NOV-3733-SL-9347 Carbones KOM - May 10-11, 2010 – Toulouse, France
1
KICK-OFF MEETING
May 10-11, 2010
NOV-3733-SL-9347 Carbones KOM - May 10-11, 2010 – Toulouse, France
2
1.1. Work Breakdown into Work Packages Work Breakdown into Work Packages and partnersand partners
2.2. Study LogicStudy Logic
3.3. DeliverablesDeliverables
4.4. ScheduleSchedule
Introduction
NOV-3733-SL-9347 Carbones KOM - May 10-11, 2010 – Toulouse, France
4
Work Breakdown into WP and Partners
0
10
20
30
40
50
60
70
80
90
WP000 WP100 WP200 WP300 WP400 WP500 WP600 WP700
NOV
CEA-LSCE
CERC
MPI-BGC
AEA
TAS-F
ETH
DLO
USTUTT
PKU
UNIABDN
METO
EFI
CLIMMOD
Man M
onth
NOV-3733-SL-9347 Carbones KOM - May 10-11, 2010 – Toulouse, France
7
Deliverables
Formal deliverables to ECFormal deliverables to EC List will be maintained by CoordinatorList will be maintained by Coordinator Each deliverable under WP responsabilities, provided to deliverable under WP responsabilities, provided to
Coordinator for validation and delivery to ECCoordinator for validation and delivery to EC
→ The T0+6/12M deliverables list is recalled in the next slidesThe T0+6/12M deliverables list is recalled in the next slides
Internal deliveries followed by the Internal deliveries followed by the coordinator:coordinator: To ensure the smooth running of the projectTo ensure the smooth running of the project To have access of the correct level of monitoringhave access of the correct level of monitoring
→ Process of monitoring of the internal deliverables is illustrated Process of monitoring of the internal deliverables is illustrated with exampleswith examples
NOV-3733-SL-9347 Carbones KOM - May 10-11, 2010 – Toulouse, France
8
Formal Deliverables
Del. no.
Deliverable nameLead
beneficiary
Dissemination
levelDelivery date
D0.1 Project presentation (M 0) NOV PU Kick-Off Meeting
D300.2
Report on all data stream that CARBONES could
benefit + Assessment of the accessibility and of the necessary
mechanisms to grant the access.
MPI-BGC PU First version → Kick-Off Meeting
D120.1
CUAG meeting #1 minutes METO PU T0+5 → 1st September, 2010
D120.2
User requirements report V0 METO PU T0+5 → 1st September, 2010
D210.1
System Requirements synthesis and justification
TASF PU T0+6 → 1st October, 2010
D220.2
Document on the complementarities with other
EU/National projects and outside Europe if relevant.
TASF PU T0+6 → 1st October, 2010
D230.1
Scientific tools and architecture definition Document
including Data models, Engineering Point of View V0,V1
TASF PU Version 0 at T0+6 → 1st October, 2010
D220.1
Services/Product Definition V0, V1 TASF PU Version 0 at T0+6 → 1st October, 2010
D720.1
Market assessment reports 1, 2, 3 AEA CO Version 0 at T0+6 → 1st October, 2010
T0 → T0 + 6 months
NOV-3733-SL-9347 Carbones KOM - May 10-11, 2010 – Toulouse, France
9
Formal Deliverables
Del. no.
Deliverable nameLead
beneficiary
Dissemination
level
Delivery date(proj. month)
D410.1
Description document of the CCDAS, V1, V2
LSCE PU Version 1 at T0+8 → 1st December 2010
D230.1
Scientific tools and architecture definition Document
including Data models, Engineering Point of View V0,V1
TASF PU Version 1 at T0+12 → 1st April 2011
D300.1
CARBONES input and forcing data presentation
document, V1
MPI-BGC PU Version 1 at T0+12 → 1st April 2011
D430.1
CCDAS validation : Error estimations: Parameter errors on
base configuration
LSCE PU Version 1 at T0+12 → 1st April 2011
D430.2
CCDAS validation : Error estimations: Errors on output
fields
LSCE PU Version 1 at T0+12 → 1st April 2011
D510.1
CARBONES dataset V0 NOV PU Version 0 at T0+12 → 1st April 2011
D520.1
CARBONES portal description : simplified version V0
CERC PU Version 0 at T0+12 → 1st April 2011
D720.3
Business development plans, 1, 2, 3 AEA CO Version 1 at T0+12 → 1st April 2011
T0 + 6 months → T0 + 12 months
NOV-3733-SL-9347 Carbones KOM - May 10-11, 2010 – Toulouse, France
10
Internal Deliveries
For the good running of the project, internal deliveries will be followed by NOVELTIS. For that, each partner has to:→ sent their documents with NOVELTIS in copy.
→ sent an email to NOVELTIS informing the data delivery with the reference.
Examples of internal deliveries: For data:
Input data from the data providers to CCDAS responsible. Example of CCDAS output data for the CARBONES portal development.
For document: The specification document of the post-processing of the CCDAS
outputs for the CARBONES portal
NOV-3733-SL-9347 Carbones KOM - May 10-11, 2010 – Toulouse, France
11
Project Schedule
Meeting DateOrganised
byPlace
Kick-Off Meeting 10-11 May 2010 NOVELTIS Toulouse, France
CUAG Consultation Meeting September 2010 METO TBD
Progress Meeting # 1 October 2010
Progress Meeting # 2 April 2011 LSCE Paris, France
User Workshop #1 and CUAG meeting #2
September 2011 AEA
Mid Term Review Meeting October 2011
Progress Meeting # 3 April 2012
Progress Meeting # 4 October 2012 LSCE Paris, France
User Workshop #2 and CUAG meeting #3
December 2012 METO
Final Meeting April 2013 NOVELTIS Toulouse, France