of 33
7/30/2019 Nov 2005 Kursk Project Report Mhc
1/33
Report
Measurement of Leak Rates at Kursk Natural Gas Regulator Stations
Kursk, Russia
November 1 - 10, 2005
Submitted to:
Alexandre Okmianski
DirectorAddGlobe LLC
Phone: (650) 357-7735 ext. 25
Fax: (650) 357-7342
Submitted by:
Milton W. Heath III
Heath Consultants Incorporated9030 Monroe Road
Houston, TX 77061
713-844-1304
November 22, 2005
7/30/2019 Nov 2005 Kursk Project Report Mhc
2/33
2
1.0 Summary and Introduction
This report describes a leak measurement program conducted in Kursk, Russia at Kursk Natural
Gas Distribution Company regulator stations. The survey was conducted from November 1st
through November 10th, 2005. During this program all standardized components, including
flanges, pipe thread connectors, block valves, regulators, plug valves and pressure relief valves in
natural gas service were surveyed for leaks. Any leaks found were tagged and measured using the
Hi Flow Sampler. These leak rate measurements were then entered into a database, where they
can be sorted both by the leak size and tag number, so that the leak rate of any individual leak can
be determined and the most significant leaks targeted for cost effective repair. These average leak
rates, known as emission factors, allow the leakage to be compared to industry averages.
2.0 Site Description
Table 1 details specific facility characteristics for the Kursk Regulator Stations.
Table 1: Site Description of Kursk Leak Measurement Sites
Site Visits Facility Type System AgeOperating
Pressures
47Regulator Stations
(above ground)47 years
0.3 MPa and 0.003
MPa
The Kursk natural gas distribution system has been operating since 1958 with approximately
8000 Kilometers of pipeline in the region. Roughly 3700 kilometers of this pipeline is situated
within the city limits of Kursk. Approximately one sixth (1/6) of this system is designed
aboveground where low pressure gas serves the residential and business communities. The vast
majority of the system (5/6) is belowground and travels along the roadways.
Within Kursk, there are reported to be 138 regulator stations, which regulate the higher pressures
(0.3 MPa) down to lower pressures (0.003 MPa) for residential service. During our eight days of
surveying from November 1st through November 10th, we were able to survey 47 of these
stations for leak detection and measurement.
7/30/2019 Nov 2005 Kursk Project Report Mhc
3/33
3
3.0 Field Program Description
During this leak survey, leak detection at the facilities was conducted using catalyticoxidation/thermal conductivity detectors (Heath Gasurveyors 6-500). The Heath Gasurveyor
instruments were calibrated in Houston, Texas on Friday October 28 th, 2005 using both 2.5%
methane in air and 99% methane in air. All identified leaks (those that screened above 0.5%
methane in air) were tagged and numbered.
Once leaks were identified, leak rate measurements were made using the Hi-Flow Sampler. The
Hi-Flow Sampler makes leak rate measurements with the same accuracy as enclosure
measurements but at a speed approaching that of leak detection screening instruments (Howard et
al., 1994; Lott et al., 1995 Howard, 1995). The Hi-Flow Sampler uses a high flow rate of air to
completely capture the gas leaking from the component. A catalytic oxidation/thermal
conductivity sensor is used to measure the sample concentration in the air stream of the high flow
system. The Hi-Flow Sampler essentially performs an enclosure measurement using the flow
regime induced by the sampler instead of a physical enclosure. A description of the Hi-Flow
Sampler and its advantages over typical screening and enclosure measurements is provided in
Appendix I.
The Hi Flow Sampler was calibrated in Houston, Texas on October 28th and then calibrated in
Kursk, Russia on November 2ndand November 10th. Verification of calibration took place in theKursk Gas engineering office and field on November 3rdand November 7th.
7/30/2019 Nov 2005 Kursk Project Report Mhc
4/33
4
4.0 Field Measurement Results
Individual leak rates for all leaks are presented in the appendices. Leak rates sorted by leakidentification number are presented in Appendix II. Leak rates sorted by component category
with emission factors are presented in Appendix III. Leaks sorted by leak rate are presented in
Appendix IV. All yearly values are based on continuous leakage throughout the year. Figures 1-6
are illustrative pictures of the work site with Hi Flow Sampling device.
A total of 47 regulator stations were inspected between November 1st and November 10th, 2005.
A total of 94 leaks were identified and measured amounting to a total leak rate of 918,591m3/yr.
Table 2 provides a summary of the results from the measurement program.
Table 2: Summary of Leak Rates at 24 Kursk Regulator Stations
Component CategoryLeak
Rate
(LPM)
Leak
Rate
(LPH)
Leak Rate
M3/Yr
Leak Rate from Valve Stem Packings (90leaks out of 244 valves surveyed)
1,614 96,828 848,213
Leak Rate from Flanges (1 leak out of 727flanges surveyed)
1.5 90 788
Leak Rate from Pressure Relief Valve (3
leaks out of 36 PRVs surveyed)132 7,944 69,589
Figure 1 - Nykoli, Chief of Gas Regulator Service Department, Assisting the project.
7/30/2019 Nov 2005 Kursk Project Report Mhc
5/33
5
Figure 2 - Verification Team from DNV and United Nations Inspects stations and reviews
methodology.
Figure 3 - Russian Carbon Fund, Kursk Gas, DNV, United Nations, Rosgasification and Heath
Consultants Inc. inspecting sites.
7/30/2019 Nov 2005 Kursk Project Report Mhc
6/33
6
Figure 4 - Max, Lead Specialist from "Center Gas Service Opt" assists with leak measurements
along with Nykoli of Kursk Gas.
7/30/2019 Nov 2005 Kursk Project Report Mhc
7/33
7
5.0 Repair and Measurement of Emission Reductions
As part of this pilot program, an effort was made to repair a few of the identified leaks using
Gore-Tex sealing materials manufactured in the USA. Once the leaks were tagged and measured,
gas crews attempted to repair seven valve packing stem leaks. Leak rate measurements were once
again taken at each of the seven valves where complete repairs were validated and emission
reductions were verified. Table 3 provides a summary of the results from the emission reduction
efforts employed. Figures 1 and 2 are pictures of the engineering technicians making the repairs
on the valves.
Table 3: Summary of Valve Stem Packing Repairs Conducted during Pilot Program
Description and
Location
Leak Rate (LPM)
BEFORE
Leak Rate
(LPM)
AFTER
Site 12, Leak 1 18 0
Site 36, Leak 1 35.8 0
Site 36, Leak 2 227.7 0Site 36, Leak 3 4.7 0
Site 36, Leak 4 64.1 0
Site 36, Leak 5 13.5 0
Site 36, Leak 6 1.7 0
Total Reductions 365.5
Figure 5 Nykoli and Alex of Kursk Gaz repair leaking valve with new Gore-Tex sealants.
7/30/2019 Nov 2005 Kursk Project Report Mhc
8/33
8
Figure 6
7/30/2019 Nov 2005 Kursk Project Report Mhc
9/33
9
6.0 Emission Factors
Emission factors are the average leakage for a particular component category. They are calculated
by finding the total leak rate for each component category and dividing by the total number of
components surveyed in that category. A total of 1007 components were surveyed from
November 1st through November 10th, 2005. Out of this total, there were 244 valves screened for
at the regulator stations, of which 90 leaks were found, equating to a leak frequency of
approximately 36.8%. This is at the high end of the leak frequency range compared to similar
studies at regulator stations in the United States natural gas industry. The emission factors for the
valves and other two component categories surveyed at the Kursk regulator stations are displayed
in Table 4 and are based on measurements prior to any repairs attempted.
