Date post: | 14-Jul-2015 |
Category: |
Engineering |
Upload: | norrazman-zaiha-zainol |
View: | 1,754 times |
Download: | 16 times |
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
OSH514 OSH514 OSH514 OSH514 ::::SAFETY MANAGAMENT IN SAFETY MANAGAMENT IN SAFETY MANAGAMENT IN SAFETY MANAGAMENT IN
CONSTRUCTION INDUSTRYCONSTRUCTION INDUSTRYCONSTRUCTION INDUSTRYCONSTRUCTION INDUSTRY
1
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Lesson Plan
Introduction
Module 1: Occ. Safety and Health management and the law
Module 2: Preparing for work
Module 3: Setting up the site
Module 4: Construction-phase safety and health
2
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
INTRODUCTION
3
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Management of OSH at site
Overview of OSH Management System
MS 1722
Policy
Organizing
Planning and Implementation
Evaluation
Action for improvement
4
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
OSH MS
Make compulsory as stated in Section 15, general
duties of employers to ensure so far as is
practicable the plant and system of works are
maintain safely and without risks to the employees,
other people (not its immediate workers) &
surrounding.
5
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
OSH MS 1722:2011
6
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
OSH MS 1722: Policy
The policy should be:-
a) specific to the organisation and appropriate to its size and the nature of its activities;
b) concise, clearly written, dated and made effective by
the signature or endorsement of the employer or the most senior accountable person in the organisation;
c) communicated and readily accessible to all persons at their workplace;
d) reviewed for continuing suitability; and
e) employee participation
7
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
OSH MS 1722: Policy
Should have the following key principles:-a) protecting the safety and health of all members of the
organisation and others who may be affected by the work
carried out;b) preventing work-related fatalities, disabilities, injuries, ill health,
diseases, property and environmental damage and near misses;
c) complying with relevant OSH national laws and regulations,
and other requirements to which the organisation subscribes;d) ensuring that employees and their representatives are
consulted and encouraged to participate actively in all elements of the OSHMS; and
e) continually improving the performance of the OSHMS.
8
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
OSH MS1722: Organising
In organising stages:-• Assign responsibility, accountability and
authority;
• Ensure competence, training and
awareness are fulfilled;
• Establish OSHMS documentation• Proper communication to the stakeholder
9
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
OSH MS1722: Planning & Implementation
In these stages:• Initial review to know the gap
• Set the OSH objectives
• Include OSH element in procurement &
contracting
• Do the HIRARC• Emergency prevention, preparedness
and response
• Management of change
10
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
OSH MS1722: Evaluation
The company should evaluate the implementation OSH thru;
• Performance monitoring and measurement
• Incident investigation
• Audit• Management review
11
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
OSH MS1722: Action for Improvement
Once evaluated and required improvement;
• Recommend and perform preventive and
corrective actions
• Findings shall be addressed
• Continual improvement
12
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
HIRARC
13
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Contents
Objectives
Accidents
Basic of accident prevention method
14
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Objectives
At the end, participants would know:
Terminologies related to hazards, risks and accidents.
Exposure to accidents and its causes and consequences
happens in construction site, and
Understood and be able to elaborate the basic method of
accidents prevention
15
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Definition of Hazard, Risk and
Danger
16
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Defined as source or condition which has
potential to cause injury and/or ill health to
humans, damage to property or damage to
workplace or environment or combination of any
of the above.
Hazard may cause harm if not in control
(uncontrolled hazards)
Note: Source OHSAS 18000 & MS1722:2003
Hazard
Hazard source
Attack of the tiger
– hazard due to potential
impact may cause harms17
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Tripping
Fallen from height
Example of Hazard
18
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Definition of OHSAS 18002 – Combination of
likelihood or probability AND consequences/
effect for a particular hazard to happen.
Definition of MS1722 – A combination of the
likelihood of an occurrence of a hazardous event or
exposure with specified period or in specified
circumstances and the severity of injury or damage
to the health of people, property, environment or any
combination of these caused by the event or
exposure.
Risks
High risk
Low risk19
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Definition of OHSAS 18002 – Combination of
likelihood or probability AND consequences/
effect for a particular hazard to happen.
Definition of MS1722 – A combination of the
likelihood of an occurrence of a hazardous event or
exposure with specified period or in specified
circumstances and the severity of injury or damage
to the health of people, property, environment or any
combination of these caused by the event or
exposure.
Risks
High risk
Low risk20
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Scope of work Hazard Risk
Grinding Eyes hit by flying
debris
Eye injury or blind
Welding Radiation from
the welding arc
Eye inflammation/
kataraks/blind
Working at height Fall from height Injury/Death
Example of Risks
21
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Danger explains relative exposure to the hazard. It shows the tendency of a
hazard hit / struck an employee in a risky situation.
Examples:
Employees who regularly handle chemicals will be more vulnerable to
the dangers of the chemicals than other employees who rarely do.
More concentrated sulfuric acid is more dangerous than the sulfuric acid
was diluted, so the risk is higher for workers handling the concentrated
acid compared to workers who handle dilute acids.
Danger
22
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
DANGER
HIGH RISK SITUATION
Sumber: Panduan ISO/IEC 51:1990 (E)
WARNING
MEDIUM RISK SITUATION
CAUTION
LOW RISK SITUATION
Do you know?
SIGNAGE MEANING THAT -
23
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
What is ACCIDENT?
24
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Events or conditions that are not planned or expected
Unfortunate Events as a result of negligence or ignorance
Events occurring unintentional
Events that occur due to reasons unknown
An accident is an unexpected sequence of events and unplanned
occurs through a logical sequence and by a combination of several
historical reasons cause harm either an injury or illness to people,
damage to property or the environment, accidents, near misses,
loss, or a combination of the above effects
Definition of accident
25
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
HUMAN
MACHINERY/
EQUIPMENT
METHOD/
PROCEDURE
MATERIALS
MEDIA
Source of accident
26
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Injuries
Disability
Loss (monetary)
Reputation
Disablement
Death
Damage
Phobia/Fear
Effect of accident
27
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Direct
(magnitud 1)
Indirect
(magnitud 8-36)
Medical
Loss of income
Damage of property
Supervisory time
Affect the performance
Reputation
New workers
Video
Cost of accident
28
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Safety issues
Falls
Mobile plant
Falling materials and collapses
Electrical accident
Trips
Health issues
Asbestos
Manual handling
Noise and vibration
Chemical
Most frequent cases
29
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
YearNo of reported
accidents
No of workplace
accident
No of accident
to/fro workplace
No of death
accident
2001 84,333 67,163 17,170 958
2002 81,810 63,423 18,387 858
2003 73,858 56,249 17,609 822
2004 69,132 50,803 18,329 846
2005 61,182 43,885 17,297 773
2006 58,321 40,617 17,704 733
2007 56,339 38,657 17,682 755
2008 54,133 35,092 19,041 981
2009 55,186 34,376 20,810 663
2010 57,656 34,911 22,745 409
Source: PERKESO & JKKP (as cited by Sayani Saidon in her research on HSE in JBPM)
Statistic
30
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Graph: No of accident vs Years
-
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010
No of reported accidents No of workplace accident No of accident to/fro workplace No of death accident 31
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Safety and health at work is the responsibility of every employer and
employee.
