Mansfield LFE ActivityMansfield LFE ActivityMansfield LFE ActivityMansfield LFE ActivitySeptember 5, 2008September 5, 2008
Valve Automation
Company Confidential 4/9/23 / Slide 2
Define the Process Situation Define the Process Situation Define the Process Situation Define the Process Situation Focus is the Rotary Vane Actuators, which comprise 75% of the sales revenue
with orders up 60%. Recently, delivery lead times have been extended to 20 weeks from 16. The
front-end activity comprises about five weeks of the lead time to fulfill the customer order.
Project Managers process purchase orders into shippable product by the cooperative effort with Accounting, Engineering, Procurement, and Production.
Binders with a checklist circulate in a linear fashion among responsible parties. Target dates for customer delivery are based upon available production
capacity and lead time to acquire components. The delivery date drives the schedule for engineering development of the BOM.
Engineering equivalent capacity of 3.2 staff (45% direct time) completes the BOMs necessary to build the products and an attendant set of associate documents are created to ship the products. Recently, Engineering Manager position is open.
Design Complexity ranges lead-time from one to three weeks in Engineering.
Valve Automation
Company Confidential 4/9/23 / Slide 3
Data Analysis Data Analysis Data Analysis Data Analysis 65 orders gathered beginning FY08 P02
to P05 (annual rate 195 orders) Average order has 2 line items Off-shore orders tend to be more
Design Complex
Valve Automation
Company Confidential 4/9/23 / Slide 4
Project Information Effect on Lead-timeProject Information Effect on Lead-timeProject Information Effect on Lead-timeProject Information Effect on Lead-time
Information availability/correctness reduce 1st Pass Yield, which increases rework activity
Valve Automation
Company Confidential 4/9/23 / Slide 5
Effect of Design Complexity on Lead-TimeEffect of Design Complexity on Lead-TimeEffect of Design Complexity on Lead-TimeEffect of Design Complexity on Lead-Time
Type
Range o
f Days
C3C2C1B
80
70
60
50
40
30
20
10
0
77
41.8
20.0811
28.6111
Boxplot of Initial Review to BOM Complete vs Type (Mean Days)
Valve Automation
Company Confidential 4/9/23 / Slide 6
Current Data Control Current Data Control Current Data Control Current Data Control
Valve Automation
Company Confidential 4/9/23 / Slide 7
WorkManager Data Control of WorkManager Data Control of Engineering Worksheets Engineering Worksheets WorkManager Data Control of WorkManager Data Control of Engineering Worksheets Engineering Worksheets
Linear Processing
Valve Automation
Company Confidential 4/9/23 / Slide 8
Time Allocation on Process ChecklistTime Allocation on Process ChecklistTime Allocation on Process ChecklistTime Allocation on Process Checklist
Begin
Target Info Complete
Date11 days
Target Engineering
Due Date30 days
0
5
10
15
20
25
30
35
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Days in Process
Sales Order Checklist Steps
Lead Time to Process Sales Order for Production
7 days7 daysTrade ComplianceTrade Compliance
Egr WS Egr WS Initial Info CompleteInitial Info Complete
14 days14 daysConfirm Info Complete Confirm Info Complete
Complete BOMComplete BOMType / Review BOMType / Review BOM
Valve Automation
Company Confidential 4/9/23 / Slide 9
Current State VSM – Order ManagementCurrent State VSM – Order ManagementCurrent State VSM – Order ManagementCurrent State VSM – Order Management
Valve Automation
Company Confidential 4/9/23 / Slide 10
Current State VSM – Order ManagementCurrent State VSM – Order ManagementCurrent State VSM – Order ManagementCurrent State VSM – Order Management
Valve Automation
Company Confidential 4/9/23 / Slide 11
Current State VSM – Order ManagementCurrent State VSM – Order ManagementCurrent State VSM – Order ManagementCurrent State VSM – Order Management
Valve Automation
Company Confidential 4/9/23 / Slide 12
Current State VSM – Order ManagementCurrent State VSM – Order ManagementCurrent State VSM – Order ManagementCurrent State VSM – Order Management
Valve Automation
Company Confidential 4/9/23 / Slide 13
Current State VSM – Order ManagementCurrent State VSM – Order ManagementCurrent State VSM – Order ManagementCurrent State VSM – Order Management
Valve Automation
Company Confidential 4/9/23 / Slide 14