Table 4. Kursk Valve Emission Factors (Assumes Continuous Leakage)
Kursk Regulator Stations
Component
Category
Number of
Components
Surveyed
Emission Factor
(Liters Per Minute)
Kursk Valve Emission
Factor (m3/Component/Yr)
Regulator Valves 244 6.61 3,476Pressure Relief
Valves36 3.68 1,933
Flanges 727 .002 1.08
7.0 References
CMA, 1989. Improving Air Quality: Guidance for Estimating Fugitive Emissions from
Equipment. Chemical Manufacturer's Association, Washington, DC 20037.
EPA, 2000. Seventh Annual Natural Gas STAR Implementation Workshop, October 11 13,2000. Houston, TX. US Environmental Protection Agency, Washington, DC.
Lott, B., T. Howard, and M. Webb, 1995. New Techniques Developed for Measuring Fugitive
Emissions. Pipe Line & Gas Industry, Vol. 78, No. 10., Oct. 1995.
Howard, T., R. Kantamaneni, and G. Jones, 1999. Cost Effective Leak Mitigation at Natural Gas
Transmission Compressor Stations. Report prepared for the Compressor Research Supervisory
Committee of PRC International; Gas Research Institute; and U.S. Environmental Protection
Agency Natural Gas Star Program. PRCI Report No. PR-246-9526.
Kantamaneni, R., G. Jones, M. Barna, P. Cooper, and T. Howard, 1997. Trends in Leak Rates atMetering and Regulating Facilities and the Effectiveness of Leak Detection and Repair (LDAR)
Programs. Report prepared for the Compressor Research Supervisory Committee of PRC
International; Gas Research Institute; and U.S. Environmental Protection Agency Natural GasStar Program (510 Third Street, 5th Floor, Washington, DC 2001).
7/30/2019 Nov 2005 Kursk Project Report Mhc
10/33
10
Appendix I
Leak Measurement Techniques
7/30/2019 Nov 2005 Kursk Project Report Mhc
11/33
11
A.1.1 Screening Techniques, Correlation Equations, and Bagging Measurements
Screening techniques, correlation equations, and enclosure (bagging) measurements have long
been the standard techniques to measure fugitive emissions from leaking process components
such as valves, flanges, and open-ended lines. Screening techniques originally started as a leak
detection method only. Correlations were then developed to relate the concentration measured
using a leak detection instrument to the leak rate. These correlations compare leak rates
measured using enclosure methods to the maximum concentrations measured either 1 cm or 1
mm from the components using a leak detector such as organic vapor analyzer (OVA) (CMA,
1989; Webb and Martino, 1992). Although these correlations make it easy to estimate leak rates,
the inaccuracies are unacceptable for true leak measurements. For any given leak, the estimated
leak rate can vary from the actual leak rate by as much as a factor of 1,000. With these
uncertainties, it is impossible to use screening techniques to determine which leaks are large
enough to justify repair on a cost-effective basis.
The most serious drawback of using screening concentrations and correlation equations is their
inability to accurately characterize leaks that are beyond the scale of typical leak detectors
("pegged sources"). The most common leak detector used when correlations are applied is the
Foxboro OVA-108 (and a recent version, the TVA-1000), which uses a flame ionization detector.
The sampling flow rate of the OVA-108 is approximately 1,000 ml/min, so if as little as 10
ml/min of methane is captured, the resulting concentration will be 10,000 ppm (1%) which is the
upper limit of the instrument. Wind speed, distance of the probe from the leak, and
characteristics of the leak such as exit velocity affect how much of the leak actually is captured
by the sample probe. These uncertainties explain the large scatter in estimating leak rates using
screening concentrations.
It is the pegged sources that contribute most to the facility emissions and losses. In our
experience, 3% - 6% of the components in a natural gas transmission facility will leak and
approximately 0.5 % will exceed the range of the leak detection instrument. One approach would
be to repair all of the pegged source leaks, or repair a percentage of these leaks that is equal to the
percent reduction of emissions that has been set as a goal. Unfortunately, this can be a costly and
ineffective strategy. Because of their inaccuracy, screening measurements cannot be used to
determine which leaks should be fixed first or what the leak reduction would result.
Bagging measurements are accurate but are too expensive and time consuming to measure every
leak at a facility. In this method, the leaking component is wrapped with a nonpermeable
material (such as Tedlar or Mylar) and a clean purge gas (such as nitrogen) sweeps through the
enclosure at a measured flow rate. Vacuum bagging may also be performed. For the case of
methane (CH4) the leak rate from the component can be calculated from the purge flow rate
through the enclosure and the concentration of methane in the outlet stream as follows:
QCH4 = Fpurge x CCH4 (1)
where:
QCH4 = leak rate of methane from the enclosed component (cfm),
Fpurge = the purge flow rate of the clean air or nitrogen (cfm), and
CCH4 = the measured concentration of methane in the exit flow (percent).
7/30/2019 Nov 2005 Kursk Project Report Mhc
12/33
12
Besides screening with a flame ionization detector, other leak detection methods are available and
are often more economical. A soap bubble solution can provide a visual leak detection method
for many natural gas facility components. Although not appropriate for liquid process streams,very hot components, OELs, and flanges with deep crevices, the use of soap can increase the
speed of leak detection by a factor of two to three times that of screening with an organic vapor
analyzer. If leak rate measurements using Indaco sampling are performed, then any effective leak
detection method can be used to find leaks.
A.1.2 Hi-Flow Sampling and Direct Measurements
To overcome the shortcomings of current leak measurement methods discussed previously,
Indaco developed a system that is able to make measurements with the same accuracy as
enclosure measurements but at a speed approaching that of leak detection screening
measurements. The Hi Flow Sampler uses a high flow rate of air and a modified enclosure to
completely capture the gas leaking from the component. Catalytic oxidation and thermal
conductivity hydrocarbon sensors are used to measure the exit concentration in the air stream of
the system. The Hi Flow Sampler essentially makes rapid vacuum enclosure measurements so
that emissions are calculated as follows:
QCH4 = Fpurge x (Csample - Cback) (2)
where:
QCH4 = leak rate of methane from the leaking component (cfm),
Fsampler= the sample flow rate of the sampler (cfm),
Cmain = the concentration of methane in the sample flow (percent), and
Cback = the concentration of methane in the background near the component (percent).
The background concentration must be subtracted from the main sample concentration because itmay be elevated due to other leaks in the vicinity of the leak being measured. Variables such as
wind speed and wind direction may cause the background concentration to fluctuate, so thebackground is measured simultaneously with the sample concentration.
The Hi Flow Sampler is packaged inside a backpack, leaving the operators hands free for
climbing ladders or descending into manholes. The instrument is controlled by a handheld LCD
with an integral 4-key control pad, which is attached to the main unit via a 6 coiled cord. The gas
sample is drawn into the unit via a flexible 1 I.D. hose. Various attachments connect to the
end of the sampling hose providing the means of capturing all the gas that is leaking from the
component under test.
The main unit consists of an intrinsically safe, high-flow blower that pulls air from around the
component being tested, through a flexible hose and into a manifold located inside the unit. The
sample passes through a venturi restrictor where the measured pressure differential is used to
calculate the samples actual flow rate. Next, a portion of the sample is drawn from the manifold
and directed to a methane sensor that measures the samples methane concentration in the range
of 0.05 to 100% gas by volume. A second identical methanesensor channel measures the
7/30/2019 Nov 2005 Kursk Project Report Mhc
13/33
13
background methane level within the vicinity of the leaking component. The final element in the
sampling system is a pump that exhausts the gas sample back into the atmosphere away from the
sampling area.
The measured flow rate and the measured methane levels (both leak and background levels) are
used to calculate the leak rate of the component being tested, with all measured and calculated
values being displayed on the hand-held control unit.
