Date post: | 20-Jan-2015 |
Category: |
Business |
Upload: | grisellcarba79 |
View: | 1,880 times |
Download: | 1 times |
OEE-Overall Equipment
Effectiveness
Guide
July 2010
OEE-When to use
1. Does your production have bottlenecks that you
are not aware of?
2. Could one machine be dragging down the entire
facility?
3. Does your equipment have excess capacity that
could be easily and inexpensively tapped?
HELPS YOU INSTANTLY
MAKE MORE WITH WHAT
YOU HAVE
OEE-Benefits
OEE- What is it
OEE is just a Best Practice that
helps you monitor and improve
the effectiveness of your
processes
OEE- Guide
OEE
Factors
Six Big
Losses
World
Class OEE
Formulas OEE
Example
Visual
OEE
OEE-Factors
Plant Operating Time
Plant Operating Time
Operating Time
Net Operating Time
Fully Productive Time Quality
Loss
Speed
Loss
Down Time
Loss
Planned
Shutdown
Time Available
i.e. LMI Mex
10hrs
Subtract
Lunch,Breaks,
Maintenace
Subtract
•Equipment failure
•Mat. Shortages,
•Changeover time Subtract
•Different material, machine wear,
operator inefficiency
Subtract
•Rework time
•Scrap
OEE Goal is to Maximize Fully
Productive Time
OEE-Factors
OEE LOSS OEE Factor
Planned Shutdown *Not part of the calculation
Down Time Loss *Availability=Ratio of Operating Time to Planned Production Time
(Operating Time=Planned Production Time-Down Time Loss)
*100% Availability means the process has been running without any recorded stops
Speed Loss *Performance= Ratio of Net Operating time to Operating Time
(Net Operating Time=Operating Time-Speed Loss)
*Interpreted as Ideal Cycle Time to Actual Cycle Time
*100% Performance means the process has been consistently running at its
theoretical maximun speed
Quality Loss *Quality=Ratio of Fully Productive Time to Net Operating Time
(Fully Productive Time=Net Operating Time-Quality Loss)
*Interpreted as the ratio of Good Pieces to Total Pieces
*100% Qaulity means there have been no reject or rework pieces
The following table is a review of the interpretation of the core concepts.
This factor can then drill down into productivity losses
OEE-6 Big Losses
Those
productivity
Losses are
called the SIX
BIG LOSSES
Six Big Loss
Category
OEE Loss
Category Event Examples Comment
Breakdowns Down Time Loss Tooling failures
Unplanned maintenance
General breakdowns
Equipment failure
Set Up and
Adjustments Down Time Loss Setup/changeover
Material shortages
Operator shortages
Major adjustments
Warm-Up Time
Small Stops Speed Loss Obstructed product flow
Component jams
Misfeeds
Sensored blocked
Delivery blocked
Cleaning / Checking
Reduced
Speed Speed Loss Rough running
Under nameplate capacity
Under designed capacity
Equipment wear
Operator inefficiency
1.Startup
Rejects Quality Loss Scrap
2.Production Rework
Rejects In process damage
In process expiration
Incorrect assembly
Anything that prevents
the process running
normal speed
1.Rejects during warm
up, start up and early
production
2. Rejects during
steady-state
production
Typically includes stops
that are under five
minutes
This loss is adressed
through set up
reduction projects
There is flexibility to
decide between a
breakdown and small
stop
OEE-World Class
OEE Factor World Class
Availability 90.0%
Performance 95.0%
Quality 99.9%
OEE 85.0%
Accepted World Class
Performance per Factor is:
Studies indicate that most manufacturing plants are around 60% performance
in OEE. A world class is considered to be 85% or more.
OEE-Formulas
Availability= Operating Time / Planned Production Time
Performance = Ideal Cycle Time / (Operating Time/Total Pieces)
Quality = Good Pieces / Total Pieces
OEE = Availability x Performance x Quality
OEE-Example
•Planned Production Time= [Shift Length –Breaks] =[600-80]=520min
•Operating Time= [Planned Production Time-Down Time]=[480-47]=433
•Good Pieces= [Total Pieces – Reject Pieces]=[19,271-423]=18,848
Item Data
Shift Length 10 hrs = 600 min
Short Breaks 2 at 10min = 20min
Meetings 30 min
Meal Break 1 at 30 min = 30 min
Down Time 47 min
Ideal Run Rate 60 pieces per minute
Total Pieces 19,271 pieces
Reject Pieces 423
OEE-Example
Availability =
= 433/520
= 0.8326923 83.3%
Performance =
= (19,271pieces/433minutes)/60 pieces per minute
= 0.7417629 74.2%
Quality =
18,848 / 19,271
0.9780499 97.8%
OEE =
.8326 x .7417 x .978
= 0.6041026 60.4%
Good Pieces/ Total Pieces
(Total Pieces/operating Time)/Ideal Run Rate
Operating Time/Planned Production Time
Availability x Performance x Quality
OEE-Visual
It is very important to have performance data
Available and In Real Time to
EVERYONE
Benefits:
•Operators quickly respond to problems
•Gauge to make adjustments that lead to incremental
improvements
•Empowers operators to take immediate action
•Helps monitor plant floor activity in real time