+ All Categories
Home > Documents > Olmeda Park Valuation - TASE · 2011. 5. 30. · Trigger-Foresight has conducted strategic and...

Olmeda Park Valuation - TASE · 2011. 5. 30. · Trigger-Foresight has conducted strategic and...

Date post: 01-Feb-2021
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
56
Confidential. Copyrights Trigger-Foresight, All rights reserved 1 Confidential. Copyrights Trigger-Foresight, All rights reserved Olmeda Park Valuation Impairment Testing as of March 31 st , 2011 May 2011 Submitted to: Sunflower Gmbh & CO.kg
Transcript
  • Confidential. Copyrights Trigger-Foresight, All rights reserved 1Confidential. Copyrights Trigger-Foresight, All rights reserved

    Olmeda Park Valuation

    Impairment Testing as of March 31st, 2011

    May 2011

    Submitted to:

    Sunflower Gmbh & CO.kg

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 2

    Disclaimer & Restriction of Liability

    The following valuation of “PHOTOVOLTAIKPARK OLMEDA DE LA CUESTA A.I.E.” (hereafter “Olmeda”) has been conducted at the request of “Sunflower Gmbh & CO.kg” (hereafter “the Partnership”).

    This opinion is provided for the information and benefit of the Board of Directors of "the Partnership”, and is submitted to the Board of Directors in connection to the Valuation.

    It is agreed that "the Partnership” and/or it’s shareholders may include, or make reference to, this opinion in, or in connection with, the financial reports submitted, or filed, as required by pertinent securities law, case law, or other sources of legal duty.

    Moreover, "the Partnership” and/or its shareholders may make use of this opinion in any proceedings related to the approval of its valuation, including, but not limited to, in meetings with or deliberations before any person, entity and/or authority that "the Partnership” and it’s shareholders deem fit.

    The use of this opinion is permitted only by "the Partnership’s” management and/or its shareholders. Trigger Foresight shall, under no circumstances, bare any liability, or hold any responsibility, towards a third party that receives this opinion with or without our consent, as mentioned before.

    In arriving at our opinion, we have relied upon, and assumed the accuracy and completeness of all of the financial and other information that was issued by “the Partnership” without assuming any responsibility for any independent verification of any such information .

    We have further relied upon the assurances that “the Partnership” is not aware of any facts or circumstances that would make any such information inaccurate or misleading.

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 3

    Disclaimer & Restriction of Liability (Cont.)

    With respect to the financial information utilized, we assumed that such information has been reasonably prepared on a basis reflecting the best currently available estimates and judgments, and that such information provides a reasonable basis upon which we could perform our analysis and form an opinion.

    We have not carried out a physical inspection of the properties and facilities of “the Partnership” and have not made or obtained any evaluations or appraisals of the “the Partnership’s” assets or liabilities (contingent or otherwise) other than publicly available information. We have not attempted to confirm whether “the Partnership” has good title to its assets.

    This study is partially based on assumptions and forecasts. Trigger-Foresight claims no responsibility for the accuracy of these assumptions and forecasts.

    This opnion does not cinstitute a due diligence process , nor does it claim to take into account all information, tests or other information included in a true due diligence process , including, for example, the thorough examination of contracts and agreements. Note also that this opinion may in no way be construed as legal advice.

    The information in this opinion does not include all of the information required by a potential investor, and in no way presumes to determine the value of “the Partnership” or its assets for any particular investor.

    This opinion refers to the valuation of Olmeda and not of "the Partnership” as a whole.

    Trigger-Foresight has no personal interest in "the Partnership” and/or it’s shareholders and no personal interest in the outcome of this valuation.

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 4

    Disclaimer & Restriction of Liability (Cont.)

    Trigger-Foresight has conducted strategic and financial consulting processes for Shikun & BinuiGroup , as well as companies held by its shareholders and/or affiliated with Shikun & Binui. However, Trigger-Foresight is not financial depended on Shikun & Binui.

    Trigger-Foresight has received professional fees for the above mentioned services provided to Shikun & Binui Group and will also receive a fee for providing this opinion. However, the opinion fee is in no way dependent on the opinion results.

    Trigger-Foresight has received an indemnification letter from “the Partnership”, which includes the following:

    • “The Partnership“ confirms that all existing information necessary for this valuation regarding Olmeda was made available to Trigger-Foresight and that to the best of its knowledge there is no other relevant information that may affect the results of this valuation.