The top flow rate of the sampler is 8 cfm. Two opposing factors influence the choice of sample
flow rate for the system. Higher flow rates provide better leak capture especially if ambient
winds are a factor or if the leak has significant momentum. However, higher flow rates also
result in limits on the size of leak that can be quantified and increase the chance of interference
from nearby leaks. For instance, at a sample flow rate of 3 cfm, a methane leak of 0.006 cfm
would result in a concentration increase of 0.2 %. A sample flow rate of 6 cfm at the same leak
would result in a concentration increase of only 0.1 %. When working in an area where a high
background concentration is present, a larger net concentration increase is easier to quantify.
A series of experiments were conducted to validate the results of the Hi Flow Sampler. A
simulated leak was used to investigate the Hi Flow Sampler's ability to capture leaks. Laboratory
tests were conducted by releasing methane from a compressed gas cylinder through a two-stage
regulator and needle valve. The methane flow rate was measured using a calibrated rotameter(Cole-Parmer, Inc.) Methane flow rates were measured before and after each sampling period.
The leak rate generator was connected to different types of components that are typically
surveyed including a flange, valve, open ended line, and a pipe thread connector. Wind speeds of
up to 4.5 m/s (10 mph) were generated near the leak with a fan. The results of these tests are
shown in Table A-1. The average difference between the metered leak rate and the Hi Flow
Sampler was 3.3% when with a maximum difference 11.1%
Table A-1. Leak Measurement Sampler Compared to Metered Leaks (Indaco Laboratory)
Leak Rate (l/min)Type of
Component Rotameter Sampler
Difference
Rotameter - Sampler
Difference/
Rotameter
Abs. Value
Difference/
Rotameter
Open Ended Line 6.33 6.02 0.31 4.9% 4.9%
Open Ended Line 61.5 61.4 0.04 0.1% 0.1%
Open Ended Line 61.5 61.7 -0.28 -0.4% 0.4%
Open Ended Line 101.5 104.7 -3.24 -3.2% 3.2%
Open Ended Line 101.5 101.8 -0.31 -0.3% 0.3%
Open Ended Line 101.5 107.9 -6.41 -6.3% 6.3%
Open Ended Line 116.7 120.1 -3.40 -2.9% 2.9%Open Ended Line 116.7 119.8 -3.07 -2.6% 2.6%
Open Ended Line 133.1 137.6 -4.50 -3.4% 3.4%
Open Ended Line 144.2 151.8 -7.60 -5.3% 5.3%
Open Ended Line 188.5 201.4 -12.94 -6.9% 6.9%
Flange 5.14 5.18 -0.04 -0.8% 0.8%
Flange 5.14 5.27 -0.13 -2.4% 2.4%
7/30/2019 Nov 2005 Kursk Project Report Mhc
14/33
14
Table A.1 (Continued)
Flange 6.28 6.14 0.14 2.3% 2.3%
Flange 6.28 6.60 -0.32 -5.1% 5.1%
Flange 6.28 6.66 -0.38 -6.1% 6.1%
Flange 6.28 6.05 0.23 3.7% 3.7%
Flange 6.28 6.05 0.23 3.7% 3.7%
Flange 6.28 6.89 -0.61 -9.8% 9.8%
Flange 6.28 5.97 0.31 4.9% 4.9%
Flange 38.7 37.2 1.41 3.7% 3.7%
Flange 56.8 59.3 -2.49 -4.4% 4.4%
Flange 58.6 57.8 0.83 1.4% 1.4%
Flange 63.3 66.1 -2.73 -4.3% 4.3%
Flange 74.1 70.9 3.20 4.3% 4.3%
Flange 80.3 78.0 2.23 2.8% 2.8%
Flange 80.3 80.2 0.08 0.1% 0.1%
Flange 84.9 81.7 3.29 3.9% 3.9%
Flange 84.9 82.3 2.63 3.1% 3.1%
Flange 85.6 82.7 2.92 3.4% 3.4%
Flange 85.6 76.1 9.51 11.1% 11.1%
Flange 88.4 87.0 1.43 1.6% 1.6%
Flange 92.4 89.6 2.78 3.0% 3.0%
Flange 100.8 96.7 4.07 4.0% 4.0%
Flange 100.8 95.2 5.57 5.5% 5.5%
Flange 101.1 101.1 0.03 0.0% 0.0%
Flange 102.1 95.7 6.42 6.3% 6.3%
Flange 112.0 106.7 5.30 4.7% 4.7%
Valve 1.56 1.59 -0.03 -1.7% 1.7%
Valve 1.56 1.56 0.00 0.2% 0.2%
Valve 1.56 1.56 0.00 0.2% 0.2%
Valve 2.54 2.49 0.05 1.8% 1.8%
Valve 2.54 2.45 0.09 3.5% 3.5%
Valve 3.44 3.48 -0.04 -1.2% 1.2%
Valve 4.22 4.47 -0.25 -6.0% 6.0%
Valve 4.22 4.47 -0.25 -6.0% 6.0%
Valve 5.14 5.36 -0.22 -4.2% 4.2%
Valve 5.14 5.21 -0.07 -1.4% 1.4%
Valve 6.28 6.49 -0.21 -3.3% 3.3%
Valve 38.7 38.7 -0.09 -0.2% 0.2%
Valve 38.7 40.4 -1.74 -4.5% 4.5%
Valve 58.7 57.4 1.28 2.2% 2.2%
Valve 58.7 60.0 -1.30 -2.2% 2.2%
Valve 78.2 76.2 2.05 2.6% 2.6%
Valve 78.2 81.1 -2.92 -3.7% 3.7%
Connector 1.56 1.58 -0.02 -1.4% 1.4%
Connector 2.54 2.53 0.01 0.5% 0.5%
Connector 2.54 2.49 0.05 1.8% 1.8%
Connector 2.01 1.94 0.07 3.4% 3.4%
Connector 3.44 3.32 0.12 3.4% 3.4%
Connector 4.22 4.49 -0.27 -6.4% 6.4%
Connector 5.14 5.30 -0.16 -3.2% 3.2%
7/30/2019 Nov 2005 Kursk Project Report Mhc
15/33
15
Table A.1 (Continued)
Average Percent Difference = -0.2%
Average Percent Absolute Difference = 3.3%
Maximum Positive Difference = 11.1%
Maximum Negative Difference = -9.8%
Table A-2 shows the results of a similar experiment conducted as a demonstration at an EPA
contract laboratory using an EPA apparatus to simulate leaks from valve bodies, valve stems, and
flanges. In this case the average difference was -4.2% with a maximum difference of 10.5%.
Table A-2. Leak Measurement Sampler Compared to Metered Leaks (EPA Test Valve)
Type of Component Leak RateDifference
Rotameter - SamplerDifference/Rotameter
Abs. Value
Difference/Rotameter
Rotameter Sampler
Valve Body 8.03 8.64 -0.61 -7.6% 7.6%
Valve Body 8.03 8.18 -0.15 -1.9% 1.9%
Valve Stem 8.09 8.1 -0.01 -0.1% 0.1%
Valve Stem 8.09 8.43 -0.34 -4.2% 4.2%
Valve Stem 8.09 8.19 -0.10 -1.3% 1.3%
Flange 8.03 8.31 -0.28 -3.5% 3.5%
Flange 8.03 8.87 -0.84 -10.5% 10.5%
Average Percent Difference = -4.2%
Average Percent Absolute Difference = 4.2%
Maximum Positive Difference = None
Maximum Negative Difference = -10.5%
References
CMA, 1989. Improving Air Quality: Guidance for Estimating Fugitive Emissions fromEquipment. Chemical Manufacturer's Association, Washington, DC 20037.
