nTof Civil engineeringStatus -5 July 2013
• EDMS approval procedure for « Execution drawings » launched on 24/05/2013. Drawings approved on 10/06/2013
• CERN preparatory works (antennas removal, radio club barrack removal, asbestos removal B559, deviation of the optical fibre, power and water temporary supply for the worksite) finished on 30/04/2013
• Contractor’s main works started on 13/05/2013:
Done:– Worksite installation– Demolition of barrack 559– Deviation of the existing networks– Earthworks– Beam shaft and opening ɸ80 in the roof of the nTOF technical gallery – Piles
Ongoing:– Concreting of the building foundations on the ISR slab
L.A.Lopez
Désamiantage
Dépose baraque du Radio-club
Démolition B559
Terrassement
Cérémonie 1er
coup de pelle
Puits du faisceau
Carottage faisceaudans galerie nTOF
Puits fini du faisceau
Déviation des réseaux
Réalisation des pieux
Planning “objectif”
Next steps
• Concreting works → September 2013
• Finishing works (waterproofing, insulation, doors, « chape », painting) → October-November 2013
• Landscaping → November 2013