+ All Categories
Home > Documents > OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

Date post: 16-Oct-2021
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
42
OCCUPANT EVACUATION ELEVATORS Overview & Case Studies Eric M. Camiel, P.E., CET March 3, 2016
Transcript
Page 1: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

OCCUPANT EVACUATION ELEVATORS

Overview & Case Studies

Eric M. Camiel, P.E., CET

March 3, 2016

Page 2: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

ELEVATORS & THE PUBLIC’S

UNDERSTANDING

Public is instructed to:

• Do not use elevators in the event of a fire!

• Use exit stairs only.

This is portrayed by:

• Signage

• Fire alarm voice messages

• People’s general knowledge

INTRODUCTION

2

Page 3: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

EGRESS BY STAIRS

Stairs may be challenging for some.

• Mobility impaired occupants

• Elderly occupants

• Small children

INTRODUCTION

3

Page 4: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

EGRESS BY STAIRS

The taller the building, the longer the

evacuation time and higher probability of

fatigue and other delays etc.

• Different movement speeds of occupants

– Age

– Mobility impairments

– Health

» Fatigue during longer evacuation times

INTRODUCTION

4

Page 5: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

CURRENT CODE PROVISIONS

International Building Code

- 2015 Edition (Added in 2009)

• Section 3008

NFPA 101 - Life Safety Code

- 2015 Edition (Added in 2012)

• Section 7.14

GAS PBS-P100 – Facilities Standards for Public Buildings

Service

- 2015 Edition (Added in 2010)

• Section 7.10.1.4

OVERALL OCCUPANT EVACUATION

ELEVATOR REQUIREMENTS

5

Page 6: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

CURRENT CODE

PROVISIONS

ASME A17.1/CSA B44 –

Safety Code for Elevators and

Escalators

- 2013 Edition (Added in 2013)

• Section 2.27.11

NFPA 72 - National Fire Alarm

& Signaling Code

- 2013 Edition (Added in 2013)

• Section 21.6

OVERALL OCCUPANT EVACUATION

ELEVATOR REQUIREMENTS

6

Page 7: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

BUILDING REQUIREMENTS

OEEs are not mandated to be provided in any of the current NFPA & ICC codes.

OEEs may be provided in lieu of additional exit stairway required for buildings more than 420 feet in height required by IBC.

GSA PBS-P100 requires OEEs in all new GSA buildings with an occupied floor higher than 120 Feet in height.

OVERALL OCCUPANT EVACUATION

ELEVATOR REQUIREMENTS

7

Page 8: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

REQUIREMENT OVERVIEW

Occupant Evacuation Operation to

comply with:

• ASME A17.1/CSA B44

– OEO sequencing

– Elevator system notifications

• NFPA 72

– OEO activation

– Voice message coordination

– Signals from fire alarm system to

elevator system

SPECIFIC OEO REQUIREMENTS

8

Page 9: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

EVACUATION REQUIREMENTS

OEO Activation

• Automatic detection throughout the building

– Fire alarm system

– Sprinkler system activation

– NOT activated on manual fire alarm boxes throughout the building

» Only manually initiated from within fire command center

– NOT activated on alarm from elevator discharge level (ASME A17.1

requirement)

SPECIFIC OEO REQUIREMENTS

9

Page 10: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

EVACUATION REQUIREMENTS

Determination of Evacuation floor group

• First alarm:

– Floor of incident

– Two floors above

– Two floors below

• Subsequent alarms: (ASME A17.1 requirement)

– All floors between alarm floors

– Two floors above group

– Two floor below group

• Total building Evacuation

– All floors

SPECIFIC OEO REQUIREMENTS

10

Page 11: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

OEO EVACUATION FLOOR GROUPS

SPECIFIC OEO REQUIREMENTS

11

15

14

13

12

11

10 Alarm

9

8

7

6

5

4

3

2

1

15

14

13

12 2nd Alarm

11

10 1st Alarm

9

8

7 3rd Alarm

6

5

4

3

2

1

One Alarm: Multiple Alarms:

Evacuation Group:

Floors 8 - 12

Evacuation Group:

Floors 5 - 14

15

14

13

12

11

10

9

8

7

6

5

4

3

2

1

Total Building

Evacuation:

Evacuation Group:

All Floors

Fire Floor Evacuating

Floor Evacuating

Floor Not Evacuating

Page 12: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

NFPA 72 REQUIREMENTS

Transmit information to elevator systems to allow for accurate

OEO sequencing.

