OVERVIEW OF RESEARCH FINDINGS VIA CHALLENING CONSTRUCITON CASES
FROM NCHRP 20-07/TASK 355
(GUIDELINES FOR RELIABLE FIT-UP OF STEEL I-GIRDER BRIDGES)
Thanh Nguyen & Don White
Georgia Institute of Technology
AASHTO/NSBA TG 10 Meeting
Raleigh, NC
May 6 2015
NCHRP 20-07/TASK 355 PROBLEM STATEMENT
• Potential construction problems:
Difficult fit-up of girders and cross-frames
Out-of-plumb girder webs
Unaccounted locked-in stresses in the girders and cross-frames
Bearings rotated beyond design limits
Out-of-alignment of deck joints & barrier rails at abutments
• Overarching factors influencing the bridge responses:
Longer spans
Tighter curvature and/or
Sharper skew
• Practices that can be used to control/limit problems:
Framing arrangements
Cross-frame detailing
Erection sequencing & other techniques/practices 2
NCHRP 20-07/TASK 355 RESEARCH OBJECTIVES
• Improved design, detailing and erection guidelines to ensure reliable fit-up of skewed &/or curved steel I-girder bridges
• Clear understanding of the implications of
Framing arrangements,
Cross-frame detailing methods, &
Erection procedures
on
Ease of fit-up during erection of the steel,
Achievement of targeted constructed geometry, &
Limiting significant additive locked-in stresses & accounting for beneficial subtractive locked-in stresses in the cross-frames & girders
3
RESEARCH TEAM
• Don White, Georgia Tech (PI)
• Thanh Nguyen, Georgia Tech
• Domenic Coletti, HDR Engineering
• Brandon Chavel, HDR Engineering
• Calvin Boring, Brayman Construction Corporation
• Mike Grubb, M.A. Grubb & Associates, LLC
4
PRESENTATION OUTLINE
• Highlight several findings & illustrate with two extreme bridge cases
Curved radially-supported case: Ford City Veterans Bridge, PA
Large span length
Tight curvature
Erection constraints
Critical choice of cross-frame detailing method
Straight-skewed case: Parametric Bridge NISSS54 (NCHRP 12-79)
Large span length
Sharp skew
Critical choice of framing arrangement & erection scheme
• Simulation results based on
As-built scheme for Ford City Bridge (results match closely with field observations)
Alternative framing arrangement & erection scheme for NISSS54 that provide low fit-up forces 5
FORD CITY BRIDGE
6
• Significant deflections in curved span
Second largest curved span length of cases studied in this research, Ls = 322’
Largest Ls/R = 0.78
Largest curved span Ls/w = 8.1
• Site constraints
Limits on location of shoring towers
• Curved span involved drop-in segments
• Detailing method
Essentially Steel Dead Load Fit (SDLF), by mistake
FORD CITY BRIDGE
7
• Steel DL & Total DL cambers from 3D FEA, the bridge deflects as a system
• TDL camber determined neglecting staged deck placement effects
• SDL and Concrete DL defl. approx. equal; bridge detailed essentially for SDLF
• SDL & TDL cambers are central to:
Setting the cross-frame drops for fabrication
Calculation of SDLF & TDLF detailing effects
FORD CITY BRIDGE – COMPLETED STRUCTURE
8
• SDLF & TDLF reduce vertical deflections of all the girders in curved span
SDLF & TDLF effects twist the girders opposite from their DL twist rotations
Twist rotations and vertical deflections are coupled
• SDLF & TDLF significantly influence the final elevations
SDLF: G1 max 2.5” higher than zero elevation line (matches field observations)
TDLF: G1 max 4.5” higher
FORD CITY BRIDGE – COMPLETED STRUCTURE
9
• TDLF enforces approximately plumb girder webs
• Highest layovers near mid-spans
6” max in curved span with NLF (girder webs 14 ft deep)
Layovers are not a structural concern
• Zero layovers at bearing locations
FORD CITY BRIDGE – COMPLETED STRUCTURE
10
• Negligible changes in fb due to SDLF & TDLF
• Significant changes in f due to SDLF & TDLF
Girders show overall lateral bending for NLF due to the twisting of the
narrow bridge cross-section
This effect is reduced by SDLF & TDLF
The f values are relatively small
FORD CITY BRIDGE – COMPLETED STRUCTURE
11
Total DL cross-frame stress contour (ksi), NLF detailing (all CF areas = 8.52 in2)