Webb, M., and P. Martino, 1992. Fugitive Hydrocarbon Emissions from Petroleum ProductionOperations. Presented at the 85th Annual Meeting of the Air and Waste ManagementAssociation, Paper No. 92-66.11.
7/30/2019 Nov 2005 Kursk Project Report Mhc
16/33
16
Appendix II
Kursk Regulator Station Leak Rates Sorted by Leak Identification Number
7/30/2019 Nov 2005 Kursk Project Report Mhc
17/33
Appendix II: Kursk Leak Rates Sorted by Leak Identification Number
17
SiteVisit
NumberMeasurement
Date
LeakTag
NumberOperatingPressure
GenericDescription
LitersPer
Minute
LitersPer
HourLiters
Per/Year
TotalEmissions
m3/year
1 1-Nov-05 1/1 0.3 MPa Valve StemPacking
13.3 798 6,990,480 6,990
2 1-Nov-05 2/1 .003MPa Valve StemPacking
49 2940 25,754,400 25,754
2 1-Nov-05 2/2 0.3 MPa Valve StemPacking
6.1 366 3,206,160 3,206
2 1-Nov-05 2/3 0.3 MPa Flange 1.5 90 788,400 788
3 1-Nov-05 3/1 .003MPa Valve StemPacking
158.5 9510 83,307,600 83,308
4 1-Nov-05 4/1 .003MPa Valve StemPacking
6.6 396 3,468,960 3,469
4 1-Nov-05 4/2 0.003MPa Valve StemPacking
4.9 294 2,575,440 2,575
4 1-Nov-05 4/3 0.003MPa Valve StemPacking
1.5 90 788,400 788
5 1-Nov-05 5/1 0.003MPa Valve StemPacking
47.8 2868 25,123,680 25,124
6 1-Nov-05 6/1 0.003MPa Valve StemPacking
7 420 3,679,200 3,679
7 1-Nov-05 7/1 0.003MPa Valve StemPacking
2 120 1,051,200 1,051
7 1-Nov-05 7/2 0.3MPa Valve StemPacking
0.3 18 157,680 158
7 1-Nov-05 7/3 0.003MPa Valve Stem
Packing
6.1 366 3,206,160 3,206
7 1-Nov-05 7/4 0.3MPa Valve StemPacking
13 780 6,832,800 6,833
7 1-Nov-05 7/5 0.003MPa Valve StemPacking
7.9 474 4,152,240 4,152
7 1-Nov-05 7/6 0.003MPa Valve StemPacking
0.2 12 105,120 105
8 1-Nov-05 8/1 0.003MPa Valve StemPacking
1.4 84 735,840 736
9 1-Nov-05 9/1 0.3MPa Valve StemPacking
20.5 1230 10,774,800 10,775
10 1-Nov-05 10/1 0.003MPa Valve StemPacking
35.6 2136 18,711,360 18,711
11 1-Nov-05 11/1 0.3MPa Valve StemPacking
21.9 1314 11,510,640 11,511
11 1-Nov-05 11/2 0.003MPa Valve StemPacking
3.4 204 1,787,040 1,787
11 1-Nov-05 11/3 0.003MPa Valve StemPacking
4.2 252 2,207,520 2,208
7/30/2019 Nov 2005 Kursk Project Report Mhc
18/33
Appendix II: Kursk Leak Rates Sorted by Leak Identification Number
18
SiteVisit
NumberMeasurement
Date
LeakTag
NumberOperatingPressure
GenericDescription
LitersPer
Minute
LitersPer
HourLiters
Per/Year
TotalEmissions
m3/year
12 2-Nov-05 12/1 0.003MPa Valve StemPacking
18 1080 9,460,800 9,461
12 2-Nov-05 12/2 0.003MPa Valve StemPacking
1.8 108 946,080 946
12 2-Nov-05 12/3 0.003MPa Valve StemPacking
4.2 252 2,207,520 2,208
12 2-Nov-05 12/4 0.003MPa Valve StemPacking
2.7 162 1,419,120 1,419
13 2-Nov-05 13/1 0.003MPa Valve StemPacking
16.7 1002 8,777,520 8,778
13 2-Nov-05 13/2 0.003MPa Valve StemPacking
13.1 786 6,885,360 6,885
13 2-Nov-05 13/3 0.003MPa Valve StemPacking
3.6 216 1,892,160 1,892
13 2-Nov-05 13/4 0.003MPa Valve StemPacking
6 360 3,153,600 3,154
13 2-Nov-05 13/5 0.003MPa Valve StemPacking
2.1 126 1,103,760 1,104
14 2-Nov-05 14/1 0.003MPa Valve StemPacking
20.9 1254 10,985,040 10,985
15 2-Nov-05 15/1 0.003MPa Valve StemPacking
20.3 1218 10,669,680 10,670
16 2-Nov-05 16/1 0.003MPa Valve StemPacking
16.3 978 8,567,280 8,567
17 2-Nov-05 17/1 0.003MPa Valve Stem
Packing
37 2220 19,447,200 19,447
17 2-Nov-05 17/2 0.003MPa Valve StemPacking
2.1 126 1,103,760 1,104
17 2-Nov-05 17/3 0.003MPa Valve StemPacking
18 1080 9,460,800 9,461
18 2-Nov-05 18/1 0.003MPa Valve StemPacking
11.5 690 6,044,400 6,044
19 2-Nov-05 19/1 0.003MPa Valve StemPacking
72.9 4374 38,316,240 38,316
19 2-Nov-05 19/2 0.003MPa Valve StemPacking
4.9 294 2,575,440 2,575
20 2-Nov-05 20/1 0.003MPa Valve StemPacking
8.8 528 4,625,280 4,625
20 2-Nov-05 20/2 0.003MPa Valve StemPacking
1.3 78 683,280 683
21 3-Nov-05 21/1 0.003MPa Valve StemPacking
35 2100 18,396,000 18,396
22 3-Nov-05 22/1 0.003MPa PressureRelief Valve
11 660 5,781,600 5,782
7/30/2019 Nov 2005 Kursk Project Report Mhc
19/33
Appendix II: Kursk Leak Rates Sorted by Leak Identification Number
19
SiteVisit
NumberMeasurement
Date
LeakTag
NumberOperatingPressure
GenericDescription
LitersPer
Minute
LitersPer
HourLiters
Per/Year
TotalEmissions
m3/year
23 3-Nov-05 23/1 0.003MPa Valve StemPacking
31.2 1872 16,398,720 16,399
24 3-Nov-05 24/1 0.3MPa Valve StemPacking
2.7 162 1,419,120 1,419
24 3-Nov-05 24/2 0.04MPa Valve StemPacking
4.5 270 2,365,200 2,365
24 3-Nov-05 24/3 0.3MPa Valve StemPacking
3.6 216 1,892,160 1,892
25 3-Nov-05 25/1 0.003MPa Valve StemPacking
7.9 474 4,152,240 4,152
25 3-Nov-05 25/2 0.003MPa Valve StemPacking
7.5 450 3,942,000 3,942
25 3-Nov-05 25/3 0.003MPa Valve StemPacking
4.4 264 2,312,640 2,313
25 3-Nov-05 25/4 0.003MPa Valve StemPacking
14.8 888 7,778,880 7,779
26 3-Nov-05 26/1 0.003MPa Valve StemPacking
23.3 1398 12,246,480 12,246
26 3-Nov-05 26/2 0.003MPa Valve StemPacking
6.7 402 3,521,520 3,522
26 3-Nov-05 26/3 0.003MPa Valve StemPacking
3.5 210 1,839,600 1,840
26 3-Nov-05 26/4 0.003MPa Valve StemPacking
9.1 546 4,782,960 4,783
27 3-Nov-05 27/1 0.003MPa Valve Stem