    • “The Partnership” concurs that this valuation is based on estimated values and expectations about future results from the project’s activities, including some estimations made by Trigger-Foresight which are not precise and are subject to change.

    • “The Partnership” agrees to reimburse, indemnify and hold harmless, Trigger Foresight upon receiving a final court ruling, for any direct or indirect damages, losses, and/or expenses incurred by, or imposed on Trigger Foresight, by any third party, as a result of any claim or suit deriving from, or in connection with this opinion, be it from investors or parties related to them. Furthermore, “The Partnership” agrees to reimburse and indemnify Trigger Foresight, immediately upon its first request, for any cost, loss, or expense of over $25,000 USD related to legal council and/or representation as a result of such a claim or suit, under the condition that Trigger Foresight give “the Partnership” notice within 14 days of receiving any demand, claim or suit, and that Trigger Foresight allow “the Partnership” to take part in its defense and refrain from agreeing to any settlement without its approval. Trigger Foresight’s right to indemnification shall be null and void if its actions in relation to this opinion are determined to be reckless, negligent, or malicious.

    • Sunflower Renewable Energy Ltd. shall bear a share of the aforementioned indemnification only to the extent of its share in “The Partnership” regardless of the other shareholders liabilities

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 5

    Details of Appraiser

    Trigger-Foresight

    Trigger-Foresight is one of Israel's leading strategic-financial consulting companies

    Trigger-Foresight works with both Israeli and international customers

    • Large and medium size companies

    • Investors, venture capital firms, private equity funds

    • Government agencies

    The company’s activities are divided into three pillars:

    • Business Strategy

    • Strategic Corporate Finance

    • Strategic Business Development

    Extensive experience in valuation for various needs:

    • M&A processes (for foreign and local investors)

    • Accounting needs (including IAS 36)

    • As part of strategic planning processes

    Shally Tshuva

    Managing Partner at Trigger-Foresight

    More than 15 years experience in business/ strategy consulting

    Leading role in tens of complex strategic and financial consulting projects with an emphasis on large companies (telecommunications, finance, holding companies, hi-tech, real estate)

    Establishment of Foresight (1993) and its management (about 5 years controlled by Israel Discount Bank)

    BA in Mathematics and Computer Science (B.Sc. with honors), MBA (MBA with honors)

    Between the years 2001 to 2008 - Lecturer of finance (valuation) and entrepreneurship at the Herzliya Interdisciplinary Center

    Shally Tshuva

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 6

    Scope of Work and Sources of Information

    The following presents a fair value analysis of the PV Project “Olmeda” as requested by "the Partnership" following the change in approach of the Spanish National Energy Committee (CNE) towards the Project’s compliance with the requirements for the 2008 Feed-in Tariff.

    Our opinion was based in part on meetings held with the following members of Sunflower Sustainable Investments Ltd. (“Sunflower”) and Shikun & Binui Renewable Energy (“SBRE”) management teams:

    • Batya Many, CFO, Sunflower

    • Meytal Kniajer, CFO, SBRE

    • Eran Migdal, Finance Director, SBRE

    Primary sources of information utilized in the formulation of our opinion were:

    • Financial reports

    • Partnership’s management’s financial performance projections for The Park

    • Additional documents and input from the company’s technical advisors in support of said projections

    • Market research and relevant public information

    We have also relied upon documents and opinions provided by the company that were written by its legal consultants.In addition, we have conducted a conversation with the company’s attorneys to further clarify these documents.

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 7

    Executive Summary

    General

    We were asked by Sunflower Gmbh & CO.kg to perform a valuation of Olmeda Park for impairment testing according to International Accounting Standard 36

    The valuation is accurate as of 31/03/2011

    Engagement date of this work: 19/05/2011

    The book value of Olmeda Park:

    • €37.77M as of 31/12/2010

    • €37.39M as of 31/3/20111

    Olmeda Park is a PV (Photovoltaics) technology based solar power generating plant, with a nominal capacity of ~6MW

    In May 2011, the company was notified that the park’s eligibility for the Feed in Tariff (FiT) was provisionally suspended

    The company has appealed the decision and is currently awaiting a response

    Valuation Summary

    Valuation is calculated using the DCF approach, in nominal Euro terms

    Due to the current uncertainty with respect to the appropriate FiT, we have valued the park using the scenario based approach –3 different scenarios for the expected cash flows were considered, with each assigned a probability of occurrence

    The probability assigned to each scenario was based on the expert opinion of the company’s lawyers in Spain2 regarding the possible outcomes of the appeal