Cooperation between employers and employees is very important to
avoid any incident that threatens the safety and health at work
This image cannot currently be displayed.
What is your roles?
32
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Fundamental of Accident
Prevention
33
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Accidents Prevention Method
Method
C = H = Hazard identification
A = Analyse the risks
T = Take action
34
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
CAMKAN HAZARD (HAZARD IDENTIFICATION)
Identify and record where each hazard or potential hazard exists arising from
any type of work
Include all types of hazards i.e. physical, biological, chemical, psychosocial
For example: -
Employees who work at height might slips and fall down.
Employees who install electrical wiring, when contact to exposed cable will get
electrocuted.
Hazard Identification
35
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Methods of identifying hazards
Observations & reference,
Documentation i.e. complaints, reports, proposals, records of accidents,
sick leave records, information from internet etc.
Systematic method i.e. HAZAN (Hazard Analysis)
Occupation health and safety audit
Hazard Identification
36
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
ANALISA RISIKO (RISK ANALYSIS)
Simple analysis method - qualitative analysis involves a two-dimensional risk
matrix or 3-dimensional like JSA, HAZOP
Generic analysis method - based on the risk of others having the same system
Complex analysis method - for the quantitative analysis of complex systems
through certain method such as Principal Failure Analysis (Fault Tree Analysis)
Hybrid method - combining semi-quantitative as qualitative and quantitative
analysis Failure Mode & Impressions (Failure Mode and Effect Analysis)
Analyse the Risk
37
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
TINDAKAN (ACTION)
Right action, practical and appropriate for controlling risks arising from
hazards
Involve risk control hierarchy that consists of 2 main options:
Eliminate the risk, or
Accept hazard but reduces the level of risk
Take action
38
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
First control method
Control the source of the hazard by ELIMINATION- Remove the hazard from the workplace - Do not perform unsafe act or dangerous practices - Eliminate harmful equipment, processes, machinery, equipment or hazardous materials
39
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Second control method
Control the source of the hazard by SUBSTITUTION- Substitute materials, equipment, machines with less dangerous and safer items- Do the same job with safer procedure/method
40
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Third control method
Hazard control by ISOLATION- Hazard isolated, contained or kept away from workers - Hazard kept away through engineering controls such as the installation of a dividing wall, barrier or security fence
- Lock off / interlocking system
41
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Fourth control method
Hazard control by ENGINEERING CONTROL- Modification & Redesign
- The work, machinery or processes can be redesigned
to make them safer.
42
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Fourth control method
Hazard control by ENGINEERING CONTROL- Automation
- Dangerous process can be automated or mechanized.
For example, computer-controlled robots can handle spot
welding operations in car assembly plants. Precautions
should be taken to protect workers from the hazards of
robotics.
43
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Fourth control method
Hazard control by ENGINEERING CONTROL- Barriers
- Hazard can be blocked before it reaches workers.
For example, guard/barriers protect workers from contact
with moving parts.
44
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Fourth control method
Hazard control by ENGINEERING CONTROL- Absorption
- Baffles can block or absorb noise.
Typically, the most effective baffles is the one that keep the
most distance between the hazard and human
45
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Fourth control method
Hazard control by ENGINEERING CONTROL- Dilution
- Some hazards can be diluted or dissipated.
For example, the ventilation system can dilute the toxic gas
before it reaches the operator.
Add water
46
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Fifth control method
Hazard control by ADMINISTRATION CONTROL
- Signboard - Signboard warning or prohibition of a hazard - Signboard rules or safe work
- OSH promotion
- OSH promotion by conducting awareness programs such as OSH, OSH day celebrations, etc.
47
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Fifth control method
Hazard control by ADMINISTRATION CONTROL
- Safe work procedures - Employees are required to use safe work procedures when
executing the works.- Employers are expected to ensure that employees comply
with safe work procedures. Safe work procedures should be
periodically reviewed and constantly updated.
- Supervision and training - Initial training on safe work procedures and refresher
training should be provided. Appropriate regulation to help
workers identify hazards and assess the possible procedures.
48
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Fifth control methodHazard control by ADMINISTRATION CONTROL
Job rotations and other procedures can reduce the time workers are exposed
to hazards. For example, employees working in a given period is limited to work
involving ergonomic problems to prevent cumulative trauma injuries. Noise
process can be scheduled when no one is at work.
Housekeeping program and hygiene (cleanliness) in the workplace, repairs
and maintenance
Housekeeping at work including cleaning, waste disposal and clean-up after the
completion of a job. spill.
Hygiene practices can reduce the risk of toxic substances absorbed by workers
or taken home to their families. Street clothing should be stored in separate
lockers to avoid being contaminated by work clothing.
49
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Last control method
PERSONNEL PROTECTIVE EQUIPMENT
50
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Job Safety Analysis
- Systematically proactive measures to prevent accidents by identify hazards for each step / activity assignments
- Use principles SREDIM (select, record, examine, Develop, install & maintain)
- A basis for the formulation of safety policy, safe systems of work or safe work procedures that can be used in the field of training (ie courses or OJT)
- Important factors to consider when forming JSA is- Accident frequency and severity level - New or rarely performed work.
51
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Job Safety Analysis
Select the work\process
Break into small significant
activities
Observe and analyze in detail
potential hazard in each activities
Develop control measures as per
hierarchy
Establish safe systems of work and
safe working instruction
Review the continually
Normally, 10 steps is okay
Hazard category
52
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Job Safety Analysis
AKTIVITI HAZARD KAWALAN
1. Periksa suis lampu dalam
keadaan OFF
1.1 kejutan elektrik 1.1.1 Matikan suis utama DB dan guna pen ujian untuk
memastikan bekalan benar-benar putus
2. Tanggalkan bulb dengan
menekan sedikit bulb lampu
kedalam soketnya
2.1 kejutan elektrik
2.2 bulb meletup
2.3.kaca tajam
2.1.1 Pastikan suis dimatikan
2.2.1 Pakai cermin mata keselamatan
2.3.1 Pakai saring tangan keselamatan
3 Tukar bulb lampu baru 3.1 kejutan elektrik
3.2 bulb meletup
3.3.kaca tajam
3.1.1 Pastikan susi dimatikan
3.2.1 Pakai cermin mata keselamatan
3.3.1 Pakai sarung tangan keselamatan
4. Nyalakan lampu (ON suis) 4.1 kejutan elektrik
4.2 bulb meletup
4.1.1 Pastikan suis ditebatkan dengan sempurna
4.2.1 Pakai cermin mata keselamatan
5. Discaj bulb lampu rosak ke
dalam bekas khas
5.1 bulb meletup
5.2.kaca tajam
5.1.1 Pastikan bulb dibuang kedalam bekas khas yang tak
mudah koyak dan di”seal”
5.1.1. Pakai cermin mata keselamatan
5.2.1 Pakai sarung tangan keselamatan
TUGASAN: Menukar bulb lampu incandescent (mentol) jenis pin
53
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
MODULE 1Laws & regulations
54
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Contents
Legislative requirement
OSHA
FMA
UBBL
CIDB
Others
55
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
FACTORIES AND MACHINERY ACT &
REGULATIONS
56
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
FMA 1967Provision for control of OSH and welfare related issues in
the factory but focus on workers
Registration and inspection of machinery and all related
equipment. Covering most premises which operations
involving engineering and machinery operations EXCEPT:
Storing locomotives / vehicles where only cleaning activities,
cleaning and repairs.