Packing
9.3 558 4,888,080 4,888
27 3-Nov-05 27/2 0.3MPa Valve StemPacking
12 720 6,307,200 6,307
28 3-Nov-05 28/1 0.003MPa Valve StemPacking
3 180 1,576,800 1,577
29 3-Nov-05 29/1 0.003MPa Valve StemPacking
21.9 1314 11,510,640 11,511
29 3-Nov-05 29/2 0.3MPa Valve StemPacking
9.4 564 4,940,640 4,941
29 3-Nov-05 29/3 0.003MPa Valve StemPacking
4.7 282 2,470,320 2,470
30 4-Nov-05 30/1 0.003MPa Valve StemPacking
14.6 876 7,673,760 7,674
31 4-Nov-05 31/1 0.003MPa PressureRelief Valve
38.1 2286 20,025,360 20,025
31 4-Nov-05 31/2 0.003MPa Valve StemPacking
19.4 1164 10,196,640 10,197
31 4-Nov-05 31/3 0.3MPa Valve StemPacking
3 180 1,576,800 1,577
7/30/2019 Nov 2005 Kursk Project Report Mhc
20/33
Appendix II: Kursk Leak Rates Sorted by Leak Identification Number
20
SiteVisit
NumberMeasurement
Date
LeakTag
NumberOperatingPressure
GenericDescription
LitersPer
Minute
LitersPer
HourLiters
Per/Year
TotalEmissions
m3/year
31 4-Nov-05 31/4 0.003MPa Valve StemPacking
25 1500 13,140,000 13,140
31 4-Nov-05 31/5 0.003MPa Valve StemPacking
1.9 114 998,640 999
32 4-Nov-05 32/1 0.003MPa Valve StemPacking
10.6 636 5,571,360 5,571
32 4-Nov-05 32/2 0.003MPa Valve StemPacking
1.1 66 578,160 578
32 4-Nov-05 32/3 0.3MPa Valve StemPacking
3.6 216 1,892,160 1,892
33 4-Nov-05 33/1 0.003MPa Valve StemPacking
47.3 2838 24,860,880 24,861
33 4-Nov-05 33/2 0.003MPa PressureRelief Valve
83.3 4998 43,782,480 43,782
33 4-Nov-05 33/3 0.003MPa Valve StemPacking
2.7 162 1,419,120 1,419
33 4-Nov-05 33/4 0.003MPa Valve StemPacking
97.2 5832 51,088,320 51,088
33 4-Nov-05 33/5 0.003MPa Valve StemPacking
10.8 648 5,676,480 5,676
36 7-Nov-05 36/1 0.003MPa Valve StemPacking
35.8 2148 18,816,480 18,816
36 7-Nov-05 36/2 0.3MPa Valve StemPacking
227.7 13662 119,679,120 119,679
36 7-Nov-05 36/3 0.3MPa Valve Stem
Packing
4.7 282 2,470,320 2,470
36 7-Nov-05 36/4 0.003MPa Valve StemPacking
64.1 3846 33,690,960 33,691
36 7-Nov-05 36/5 0.003MPa Valve StemPacking
13.5 810 7,095,600 7,096
36 7-Nov-05 36/6 0.003MPa Valve StemPacking
1.7 102 893,520 894
37 8-Nov-05 37/1 0.003MPa Valve StemPacking
19.4 1164 10,196,640 10,197
37 8-Nov-05 37/2 0.3MPa Valve StemPacking
47.7 2862 25,071,120 25,071
37 8-Nov-05 37/3 0.003MPa Valve StemPacking
1 60 525,600 526
37 8-Nov-05 37/4 0.003MPa Valve StemPacking
14.6 876 7,673,760 7,674
38 9-Nov-05 38/1 0.003MPa Valve StemPacking
4 240 2,102,400 2,102
39 9-Nov-05 39/1 0.003MPa Valve StemPacking
3.7 222 1,944,720 1,945
7/30/2019 Nov 2005 Kursk Project Report Mhc
21/33
Appendix II: Kursk Leak Rates Sorted by Leak Identification Number
21
SiteVisit
NumberMeasurement
Date
LeakTag
NumberOperatingPressure
GenericDescription
LitersPer
Minute
LitersPer
HourLiters
Per/Year
TotalEmissions
m3/year
41 9-Nov-05 41/1 0.003MPa Valve StemPacking
5.2 312 2,733,120 2,733
41 9-Nov-05 41/2 0.003MPa Valve StemPacking
4.6 276 2,417,760 2,418
42 9-Nov-05 42/1 0.003MPa Valve StemPacking
9.6 576 5,045,760 5,046
43 9-Nov-05 43/1 0.003MPa Valve StemPacking
4.2 252 2,207,520 2,208
44 9-Nov-05 44/1 0.003MPa Valve StemPacking
0.2 12 105,120 105
45 9-Nov-05 45/1 0.003MPa Valve StemPacking
7 420 3,679,200 3,679
0 0 0
Total Leak Rate 1747.7 104862 918,591,120 918,591Total Number of Leaks 94
Number of Components Counted 1007
Number of Stations Inspected 47
Emission Factor Per Component(all)
1.7 104.133 912,206 912
7/30/2019 Nov 2005 Kursk Project Report Mhc
22/33
22
Appendix III
Kursk Regulator Station Leak Rates Sorted by Component Category with
Emission Factors
7/30/2019 Nov 2005 Kursk Project Report Mhc
23/33
Appendix III: Kursk Leak Rates Sorted by Component Category with Emission Factors
23
SiteVisit
NumberMeasurement
Date
LeakTag
NumberOperatingPressure
GenericDescription
LitersPer
Minute
LitersPer
HourLiters
Per/Year
TotalEmissions
m3/year
36 7-Nov-05 36/2 0.3MPa Valve StemPacking
227.7 13662 119,679,120 119,679
3 1-Nov-05 3/1 .003MPa Valve StemPacking
158.5 9510 83,307,600 83,308
33 4-Nov-05 33/4 0.003MPa Valve StemPacking
97.2 5832 51,088,320 51,088
19 2-Nov-05 19/1 0.003MPa Valve StemPacking
72.9 4374 38,316,240 38,316
36 7-Nov-05 36/4 0.003MPa Valve StemPacking
64.1 3846 33,690,960 33,691
2 1-Nov-05 2/1 .003MPa Valve StemPacking
49 2940 25,754,400 25,754
5 1-Nov-05 5/1 0.003MPa Valve StemPacking
47.8 2868 25,123,680 25,124
37 8-Nov-05 37/2 0.3MPa Valve StemPacking
47.7 2862 25,071,120 25,071
33 4-Nov-05 33/1 0.003MPa Valve StemPacking
47.3 2838 24,860,880 24,861
17 2-Nov-05 17/1 0.003MPa Valve StemPacking
37 2220 19,447,200 19,447
36 7-Nov-05 36/1 0.003MPa Valve StemPacking
35.8 2148 18,816,480 18,816
10 1-Nov-05 10/1 0.003MPa Valve StemPacking
35.6 2136 18,711,360 18,711
21 3-Nov-05 21/1 0.003MPa Valve Stem
Packing
35 2100 18,396,000 18,396
23 3-Nov-05 23/1 0.003MPa Valve StemPacking
31.2 1872 16,398,720 16,399
31 4-Nov-05 31/4 0.003MPa Valve StemPacking
25 1500 13,140,000 13,140
26 3-Nov-05 26/1 0.003MPa Valve StemPacking
23.3 1398 12,246,480 12,246
11 1-Nov-05 11/1 0.3MPa Valve StemPacking
