line 61.5 61.7 -0.28 -0.4% 0.4%

    Open Ended Line 101.5 104.7 -3.24 -3.2% 3.2%

    Open Ended Line 101.5 101.8 -0.31 -0.3% 0.3%

    Open Ended Line 101.5 107.9 -6.41 -6.3% 6.3%

    Open Ended Line 116.7 120.1 -3.40 -2.9% 2.9%Open Ended Line 116.7 119.8 -3.07 -2.6% 2.6%

    Open Ended Line 133.1 137.6 -4.50 -3.4% 3.4%

    Open Ended Line 144.2 151.8 -7.60 -5.3% 5.3%

    Open Ended Line 188.5 201.4 -12.94 -6.9% 6.9%

    Flange 5.14 5.18 -0.04 -0.8% 0.8%

    Flange 5.14 5.27 -0.13 -2.4% 2.4%

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    14/33

    14

    Table A.1 (Continued)

    Flange 6.28 6.14 0.14 2.3% 2.3%

    Flange 6.28 6.60 -0.32 -5.1% 5.1%

    Flange 6.28 6.66 -0.38 -6.1% 6.1%

    Flange 6.28 6.05 0.23 3.7% 3.7%

    Flange 6.28 6.05 0.23 3.7% 3.7%

    Flange 6.28 6.89 -0.61 -9.8% 9.8%

    Flange 6.28 5.97 0.31 4.9% 4.9%

    Flange 38.7 37.2 1.41 3.7% 3.7%

    Flange 56.8 59.3 -2.49 -4.4% 4.4%

    Flange 58.6 57.8 0.83 1.4% 1.4%

    Flange 63.3 66.1 -2.73 -4.3% 4.3%

    Flange 74.1 70.9 3.20 4.3% 4.3%

    Flange 80.3 78.0 2.23 2.8% 2.8%

    Flange 80.3 80.2 0.08 0.1% 0.1%

    Flange 84.9 81.7 3.29 3.9% 3.9%

    Flange 84.9 82.3 2.63 3.1% 3.1%

    Flange 85.6 82.7 2.92 3.4% 3.4%

    Flange 85.6 76.1 9.51 11.1% 11.1%

    Flange 88.4 87.0 1.43 1.6% 1.6%

    Flange 92.4 89.6 2.78 3.0% 3.0%

    Flange 100.8 96.7 4.07 4.0% 4.0%

    Flange 100.8 95.2 5.57 5.5% 5.5%

    Flange 101.1 101.1 0.03 0.0% 0.0%

    Flange 102.1 95.7 6.42 6.3% 6.3%

    Flange 112.0 106.7 5.30 4.7% 4.7%

    Valve 1.56 1.59 -0.03 -1.7% 1.7%

    Valve 1.56 1.56 0.00 0.2% 0.2%

    Valve 1.56 1.56 0.00 0.2% 0.2%

    Valve 2.54 2.49 0.05 1.8% 1.8%

    Valve 2.54 2.45 0.09 3.5% 3.5%

    Valve 3.44 3.48 -0.04 -1.2% 1.2%

    Valve 4.22 4.47 -0.25 -6.0% 6.0%

    Valve 4.22 4.47 -0.25 -6.0% 6.0%

    Valve 5.14 5.36 -0.22 -4.2% 4.2%

    Valve 5.14 5.21 -0.07 -1.4% 1.4%

    Valve 6.28 6.49 -0.21 -3.3% 3.3%

    Valve 38.7 38.7 -0.09 -0.2% 0.2%

    Valve 38.7 40.4 -1.74 -4.5% 4.5%

    Valve 58.7 57.4 1.28 2.2% 2.2%

    Valve 58.7 60.0 -1.30 -2.2% 2.2%

    Valve 78.2 76.2 2.05 2.6% 2.6%

    Valve 78.2 81.1 -2.92 -3.7% 3.7%

    Connector 1.56 1.58 -0.02 -1.4% 1.4%

    Connector 2.54 2.53 0.01 0.5% 0.5%

    Connector 2.54 2.49 0.05 1.8% 1.8%

    Connector 2.01 1.94 0.07 3.4% 3.4%

    Connector 3.44 3.32 0.12 3.4% 3.4%

    Connector 4.22 4.49 -0.27 -6.4% 6.4%

    Connector 5.14 5.30 -0.16 -3.2% 3.2%

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    15/33

    15

    Table A.1 (Continued)

    Average Percent Difference = -0.2%

    Average Percent Absolute Difference = 3.3%

    Maximum Positive Difference = 11.1%

    Maximum Negative Difference = -9.8%

    Table A-2 shows the results of a similar experiment conducted as a demonstration at an EPA

    contract laboratory using an EPA apparatus to simulate leaks from valve bodies, valve stems, and

    flanges. In this case the average difference was -4.2% with a maximum difference of 10.5%.

    Table A-2. Leak Measurement Sampler Compared to Metered Leaks (EPA Test Valve)

    Type of Component Leak RateDifference

    Rotameter - SamplerDifference/Rotameter

    Abs. Value

    Difference/Rotameter

    Rotameter Sampler

    Valve Body 8.03 8.64 -0.61 -7.6% 7.6%

    Valve Body 8.03 8.18 -0.15 -1.9% 1.9%

    Valve Stem 8.09 8.1 -0.01 -0.1% 0.1%

    Valve Stem 8.09 8.43 -0.34 -4.2% 4.2%

    Valve Stem 8.09 8.19 -0.10 -1.3% 1.3%

    Flange 8.03 8.31 -0.28 -3.5% 3.5%

    Flange 8.03 8.87 -0.84 -10.5% 10.5%

    Average Percent Difference = -4.2%

    Average Percent Absolute Difference = 4.2%

    Maximum Positive Difference = None

    Maximum Negative Difference = -10.5%

    References

    CMA, 1989. Improving Air Quality: Guidance for Estimating Fugitive Emissions fromEquipment. Chemical Manufacturer's Association, Washington, DC 20037.