Areas where only five or fewer employees whose work does not
involve the use of machinery57
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
FMA 1967
Generally, the act:
Contains 11 regulations on OSH & 4 supported regulations
(administration, penalty & certification)
Registration of competent personnel,
Provision of maintenance and inspection & T&C of machinery and
installation
Endorsement for hazardous machinery
Certification for machinery installation
58
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
FMA 1967
Regulations relating to construction:
Building Operations and Works of Engineering Construction Safety
(BOWECS) 1986
Safety, Health and Welfare Regulations 1970
Notification, Certificate Of Fitness & Inspection Regulations 1970
Fencing Of Machinery And Safety Regulations 1970
59
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
FMA 1967
Others are:
Steam Boiler And Unfired Pressure Vessel Regulations 1970
Electric Passenger And Goods Lift Regulations 1970
Persons-In-Charge Regulations 1970
Administration Regulations 1970
Certificates Of Competency – Examinations Regulations 1970
Compoundable Offences Regulations 1978
Lead Regulations 1984
Asbestos Process Regulations 1986 60
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Notification, Certificate of Fitness and Inspection 1970
Provision for
Pursuant to Section 35 (1) required registration of BOWEC within seven
days from date of commencement, the regulation specify the forms that
must be used to notify the DOSH officer of a new occupancy of a
factory, the start of building work, the installation of certain machinery
and the notification of accidents and diseases
Describes the certificate of fitness that must be held for steam boilers,
unfired pressure vessel and hoisting machines
61
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
BOWECS 1986
Provision for
Safety of the construction which explains on the hazard and risk
emerge from construction and control measures
Detailing on concrete and structural work
Provision for construction’s structures likes catch platform, chutes,
safety belts, ladders and scaffolds
Safety in construction’s works likes demolition, excavation, manual
handling, piling, blasting and explosion
Safety of hand and power tools62
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Safety, Health and Welfare Regulations 1970
Provision for
Safe means of access and safe place of employment, provision of edge
protection on floor openings and stairs (Regulation 7, 8)
All stairways and floors must be of good construction and properly
maintained; ladders must be of adequate construction and maintained
in a sound condition (Regulations 9 to 11)
Persons must be protected from falls of more than 10 feet by the use of
safety belts or ropes (Regulation 12)
63
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Safety, Health and Welfare Regulations 1970
Provision for
Adequate protection are necessary before working inside a confined space
(Regulation 13)
Flammable and dangerous liquids must be securely stored and precautions
taken against fire and explosion (Regulations 14 to 17, 21, 22)
Materials and finished goods must be securely stacked and stored
(Regulations 19, 20)
Specifications are laid down for cleaning of surfaces inside factory
(Regulation 23)64
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Safety, Health and Welfare Regulations 1970
Provision for
Lighting, ventilation and climate requirements are all detailed (Regulations
24-29)
Working clothes and protective equipment (Regulation 32)
Welfare facilities such as toilets, drinking water, washing facilities and first
aid (Regulation 33 to 38)
65
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
OCCUPATIONAL SAFETY AND
HEALTH ACT 1994 & REGULATIONS
66
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
INTRODUCTION
FMA 1967 is too prescriptive which overtime become
irrelevant and just covering mostly on workers involving
in manufacturing, mining & construction
OSHA 1994 more holistic with systematic and simpler
method to control the hazard and risk
67
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
OSHA 1994
Contains 67 section, 7 regulations & 2 orders
One stop center – main act for OSH related issues
Duty of Care
So far as is practicable
Self-regulation
Welfare of the workers
Participation of all level68
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
The purpose of the Act:
• To ensure the safety, health and welfare of persons at work
against safety risks arising from work activities
• Protecting other people and surrounding against health and safety
risks arising from the activities of persons at work.
• Promote a safe work environment for people at work that are
tailored to their physiological and psychological needs.
OSHA 1994
69
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Main provision:-
Section 15 – Responsibility of employer
Ensure the safety and health of the workers are maintained
Ensure the working environment free from hazard or risk
Section 16 – OSH polisy
Prepared, communicate and maintain the OSH policy according to act
Section 17 – Responsibility of employers to the public or people other than
his employee
OSHA 1994
70
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Main provision:-
Section 24 - Responsibility of Employee
To ensure the safety and health of yourself and others
Cooperation with employers for compliance with the Act
Section 29 - Appointment of OSH Officer
OSH officer appointed by resolution of OSH regulations
Section 30 - Establishment of Safety Committee
Establish and permit the Safety Committee to perform their roles effectively
Section 32 - NADOOPOD
A report on the accident and dangerous occurrence, occupational poisoning / disease
to the authorities
OSHA 1994
71
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
OTHER RELATED ACTS
72
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
FIRE SERVICES ACT 1988
The provisions necessary for the Fire and Rescue Department
to function effectively and efficiently, to protect people and
property from the risk of fire and for purposes connected
therewith.
Contains 63 sections and 4 rules
Key provisions: -
Elimination of fire hazard
Requirements of fire fighting equipment
Certificate Requirements (Fire Certificate) - needs to CFO
73
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
UBBL 1984
Enforced by local government for each state
Details specifications for premises such as lighting, ventilation,
fire protection systems etc.
Issuance of certificate of fitness for occupation (CFO) when
provisioning requirements are met
74
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
ENVIRONMENTAL QUALITY ACT 1974
The provisions necessary to prevent, eliminate, control hazards
and risks that threaten the quality of the environment.
Intended to advise the Director-General to carry out his duties
with respect to the environment.
Contains 51 provisions and regulations 30 which includes
pollution, waste management, emissions banned substances etc.
75
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
ELECTRICITY SUPPLY ACT 1990
Provisions for the electrical installations and electrical equipment to
ensure the safety of the installation / equipment and also the people
involved.
Details for safety factors involving electrical works, and also
competent person who is authorized to perform electrical engineering
work
Electricity Regulations 1994 require the installation must be tested
and approved before use and should be maintained by a competent
person 76
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
CIDB 1994
Promotions and boost quality in the construction industry
Promote the use of standards and the development of
construction techniques and building materials
Accreditation of skilled workforce and site supervisor
Accredit and register the construction contractors as well as
suspend, terminate and re-registration the blacklisted company
77
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
MODULE 2Preparing for Works
78
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Contents
Introduction
Planning the work
Organizing the work
Notifying the site to HSE
79
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Objective
To expose to the participant on the
preparation required before stating the
construction works
80
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
To ensure that health and safety issues are planned, organized,
controlled, monitored and reviewed.
Everyone controlling site work has health and safety
responsibilities.
Ensuring that the proposed work is not going to put others at risk
requires planning and organization.
Planning for the entire duration of the project
Introduction
81
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Gathering as much health and safety information about the
project and the proposed site before work begins is important.
Sources of information include:
the client, the design team & contract documents;
contractors and consultants;
equipment and material suppliers; and
HSE guidance and standards.
Planning the work
82
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Investigate the history of the site and its surroundings.
Inspect the site for any unusual features which might affect the work, or
how the work will affect others. Pay particular attention to:
asbestos or other contaminants;
overhead power lines and underground services;
unusual ground conditions;
public rights of way across the site;
nearby schools, footpaths, roads or railways; and
other activities going on at the site.