    The total value is the average of the values of the scenarios weighted according to their assigned probability (the probability of obtaining the corresponding tariff)

    A rate of 10.31% (nominal terms) was used to discount the cash flows

    This paper estimates the value of Olmeda Park as of 31 March, 2011 at € 30.9M

    Source: Company’s documents(1) Refers to book value as of 31/12/2010 less depreciation for Q1/2011; (2) Expert opinion summarized in Appendix E

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 8

    Agenda

    21 Company and Business Overview

    22 Market and Business Environment Analysis

    23 Valuation

    24 Appendix

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 9

    24

    Agenda

    21

    22

    23

    Company and Business Overview

    Market and Business Environment Analysis

    Valuation

    Appendix

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 10

    Company and Business Overview

    Olmeda - PV Park

    General

    Olmeda is a Photovoltaic Park jointly owned by SBRE (50%) and Sunflower (50%)

    The park is located in Cuenca (about 150km from Madrid, Spain)

    The land has been leased for 25 years, with an option for an additional 15 years (2 has past)

    The park consists of 63 production units

    • 62 with 96kW nominal power each and 1 with 48kW nominal power

    The project is managed by a non-related third party O&M supplier

    Power transmission is supplied by Union Fenosa

    Production of electricity started in 2008

    Financing provided by German Bank since 2009

    Key Indicators

    Area ~72,600m2

    Total nominal power 6 MW

    Total peak power 6,986kW

    Total investment(before depreciation)

    €42.6 M

    Source: Company Presentations

    Location

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 11

    Company and Business Overview

    Holding Structure

    Limited Partner

    SUN FLOWER GMBH & CO. KG.

    Sunflower Olmeda Management GmbH

    Limited Partner

    50% 50% 50% 50%

    100%…

    PHOTOVOLTAIKPARK3

    OLMEDA DE LA CUESTA A.I.E.

    100%…

    63 SPVs1 + ALCARIA2

    (1) Park owners (See Appendix A for detailed list of SPVs); (2) Holder of Licenses; (3) Debt holderSource: Company Documents

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 12

    Company and Business Overview

    Olmeda Park - Milestones

    2008June Gilatz Spain acquired the

    park with a capacity of 3.84MW

    July Agreement signed to

    expand capacity to 6MW

    September Installations were

    connected to the electricity grid for the first time

    December Definitive connection of

    the plant at the substation Olmeda de la Cuesta

    Started production at full capacity

    2011May The CNE informed "the

    Partnership" that according to its findings, they did not fully comply with the requirements of RD 661/2007

    Provisional suspension of payment of the Feed-in Tariff

    "The Partnership" appealed the CNE’s decision, requesting that the feed-in tariff be restored

    The company is awaiting for the CNE response

    2009Feb AIE Parque Solar Olmeda

    de la Cuesta was incorporated

    The park was acquired by “Shikun & Binui Renewable Energy” and “Sunflower Sustainable Investments”

    May Financing contract

    achieved

    2010October "The Partnership" was

    approached by the National Energy Committee (CNE) regarding it’s compliance with the requirements for the 2008 Feed-in Tariff

    November Change in regulation

    limiting the period of eligibility for the FiT and reducing the tariff applicable for new projects

    December New Energy Transport Tax

    imposed Production limit for

    guaranteed FiT imposed

    Source: Company’s documents; “Summary of the Situation of the Olmeda Park from June 2008 to May 2011”- Brenes Abogados, S.L.P.

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 13

    Company and Business Overview

    Olmeda Park - Recent Regulatory Developments

    “The Audit”“Provisional Suspension

    of the FiT” “The Appeal”

    18-19 May 2011 The Notary of Cuenca performed a

    physical inspection and certified that the current status of the park was similar to photographs dated 26 September 2008 (evidencing the completion of the plant reviewed) and similar to the status verified by the Notary on 26 September 2008

    20 May 2011 “The Partnership” submitted their

    defense against the provisional suspension of the FiT, including supplemental documentation, supporting their belief that the CNE’s conclusions were erroneous

    2 March 2011 The CNE reviewed the submitted

    documents and found that the documents were not sufficient proof of installation prior to 30 September 2008

    14 April 2011 The Board of the CNE instructed the

    precautionary provisional suspension of FiT payments

    6 May 2011 The Directorate General for Energy

    and Mines initiated proceedings to verify whether or not the park’s installations complied with the requirements for FiT eligibility set forth in RD 661/2007