    Webb, M., and P. Martino, 1992. Fugitive Hydrocarbon Emissions from Petroleum ProductionOperations. Presented at the 85th Annual Meeting of the Air and Waste ManagementAssociation, Paper No. 92-66.11.

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    16/33

    16

    Appendix II

    Kursk Regulator Station Leak Rates Sorted by Leak Identification Number

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    17/33

    Appendix II: Kursk Leak Rates Sorted by Leak Identification Number

    17

    SiteVisit

    NumberMeasurement

    Date

    LeakTag

    NumberOperatingPressure

    GenericDescription

    LitersPer

    Minute

    LitersPer

    HourLiters

    Per/Year

    TotalEmissions

    m3/year

    1 1-Nov-05 1/1 0.3 MPa Valve StemPacking

    13.3 798 6,990,480 6,990

    2 1-Nov-05 2/1 .003MPa Valve StemPacking

    49 2940 25,754,400 25,754

    2 1-Nov-05 2/2 0.3 MPa Valve StemPacking

    6.1 366 3,206,160 3,206

    2 1-Nov-05 2/3 0.3 MPa Flange 1.5 90 788,400 788

    3 1-Nov-05 3/1 .003MPa Valve StemPacking

    158.5 9510 83,307,600 83,308

    4 1-Nov-05 4/1 .003MPa Valve StemPacking

    6.6 396 3,468,960 3,469

    4 1-Nov-05 4/2 0.003MPa Valve StemPacking

    4.9 294 2,575,440 2,575

    4 1-Nov-05 4/3 0.003MPa Valve StemPacking

    1.5 90 788,400 788

    5 1-Nov-05 5/1 0.003MPa Valve StemPacking

    47.8 2868 25,123,680 25,124

    6 1-Nov-05 6/1 0.003MPa Valve StemPacking

    7 420 3,679,200 3,679

    7 1-Nov-05 7/1 0.003MPa Valve StemPacking

    2 120 1,051,200 1,051

    7 1-Nov-05 7/2 0.3MPa Valve StemPacking

    0.3 18 157,680 158

    7 1-Nov-05 7/3 0.003MPa Valve Stem

    Packing

    6.1 366 3,206,160 3,206

    7 1-Nov-05 7/4 0.3MPa Valve StemPacking

    13 780 6,832,800 6,833

    7 1-Nov-05 7/5 0.003MPa Valve StemPacking

    7.9 474 4,152,240 4,152

    7 1-Nov-05 7/6 0.003MPa Valve StemPacking

    0.2 12 105,120 105

    8 1-Nov-05 8/1 0.003MPa Valve StemPacking

    1.4 84 735,840 736

    9 1-Nov-05 9/1 0.3MPa Valve StemPacking

    20.5 1230 10,774,800 10,775

    10 1-Nov-05 10/1 0.003MPa Valve StemPacking

    35.6 2136 18,711,360 18,711

    11 1-Nov-05 11/1 0.3MPa Valve StemPacking

    21.9 1314 11,510,640 11,511

    11 1-Nov-05 11/2 0.003MPa Valve StemPacking

    3.4 204 1,787,040 1,787

    11 1-Nov-05 11/3 0.003MPa Valve StemPacking

    4.2 252 2,207,520 2,208

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    18/33

    Appendix II: Kursk Leak Rates Sorted by Leak Identification Number

    18

    SiteVisit

    NumberMeasurement

    Date

    LeakTag

    NumberOperatingPressure

    GenericDescription

    LitersPer

    Minute

    LitersPer

    HourLiters

    Per/Year

    TotalEmissions

    m3/year

    12 2-Nov-05 12/1 0.003MPa Valve StemPacking

    18 1080 9,460,800 9,461

    12 2-Nov-05 12/2 0.003MPa Valve StemPacking

    1.8 108 946,080 946

    12 2-Nov-05 12/3 0.003MPa Valve StemPacking

    4.2 252 2,207,520 2,208

    12 2-Nov-05 12/4 0.003MPa Valve StemPacking

    2.7 162 1,419,120 1,419

    13 2-Nov-05 13/1 0.003MPa Valve StemPacking

    16.7 1002 8,777,520 8,778

    13 2-Nov-05 13/2 0.003MPa Valve StemPacking

    13.1 786 6,885,360 6,885

    13 2-Nov-05 13/3 0.003MPa Valve StemPacking

    3.6 216 1,892,160 1,892

    13 2-Nov-05 13/4 0.003MPa Valve StemPacking

    6 360 3,153,600 3,154

    13 2-Nov-05 13/5 0.003MPa Valve StemPacking

    2.1 126 1,103,760 1,104

    14 2-Nov-05 14/1 0.003MPa Valve StemPacking

    20.9 1254 10,985,040 10,985

    15 2-Nov-05 15/1 0.003MPa Valve StemPacking

    20.3 1218 10,669,680 10,670

    16 2-Nov-05 16/1 0.003MPa Valve StemPacking

    16.3 978 8,567,280 8,567

    17 2-Nov-05 17/1 0.003MPa Valve Stem

    Packing

    37 2220 19,447,200 19,447

    17 2-Nov-05 17/2 0.003MPa Valve StemPacking

    2.1 126 1,103,760 1,104

    17 2-Nov-05 17/3 0.003MPa Valve StemPacking

    18 1080 9,460,800 9,461

    18 2-Nov-05 18/1 0.003MPa Valve StemPacking

    11.5 690 6,044,400 6,044

    19 2-Nov-05 19/1 0.003MPa Valve StemPacking

    72.9 4374 38,316,240 38,316