• Relays between control equipment

• Serial communications between control equipment

– Required to be listed

SPECIFIC OEO REQUIREMENTS

12

Page 13: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

NFPA 72 REQUIREMENTS

Functions at the fire command center:

• Annunciate evacuation status of each floor

• Provide manual controls for OEO manipulation by authorities

• Provide manual means for initiating Total Building Evacuation

SPECIFIC OEO REQUIREMENTS

13

FIRE COMMAND

CENTER

Page 14: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

ASME A17.1/B44 REQUIREMENTS

OEO Sequencing

• Automatically start OEO upon signals

from fire alarm system

• All passenger elevators serve only floors

evacuating

• Only discharge passengers at elevator

discharge level

• Continue operation until fire alarm system

is re-set

SPECIFIC OEO REQUIREMENTS

14

Page 15: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

ASME A17.1/B44 REQUIREMENTS

OEO Evacuation priorities

• Assign priority to fire floors based on

sequence

alarms are received

– 1st alarm floor = first evacuation priority

– 2nd alarm floor = second evacuation priority

– Etc.

Total building evacuation priorities

• Assign priorities based on distance from

elevator discharge level

– Highest floor = first priority

– One floor below highest floor = second

priority

– Etc.

SPECIFIC OEO REQUIREMENTS

15

Page 16: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

OEO EVACUATION FLOOR GROUPS

SPECIFIC OEO REQUIREMENTS

16

Floor AlarmEvac.

Priority

15

14

13

12 2

11 3

10 Alarm 1

9 4

8 5

7

6

5

4

3

2

1

Floor AlarmEvac.

Priority

15

14 4

13 5

12 2nd Alarm 2

11 6

10 1st Alarm 1

9 7

8 8

7 3rd Alarm 3

6 9

5 10

4

3

2

1

One Alarm: Multiple Alarms:

Evacuation Group:

Floors 8 - 12

Evacuation Group:

Floors 5 - 14

FloorEvac.

Priority

15 1

14 2

13 3

12 4

11 5

10 6

9 7

8 8

7 9

6 10

5 11

4 12

3 13

2 14

1 15

Total Building

Evacuation:

Evacuation Group:

All Floors

Fire Floor Evacuating

Floor Evacuating

Floor Not Evacuating

Page 17: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

ASME A17.1/B44 REQUIREMENTS

SPECIFIC OEO REQUIREMENTS

17

Elevator system notification

• Variable message signage in

each lobby

– Normal Operation

» “Elevators operating normally”

– During OEO

» Elevators available for

evacuation

» Time of arrival for elevators

» Elevators unavailable

Page 18: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

OEO SEQUENCE OVERVIEW

18

Page 19: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

OEO RESPONSIBILITIES

19

FIRE ALARM SYSTEM

Determine evacuation group of floors

Send evacuation group to elevator system for OEO service

Broadcast floor voice messages

• Specific message for evacuation group

• Other message for all other floors

Manual OEO controls

• Floor selection

• Total building evacuation

OEO annunciation in Fire Command

Center

Page 20: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

OEO RESPONSIBILITIES

20

ELEVATOR SYSTEM

Send signal(s) to fire alarm system indicating

availability of elevators for OEO.

Evacuate floors indicated by fire alarm system

Elevator movement per A17.1 sequencing

Variable message signage

• Display approved messages

• Display time of elevator arrival on evacuating floors

In-car notification of elevator occupants

• Voice message

• Visual signal or variable message signage

Page 21: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

LA FEDERAL COURTHOUSE OVERVIEW

21

Page 22: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

LA FEDERAL COURTHOUSE OVERVIEW

22

PROJECT SPECIFICS

Federal Courthouse

• 11 stories above grade

• 2 stories below grade

• Atrium connecting floors 1-11

Page 23: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

LA FEDERAL COURTHOUSE OVERVIEW

23

PROJECT SPECIFICS

Occupants:

• US District Court

• US Marshals Service

• US Attorneys Office

• GSA Field Office

• Homeland Security

• Public Defenders Office

Uses

• Courtrooms

• Prisoner areas

• Offices

• Mechanical Spaces

Page 24: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

LA FEDERAL COURTHOUSE OVERVIEW

24

PROJECT REQUIREMENTS

OEEs required under P100

• New High Rise building

• Highest floor is 220 feet

– Taller than 120 feet

Codes of Record

• 2010 edition of GSA PBS-P100

• 2012 IBC

• 2013 NFPA 72

• 2010 ASME A17.1 ****

**** 2010 edition of ASME A17.1 does not have language for OEEs or OEO. First edition to include this was 2013 edition.

Page 25: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

LA FEDERAL COURTHOUSE OVERVIEW

25

OEE APPROACH

IBC features required for OEEs were implemented in design.

• Sprinkler water prevention from entering hoistways

• Lobby sizes

• Arrangement of lobbies and exit stairs

• Standby power

• Voice alarm communication fire alarm system

• Etc…

Variable message signage was provided by Fire Alarm System

• GSA approval was obtained to not provide estimated time of elevator arrival on variable message signage.