    9 May 2011 “The Partnership” was notified of

    the aforementioned proceedings and received a copy of CNE’s report

    23 October 2008 An audit methodology to verify the

    eligibility of candidates that received the FiT according to RD 661/207 was defined

    5 October 2010 The 63 installations of Olmeda

    received requests from the CNE to submit specific documentation proving that the park possessed and installed all panels and inverters before 30 September 2008

    22-25 November 2010 “The Partnership” submitted all

    documents requested by the CNE. No further clarification or documentary support was requested, therefore, none was provided

    Source: Company’s lawyers

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 14

    Company and Business Overview

    Financial Results

    Revenue and Margin Evolution

    4,936 4,849

    1,054

    4,276 4,274

    933

    86.6%

    88.1%88.5%

    2009 2010 Q1/2011

    Energy Production and Feed-in Tariff

    10,499 10,408 2,216

    0.4700.466

    0.476

    2009 2010 Q1/2011

    Source: Company, Financial Reports

    (€, '000)

    Revenues Gross Profit Gross Margin Production (MWh) Feed-in Tariff (€)

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 15

    Company and Business Overview

    Financial Results (Cont.)

    P&L

    Source: Company, Financial Reports(1) Except for Guaranteed Price, in Euros

    YoYProduction:

    AC kWh Produced -0.9%

    €, Thousands1

    % of Revenues €, Thousands1

    % of Revenues

    Revenues:

    Garanteed Price (€) -0.9%

    Total Revenues 4,936 100% 4,849 100.0% -1.8%

    Operating Costs:

    Energy Cost 58 1.2% 104 2.1%

    Rent cost 17 0.3% 17 0.4%

    Insurance 42 0.9% 45 0.9%

    Maintenance 437 8.8% 394 8.1%

    Supplier Bonnus 104 2.1% 53 1.1%

    Other 2 0.0% (38) -0.8%

    Total Operating Costs 660 13.4% 576 11.9% -12.8%

    Gross Profit 4,276 86.6% 4,274 88.1% -0.1%

    G&A 3 0.1% 90 1.9%

    Operating Profit 4,273 86.6% 4,184 86.3% -2.1%

    2009 2010

    10,498,801 10,408,350

    0.46590.4702

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 16

    Agenda

    21

    22

    23

    Company and Business Overview

    Market and Business Environment Analysis

    Valuation

    24 Appendix

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 17

    Market and Business Environment Analysis

    Renewable Energy - Technologies

    RenewableEnergy

    Wind Energy Solar EnergyBiomassEnergy

    GeothermalEnergy

    MarineEnergy

    HydroelectricEnergy

    SolarThermal

    (CSP)PV

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 18

    40%35%

    29%23%

    21%17% 18%

    10% 9%6% 7%

    9%5% 7%

    9% 7%1%

    6% 4%1% 0%

    9%

    7%

    10%

    11%

    10%13%

    6%

    13%13%

    12% 11% 8% 12% 9%7%

    8%14%

    7% 9%9% 10%

    Sw

    ede

    n

    Latv

    ia

    Fin

    land

    Au

    str

    ia

    Po

    rtu

    ga

    l

    De

    nm

    ark

    Ro

    ma

    nia

    Fra

    nce

    Spain

    Ge

    rma

    ny

    Gre

    ece

    US

    A

    Ita

    ly

    Ch

    ina

    Bu

    lga

    ria

    Po

    land

    UK

    Cze

    ch

    Hu

    ng

    ary

    Isra

    el

    Ma

    lta

    2020 Target

    2005 Actual49%

    42%39%

    34%31% 30%

    24% 23%22%

    18% 18% 17% 17% 16% 16% 15% 15%13% 13%

    10% 10%

    1

    (Renewables share of total energy consumption, including hydro)

    Market and Business Environment Analysis

    Renewable Energy - National Targets

    National governments in Europe, US and China have set aggressive targets for renewable energy by 2020

    Source: IEA, European Commission(1) USA actuals for 2004, target for 2015

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 19

    Solar Power Tower

    Dish Stirling

    Concentrated PV

    Thin FilmCrystallized

    Silicon

    PV(photovaltaic)

    CSP(ConcentratedSolar Power)

    Experimental NicheCommon ExperimentalGrowing Traditional

    high concentration lenses or mirrors to focus sunlight onto miniature solar cells

    a solar cell that is made by depositing one or more thin layers (thin film) of photovoltaic material on a substrate