Pre-inspection
83
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
When estimating costs and preparing the programme, consider any
particular health and safety hazards associated with the work.
Make sure suitable allowances have been made in the price.
The job will run more smoothly, efficiently and profitably if hazards
have been predicted, planned for and controlled from the outset.
Having to stop or reschedule work to deal with emergencies wastes
time and money.
Work programme
84
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Inspect the machinery, plants, equipment to ensure suitability
Plan for the delivery of material, plant, equipment etc. and its storage area
Obtain health and safety information (MSDS, CSDS or manual). It may be
necessary to:
Get a specialist who is familiar with the necessary precautions;
Carry out an assessment of the health risks arising from substances
or equipment; and
act on your findings, e.g. by eliminating harmful substances where possible,
or by using a less hazardous method of work or providing training on the safe
use of the material or equipment.
Material/machinery safety
85
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Discuss and ask the contractor on safe working practice
Identify potential hazards and risks that may arise from their works
Assess the exposure of hazard to others (public and other
contractors)
Establish safety measures
Emergency and rescue procedures
Training need analysis
PPE requirements
Safe working methods
86
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Manpower requirement
Experienced, background & trained worker
Subcontractor management
Monitoring and supervision
Safe working instruction – to be communicated and understood
Coordination among the contractors
Work programme – scheduling and organizing the jobs and
resources
Organising the work
87
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Subjected to Section 35 under Factories And Machinery Act
1967, every person who undertakes any building operations or
works of engineering construction shall notify to Department of
Occupational Safety and Health not later than seven days from
the commencement of construction activities.
The notification is exempted to the construction activities that
can be completed in a period less than six (6) weeks and does
not involve the use of machinery.
Notify the authority
88
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Construction Industry Development Board
Contractor registration
Worker’s Safety Induction Course – green card
Site registration and levy for contract sum above RM 0.5 M
Department of Occupational Safety and Health
Certificate of Fitness for machinery
Registration of on site batching plant
Appointment or termination of Safety Officer
Authority concerned
89
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Department of Environment
Effluent discharge
Disturbance to nature
Local authorities - UBBL
Others – BOMBA, Police or Health
Authority concerned
90
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
MODULE 3Setting up the Site
91
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Contents
Site requirement
Facilities
Safety Plan
92
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Objectives
At the end, participants would know:
Fundamental health and safety issues that required to be
addressed when setting up the site
93
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Site Requirement
94
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Site access
Activities in and out of the site must go through a
designated gateway.
Must be no barriers and is suitable for vehicles
and equipment in and out. Foreign routes for
pedestrians.
Safe access onto and around the site for people and vehicles.
Ensure vehicles can be kept clear of pedestrians at vehicle loading/unloading areas,
parking and maneuvering places and areas where drivers’ vision may be obstructed.
95
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Worker’s safe passage
Worker walkway must be free from obstructions, have adequate light (50 lux) and signboards
Employees are not allowed to use the shortcut that expose them to danger.
* Rule 10 BOWEC - Access to Workplace
* Rule 20 BOWEC - Illumination of Passageways etc.96
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Site boundaries
Preventing unauthorized access / trespassers
Protecting the public from hazard from the site
Minimum height of 2 meters and not have any gaps or holes.
HOARDING
97
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Facilities
98
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Welfare facilities
The construction industry involves a lot of manual work and physical.
Welfare facilities should be provided so that the workers can reduce fatigue and
improve health in turn stimulate the job. Welfare facilities should be available are:
� Clean water to drink
� Preparation of food / dining
� Place locker / break room
� Sanitary / clean room
99
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Waste area
Proper waste management at site
Designated area for temporary waste collection before shipping
out from the construction site100
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Storage
Tidy, floor clean and dry, free of tripping hazard or slippery condition.
When storing materials, ensure a safe load for the floor or racks
Maintain the work passage or emergency routes are not blocked
Ensure that building materials are not stored within 2 m of open space during
construction
101
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Hazardous material’s storage
The storage area of flammable materials must have adequate warning signs and no
smoking in the vicinity of 6 meters from it.
Flammable waste materials must be stored in special storage before being taken
out for disposal.
Hazardous materials i.e. flammable liquid
should be stored separately from other
non-combustible materials and the storage
required special design.
Should have good air circulation.
102
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Illumination
Installation of emergency lights for emergency purposes
Avoid working in dark place or insufficient brightness
Natural light is available for
people to see to do their work
and move about the site safely.
Provide sufficient illumination to
prevent accident
103
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Safety Planning
104
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Safety Planning
Emergency procedures
Planning for an emergency
Fire safety
First aid
NADOOPOD
On site regulations
105
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Emergency procedures
Emergency response plan should be established and maintained.
Be able to identify the potential for accidents and emergency
situations
Address the prevention of occupational safety and health risk
associated with them.
The plan should be made according to the size and nature of activity
based on relevant international standard.
106
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Emergency procedures
The emergency procedures should:
(a) ensure that the necessary information, internal communication and
coordination are provided to protect all people in the event of an emergency at
the worksite;
(b) provide information and communication with the relevant authorities and the
neighbourhood and the emergency response services;
(c) address first aid, fire fighting and evacuation at construction sites; and
(d) provide relevant information and training to all members of the
organization, at all levels, including regular exercise in emergency response.107
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Planning for an emergency
1. Perform HIRARC to identify immediate
dangers
3. Objective/scope of the plan
5. Delegate roles and
responsibility
2. Review existing emergency plan
4. The best plan that suit
the current work
6. Make the plan works
108
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Fire safety
Flammable gases, liquids, solids
Source of ignition:- Static electricity- Smoking
materials- Naked flame
- Electrical equipment
- Hot surface
From the air or oxidizing
substances
109
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Fire safety
Classification of fires as per MS 1182:1990
Class D: Fires involving metals.
Class C: Fires involving gases
Class A: Fires involving solid materials, usually of an organic nature, in which
combustion normally takes place with the formation of glowing embers.
Class B: Fires involving liquids or liquefiable solids.
Class E: Fires involving electrical.
110
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Fire safety: means of giving warning
Set up an alert system
Periodically test the system to familiarize
Improvement to ensure the alert system is audible
and recognizable by the workers
111
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Fire safety: means of escape
Is a structural means whereby a safe route(s) is provided for
persons to travel from any point in a building to a place of safety.
Escape route should not be obstructed , safest way to safer place,
and communicated to workers
In planning means of escape, three major elements to consider:
travel distances (or, alternatively, direct distances);
escape route and exit capacities;
the number of occupants for whom means of escape must be provided112
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Fire safety: means of fighting fire
Type of Fire Extinguishers
• 4 main fire extinguishers:
• Water – Class A
• Foam – Class A and B
• Carbon dioxide – Class B and E
• Dry Chemical Powder – Class A, B, C and E
113
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Fire safety: means of fighting fire
How to Use the Fire Extinguishers
114
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Fire safety
IN THE EVENT OF FIRE
• Activate the emergency bell
• Evacuate the area and foes to safer place
• Call the fire brigade
• Inform the person in charge (BOMBA) whoever trap in
the building
If emergency siren activated, RESPONSE IMMEDIATELY
even though it is a drill
115
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
First aid
• Provide adequate and appropriate equipment, facilities and personnel to enable first aid to be given to workers when needed.