CFs with large stresses
in curved span
FORD CITY BRIDGE – COMPLETED STRUCTURE
12
Total DL cross-frame stress contour for the curved span (ksi), NLF detailing
FORD CITY BRIDGE – COMPLETED STRUCTURE
13
Detailing
Method
Average CF
Force
Percentage
Increase
Relative to
NLF
NLF 32 NA
SDLF 40 23 %
TDLF 46 44 %
Table 1: Average Total DL CF Forces in Curved Span(kips)
FORD CITY BRIDGE – STEEL ERECTION
14As-built erection stage involving drop-in segments
FORD CITY BRIDGE – STEEL ERECTION
15As-built erection stage involving drop-in segments
G1G2G3G4
FORD CITY BRIDGE – STEEL ERECTION
16
• As-built erection simulation for Ford City Bridge
Including the effects of:
Holding crane
Lifting crane & spreader beam with optimum pick points
Shoring towers
Detailing methods
Cross-frames installed sequentially after girder segments are installed
Separate analyses for fit-up at top and bottom CF connections
For system stability & geometry control, all the CFs are installed & the connections are fully tightened at each stage of the erection
Crane and tower elevations:
No-load elevations
These elevations can be adjusted to achieve some reduction in the fit-up forces (Iteration on elevations in simulations is outside our scope)
FORD CITY BRIDGE – STEEL ERECTION
17
Table 2: Max fit-up forces (kips)
• Fit-up force: forces developed in the connection after the installation
• Typical come-along capacity = 20 kips
• Fit-up force larger than 40 kips is taken as difficult
DetailingMethod Fmax (kip) Level of Difficulty
NLF 38 Moderate
SDLF 86 Difficult
TDLF 130 Very difficult
FORD CITY BRIDGE – STEEL ERECTION
18
Table 3: Girder splice fit-up moments (kip*ft) and equivalent flange fit-up forces (kip)
DetailingMethod
M(kip*ft)Equivalent Flange
Force (kip)Level of Difficulty
NLF 315 22 Relatively easy
SDLF 7566 540 Very difficult
TDLF 11267 804 Extremely difficult
RESEARCH FINDINGS – CURVED RADIALLY-SUPPORTED BRIDGES
More difficult fit-up of girders and cross-frames in curved radially-supported bridges in cases involving:
Large span lengths
High Ls/R and/or Ls/w
Erection schemes with:
Drop-in segments
Site and/or job constraints that place limitations on the number and/or location of shoring towers and cranes
Erection from inside to the outside of the curve
19
RESEARCH FINDINGS – CURVED RADIALLY-SUPPORTED BRIDGES
More difficult fit-up of girders and cross-frames in curved radially-supported bridges in cases involving:
Use of TDLF
Use of SDLF in some extreme cases
20
Curved Bridges with Radial or Skewed Supports
Recommended Acceptable Avoid
Span lengths greater than 250’ +/-
and L/R > 0.1 +/-NLF SDLF TDLF
All other cases SDLF NLF TDLF
Table 4: NSBA Guide Document Recommendation on Fit Conditions for Curved Bridges
RESEARCH FINDINGS – CURVED RADIALLY-SUPPORTED BRIDGES
• Effects of SDLF & TDLF on the completed structure
Increase in elevation profiles
Approximately plumb webs under corresponding load condition
Negligible changes in fb; Significant changes in f Average CF forces are increased; Max CF forces are increased in
most cases (influence on distribution of CF forces will be illustrated for a range of bridges in our final reporting )
A simple “adjustment factor” can be used to account for the additive effects of SDLF and TDLF on CF forces and f values
For extreme cases, detailing effects should be considered in the analysis of the structure to predict CF forces & f values
21
RESEARCH FINDINGS – CURVED RADIALLY-SUPPORTED BRIDGES
• In a large number of cases with proper erection schemes and use of NLF or SDLF, cross-frame and girder fit-up forces are very manageable
• In extreme cases, all the CFs should be installed in sequence & the connections should be fully tightened at each stage of the erection
• For cases with potential high fit-up difficulty, the erection engineer may consider analyzing the erection sequence to predict the fit-up forces including the effects of:
Placement of cranes and shoring towers, etc.