    19 2-Nov-05 19/2 0.003MPa Valve StemPacking

    4.9 294 2,575,440 2,575

    20 2-Nov-05 20/1 0.003MPa Valve StemPacking

    8.8 528 4,625,280 4,625

    20 2-Nov-05 20/2 0.003MPa Valve StemPacking

    1.3 78 683,280 683

    21 3-Nov-05 21/1 0.003MPa Valve StemPacking

    35 2100 18,396,000 18,396

    22 3-Nov-05 22/1 0.003MPa PressureRelief Valve

    11 660 5,781,600 5,782

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    19/33

    Appendix II: Kursk Leak Rates Sorted by Leak Identification Number

    19

    SiteVisit

    NumberMeasurement

    Date

    LeakTag

    NumberOperatingPressure

    GenericDescription

    LitersPer

    Minute

    LitersPer

    HourLiters

    Per/Year

    TotalEmissions

    m3/year

    23 3-Nov-05 23/1 0.003MPa Valve StemPacking

    31.2 1872 16,398,720 16,399

    24 3-Nov-05 24/1 0.3MPa Valve StemPacking

    2.7 162 1,419,120 1,419

    24 3-Nov-05 24/2 0.04MPa Valve StemPacking

    4.5 270 2,365,200 2,365

    24 3-Nov-05 24/3 0.3MPa Valve StemPacking

    3.6 216 1,892,160 1,892

    25 3-Nov-05 25/1 0.003MPa Valve StemPacking

    7.9 474 4,152,240 4,152

    25 3-Nov-05 25/2 0.003MPa Valve StemPacking

    7.5 450 3,942,000 3,942

    25 3-Nov-05 25/3 0.003MPa Valve StemPacking

    4.4 264 2,312,640 2,313

    25 3-Nov-05 25/4 0.003MPa Valve StemPacking

    14.8 888 7,778,880 7,779

    26 3-Nov-05 26/1 0.003MPa Valve StemPacking

    23.3 1398 12,246,480 12,246

    26 3-Nov-05 26/2 0.003MPa Valve StemPacking

    6.7 402 3,521,520 3,522

    26 3-Nov-05 26/3 0.003MPa Valve StemPacking

    3.5 210 1,839,600 1,840

    26 3-Nov-05 26/4 0.003MPa Valve StemPacking

    9.1 546 4,782,960 4,783

    27 3-Nov-05 27/1 0.003MPa Valve Stem

    Packing

    9.3 558 4,888,080 4,888

    27 3-Nov-05 27/2 0.3MPa Valve StemPacking

    12 720 6,307,200 6,307

    28 3-Nov-05 28/1 0.003MPa Valve StemPacking

    3 180 1,576,800 1,577

    29 3-Nov-05 29/1 0.003MPa Valve StemPacking

    21.9 1314 11,510,640 11,511

    29 3-Nov-05 29/2 0.3MPa Valve StemPacking

    9.4 564 4,940,640 4,941

    29 3-Nov-05 29/3 0.003MPa Valve StemPacking

    4.7 282 2,470,320 2,470

    30 4-Nov-05 30/1 0.003MPa Valve StemPacking

    14.6 876 7,673,760 7,674

    31 4-Nov-05 31/1 0.003MPa PressureRelief Valve

    38.1 2286 20,025,360 20,025

    31 4-Nov-05 31/2 0.003MPa Valve StemPacking

    19.4 1164 10,196,640 10,197

    31 4-Nov-05 31/3 0.3MPa Valve StemPacking

    3 180 1,576,800 1,577

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    20/33

    Appendix II: Kursk Leak Rates Sorted by Leak Identification Number

    20

    SiteVisit

    NumberMeasurement

    Date

    LeakTag

    NumberOperatingPressure

    GenericDescription

    LitersPer

    Minute

    LitersPer

    HourLiters

    Per/Year

    TotalEmissions

    m3/year

    31 4-Nov-05 31/4 0.003MPa Valve StemPacking

    25 1500 13,140,000 13,140

    31 4-Nov-05 31/5 0.003MPa Valve StemPacking

    1.9 114 998,640 999

    32 4-Nov-05 32/1 0.003MPa Valve StemPacking

    10.6 636 5,571,360 5,571

    32 4-Nov-05 32/2 0.003MPa Valve StemPacking

    1.1 66 578,160 578

    32 4-Nov-05 32/3 0.3MPa Valve StemPacking

    3.6 216 1,892,160 1,892

    33 4-Nov-05 33/1 0.003MPa Valve StemPacking

    47.3 2838 24,860,880 24,861

    33 4-Nov-05 33/2 0.003MPa PressureRelief Valve

    83.3 4998 43,782,480 43,782

    33 4-Nov-05 33/3 0.003MPa Valve StemPacking

    2.7 162 1,419,120 1,419

    33 4-Nov-05 33/4 0.003MPa Valve StemPacking

    97.2 5832 51,088,320 51,088

    33 4-Nov-05 33/5 0.003MPa Valve StemPacking

    10.8 648 5,676,480 5,676

    36 7-Nov-05 36/1 0.003MPa Valve StemPacking

    35.8 2148 18,816,480 18,816

    36 7-Nov-05 36/2 0.3MPa Valve StemPacking

    227.7 13662 119,679,120 119,679

    36 7-Nov-05 36/3 0.3MPa Valve Stem

    Packing

    4.7 282 2,470,320 2,470

    36 7-Nov-05 36/4 0.003MPa Valve StemPacking

    64.1 3846 33,690,960 33,691

    36 7-Nov-05 36/5 0.003MPa Valve StemPacking

    13.5 810 7,095,600 7,096