21.9 1314 11,510,640 11,511
29 3-Nov-05 29/1 0.003MPa Valve StemPacking
21.9 1314 11,510,640 11,511
14 2-Nov-05 14/1 0.003MPa Valve StemPacking
20.9 1254 10,985,040 10,985
9 1-Nov-05 9/1 0.3MPa Valve StemPacking
20.5 1230 10,774,800 10,775
15 2-Nov-05 15/1 0.003MPa Valve StemPacking
20.3 1218 10,669,680 10,670
31 4-Nov-05 31/2 0.003MPa Valve StemPacking
19.4 1164 10,196,640 10,197
7/30/2019 Nov 2005 Kursk Project Report Mhc
24/33
Appendix III: Kursk Leak Rates Sorted by Component Category with Emission Factors
24
SiteVisit
NumberMeasurement
Date
LeakTag
NumberOperatingPressure
GenericDescription
LitersPer
Minute
LitersPer
HourLiters
Per/Year
TotalEmissions
m3/year
37 8-Nov-05 37/1 0.003MPa Valve StemPacking
19.4 1164 10,196,640 10,197
12 2-Nov-05 12/1 0.003MPa Valve StemPacking
18 1080 9,460,800 9,461
17 2-Nov-05 17/3 0.003MPa Valve StemPacking
18 1080 9,460,800 9,461
13 2-Nov-05 13/1 0.003MPa Valve StemPacking
16.7 1002 8,777,520 8,778
16 2-Nov-05 16/1 0.003MPa Valve StemPacking
16.3 978 8,567,280 8,567
25 3-Nov-05 25/4 0.003MPa Valve StemPacking
14.8 888 7,778,880 7,779
30 4-Nov-05 30/1 0.003MPa Valve StemPacking
14.6 876 7,673,760 7,674
37 8-Nov-05 37/4 0.003MPa Valve StemPacking
14.6 876 7,673,760 7,674
36 7-Nov-05 36/5 0.003MPa Valve StemPacking
13.5 810 7,095,600 7,096
1 1-Nov-05 1/1 0.3 MPa Valve StemPacking
13.3 798 6,990,480 6,990
13 2-Nov-05 13/2 0.003MPa Valve StemPacking
13.1 786 6,885,360 6,885
7 1-Nov-05 7/4 0.3MPa Valve StemPacking
13 780 6,832,800 6,833
27 3-Nov-05 27/2 0.3MPa Valve Stem
Packing
12 720 6,307,200 6,307
18 2-Nov-05 18/1 0.003MPa Valve StemPacking
11.5 690 6,044,400 6,044
33 4-Nov-05 33/5 0.003MPa Valve StemPacking
10.8 648 5,676,480 5,676
32 4-Nov-05 32/1 0.003MPa Valve StemPacking
10.6 636 5,571,360 5,571
42 9-Nov-05 42/1 0.003MPa Valve StemPacking
9.6 576 5,045,760 5,046
29 3-Nov-05 29/2 0.3MPa Valve StemPacking
9.4 564 4,940,640 4,941
27 3-Nov-05 27/1 0.003MPa Valve StemPacking
9.3 558 4,888,080 4,888
26 3-Nov-05 26/4 0.003MPa Valve StemPacking
9.1 546 4,782,960 4,783
20 2-Nov-05 20/1 0.003MPa Valve StemPacking
8.8 528 4,625,280 4,625
7 1-Nov-05 7/5 0.003MPa Valve StemPacking
7.9 474 4,152,240 4,152
7/30/2019 Nov 2005 Kursk Project Report Mhc
25/33
Appendix III: Kursk Leak Rates Sorted by Component Category with Emission Factors
25
SiteVisit
NumberMeasurement
Date
LeakTag
NumberOperatingPressure
GenericDescription
LitersPer
Minute
LitersPer
HourLiters
Per/Year
TotalEmissions
m3/year
25 3-Nov-05 25/1 0.003MPa Valve StemPacking
7.9 474 4,152,240 4,152
25 3-Nov-05 25/2 0.003MPa Valve StemPacking
7.5 450 3,942,000 3,942
6 1-Nov-05 6/1 0.003MPa Valve StemPacking
7 420 3,679,200 3,679
45 9-Nov-05 45/1 0.003MPa Valve StemPacking
7 420 3,679,200 3,679
26 3-Nov-05 26/2 0.003MPa Valve StemPacking
6.7 402 3,521,520 3,522
4 1-Nov-05 4/1 .003MPa Valve StemPacking
6.6 396 3,468,960 3,469
2 1-Nov-05 2/2 0.3 MPa Valve StemPacking
6.1 366 3,206,160 3,206
7 1-Nov-05 7/3 0.003MPa Valve StemPacking
6.1 366 3,206,160 3,206
13 2-Nov-05 13/4 0.003MPa Valve StemPacking
6 360 3,153,600 3,154
41 9-Nov-05 41/1 0.003MPa Valve StemPacking
5.2 312 2,733,120 2,733
4 1-Nov-05 4/2 0.003MPa Valve StemPacking
4.9 294 2,575,440 2,575
19 2-Nov-05 19/2 0.003MPa Valve StemPacking
4.9 294 2,575,440 2,575
29 3-Nov-05 29/3 0.003MPa Valve Stem
Packing
4.7 282 2,470,320 2,470
36 7-Nov-05 36/3 0.3MPa Valve StemPacking
4.7 282 2,470,320 2,470
41 9-Nov-05 41/2 0.003MPa Valve StemPacking
4.6 276 2,417,760 2,418
24 3-Nov-05 24/2 0.04MPa Valve StemPacking
4.5 270 2,365,200 2,365
25 3-Nov-05 25/3 0.003MPa Valve StemPacking
4.4 264 2,312,640 2,313
11 1-Nov-05 11/3 0.003MPa Valve StemPacking
4.2 252 2,207,520 2,208
12 2-Nov-05 12/3 0.003MPa Valve StemPacking
4.2 252 2,207,520 2,208
43 9-Nov-05 43/1 0.003MPa Valve StemPacking
4.2 252 2,207,520 2,208
38 9-Nov-05 38/1 0.003MPa Valve StemPacking
4 240 2,102,400 2,102
39 9-Nov-05 39/1 0.003MPa Valve StemPacking
3.7 222 1,944,720 1,945
7/30/2019 Nov 2005 Kursk Project Report Mhc
26/33
Appendix III: Kursk Leak Rates Sorted by Component Category with Emission Factors
26
SiteVisit
NumberMeasurement
Date
LeakTag
NumberOperatingPressure
GenericDescription
LitersPer
Minute
LitersPer
HourLiters
Per/Year
TotalEmissions
m3/year
13 2-Nov-05 13/3 0.003MPa Valve StemPacking
3.6 216 1,892,160 1,892
24 3-Nov-05 24/3 0.3MPa Valve StemPacking
3.6 216 1,892,160 1,892
32 4-Nov-05 32/3 0.3MPa Valve StemPacking
3.6 216 1,892,160 1,892
26 3-Nov-05 26/3 0.003MPa Valve StemPacking
3.5 210 1,839,600 1,840
11 1-Nov-05 11/2 0.003MPa Valve StemPacking
3.4 204 1,787,040 1,787
28 3-Nov-05 28/1 0.003MPa Valve StemPacking
3 180 1,576,800 1,577
31 4-Nov-05 31/3 0.3MPa Valve StemPacking
3 180 1,576,800 1,577
12 2-Nov-05 12/4 0.003MPa Valve StemPacking
2.7 162 1,419,120 1,419
24 3-Nov-05 24/1 0.3MPa Valve StemPacking
2.7 162 1,419,120 1,419
33 4-Nov-05 33/3 0.003MPa Valve StemPacking
2.7 162 1,419,120 1,419
13 2-Nov-05 13/5 0.003MPa Valve StemPacking
2.1 126 1,103,760 1,104