22
STRAIGHT SKEWED BRIDGE: NISSS54
23
Framing Plan 1 (Original Design)
• Parallel skew, large Ls = 300 ft. & high Is = 0.68
• Small stagger between CFs, large number of CFs
• Significant nuisance transverse stiffness
• Offsets (first intermediate CF to the bearing line) smaller than 1.5 x girder depth
STRAIGHT SKEWED BRIDGE: NISSS54
24
Framing Plan 2 (Alternative Design)
• Offsets at least 1.5 x girder depth
• CFs are equally spaced except at the offsets adjacent to the bearing lines. Every other CF is left out within the interior of bridge plan. This reduced the number of CFs significantly & increased stagger distances
• Low nuisance transverse stiffness
NISSS54 – COMPLETED STRUCTURE
25
Detailing
Method
Framing Plan 1
(Original)
Framing Plan 2
(Alternative)
NLF 354.0 58.5
SDLF 181.9 31.2
TDLF 18.1 8.8
Table 5: Comparison of Max Total DL Cross-Frame Forces (kips)
between Framing Plans 1 and 2*
*Results shown are based on line girder analysis cambers
NISSS54 – COMPLETED STRUCTURE
26
• G1 is a fascia girder. G5 is the innermost interior girder
• With the use of line girder analysis cambers, the desired elevations are obtained
only for the targeted DL condition
NISSS54 – COMPLETED STRUCTURE
27
• NLF and SDLF give high layovers at the skewed bearings, placing higher
rotation demand on the bearings
This effect can be offset by using beveled sole plates
• TDLF effectively enforces plumb webs
NISSS54 – COMPLETED STRUCTURE
28
• Measurable changes in fb due to SDLF/TDLF effects for this bridge
Due to changes in vertical forces transferred from CFs to the girders
These changes are not significant in the majority of cases
• TDLF gives close to zero f under TDL
NISSS54 – STEEL ERECTION
29
Shoring Tower
Field Splice
Lifting Points
G1G2
• Large span length requires a field splice & shoring tower
• Shoring tower and lifting crane are set at SDL elevations
• Only a few CFs are installed for stability before the field splice is made
• The rest of the CFs are installed after the splice is made so that all the steel is
deflected close to the SDL elevation profile
NISSS54 – STEEL ERECTION
30
Table 6: Max fit-up forces (kips)
• NLF is not considered
Fit-up difficulty (short of substantial shoring of the span)
High bearing rotation demands & girder layovers
• Typical come-along capacity = 20 kips
• Fit-up force larger than 40 kips is taken as difficult
DetailingMethod
Fmax (kip) Level of Difficulty
SDLF 8.4 Relatively easy
TDLF 47.9 Somewhat difficult
RESEARCH FINDINGS FOR STRAIGHT SKEWED BRIDGES
Difficult fit-up of cross-frames in straight skewed bridges when
• Large span length
• High skew index
• Use of TDLF
31
Square Bridges and Skewed Bridges up to 20 deg +/- Skew
Recommended Acceptable Avoid
Any span length Any None
Skewed Bridges with Skew > 20 deg +/- and Is ≤ 0.30 +/-
Recommended Acceptable Avoid
Any span length TDLF or SDLF NLF
Skewed Bridges with Skew > 20 deg +/- and Is > 0.30 +/-
Recommended Acceptable Avoid
Span lengths up to 200’ +/- SDLF TDLF NLF
Span lengths greater than 200’ +/- SDLF TDLF & NLF
Table 7: NSBA Guide Recommendation on Fit Cond. for Straight Bridges
RESEARCH FINDINGS FOR STRAIGHT SKEWED BRIDGES
• Use of NLF is not recommended for bridges w/ sharp skew
• In almost all cases with proper erection schemes and use of SDLF, cross-frame fit-up forces are relatively low
• Alternative framing arrangement reduces the number of cross-frames as well as cross-frame forces
• Effects of SDLF & TDLF in the final structure
DLF detailing with line girder cambers gives correct elevations ONLY for the targeted steel or total DL condition
Effectively plumb webs under corresponding load condition
For extreme cases, measurable changes in fb . TDLF gives close to zero funder TDL
Total DL CF forces are nearly offset by TDLF
Engineers can use a reduction factor to account for the beneficial subtractive effects of SDLF and TDLF on CF forces and fvalues 32
Thank you!
Questions?
33