    36 7-Nov-05 36/6 0.003MPa Valve StemPacking

    1.7 102 893,520 894

    37 8-Nov-05 37/1 0.003MPa Valve StemPacking

    19.4 1164 10,196,640 10,197

    37 8-Nov-05 37/2 0.3MPa Valve StemPacking

    47.7 2862 25,071,120 25,071

    37 8-Nov-05 37/3 0.003MPa Valve StemPacking

    1 60 525,600 526

    37 8-Nov-05 37/4 0.003MPa Valve StemPacking

    14.6 876 7,673,760 7,674

    38 9-Nov-05 38/1 0.003MPa Valve StemPacking

    4 240 2,102,400 2,102

    39 9-Nov-05 39/1 0.003MPa Valve StemPacking

    3.7 222 1,944,720 1,945

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    21/33

    Appendix II: Kursk Leak Rates Sorted by Leak Identification Number

    21

    SiteVisit

    NumberMeasurement

    Date

    LeakTag

    NumberOperatingPressure

    GenericDescription

    LitersPer

    Minute

    LitersPer

    HourLiters

    Per/Year

    TotalEmissions

    m3/year

    41 9-Nov-05 41/1 0.003MPa Valve StemPacking

    5.2 312 2,733,120 2,733

    41 9-Nov-05 41/2 0.003MPa Valve StemPacking

    4.6 276 2,417,760 2,418

    42 9-Nov-05 42/1 0.003MPa Valve StemPacking

    9.6 576 5,045,760 5,046

    43 9-Nov-05 43/1 0.003MPa Valve StemPacking

    4.2 252 2,207,520 2,208

    44 9-Nov-05 44/1 0.003MPa Valve StemPacking

    0.2 12 105,120 105

    45 9-Nov-05 45/1 0.003MPa Valve StemPacking

    7 420 3,679,200 3,679

    0 0 0

    Total Leak Rate 1747.7 104862 918,591,120 918,591Total Number of Leaks 94

    Number of Components Counted 1007

    Number of Stations Inspected 47

    Emission Factor Per Component(all)

    1.7 104.133 912,206 912

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    22/33

    22

    Appendix III

    Kursk Regulator Station Leak Rates Sorted by Component Category with

    Emission Factors

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    23/33

    Appendix III: Kursk Leak Rates Sorted by Component Category with Emission Factors

    23

    SiteVisit

    NumberMeasurement

    Date

    LeakTag

    NumberOperatingPressure

    GenericDescription

    LitersPer

    Minute

    LitersPer

    HourLiters

    Per/Year

    TotalEmissions

    m3/year

    36 7-Nov-05 36/2 0.3MPa Valve StemPacking

    227.7 13662 119,679,120 119,679

    3 1-Nov-05 3/1 .003MPa Valve StemPacking

    158.5 9510 83,307,600 83,308

    33 4-Nov-05 33/4 0.003MPa Valve StemPacking

    97.2 5832 51,088,320 51,088

    19 2-Nov-05 19/1 0.003MPa Valve StemPacking

    72.9 4374 38,316,240 38,316

    36 7-Nov-05 36/4 0.003MPa Valve StemPacking

    64.1 3846 33,690,960 33,691

    2 1-Nov-05 2/1 .003MPa Valve StemPacking

    49 2940 25,754,400 25,754

    5 1-Nov-05 5/1 0.003MPa Valve StemPacking

    47.8 2868 25,123,680 25,124

    37 8-Nov-05 37/2 0.3MPa Valve StemPacking

    47.7 2862 25,071,120 25,071

    33 4-Nov-05 33/1 0.003MPa Valve StemPacking

    47.3 2838 24,860,880 24,861

    17 2-Nov-05 17/1 0.003MPa Valve StemPacking

    37 2220 19,447,200 19,447

    36 7-Nov-05 36/1 0.003MPa Valve StemPacking

    35.8 2148 18,816,480 18,816

    10 1-Nov-05 10/1 0.003MPa Valve StemPacking

    35.6 2136 18,711,360 18,711

    21 3-Nov-05 21/1 0.003MPa Valve Stem

    Packing

    35 2100 18,396,000 18,396

    23 3-Nov-05 23/1 0.003MPa Valve StemPacking

    31.2 1872 16,398,720 16,399

    31 4-Nov-05 31/4 0.003MPa Valve StemPacking

    25 1500 13,140,000 13,140

    26 3-Nov-05 26/1 0.003MPa Valve StemPacking

    23.3 1398 12,246,480 12,246

    11 1-Nov-05 11/1 0.3MPa Valve StemPacking

    21.9 1314 11,510,640 11,511

    29 3-Nov-05 29/1 0.003MPa Valve StemPacking

    21.9 1314 11,510,640 11,511

    14 2-Nov-05 14/1 0.003MPa Valve StemPacking

    20.9 1254 10,985,040 10,985

    9 1-Nov-05 9/1 0.3MPa Valve StemPacking

    20.5 1230 10,774,800 10,775

    15 2-Nov-05 15/1 0.003MPa Valve StemPacking

    20.3 1218 10,669,680 10,670

    31 4-Nov-05 31/2 0.003MPa Valve StemPacking

    19.4 1164 10,196,640 10,197

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    24/33

    Appendix III: Kursk Leak Rates Sorted by Component Category with Emission Factors