17 2-Nov-05 17/2 0.003MPa Valve StemPacking
2.1 126 1,103,760 1,104
7 1-Nov-05 7/1 0.003MPa Valve Stem
Packing
2 120 1,051,200 1,051
31 4-Nov-05 31/5 0.003MPa Valve StemPacking
1.9 114 998,640 999
12 2-Nov-05 12/2 0.003MPa Valve StemPacking
1.8 108 946,080 946
36 7-Nov-05 36/6 0.003MPa Valve StemPacking
1.7 102 893,520 894
4 1-Nov-05 4/3 0.003MPa Valve StemPacking
1.5 90 788,400 788
8 1-Nov-05 8/1 0.003MPa Valve StemPacking
1.4 84 735,840 736
20 2-Nov-05 20/2 0.003MPa Valve StemPacking
1.3 78 683,280 683
32 4-Nov-05 32/2 0.003MPa Valve StemPacking
1.1 66 578,160 578
37 8-Nov-05 37/3 0.003MPa Valve StemPacking
1 60 525,600 526
7 1-Nov-05 7/2 0.3MPa Valve StemPacking
0.3 18 157,680 158
7/30/2019 Nov 2005 Kursk Project Report Mhc
27/33
Appendix III: Kursk Leak Rates Sorted by Component Category with Emission Factors
27
SiteVisit
NumberMeasurement
Date
LeakTag
NumberOperatingPressure
GenericDescription
LitersPer
Minute
LitersPer
HourLiters
Per/Year
TotalEmissions
m3/year
7 1-Nov-05 7/6 0.003MPa Valve StemPacking
0.2 12 105,120 105
44 9-Nov-05 44/1 0.003MPa Valve StemPacking
0.2 12 105,120 105
(LPM) (LPH) (Liters/Yr) (M3/Year)
Total Leak Rate for Valves 1613.8 96828 848213280 848213.3
Total Valves Screened 244
Emission Factor (per component) 6.61 396.8 3,476,284 3,476
33 4-Nov-05 33/2 0.003MPa PressureRelief Valve
83.3 4998 43,782,480 43,782
31 4-Nov-05 31/1 0.003MPa PressureRelief Valve
38.1 2286 20,025,360 20,025
22 3-Nov-05 22/1 0.003MPa PressureRelief Valve
11 660 5,781,600 5,782
(LPM) (LPH) (Liters/Yr) (M3/Year)
Total Leak Rate for PressureRelief Valves
132.4 7944 69589440 69589.44
Total PRVs Screened 36
Emission Factor (per component) 3.68 220.7 1,933,040 1,933
2 1-Nov-05 2/3 0.3 MPa Flange 1.5 90 788,400 788
(LPM) (LPH) (Liters/Yr) (M3/Year)
Total Leak Rate for Flanges 1.5 90 788400 788.4
Total Flanges Screened 727
Emission Factor (per component) 0.002 0.124 1084.46 1.08
7/30/2019 Nov 2005 Kursk Project Report Mhc
28/33
28
Appendix IV
Kursk Regulator Station Leak Rates Measurements Sorted by Leak Rate
7/30/2019 Nov 2005 Kursk Project Report Mhc
29/33
Appendix IV: Kursk Leak Rates Sorted by Leak Rate
29
SiteVisit
Number
MeasurementDate
LeakTag
Number
OperatingPressure
GenericDescription
LitersPer
Minute
LitersPer
Hour
LitersPer/Year
TotalEmissions
m3/year
36 7-Nov-05 36/2 0.3MPa Valve StemPacking
227.7 13662 119,679,120 119,679
3 1-Nov-05 3/1 .003MPa Valve StemPacking
158.5 9510 83,307,600 83,308
33 4-Nov-05 33/4 0.003MPa Valve StemPacking
97.2 5832 51,088,320 51,088
33 4-Nov-05 33/2 0.003MPa PressureRelief Valve
83.3 4998 43,782,480 43,782
19 2-Nov-05 19/1 0.003MPa Valve StemPacking
72.9 4374 38,316,240 38,316
36 7-Nov-05 36/4 0.003MPa Valve StemPacking
64.1 3846 33,690,960 33,691
2 1-Nov-05 2/1 .003MPa Valve StemPacking
49 2940 25,754,400 25,754
5 1-Nov-05 5/1 0.003MPa Valve StemPacking
47.8 2868 25,123,680 25,124
37 8-Nov-05 37/2 0.3MPa Valve StemPacking
47.7 2862 25,071,120 25,071
33 4-Nov-05 33/1 0.003MPa Valve StemPacking
47.3 2838 24,860,880 24,861
31 4-Nov-05 31/1 0.003MPa PressureRelief Valve
38.1 2286 20,025,360 20,025
17 2-Nov-05 17/1 0.003MPa Valve StemPacking
37 2220 19,447,200 19,447
36 7-Nov-05 36/1 0.003MPa Valve Stem
Packing
35.8 2148 18,816,480 18,816
10 1-Nov-05 10/1 0.003MPa Valve StemPacking
35.6 2136 18,711,360 18,711
21 3-Nov-05 21/1 0.003MPa Valve StemPacking
35 2100 18,396,000 18,396
23 3-Nov-05 23/1 0.003MPa Valve StemPacking
31.2 1872 16,398,720 16,399
31 4-Nov-05 31/4 0.003MPa Valve StemPacking
25 1500 13,140,000 13,140
26 3-Nov-05 26/1 0.003MPa Valve StemPacking
23.3 1398 12,246,480 12,246
11 1-Nov-05 11/1 0.3MPa Valve StemPacking
21.9 1314 11,510,640 11,511
29 3-Nov-05 29/1 0.003MPa Valve StemPacking
21.9 1314 11,510,640 11,511
14 2-Nov-05 14/1 0.003MPa Valve StemPacking
20.9 1254 10,985,040 10,985
9 1-Nov-05 9/1 0.3MPa Valve StemPacking
20.5 1230 10,774,800 10,775
7/30/2019 Nov 2005 Kursk Project Report Mhc
30/33
Appendix IV: Kursk Leak Rates Sorted by Leak Rate
30
SiteVisit
Number
MeasurementDate
LeakTag
Number
OperatingPressure
GenericDescription
LitersPer
Minute
LitersPer
Hour
LitersPer/Year
TotalEmissions
m3/year
15 2-Nov-05 15/1 0.003MPa Valve StemPacking
20.3 1218 10,669,680 10,670
31 4-Nov-05 31/2 0.003MPa Valve StemPacking
19.4 1164 10,196,640 10,197
37 8-Nov-05 37/1 0.003MPa Valve StemPacking
19.4 1164 10,196,640 10,197
12 2-Nov-05 12/1 0.003MPa Valve StemPacking
18 1080 9,460,800 9,461
17 2-Nov-05 17/3 0.003MPa Valve StemPacking
18 1080 9,460,800 9,461
13 2-Nov-05 13/1 0.003MPa Valve StemPacking
16.7 1002 8,777,520 8,778
16 2-Nov-05 16/1 0.003MPa Valve StemPacking
16.3 978 8,567,280 8,567
25 3-Nov-05 25/4 0.003MPa Valve StemPacking
14.8 888 7,778,880 7,779
30 4-Nov-05 30/1 0.003MPa Valve StemPacking
14.6 876 7,673,760 7,674
37 8-Nov-05 37/4 0.003MPa Valve StemPacking
14.6 876 7,673,760 7,674
36 7-Nov-05 36/5 0.003MPa Valve StemPacking
13.5 810 7,095,600 7,096
1 1-Nov-05 1/1 0.3 MPa Valve StemPacking