• Provision for first aid
– First aid box should be located at potential hazardous place
– First aid box equipped with enough equipment to cope with numbers of workers
– An appointed person for first aid for every 50 workers
– Information communicated to workers on details of appointed person or first and where to find them and easily recognizable.
• Workplace more than 200 workers should provide properly equipped first aid or treatment room. 116
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
First aid
• In the event of accident at work place:
– Alert the qualified first aider/doctor/ambulance
– Pay attention to the surrounding and ensure the area is safe
– Isolate the source of accident and evaluate the situation or condition of the victim. If possible, do not attempt to move the victim
– Check the breathing and heart beat. If bleeding, make effort to stop the bleeding by pressing the injured area.
– Ensure victim not shivering and motivate the victim.
– Do not remove any evidence.
117
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Reporting the accidents
• Under the OSHA 1994 and NADOOPOD 2004 regulations
• Whoever in control at site has obligation to report any incidents or accidents based on details as prescribed in regulations
• Generally, immediately report on accidents, dangerous occurrences, occupational poisoning & occupational diseases to authorities.
118
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
On site regulations
• Every workplace has specific regulations for safe work.
• In form of written - includes all operations especially those involve in high risks as working at heights, excavation, confine space and so on.
119
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Signage
120
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Signage
121
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Signage
122
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Signage
123
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
MODULE 4Construction Phase
124
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
CONTENTS
Overview of Construction Safety
Stage 1: Infrastructure Work
Stage 2: Substructure
Stage 3: Super structure
Stage 4: Finishing works
General requirements
125
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Overview of Construction Safety
Stage 1: Infrastructure Work
Stage 2: Substructure
Stage 3: Super structure
Stage 4: Finishing works
General requirements
126
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
10 common accidents
Physical Health
1. Falls incl. from height 1. Asbestos
2. Mobile plant 2. Manual handling
3. Falling objects & collapse 3. Noise &vibration
4. Electrical accidents 4. Chemicals
5. Trips
127
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 1: Infrastructure Work
Survey work
Site clearing
Logistic – mobilisation of materials, machine, man etc.
Earthwork
Service relocation work
Confined space
Demolition
128
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 1: Survey work
129
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 1: Survey work
JOB SCOPE: SURVEY WORKHAZARDCATEGORY:
1. BIOLOGICAL
2. ERGONOMIC
3. PSYCOSOCIAL
WORKPLACE HAZARD RISKS
1. BITTEN/STUNG 1. SWOLLEN
2. REPITITIVE MOVEMENT 2. BACK PAIN
3. FALLS 3. INJURY
4. HEAT STRESS 4. FAINT/UNCONCIOUS
CONTRIBUTING FACTOR CONTROL MEASURE
1. WILD ANIMAL OR INSECTS 1. INSECT REPELENT CREAM
2. LIFTING HEAVY EQUIPMENTS 2.PPE - COVERALL, SAFETY BOOT, HAT
3. TRIPPING & SLIPPING 3. PROPER MANUAL HANDLING ETC
4. SUN RADIANCE130
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 1: Site clearing
131
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 1: Site clearing
JOB SCOPE: SITE CLEARINGHAZARDCATEGORY:
1. BIOLOGICAL
2. PHYSICAL
3. PSYCOSOCIAL
WORKPLACE HAZARD RISKS
1. BITTEN/STUNG 1. SWOLLEN
2. MACHINERY OVERTURN 2. INJURY
3. FALLS 3. INJURY
4. HEAT STRESS 4. FAINT/UNCONCIOUS
CONTRIBUTING FACTOR CONTROL MEASURE
1. WILD ANIMAL OR INSECTS 1. INSECT REPELENT CREAM
2. UNEVEN @ UNSTABLE GROUND 2. PPE - COVERALL, SAFETY BOOT, HAT
3. TRIPPING & SLIPPING 3. PROPER MANUAL HANDLING
4. SUN RADIANCE 4. JOB ROTATION ETC132
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 1: Earth work
133
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 1: Earth work
JOB SCOPE: EARTH WORKHAZARDCATEGORY:
1. BIOLOGICAL
2. PHYSICAL
3. PSYCOSOCIAL
WORKPLACE HAZARD RISKS
1. EXTREME WEATHER 1. ILL HEALTH
2. MACHINERY OVERTURN 2. INJURY
3. SLIP, TRIP OR FALLS 3. INJURY
4. HEAT STRESS 4. FAINT/UNCONCIOUS
CONTRIBUTING FACTOR CONTROL MEASURE
1. WILD ANIMAL OR INSECTS 1. INSECT REPELENT CREAM
2. UNEVEN/UNSTABLE/SOFT GROUND 2. STABILISED THE GROUND, LEVELING
3. TRIPPING & SLIPPING 3. PROPER MANUAL HANDLING
4. SUN RADIANCE 4. PPE - COVERALL, SAFETY BOOT, HAT ETC134
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 1: Service relocation work
135
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 1: Service relocation work
JOB SCOPE: SERVICE RELOCATION WORKHAZARDCATEGORY:
1. BIOLOGICAL
2. CHEMICAL
3. PSYCOSOCIAL
WORKPLACE HAZARD RISKS
1. MACHINERY OVERTURN 1. INJURY
2. ENBANKMENT COLLAPSE 2. INJURY, DEATH
3. SLIP, TRIP & FALLS 3. INJURY
4. UTILITIES DAMAGE 4. UTILITIES BREAKDOWN
CONTRIBUTING FACTOR CONTROL MEASURE
1. UNEVEN GROUND 1. STABILSED THE GROUND
2. SOFT/UNSTABLE SOIL 2. STABILISED SOIL, SUPERVISION
3. TRIPPING & SLIPPING 3. PROPER MANUAL HANDLING, COMPETENCY
4. EXCAVATION 4. PPE - COVERALL, SAFETY BOOT, HAT ETC136
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 1: Confined space
• OKSIGEN > 23% (oxygen richness) cause flammable
materials or liquids easily caught fire• When Oxygen < 19.5% � oxygen deficiency causing
dizziness and faint/unconcoius
137
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Why confined space is dangerous place
Closed manhole/sewage tunnel for a long period accumulate
toxic gaseous or flammable gaseous likes hydrogen sulfide, ammonia, methane or else.
H2S
CH4
Sometimes, toxic
materials/substances/wastes were illegally
dump into the sewage
lines or manholes.
Also contaminated
due to leaks of tanks or pipelines
containing toxic
materials which seep through the
sol to the sewage lines or manhole.
138
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 1: Confined space
Prior to confined space works, obtain permit from relevant
authorities and ensure the site has been inspected by competent person and approved to enter.
139
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 1: Confined space
JOB SCOPE: CONFINED SPACEHAZARDCATEGORY:
1. BIOLOGICAL
2. CHEMICAL
3. PSYCOSOCIAL
4. ERGONOMICS
WORKPLACE HAZARD RISKS
1. SUFFOCATION 1. FAINT/DEATH
2. ELECTROCUTION 2. INJURY, DEATH
3. SLIP, TRIP, FALLS 3. INJURY
4. INHALATION OF TOXIC GASEOUS 4. FAINT/UNCONCIOUS/DEATH
CONTRIBUTING FACTOR CONTROL MEASURE
1. RESPIRATORY FAILURE 1. ADEQUATE VENTILATION, GAS DETECTOR
2. ELECTRICAL INSTALLATION/CABLE 2. CABLE DETECTION, PTW APPROVAL
3. TRIPPING & SLIPPING 3. PROPER MANUAL HANDLING
4. TOXIC GASOUES 4. PPE - COVERALL, SAFETY BOOT, HAT, SCBA140
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
PPE confined space
If the concentration still hazardous, the workers shall wear proper
PPE likes respirator or self-contained breathing apparatus (SCBA)
??