    24

    SiteVisit

    NumberMeasurement

    Date

    LeakTag

    NumberOperatingPressure

    GenericDescription

    LitersPer

    Minute

    LitersPer

    HourLiters

    Per/Year

    TotalEmissions

    m3/year

    37 8-Nov-05 37/1 0.003MPa Valve StemPacking

    19.4 1164 10,196,640 10,197

    12 2-Nov-05 12/1 0.003MPa Valve StemPacking

    18 1080 9,460,800 9,461

    17 2-Nov-05 17/3 0.003MPa Valve StemPacking

    18 1080 9,460,800 9,461

    13 2-Nov-05 13/1 0.003MPa Valve StemPacking

    16.7 1002 8,777,520 8,778

    16 2-Nov-05 16/1 0.003MPa Valve StemPacking

    16.3 978 8,567,280 8,567

    25 3-Nov-05 25/4 0.003MPa Valve StemPacking

    14.8 888 7,778,880 7,779

    30 4-Nov-05 30/1 0.003MPa Valve StemPacking

    14.6 876 7,673,760 7,674

    37 8-Nov-05 37/4 0.003MPa Valve StemPacking

    14.6 876 7,673,760 7,674

    36 7-Nov-05 36/5 0.003MPa Valve StemPacking

    13.5 810 7,095,600 7,096

    1 1-Nov-05 1/1 0.3 MPa Valve StemPacking

    13.3 798 6,990,480 6,990

    13 2-Nov-05 13/2 0.003MPa Valve StemPacking

    13.1 786 6,885,360 6,885

    7 1-Nov-05 7/4 0.3MPa Valve StemPacking

    13 780 6,832,800 6,833

    27 3-Nov-05 27/2 0.3MPa Valve Stem

    Packing

    12 720 6,307,200 6,307

    18 2-Nov-05 18/1 0.003MPa Valve StemPacking

    11.5 690 6,044,400 6,044

    33 4-Nov-05 33/5 0.003MPa Valve StemPacking

    10.8 648 5,676,480 5,676

    32 4-Nov-05 32/1 0.003MPa Valve StemPacking

    10.6 636 5,571,360 5,571

    42 9-Nov-05 42/1 0.003MPa Valve StemPacking

    9.6 576 5,045,760 5,046

    29 3-Nov-05 29/2 0.3MPa Valve StemPacking

    9.4 564 4,940,640 4,941

    27 3-Nov-05 27/1 0.003MPa Valve StemPacking

    9.3 558 4,888,080 4,888

    26 3-Nov-05 26/4 0.003MPa Valve StemPacking

    9.1 546 4,782,960 4,783

    20 2-Nov-05 20/1 0.003MPa Valve StemPacking

    8.8 528 4,625,280 4,625

    7 1-Nov-05 7/5 0.003MPa Valve StemPacking

    7.9 474 4,152,240 4,152

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    25/33

    Appendix III: Kursk Leak Rates Sorted by Component Category with Emission Factors

    25

    SiteVisit

    NumberMeasurement

    Date

    LeakTag

    NumberOperatingPressure

    GenericDescription

    LitersPer

    Minute

    LitersPer

    HourLiters

    Per/Year

    TotalEmissions

    m3/year

    25 3-Nov-05 25/1 0.003MPa Valve StemPacking

    7.9 474 4,152,240 4,152

    25 3-Nov-05 25/2 0.003MPa Valve StemPacking

    7.5 450 3,942,000 3,942

    6 1-Nov-05 6/1 0.003MPa Valve StemPacking

    7 420 3,679,200 3,679

    45 9-Nov-05 45/1 0.003MPa Valve StemPacking

    7 420 3,679,200 3,679

    26 3-Nov-05 26/2 0.003MPa Valve StemPacking

    6.7 402 3,521,520 3,522

    4 1-Nov-05 4/1 .003MPa Valve StemPacking

    6.6 396 3,468,960 3,469

    2 1-Nov-05 2/2 0.3 MPa Valve StemPacking

    6.1 366 3,206,160 3,206

    7 1-Nov-05 7/3 0.003MPa Valve StemPacking

    6.1 366 3,206,160 3,206

    13 2-Nov-05 13/4 0.003MPa Valve StemPacking

    6 360 3,153,600 3,154

    41 9-Nov-05 41/1 0.003MPa Valve StemPacking

    5.2 312 2,733,120 2,733

    4 1-Nov-05 4/2 0.003MPa Valve StemPacking

    4.9 294 2,575,440 2,575

    19 2-Nov-05 19/2 0.003MPa Valve StemPacking

    4.9 294 2,575,440 2,575

    29 3-Nov-05 29/3 0.003MPa Valve Stem

    Packing

    4.7 282 2,470,320 2,470

    36 7-Nov-05 36/3 0.3MPa Valve StemPacking

    4.7 282 2,470,320 2,470

    41 9-Nov-05 41/2 0.003MPa Valve StemPacking

    4.6 276 2,417,760 2,418

    24 3-Nov-05 24/2 0.04MPa Valve StemPacking

    4.5 270 2,365,200 2,365

    25 3-Nov-05 25/3 0.003MPa Valve StemPacking

    4.4 264 2,312,640 2,313

    11 1-Nov-05 11/3 0.003MPa Valve StemPacking

    4.2 252 2,207,520 2,208

    12 2-Nov-05 12/3 0.003MPa Valve StemPacking

    4.2 252 2,207,520 2,208

    43 9-Nov-05 43/1 0.003MPa Valve StemPacking

    4.2 252 2,207,520 2,208

    38 9-Nov-05 38/1 0.003MPa Valve StemPacking

    4 240 2,102,400 2,102

    39 9-Nov-05 39/1 0.003MPa Valve StemPacking

    3.7 222 1,944,720 1,945

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    26/33

    Appendix III: Kursk Leak Rates Sorted by Component Category with Emission Factors