13.3 798 6,990,480 6,990
13 2-Nov-05 13/2 0.003MPa Valve Stem
Packing
13.1 786 6,885,360 6,885
7 1-Nov-05 7/4 0.3MPa Valve StemPacking
13 780 6,832,800 6,833
27 3-Nov-05 27/2 0.3MPa Valve StemPacking
12 720 6,307,200 6,307
18 2-Nov-05 18/1 0.003MPa Valve StemPacking
11.5 690 6,044,400 6,044
22 3-Nov-05 22/1 0.003MPa PressureRelief Valve
11 660 5,781,600 5,782
33 4-Nov-05 33/5 0.003MPa Valve StemPacking
10.8 648 5,676,480 5,676
32 4-Nov-05 32/1 0.003MPa Valve StemPacking
10.6 636 5,571,360 5,571
42 9-Nov-05 42/1 0.003MPa Valve StemPacking
9.6 576 5,045,760 5,046
29 3-Nov-05 29/2 0.3MPa Valve StemPacking
9.4 564 4,940,640 4,941
27 3-Nov-05 27/1 0.003MPa Valve StemPacking
9.3 558 4,888,080 4,888
7/30/2019 Nov 2005 Kursk Project Report Mhc
31/33
Appendix IV: Kursk Leak Rates Sorted by Leak Rate
31
SiteVisit
Number
MeasurementDate
LeakTag
Number
OperatingPressure
GenericDescription
LitersPer
Minute
LitersPer
Hour
LitersPer/Year
TotalEmissions
m3/year
26 3-Nov-05 26/4 0.003MPa Valve StemPacking
9.1 546 4,782,960 4,783
20 2-Nov-05 20/1 0.003MPa Valve StemPacking
8.8 528 4,625,280 4,625
7 1-Nov-05 7/5 0.003MPa Valve StemPacking
7.9 474 4,152,240 4,152
25 3-Nov-05 25/1 0.003MPa Valve StemPacking
7.9 474 4,152,240 4,152
25 3-Nov-05 25/2 0.003MPa Valve StemPacking
7.5 450 3,942,000 3,942
6 1-Nov-05 6/1 0.003MPa Valve StemPacking
7 420 3,679,200 3,679
45 9-Nov-05 45/1 0.003MPa Valve StemPacking
7 420 3,679,200 3,679
26 3-Nov-05 26/2 0.003MPa Valve StemPacking
6.7 402 3,521,520 3,522
4 1-Nov-05 4/1 .003MPa Valve StemPacking
6.6 396 3,468,960 3,469
2 1-Nov-05 2/2 0.3 MPa Valve StemPacking
6.1 366 3,206,160 3,206
7 1-Nov-05 7/3 0.003MPa Valve StemPacking
6.1 366 3,206,160 3,206
13 2-Nov-05 13/4 0.003MPa Valve StemPacking
6 360 3,153,600 3,154
41 9-Nov-05 41/1 0.003MPa Valve Stem
Packing
5.2 312 2,733,120 2,733
4 1-Nov-05 4/2 0.003MPa Valve StemPacking
4.9 294 2,575,440 2,575
19 2-Nov-05 19/2 0.003MPa Valve StemPacking
4.9 294 2,575,440 2,575
29 3-Nov-05 29/3 0.003MPa Valve StemPacking
4.7 282 2,470,320 2,470
36 7-Nov-05 36/3 0.3MPa Valve StemPacking
4.7 282 2,470,320 2,470
41 9-Nov-05 41/2 0.003MPa Valve StemPacking
4.6 276 2,417,760 2,418
24 3-Nov-05 24/2 0.04MPa Valve StemPacking
4.5 270 2,365,200 2,365
25 3-Nov-05 25/3 0.003MPa Valve StemPacking
4.4 264 2,312,640 2,313
11 1-Nov-05 11/3 0.003MPa Valve StemPacking
4.2 252 2,207,520 2,208
12 2-Nov-05 12/3 0.003MPa Valve StemPacking
4.2 252 2,207,520 2,208
7/30/2019 Nov 2005 Kursk Project Report Mhc
32/33
Appendix IV: Kursk Leak Rates Sorted by Leak Rate
32
SiteVisit
Number
MeasurementDate
LeakTag
Number
OperatingPressure
GenericDescription
LitersPer
Minute
LitersPer
Hour
LitersPer/Year
TotalEmissions
m3/year
43 9-Nov-05 43/1 0.003MPa Valve StemPacking
4.2 252 2,207,520 2,208
38 9-Nov-05 38/1 0.003MPa Valve StemPacking
4 240 2,102,400 2,102
39 9-Nov-05 39/1 0.003MPa Valve StemPacking
3.7 222 1,944,720 1,945
13 2-Nov-05 13/3 0.003MPa Valve StemPacking
3.6 216 1,892,160 1,892
24 3-Nov-05 24/3 0.3MPa Valve StemPacking
3.6 216 1,892,160 1,892
32 4-Nov-05 32/3 0.3MPa Valve StemPacking
3.6 216 1,892,160 1,892
26 3-Nov-05 26/3 0.003MPa Valve StemPacking
3.5 210 1,839,600 1,840
11 1-Nov-05 11/2 0.003MPa Valve StemPacking
3.4 204 1,787,040 1,787
28 3-Nov-05 28/1 0.003MPa Valve StemPacking
3 180 1,576,800 1,577
31 4-Nov-05 31/3 0.3MPa Valve StemPacking
3 180 1,576,800 1,577
12 2-Nov-05 12/4 0.003MPa Valve StemPacking
2.7 162 1,419,120 1,419
24 3-Nov-05 24/1 0.3MPa Valve StemPacking
2.7 162 1,419,120 1,419
33 4-Nov-05 33/3 0.003MPa Valve Stem
Packing
2.7 162 1,419,120 1,419
13 2-Nov-05 13/5 0.003MPa Valve StemPacking
2.1 126 1,103,760 1,104
17 2-Nov-05 17/2 0.003MPa Valve StemPacking
2.1 126 1,103,760 1,104
7 1-Nov-05 7/1 0.003MPa Valve StemPacking
2 120 1,051,200 1,051
31 4-Nov-05 31/5 0.003MPa Valve StemPacking
1.9 114 998,640 999
12 2-Nov-05 12/2 0.003MPa Valve StemPacking
1.8 108 946,080 946
36 7-Nov-05 36/6 0.003MPa Valve StemPacking
1.7 102 893,520 894
2 1-Nov-05 2/3 0.3 MPa Flange 1.5 90 788,400 788
4 1-Nov-05 4/3 0.003MPa Valve StemPacking
1.5 90 788,400 788
8 1-Nov-05 8/1 0.003MPa Valve StemPacking
1.4 84 735,840 736
7/30/2019 Nov 2005 Kursk Project Report Mhc
33/33
Appendix IV: Kursk Leak Rates Sorted by Leak Rate
SiteVisit
Number
MeasurementDate
LeakTag
Number
OperatingPressure
GenericDescription
LitersPer
Minute
LitersPer
Hour
LitersPer/Year
TotalEmissions
m3/year
20 2-Nov-05 20/2 0.003MPa Valve StemPacking
1.3 78 683,280 683
32 4-Nov-05 32/2 0.003MPa Valve StemPacking
1.1 66 578,160 578
37 8-Nov-05 37/3 0.003MPa Valve StemPacking
1 60 525,600 526
7 1-Nov-05 7/2 0.3MPa Valve StemPacking
0.3 18 157,680 158
7 1-Nov-05 7/6 0.003MPa Valve StemPacking
0.2 12 105,120 105
44 9-Nov-05 44/1 0.003MPa Valve StemPacking
0.2 12 105,120 105
0 0 0
Total Leak Rate 1361.5 81690 715,604,400 715,604
Total Number of Leaks 94
Number of Components Counted 1007
Number of Stations Inspected 47
Emission Factor Per Component 1.4 81.1221 710,630 711