??
??
Fresh air
O2
O2
O2
O2
141
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Equipment used for confined space entry
142
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 1: Demolition
• Done by competence person or company registered with authorities
• Method of demolition is depending on design and construction of the building
• Prior to work, approval from relevant authorities 143
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 1: Demolition
JOB SCOPE: DEMOLITIONHAZARDCATEGORY:
1. BIOLOGICAL
2. ERGONOMIC
3. PSYCOSOCIAL
WORKPLACE HAZARD RISKS
1. HIT BY FLYING OBJECT 1. INJURY
2. ERGONOMICS 2. BACK PAIN
3. SLIP, TRIP, FALLS 3. INJURY
4. HEAT STRESS 4. FAINT/UNCONCIOUS
5. FALL FROM HEIGHT 5. INJURY DEATH
CONTRIBUTING FACTOR CONTROL MEASURE
1. FLYING OBJECT/DEBRIS 1. ISOLATION, NETTING
2. REPITITIVE MOVEMENT 2. JOB ROTATION, PROPER EQUIPMENT
3. TRIPPING & SLIPPING 3. PROPER MANUAL HANDLING
4. SUN RADIANCE 4. PPE - COVERALL, SAFETY BOOT, HAT ETC144
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
General requirements
• Remove fragile object such as glasses and disconnect gas pipelines, electricity, water
• Sufficient warning sign and ensure proper
communication to stakeholder especially public• Get consent from relevant authorities• Thorough inspection of the structures of the building
to be demolished.• Supervised and monitor by competent person during
the works• Where practicable, works only on approved platform
design for the work• Obey safe procedure working at height
145
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 2: Substructure
Foundation works
Piling work safety
Concreting work safety
Welding and cutting work safety
146
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 2: Piling work
147
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 2: Piling work
JOB SCOPE: PILING WORKHAZARDCATEGORY:
1. PHYSICAL
2. ERGONOMIC
3. PSYCOSOCIAL
WORKPLACE HAZARD RISKS
1. NOISE AND VIBRATION 1. HEARING PROBLEM, DEAFNESS
2. GROUND FAILURE 2. INJURY, DEATH
3. FALLS 3. INJURY
4. HEAT STRESS 4. FAINT/UNCONCIOUS
CONTRIBUTING FACTOR CONTROL MEASURE
1. NOISE 1. ISOLATION
2. SOFT GROUND, UNSTABLE 2. SOP, SUPERVISION
3. OPENING, EXCAVATION 3. SIGNAGE, PTW,
4. SUN RADIANCE 4. PPE - COVERALL, SAFETY BOOT, HAT ETC148
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 2: Concreting work
149
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 2: Concreting work
JOB SCOPE: CONCRETING WORKHAZARDCATEGORY:
1. PHYSICAL
2. ERGONOMIC
3. PSYCOSOCIAL
WORKPLACE HAZARD RISKS
1. FALLING FROM HEIGHT 1. INJURY, DEATH
2. REPITITIVE MOVEMENT 2. BACK PAIN
3. SLIP, TRIP, FALLS 3. INJURY
4. HEAT STRESS 4. FAINT/UNCONCIOUS
CONTRIBUTING FACTOR CONTROL MEASURE
1. UNSAFE ACT, NEGLIGENT 1. SIGNAGE, RAILINGS, NETTING
2. LIFTING HEAVY EQUIPMENTS 2. PROPER MANUAL HANDLING
3. TRIPPING & SLIPPING 3. HOUSEKEEPING
4. SUN RADIANCE 4. PPE - COVERALL, SAFETY BOOT, HAT ETC150
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 2: Welding and cutting
Gas cutting and welding
Oxy-acetylene
Electrical arc welding
151
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 2: Welding and cutting
JOB SCOPE: WELDING AND CUTTING HAZARDCATEGORY:
1. PHYSICAL
2. CHEMICAL
3. BIOLOGICAL
WORKPLACE HAZARD RISKS
1. FALLING OBJECT 1. INJURY
2. SMOKE, HARMFUL GASEOUS 2. RESPIRATORY PROBLEM
3. FIRE & EXPLOSION 3. INJURY , DEATH
4. HEAT STRESS 4. FAINT/UNCONCIOUS
CONTRIBUTING FACTOR CONTROL MEASURE
1. NEGLIGENT 1. HOUSEKEEPING, TOE BOARD
2. TOXIC GASOUES OF WELDING 2. VENTILATION, RESPIRATOR
3. WELDING EQUIPMENT 3. SOP, SUPERVISION
4. SUN RADIANCE4. PPE – WELDER MASK, SAFETY BOOT, HAT
ETC 152
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 2: Welding and cutting
• Ensure work place well ventilated
• Ensure work place or surrounding free from flammable or combustible materials
• If arc welding, emergency cut off located at reachable distance
• All the equipment are inspected and free from defect.
• Stand by extinguishment equipment in case of fire153
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 2: Welding and cutting
• Gas cylinder stored upright and in special secured cage with good ventilation
• Keep distance gas cylinder storage from occupied place and flammable materials
• Isolate and label empty cylinder
• Do not store cylinder in confined space or under ground store or enclosed place. 154
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 3: Super structure
Scaffolds
Temporary structure
Chutes
Catch platform
Ladder safety
Lifting Operations
Passenger Hoist
Lifting crane155
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 3: Scaffolding
Sebuah platfom sementara yang tinggi bagi
membantu melaksanakan sesuatu kerja
156
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 3: Scaffolding
157
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 3: Scaffolding safety
• The scaffolding should be designed, erected, modified, maintained and dismantled by ONLY competent and skilled worker which supervised by competent personnel.
• Mandatory requirement to inspect and approve the scaffolding once in a week or after bad weather (rains, heavy storm etc) and such inspection should be recorded.
• Safety of scaffold depending on:
– Erection comply with manufacturer’s OEM, specification, code of practice and done by skilled and competence workers
– The in and out pathway is safe 158
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 3: Scaffolding tag
159
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 3: Scaffolding safety
• Static scaffold should not be more than 15 m & mobile not more than 9.6 m or 12 m if secured to fixed structure.
• Minimum size for wheel of mobile scaffold is 5 inches and properly secured on level ground and locked before working.
• Do not move/push the mobile while people or materials still on top
• Mechanically push or pull the scaffold is not recommended 160
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 3: Scaffolding safety
• No gap more than 1” between platform.
• Platform more than 2 meter should install guard rail high about 1 meter from platform and toe board min 6 inches high.