    26

    SiteVisit

    NumberMeasurement

    Date

    LeakTag

    NumberOperatingPressure

    GenericDescription

    LitersPer

    Minute

    LitersPer

    HourLiters

    Per/Year

    TotalEmissions

    m3/year

    13 2-Nov-05 13/3 0.003MPa Valve StemPacking

    3.6 216 1,892,160 1,892

    24 3-Nov-05 24/3 0.3MPa Valve StemPacking

    3.6 216 1,892,160 1,892

    32 4-Nov-05 32/3 0.3MPa Valve StemPacking

    3.6 216 1,892,160 1,892

    26 3-Nov-05 26/3 0.003MPa Valve StemPacking

    3.5 210 1,839,600 1,840

    11 1-Nov-05 11/2 0.003MPa Valve StemPacking

    3.4 204 1,787,040 1,787

    28 3-Nov-05 28/1 0.003MPa Valve StemPacking

    3 180 1,576,800 1,577

    31 4-Nov-05 31/3 0.3MPa Valve StemPacking

    3 180 1,576,800 1,577

    12 2-Nov-05 12/4 0.003MPa Valve StemPacking

    2.7 162 1,419,120 1,419

    24 3-Nov-05 24/1 0.3MPa Valve StemPacking

    2.7 162 1,419,120 1,419

    33 4-Nov-05 33/3 0.003MPa Valve StemPacking

    2.7 162 1,419,120 1,419

    13 2-Nov-05 13/5 0.003MPa Valve StemPacking

    2.1 126 1,103,760 1,104

    17 2-Nov-05 17/2 0.003MPa Valve StemPacking

    2.1 126 1,103,760 1,104

    7 1-Nov-05 7/1 0.003MPa Valve Stem

    Packing

    2 120 1,051,200 1,051

    31 4-Nov-05 31/5 0.003MPa Valve StemPacking

    1.9 114 998,640 999

    12 2-Nov-05 12/2 0.003MPa Valve StemPacking

    1.8 108 946,080 946

    36 7-Nov-05 36/6 0.003MPa Valve StemPacking

    1.7 102 893,520 894

    4 1-Nov-05 4/3 0.003MPa Valve StemPacking

    1.5 90 788,400 788

    8 1-Nov-05 8/1 0.003MPa Valve StemPacking

    1.4 84 735,840 736

    20 2-Nov-05 20/2 0.003MPa Valve StemPacking

    1.3 78 683,280 683

    32 4-Nov-05 32/2 0.003MPa Valve StemPacking

    1.1 66 578,160 578

    37 8-Nov-05 37/3 0.003MPa Valve StemPacking

    1 60 525,600 526

    7 1-Nov-05 7/2 0.3MPa Valve StemPacking

    0.3 18 157,680 158

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    27/33

    Appendix III: Kursk Leak Rates Sorted by Component Category with Emission Factors

    27

    SiteVisit

    NumberMeasurement

    Date

    LeakTag

    NumberOperatingPressure

    GenericDescription

    LitersPer

    Minute

    LitersPer

    HourLiters

    Per/Year

    TotalEmissions

    m3/year

    7 1-Nov-05 7/6 0.003MPa Valve StemPacking

    0.2 12 105,120 105

    44 9-Nov-05 44/1 0.003MPa Valve StemPacking

    0.2 12 105,120 105

    (LPM) (LPH) (Liters/Yr) (M3/Year)

    Total Leak Rate for Valves 1613.8 96828 848213280 848213.3

    Total Valves Screened 244

    Emission Factor (per component) 6.61 396.8 3,476,284 3,476

    33 4-Nov-05 33/2 0.003MPa PressureRelief Valve

    83.3 4998 43,782,480 43,782

    31 4-Nov-05 31/1 0.003MPa PressureRelief Valve

    38.1 2286 20,025,360 20,025

    22 3-Nov-05 22/1 0.003MPa PressureRelief Valve

    11 660 5,781,600 5,782

    (LPM) (LPH) (Liters/Yr) (M3/Year)

    Total Leak Rate for PressureRelief Valves

    132.4 7944 69589440 69589.44

    Total PRVs Screened 36

    Emission Factor (per component) 3.68 220.7 1,933,040 1,933

    2 1-Nov-05 2/3 0.3 MPa Flange 1.5 90 788,400 788

    (LPM) (LPH) (Liters/Yr) (M3/Year)