Sequencing of A17.1-2013 was not provided

Page 26: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

LA FEDERAL COURTHOUSE OVERVIEW

26

EVACUATION APPROACH

Building has a very large atrium extending from floors 1-11

• Building is general evacuation, not partial evacuation

• Elevators continue to serve all floors in event of fire alarm

• Variable message signage and fire alarm system voice message

indicates elevators are available for evacuation.

Page 27: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

LA FEDERAL COURTHOUSE OVERVIEW

27

EVACUATION APPROACH

Variable message signage provided by Fire Alarm System

Specific OEO Sequencing of A17.1-2013 was not provided as

2013 edition is not adopted.

• OEE requirements have been met except for the sequencing

requirements of A17.1-2013 edition.

Page 28: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

LA FEDERAL COURTHOUSE OVERVIEW

28

CONCLUSION

Construction began in 2013

Completion in 2016

Page 29: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

TRANSBAY BLOCK 5 OVERVIEW

29

Page 30: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

TRANSBAY BLOCK 5 OVERVIEW

30

PROJECT SPECIFICS

Mixed Use Building

• 43 stories above grade

• 550 feet tall

• ~700,000 ft2 Class A Office Space

• ~10,000 ft2 Retail Space

• Transbay Development area of San

Francisco

Page 31: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

TRANSBAY BLOCK 5 OVERVIEW

31

PROJECT REQUIREMENTS

OEEs elected in lieu of additional exit stair

• New High Rise building

• Highest floor is ~550 feet

– Taller than 420 feet

Codes of Record

• 2012 IBC

• 2013 NFPA 72

• 2010 ASME A17.1 ****

**** 2010 edition of ASME A17.1 does not have language for OEEs or OEO. First edition to include this was 2013 edition.

Approval obtained by Authorities to use 2013 Edition for OEO guidance.

Page 32: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

TRANSBAY BLOCK 5 OVERVIEW

32

OEE APPROACH

Eliminated need for 3rd exit stair

• Small footprint floor area especially on higher

floors

• Freed approx. 200 ft2 per floor

• Long term monetary impact of gained space

Page 33: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

Goal for strict adherence to all OEE requirements in IBC,

NFPA 72 and A17.1.

• Elevator system to provide variable message signage

– Including time to arrival for elevators

» Has not been provided on other OEE projects

• Fire alarm system to control OEO and provide per floor signals

– FAS to Elevator Interface could be serial communications

» Would be the first time this technology is utilized for OEO

TRANSBAY BLOCK 5 OVERVIEW

33

Page 34: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

TRANSBAY BLOCK 5 OVERVIEW

34

CONCLUSION

Construction

began October

2015

Expected

completion in 2018

Page 35: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

181 FREMONT STREET OVERVIEW

35

Page 36: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

181 FREMONT STREET OVERVIEW

36

PROJECT SPECIFICS

Mixed Use Building

• 70 stories above grade

• 800 feet tall

• 435,000 ft2 Class A Office Space

• 67 Residential Units

• Transbay Development area of San

Francisco

Page 37: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

181 FREMONT STREET OVERVIEW

37

PROJECT REQUIREMENTS

OEEs elected in lieu of additional exit stair

• New High Rise building

• Highest floor is ~700 feet

– Taller than 420 feet

Codes of Record

• 2012 IBC

• 2013 NFPA 72

• 2010 ASME A17.1 ****

**** 2010 edition of ASME A17.1 does not have language for OEEs or OEO. First edition to include this was 2013 edition.

Approval obtained by Authorities to use 2013 Edition for OEO guidance.

Page 38: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

181 FREMONT STREET OVERVIEW

38

OEE DECISION

Eliminated need for

3rd exit stair

Small footprint floor

area

Freed ~ 200 ft2 per

floor.

• Additional 116,000 ft2

of space for offices

and residential.

Long term monetary

impact of gained

space

Page 39: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

181 FREMONT STREET OVERVIEW

39

CONCLUSION

Construction began in 2013

Expected completion in 2017

Page 40: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

SUMMARY

40

CURRENT STATUS OF OEE IMPLEMENTATION

OEEs are being utilized more regularly

• California is most concentrated area of OEEs (All three discussed

today)

• Expected to be more widely adopted in other areas of country /

internationally

– New York City Building(s) Planned with OEEs

• As OEE awareness expands, more projects will incorporate them.

Page 41: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

SUMMARY

41

NEED FOR ADDITIONAL RESEARCH

OEE installations should be analyzed once complete

• Identify future developments in requirements

• Determine level of effectiveness in real-world scenarios

– Observation of OEO training / drills

– Development of accurate egress models for these buildings

Page 42: OCCUPANT EVACUATION ELEVATORS Overview & Case Studies

www.jensenhughes.comwww.jensenhughes.comCopyright © JENSEN HUGHES. All rights reserved.

QUESTIONS?

42

ContactEric M. Camiel, P.E., CET

+1 401-736-8992

[email protected]

For More Information Visit

www.jensenhughes.com


Recommended