Current State VSM – Order ManagementCurrent State VSM – Order ManagementCurrent State VSM – Order ManagementCurrent State VSM – Order Management
Valve Automation
Company Confidential 4/9/23 / Slide 15
Current State VSM – Binder FlowCurrent State VSM – Binder FlowCurrent State VSM – Binder FlowCurrent State VSM – Binder Flow
Valve Automation
Company Confidential 4/9/23 / Slide 16
Waste Reduction OpportunitiesWaste Reduction OpportunitiesWaste Reduction OpportunitiesWaste Reduction Opportunities More effort up front before order is accepted
– Engineering requests further updates after PM assumes sufficient information has been completed
Reduce waiting time between steps– ~33% Lead-time is Wait Time (Waste)
Clear tracking of binder locations/status– 6 to 20 binders at a time in Sales offices– 2 to 4 binders at a time in Engineer’s office
Reduce time between QA review until BOM complete Set Target Performance, make performance visible, and
countermeasure gaps Capture initialization dates and assign tracking control Reduce process variation within certain steps
Valve Automation
Company Confidential 4/9/23 / Slide 17
Near-term Incremental ActionsNear-term Incremental ActionsNear-term Incremental ActionsNear-term Incremental Actions• Determine required start date of Engineering effort based on
Design Complexity and initial checklist preparation lead time
• Broadcast Engineering Due Date using Outlook Meeting manager
• Define gate target dates to measure actual performance dates
• Developed model for visual presentation of real-time data for actual performance to gate targets highlighted with the need by red/yellow for immediate action
• Electronically track Binders with a self-check in/out tracking system, capture initialization and transfer dates
Valve Automation
Company Confidential 4/9/23 / Slide 18
Respond to TargetsRespond to TargetsRespond to TargetsRespond to TargetsCapture the START DATE when the Capture the START DATE when the customer quote is issued as a PO. customer quote is issued as a PO. Set PRELIMINARY Target Dates that Set PRELIMINARY Target Dates that
are revised as more information are revised as more information becomes available.becomes available.
Valve Automation
Company Confidential 4/9/23 / Slide 19
Project ControlProject ControlProject ControlProject Control
Valve Automation
Company Confidential 4/9/23 / Slide 20
Project ControlProject ControlProject ControlProject Control
Workflow & Project TrackingWorkflow & Project Tracking
Information Processing Information Processing
FILECODERFILECODER
ORACLEORACLE
Scanned barcode in binder Scanned barcode in binder will enter data into fieldwill enter data into field
Data may be COPY/PASTE into any MS-application (Excel, Word, Access)
Trace user who performed the transaction
Valve Automation
Company Confidential 4/9/23 / Slide 23
Long-term Actions (proposed timeline)Long-term Actions (proposed timeline)Long-term Actions (proposed timeline)Long-term Actions (proposed timeline)ID Task Name
2008
Q3Q3
1Develop consensus Future State VSM uniform among all VA sites. Determine KAIZEN Activity
12
Apply eDOCS to eliminate physical binders (use parallel processing), retain scanned documents, and promote workflow. Move to parallel processing since data can be shared and reconciled. Link to ORACLE.
Review office architecture/layout for teaming activity
Expand Engineering capacity to replace retiring staff. Increase direct time on Order Management activity by providing separate production support.
Develop a policy to assure complete design information sooner from customer or jog project date until it becomes available, which delays delivery date.
Automate repetitive predetermined activities for discounting, Import/Export, and taxing
Train and enforce Request and Promise date application
Define start date, target dates and policy to address performance gaps.
Q4
2010
Q2Q1
2009
Q4Q2Q1
11Integrate ORACLE data to monitor Order Management and product configuration capability
6Lean Office Training (5s, 8 Waste, Visual Factory Management, VSM Familiarization, Standard Work)
8Begin Lean Office Assessment incorporate with shopfloor assessment for site rating.
Apply Binder Tracking system (sequential/serial process) using barcodes and software application. Enhance Visual reports using software reports.
2
7
4
3
9
10
5