    Total Leak Rate for Flanges 1.5 90 788400 788.4

    Total Flanges Screened 727

    Emission Factor (per component) 0.002 0.124 1084.46 1.08

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    28/33

    28

    Appendix IV

    Kursk Regulator Station Leak Rates Measurements Sorted by Leak Rate

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    29/33

    Appendix IV: Kursk Leak Rates Sorted by Leak Rate

    29

    SiteVisit

    Number

    MeasurementDate

    LeakTag

    Number

    OperatingPressure

    GenericDescription

    LitersPer

    Minute

    LitersPer

    Hour

    LitersPer/Year

    TotalEmissions

    m3/year

    36 7-Nov-05 36/2 0.3MPa Valve StemPacking

    227.7 13662 119,679,120 119,679

    3 1-Nov-05 3/1 .003MPa Valve StemPacking

    158.5 9510 83,307,600 83,308

    33 4-Nov-05 33/4 0.003MPa Valve StemPacking

    97.2 5832 51,088,320 51,088

    33 4-Nov-05 33/2 0.003MPa PressureRelief Valve

    83.3 4998 43,782,480 43,782

    19 2-Nov-05 19/1 0.003MPa Valve StemPacking

    72.9 4374 38,316,240 38,316

    36 7-Nov-05 36/4 0.003MPa Valve StemPacking

    64.1 3846 33,690,960 33,691

    2 1-Nov-05 2/1 .003MPa Valve StemPacking

    49 2940 25,754,400 25,754

    5 1-Nov-05 5/1 0.003MPa Valve StemPacking

    47.8 2868 25,123,680 25,124

    37 8-Nov-05 37/2 0.3MPa Valve StemPacking

    47.7 2862 25,071,120 25,071

    33 4-Nov-05 33/1 0.003MPa Valve StemPacking

    47.3 2838 24,860,880 24,861

    31 4-Nov-05 31/1 0.003MPa PressureRelief Valve

    38.1 2286 20,025,360 20,025

    17 2-Nov-05 17/1 0.003MPa Valve StemPacking

    37 2220 19,447,200 19,447

    36 7-Nov-05 36/1 0.003MPa Valve Stem

    Packing

    35.8 2148 18,816,480 18,816

    10 1-Nov-05 10/1 0.003MPa Valve StemPacking

    35.6 2136 18,711,360 18,711

    21 3-Nov-05 21/1 0.003MPa Valve StemPacking

    35 2100 18,396,000 18,396

    23 3-Nov-05 23/1 0.003MPa Valve StemPacking

    31.2 1872 16,398,720 16,399

    31 4-Nov-05 31/4 0.003MPa Valve StemPacking

    25 1500 13,140,000 13,140

    26 3-Nov-05 26/1 0.003MPa Valve StemPacking

    23.3 1398 12,246,480 12,246

    11 1-Nov-05 11/1 0.3MPa Valve StemPacking

    21.9 1314 11,510,640 11,511

    29 3-Nov-05 29/1 0.003MPa Valve StemPacking

    21.9 1314 11,510,640 11,511

    14 2-Nov-05 14/1 0.003MPa Valve StemPacking

    20.9 1254 10,985,040 10,985

    9 1-Nov-05 9/1 0.3MPa Valve StemPacking

    20.5 1230 10,774,800 10,775

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    30/33

    Appendix IV: Kursk Leak Rates Sorted by Leak Rate

    30

    SiteVisit

    Number

    MeasurementDate

    LeakTag

    Number

    OperatingPressure

    GenericDescription

    LitersPer

    Minute

    LitersPer

    Hour

    LitersPer/Year

    TotalEmissions

    m3/year

    15 2-Nov-05 15/1 0.003MPa Valve StemPacking

    20.3 1218 10,669,680 10,670

    31 4-Nov-05 31/2 0.003MPa Valve StemPacking

    19.4 1164 10,196,640 10,197

    37 8-Nov-05 37/1 0.003MPa Valve StemPacking

    19.4 1164 10,196,640 10,197

    12 2-Nov-05 12/1 0.003MPa Valve StemPacking

    18 1080 9,460,800 9,461

    17 2-Nov-05 17/3 0.003MPa Valve StemPacking

    18 1080 9,460,800 9,461

    13 2-Nov-05 13/1 0.003MPa Valve StemPacking

    16.7 1002 8,777,520 8,778

    16 2-Nov-05 16/1 0.003MPa Valve StemPacking

    16.3 978 8,567,280 8,567

    25 3-Nov-05 25/4 0.003MPa Valve StemPacking

    14.8 888 7,778,880 7,779

    30 4-Nov-05 30/1 0.003MPa Valve StemPacking

    14.6 876 7,673,760 7,674

    37 8-Nov-05 37/4 0.003MPa Valve StemPacking

    14.6 876 7,673,760 7,674

    36 7-Nov-05 36/5 0.003MPa Valve StemPacking

    13.5 810 7,095,600 7,096

    1 1-Nov-05 1/1 0.3 MPa Valve StemPacking

    13.3 798 6,990,480 6,990

    13 2-Nov-05 13/2 0.003MPa Valve Stem

    Packing

    13.1 786 6,885,360 6,885

    7 1-Nov-05 7/4 0.3MPa Valve StemPacking

    13 780 6,832,800 6,833

    27 3-Nov-05 27/2 0.3MPa Valve StemPacking

    12 720 6,307,200 6,307

    18 2-Nov-05 18/1 0.003MPa Valve StemPacking

    11.5 690 6,044,400 6,044

    22 3-Nov-05 22/1 0.003MPa PressureRelief Valve

    11 660 5,781,600 5,782

    33 4-Nov-05 33/5 0.003MPa Valve StemPacking

    10.8 648 5,676,480 5,676

    32 4-Nov-05 32/1 0.003MPa Valve StemPacking

    10.6 636 5,571,360 5,571

    42 9-Nov-05 42/1 0.003MPa Valve StemPacking

    9.6 576 5,045,760 5,046

    29 3-Nov-05 29/2 0.3MPa Valve StemPacking

    9.4 564 4,940,640 4,941

    27 3-Nov-05 27/1 0.003MPa Valve StemPacking

    9.3 558 4,888,080 4,888

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    31/33

    Appendix IV: Kursk Leak Rates Sorted by Leak Rate

    31

    SiteVisit

    Number

    MeasurementDate

    LeakTag

    Number

    OperatingPressure

    GenericDescription

    LitersPer