• Calculation and endorsement for scaffold more than 40 m high for tubular and 15 m for other types
• Structure strengthening required for loading bay or storage bay and safely blockaded with guard rail and toe board 161
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 3: Scaffolds & Formwork
JOB SCOPE: SCAFFOLDS AND FORMWORKHAZARDCATEGORY:
1. PHYSICAL
2. ERGONOMICS
3. BIOLOGICAL
WORKPLACE HAZARD RISKS
1. FALLING OBJECT 1. INJURY
2. ELECTROCUTION 2. INJURY DEATH
3. COLLAPSE 3. INJURY , DEATH
4. HEAT STRESS 4. FAINT/UNCONCIOUS
CONTRIBUTING FACTOR CONTROL MEASURE
1. NEGLIGENT 1. HOUSEKEEPING, TOE BOARD
2. ELECTRICAL 2. EARTHING, CHECK THE POWERED EQPT ETC
3. UNSTABLE STRUCTURE 3. SOP, COMPETENCY, INSPECTION
4. SUN RADIANCE4. PPE – WELDER MASK, SAFETY BOOT, HAT
ETC 162
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 3: Fall prevention method
Personal Fall
Arrest System(PFAS)
Guardrails Safety netting
163
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 3: Fall prevention method
164
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Temporary structure
Use of approved chute for waste removal for height more than 6 m
Barricade, isolate or fence off the collection area
165
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Temporary structure
Construction waste that falls can be arrested by the use of catch
platforms.
Catch platforms should be cleaned daily to avoid the overloading
which will cause it to collapse.
CATCH PLATFORM
166
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 3: Ladder safety
Straight ladder or access ladder – for accessing to
and from a space or place
Step ladder – for performance of work
167
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 3: Ladder safety
• Set the ladder on a flat and firm ground
• Do not work on the stairs in front of a closed door
• Tie the ladder at the top and bottom in the absence of helper
• Stairs must have a height of 1m above the landing (roof & height)
• Use the principle of 1:4
168
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 3: Ladder safety
JOB SCOPE: LADDER SAFETYHAZARDCATEGORY:
1. PHYSICAL
2. ERGONOMIC
WORKPLACE HAZARD RISKS
1. FALL FROM HEIGHT 1. INJURY
2. REPITITIVE MOVEMENT 2. BODY PAIN
3. FALLING OBJECT 3. INJURY
4. AWKWARD POSTURE 4. BODY PAIN
CONTRIBUTING FACTOR CONTROL MEASURE
1. UNSAFE ACT, NEGLIGENT 1. PROPER TRAINING, LADDER INSPECTION
2. LIFTING HEAVY EQUIPMENTS 2. PROPER MANUAL HANDLING
3. UNSAFE ACT 3. SUPERVISION, SAFE WORK PROCEDURE
4. AWKWARD POSTURE 4. PPE - COVERALL, SAFETY BOOT, HAT ETC169
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 3: Passenger Hoist
• Hoist must be installed or dismantled by trained and competence person
• Only operate approved hoist
• The hoist should be operated by trained hoist operator
• Hoist must be equipped with 'fall arrester' and 'over-run', in place of 2m high fence out and the safe working load as shown in the hoist. 170
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 3: Passenger Hoist
JOB SCOPE: PASSENGER HOISTHAZARDCATEGORY:
1. PHYSICAL
WORKPLACE HAZARD RISKS
1. FALL FROM HEIGHT 1. INJURY
2. PINCHED/STUCK IN BETWEEN 2. INJURY
3. FALLING OBJECT 3. INJURY
CONTRIBUTING FACTOR CONTROL MEASURE
1. UNSAFE LIFTING DEVICES 1. CERTIFIED LIFTING DEVICES
2. NEGLIGENT 2. PROPER TRAINING, SOP
3. NEGLIGENT 3. SAFE WALKWAY, OVERHEAD PROTECTION
4. SIGNAGE171
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 3: Lifting crane
• A crane is equipment that be able to lift up or down or transfer loads using its long boom
• Type found at site:– Crawler crane
– Mobile crane
– Tower crane 172
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Risks associated with crane
173
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Loads
• Load calculation basing on material’s delivery note
• Ensure calculation is right and should be done by competent person
• Ensure the loading capacity within acceptable range of the crane
• Load capacity depending on
• Ground condition & surface condition
• Wind direction
• Other loads
• Cable, sling and other lifting equipment
• Ensure the crane operator know:
• Load capacity
• Scope
• Lifting procedure 174
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Accident involving crane
IMBALANCE LOADS
175
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 3: Lifting crane
JOB SCOPE: LIFTING CRANEHAZARDCATEGORY:
1. PHYSICAL
WORKPLACE HAZARD RISKS
1. FALLING OBJECT 1. INJURY
2. CRANE FAILURE 2. DAMAGE PROPERTY, INJURY, DEATH
3. GROUND/FOUNDATION FAILURE 3. DAMAGE PROPERTY, INJURY, DEATH
4. COMMUNICATION FAILURE 4. MISPLACE, ACCIDENT
CONTRIBUTING FACTOR CONTROL MEASURE
1. HUMAN/MECHANICAL ERROR 1. APPROVED CRANE,
2. HUMAN/MECHANICAL ERROR 2. LIFTING/RIGGING SOP
3. SOFT/UNSTABLE SOIL 3. PROPER CRANE HANDLING
4. INCOMPETENT, HUMAN ERROR 4. TRAINED OPERATOR176
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 4: Finishing works
Roofing work
Insulation & cladding work
Electrical safety
Testing and Commissioning
177
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 4: Roofing work
• Risk associated with working on the roof– Falling from roof
– Falling when stepping onto rotten roof
– Fall from stair or scaffolding
– Lightning strike when bad weather 178
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 4: Roofing work
179
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 4: Roofing work
JOB SCOPE: ROOFING WORKHAZARDCATEGORY:
1. PHYSICAL
2. ERGONOMIC
WORKPLACE HAZARD RISKS
1. FALLING FROM HEIGHT 1. INJURY, DEATH
2. FALLING OBJECT 2. INJURY, DEATH
3. STRIKE BY LIGTHNING 3. INJURY, DEATH
4. HEAT STRESS 4. FAINT/UNCONCIOUS
CONTRIBUTING FACTOR CONTROL MEASURE
1. HUMAN/MECHANICAL ERROR 1. FALL PROTECTION, WARNING SIGN
2. INSECURED, HUMAN ERROR 2. TRAINING
3. LIGTHNING 3. SOP, SAFE WORKING INSTRUCTION
4. SUN RADIANCE 4. PPE - COVERALL, SAFETY BOOT, HAT ETC180
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 4: Painting
181
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 4: Painting
JOB SCOPE: PAINTING HAZARDCATEGORY:
1. PHYSICAL
2. CHEMICAL
3. ERGONOMICS
WORKPLACE HAZARD RISKS
1. FALLING FROM HEIGHT 1. INJURY
2. FALLING OBJECT 2. INJURY
3. AWKWARD POSTURE 3. BODY PAIN
4. HEAT STRESS 4. FAINT/UNCONCIOUS
CONTRIBUTING FACTOR CONTROL MEASURE
1. HUMAN BEHAVIOUR 1. FALL PROTECTION, SIGNAGE
2. UNSAFE ACT 2. TRAINING, SUPERVISON
3. REPEATITIVE MOVEMENT 3. PROPER MANUAL HANDLING
4. SUN RADIANCE 4. PPE - COVERALL, SAFETY BOOT, HAT182
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 4: Plastering
183
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 4: Plastering
JOB SCOPE: PLASTERINGHAZARDCATEGORY:
1. PHYSICAL
2. CHEMICAL
3. ERGONOMICS
WORKPLACE HAZARD RISKS
1. FALLING FROM HEIGHT 1. INJURY
2. FALLING OBJECT 2. INJURY
3. AWKWARD POSTURE 3. BODY PAIN
4. HEAT STRESS 4. FAINT/UNCONCIOUS
CONTRIBUTING FACTOR CONTROL MEASURE
1. HUMAN BEHAVIOUR 1. FALL PROTECTION, SIGNAGE
2. UNSAFE ACT 2. TRAINING, SUPERVISON
3. REPEATITIVE MOVEMENT 3. PROPER MANUAL HANDLING
4. SUN RADIANCE 4. PPE - COVERALL, SAFETY BOOT, HAT184
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 4: Electrical safety
• Object non conductive (insulation) – wood, plastic, glass,
rubber etc
• Electrical energy is hazard that is -
• Unseen
• No smell