    Minute

    LitersPer

    Hour

    LitersPer/Year

    TotalEmissions

    m3/year

    26 3-Nov-05 26/4 0.003MPa Valve StemPacking

    9.1 546 4,782,960 4,783

    20 2-Nov-05 20/1 0.003MPa Valve StemPacking

    8.8 528 4,625,280 4,625

    7 1-Nov-05 7/5 0.003MPa Valve StemPacking

    7.9 474 4,152,240 4,152

    25 3-Nov-05 25/1 0.003MPa Valve StemPacking

    7.9 474 4,152,240 4,152

    25 3-Nov-05 25/2 0.003MPa Valve StemPacking

    7.5 450 3,942,000 3,942

    6 1-Nov-05 6/1 0.003MPa Valve StemPacking

    7 420 3,679,200 3,679

    45 9-Nov-05 45/1 0.003MPa Valve StemPacking

    7 420 3,679,200 3,679

    26 3-Nov-05 26/2 0.003MPa Valve StemPacking

    6.7 402 3,521,520 3,522

    4 1-Nov-05 4/1 .003MPa Valve StemPacking

    6.6 396 3,468,960 3,469

    2 1-Nov-05 2/2 0.3 MPa Valve StemPacking

    6.1 366 3,206,160 3,206

    7 1-Nov-05 7/3 0.003MPa Valve StemPacking

    6.1 366 3,206,160 3,206

    13 2-Nov-05 13/4 0.003MPa Valve StemPacking

    6 360 3,153,600 3,154

    41 9-Nov-05 41/1 0.003MPa Valve Stem

    Packing

    5.2 312 2,733,120 2,733

    4 1-Nov-05 4/2 0.003MPa Valve StemPacking

    4.9 294 2,575,440 2,575

    19 2-Nov-05 19/2 0.003MPa Valve StemPacking

    4.9 294 2,575,440 2,575

    29 3-Nov-05 29/3 0.003MPa Valve StemPacking

    4.7 282 2,470,320 2,470

    36 7-Nov-05 36/3 0.3MPa Valve StemPacking

    4.7 282 2,470,320 2,470

    41 9-Nov-05 41/2 0.003MPa Valve StemPacking

    4.6 276 2,417,760 2,418

    24 3-Nov-05 24/2 0.04MPa Valve StemPacking

    4.5 270 2,365,200 2,365

    25 3-Nov-05 25/3 0.003MPa Valve StemPacking

    4.4 264 2,312,640 2,313

    11 1-Nov-05 11/3 0.003MPa Valve StemPacking

    4.2 252 2,207,520 2,208

    12 2-Nov-05 12/3 0.003MPa Valve StemPacking

    4.2 252 2,207,520 2,208

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    32/33

    Appendix IV: Kursk Leak Rates Sorted by Leak Rate

    32

    SiteVisit

    Number

    MeasurementDate

    LeakTag

    Number

    OperatingPressure

    GenericDescription

    LitersPer

    Minute

    LitersPer

    Hour

    LitersPer/Year

    TotalEmissions

    m3/year

    43 9-Nov-05 43/1 0.003MPa Valve StemPacking

    4.2 252 2,207,520 2,208

    38 9-Nov-05 38/1 0.003MPa Valve StemPacking

    4 240 2,102,400 2,102

    39 9-Nov-05 39/1 0.003MPa Valve StemPacking

    3.7 222 1,944,720 1,945

    13 2-Nov-05 13/3 0.003MPa Valve StemPacking

    3.6 216 1,892,160 1,892

    24 3-Nov-05 24/3 0.3MPa Valve StemPacking

    3.6 216 1,892,160 1,892

    32 4-Nov-05 32/3 0.3MPa Valve StemPacking

    3.6 216 1,892,160 1,892

    26 3-Nov-05 26/3 0.003MPa Valve StemPacking

    3.5 210 1,839,600 1,840

    11 1-Nov-05 11/2 0.003MPa Valve StemPacking

    3.4 204 1,787,040 1,787

    28 3-Nov-05 28/1 0.003MPa Valve StemPacking

    3 180 1,576,800 1,577

    31 4-Nov-05 31/3 0.3MPa Valve StemPacking

    3 180 1,576,800 1,577

    12 2-Nov-05 12/4 0.003MPa Valve StemPacking

    2.7 162 1,419,120 1,419

    24 3-Nov-05 24/1 0.3MPa Valve StemPacking

    2.7 162 1,419,120 1,419

    33 4-Nov-05 33/3 0.003MPa Valve Stem

    Packing

    2.7 162 1,419,120 1,419

    13 2-Nov-05 13/5 0.003MPa Valve StemPacking

    2.1 126 1,103,760 1,104

    17 2-Nov-05 17/2 0.003MPa Valve StemPacking

    2.1 126 1,103,760 1,104

    7 1-Nov-05 7/1 0.003MPa Valve StemPacking

    2 120 1,051,200 1,051

    31 4-Nov-05 31/5 0.003MPa Valve StemPacking

    1.9 114 998,640 999

    12 2-Nov-05 12/2 0.003MPa Valve StemPacking

    1.8 108 946,080 946

    36 7-Nov-05 36/6 0.003MPa Valve StemPacking

    1.7 102 893,520 894

    2 1-Nov-05 2/3 0.3 MPa Flange 1.5 90 788,400 788

    4 1-Nov-05 4/3 0.003MPa Valve StemPacking

    1.5 90 788,400 788

    8 1-Nov-05 8/1 0.003MPa Valve StemPacking

    1.4 84 735,840 736

  • 7/30/2019 Nov 2005 Kursk Project Report Mhc

    33/33

    Appendix IV: Kursk Leak Rates Sorted by Leak Rate

    SiteVisit

    Number

    MeasurementDate

    LeakTag

    Number

    OperatingPressure

    GenericDescription

    LitersPer

    Minute

    LitersPer

    Hour

    LitersPer/Year

    TotalEmissions

    m3/year

    20 2-Nov-05 20/2 0.003MPa Valve StemPacking

    1.3 78 683,280 683

    32 4-Nov-05 32/2 0.003MPa Valve StemPacking

    1.1 66 578,160 578

    37 8-Nov-05 37/3 0.003MPa Valve StemPacking

    1 60 525,600 526

    7 1-Nov-05 7/2 0.3MPa Valve StemPacking

    0.3 18 157,680 158

    7 1-Nov-05 7/6 0.003MPa Valve StemPacking

    0.2 12 105,120 105

    44 9-Nov-05 44/1 0.003MPa Valve StemPacking

    0.2 12 105,120 105

    0 0 0

    Total Leak Rate 1361.5 81690 715,604,400 715,604

    Total Number of Leaks 94

    Number of Components Counted 1007

    Number of Stations Inspected 47

    Emission Factor Per Component 1.4 81.1221 710,630 711


Recommended