• Quiet
• Electrical energy flow thru
conductor -
• Metal
• Water
• Human body
185
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 4: Electrical safety
• Basic safety precaution in electrical is important when performing electrical work. Hazard from electrical • Electrocuted
• Fire
• Electric static
• Explosion
• Two main protection from electricity: -• Protection from direct contact – insulation
• Protection from indirect contact – earthing
186
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 4: Electrical safety
The degree of electrocution
depending on:
• Flow of current in body
• Amount of current enter the
body
• Period of exposure
187
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 4: Electrical safety
AMOUNT OF CURRENT
SEVERITY / CONSEQUENCES
< 1 mA NO HARM
1-8 mA SLIGHTLY SHOCK, BUT NOT SO HURT AND MIGHT TEMPORARY LOOSE MUSCLE
CONTROL
8-15 mA PANTFUL SHOCK EFFECT, HAZARD RELEASE BY ITSELF
15-20 mA PAINFUL SHOCK EFFECT, THE HAZARD CAN NOT BE RELEASED ON ITS OWN AND
LOSS OF MUSCLE CONTROL
20-50 mA PAINFUL; SEVERE CONTRACTION IN THE MUSCLES AND DIFFICULTY IN
BREATHING
100-200 mA VENTRICULAR FIBRILLATION WHICH IS A HEART CONDITION THAT CAN RESULT
IN DEATH
> 200 mA SEVERE BURNS AND SEVERE CONTRACTION IN THE MUSCLES, CAUSING THE
MUSCLES IN THE CHEST COMPRESS THE HEART AND CAUSE CARDIAC ARREST
(DEATH)188
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 4: Electrical safety
JOB SCOPE: ELECTRICAL WORKHAZARDCATEGORY:
1. PHYSICAL
2. ERGONOMIC
WORKPLACE HAZARD RISKS
1. ELECTROCUTION 1. INJURY, DEATH
2. SHARP EDGE 2. BACK PAIN
3. TRIP, SLIP OR FALLS 3. INJURY
4. HEAT STRESS 4. FAINT/UNCONCIOUS
CONTRIBUTING FACTOR CONTROL MEASURE
1. ELECTRICITY 1. LOCKOUT TAG OUT PROCEDURE
2. LIFTING HEAVY EQUIPMENTS 2. PPE - COVERALL, SAFETY BOOT, HAT
3. TRIPPING & SLIPPING 3. GOOD MANUAL HANDLING & HOUSEKEEPING
4. SUN RADIANCE 4. SOP, TRAINING AND COMPETENCY ETC189
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Stage 4: Electrical safety
MCB
MCCBELCB / RCCB
FUSE
HRC FUSE CUT OUT FUSE190
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
General requirements
Hand power tool safety
Road traffic management
Working over water
Permit to Work
191
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
General requirements
Hand power tool safetySection 147 – 153 BOWEC – Hand & Power Tools
192
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
General requirements
Hand power tool safety
� Well maintained
� Right tools
� Inspect before use
� Follow instruction
� Right PPE
193
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
General requirements
� Do not use defective tools
� Must have protection or guarding
Hand power tool safety
194
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
General requirements
� Use according to the capacity
specified by the manufacturer
� Wear appropriate PPE - gloves
and safety shoes
� Store in a dry place
� Precautious if working in a
humid place
� Ensure sufficient light
Hand power tool safety
195
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
General requirements
Use of modified tool – grinder
196
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
General requirements
• Work system should be planned carefully so as not to
endanger road users and workers themselves.
• Accidents can happen to other users as a result of broken
machinery or vehicles site if negligent.
Traffic management
197
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
General requirements
• Traffic Signal Manual must be used to determine the needs
and size of the safety zone signal is necessary.
• Local authorities and the police
should be contacted to determine if the right job path should be closed
and traffic control systems such as
temporary traffic lights and clear signage should be used to control
the flow of traffic
Traffic management
198
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
General requirements
• Working over the water surface exposes the workers to risk of drowning or swept away when fall into the water.
• Safety precautions must be observed so that the employee is not dropped or pushed into the water.
• Determine the employee can be saved in the shortest period if they fall into the water.
Working over water
199
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
General requirements
• Helmet and non slippery safety boot shall be wearing all time
• Workers shall wears floatable safety jacket
Working over water
200
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
General requirements
• When working on swift currents, run the rope or net across the surface
of the water on the downstream side of all workplace locations and
equipped with floats or other tools that can help the employee to float
during emergency.
• The line must be tied to a solid structure at each end.
Working over water
201
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
General requirements
• Rescue Line (grab lines) should be placed with some distance (reachable distance) to the structure or platform.
Working over water• A platform must be
built properly and equipped with retaining bar and toe-board around.
• Safety nets will catch fallen worker which then can be rescued by boat.
202
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
PTW system is a formal written system used to regulate certain occupations that have been identified to possess potential hazards and risks and also one of the means of communication between employers (who create jobs & Hazard) and employees.
Based on the definition by the International Association of Oil and Gas Association (OGP) in the Guidelines in PTW system, serial Report 6.29/189; published in January 1993
203
Permit To Work
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
To avoid or reduce the risk of a serious accident or
incident for the work to be carried out
To control and coordinate work activities
To provide a system of communication between the end
users or employers with subcontractors
Evidence or record of evidence
204
Objective of PTW
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
� A formal written system detailing on working, attached with
HIRARC or similar
� A form of safe work instructions
� Ensure that all elements of the work system are adhered to
� Clearly identifies the responsibilities of each person
involved
� The involvement of all relevant parties, including contractors
� Ensure everyone is trained
� A checking mechanism (check & balance)
205
Characteristic of PTW
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
Hot work such as welding, gas cutting, etc
Electrical works
Working with hazardous materials
Confined space
Working over/in the water
Handle radioactive materials and explosives
Lifting heavy materials etc.
...........SO ON...
206
Example of PTW
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
� Hot work Permit
� General Work Permit i.e. Cold Work
� Electrical Work Permit
� Radiation Work Permit
� Pressure Testing Permit
� Lifting Permit
� Blasting Permit etc
207
Type of PTW
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
208
Procedure of PTW
Oleh: Engr. Norrazman Zaiha bin Zainol Email: [email protected]
OSH514 : SAFETY IN CONSTRUCTION
THE END
Thanks you
209