    A solar cell or converts light directly into electricity by the photovoltaic effect

    Parabolic Trough

    Fresnel Reflector

    special mirrors shaped as linearparabolas are used which reflect the sun rays on to an absorption tube

    circular array of large individually tracking mirrors Heliostats are used to concentrate sunlight on toa focal point mounted at the top of a tower

    dish-shaped mirror is used to reflect sunlight on to a central collectinglocation which is a focal point of the dish

    line focus system which uses rows of flat mirrors in which solar radiation is concentrated on an elevated inverted linear absorber

    Niche

    Source: Business Insights

    Market and Business Environment Analysis

    Solar Energy Technologies

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 20

    (MW)

    1,2001,800

    2,500

    4,000

    7,350

    8,900

    15,000

    N/A

    50%

    39%

    60%

    84%

    21%

    69%

    2004 2005 2006 2007 2008 2009 2010

    Production

    YoY Growth

    China33%

    Europe26%

    Japan16%

    Taiwan11%

    Others14%

    Market and Business Environment Analysis

    PV - Panel Production

    Global PV Panel Production PV Panel Production by Country

    Global solar PV production recorded a robust growth of 84% in 2008 driven by government incentives in Germany, Spain and the US

    Although the US is a key market for solar PV, it was not a major manufacturer in 2008

    Source: TFCO Research, Business Insights

    (2008)

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 21

    (GW)

    0.1 1.3

    5.0

    10.4

    16.1

    0.1

    0.4

    0.9

    1.2

    1.8

    0.7

    2.2

    3.3

    3.9

    5.1

    1

    4

    9

    16

    23

    1999 2004 2007 2008 2009

    Others

    North America

    Europe

    305

    363

    365

    465

    526

    1,188

    1,646

    2,343

    2,628

    3,423

    9,677

    China

    Belgium

    France

    Czech Republic

    Korea

    Italy

    US

    Other

    Japan

    Spain

    Germany

    (MW)

    Market and Business Environment Analysis

    PV - Installed Capacity

    Global PV Installed Capacity PV Installed Capacity by Country (2009)

    The key driver for solar PV growth has been Europe’s strategic transition to renewable energy aimed at reducing carbon emissions

    Top 10 countries accounted for ~90% of total Solar PV installed capacity in 2009

    Source: TFCO Research, Business Insights

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 22

    Market and Business Environment Analysis

    PV - Key Manufacturers

    Source: TFCO Research, Business Insights

    Japan

    Crystalline PV

    Germany

    US

    Thin Film

    China

    Taiwan

    (2009)

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 23

    Market and Business Environment Analysis

    Spanish Solar Market - Overview

    General

    Additional Solar Power Capacity

    Electricity Generation Mix

    Nat. Gas 30%

    Nuclear 20%

    Hydro 20%Wind 16%

    Coal 6%

    Oil 4%

    Solar 2%

    Biomass 2%

    47 545

    2,500

    270 500 500 5001,199

    1,955

    4,715

    6,173

    13,841

    11,578

    9,865

    2006 2007 2008 2009 2010 E 2011 E 2012 E

    Spain

    Europe

    Spain is one of the leading countries in solar energy production

    In 2004 the government removed economic barriers relating to the connection of renewable energy to the electricity grid

    A Feed-in Tariff policy for large scale solar plants was adopted

    In 2007 the first European solar power plant began operation in Spain

    After the 2008 financial crisis, subsidies were drastically cut and a cap of 500MW per year was imposed for future increases in capacity

    Total solar production capacity (2010): 4GW

    Total solar energy production (2010): 6.9TWh (~2.7% of the country’s electricity demand)

    Source: IDAE 2010; Goldman Sachs Global Investment Research

    (2010)

    (MW)

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 24

    Market and Business Environment Analysis

    Spanish Solar Market - Regulation

    Regulation History

    Spanish government committed to achieving a target of 12% of primary energy from renewable sources by 2010 (in fact they have reached ~20% of energy production from renewable sources, with solar power accounting for ~2%)

    In 2004, legislation (Royal Decree 436/2004) was enacted to encouraged the installation of solar power plants by offering high guaranteed feed-in tariffs (FiTs)

    In 2008, specific legislation (Royal Decree 1578/2008) was updated to include Photovoltaic (PV) power plants

    Following a rapid increase in solar power plants installations, the government imposed a limit on additional capacity growth of 500MW per year

    Recent Developments

    In Aug. 2010 the government announced cuts of 5%-45% in the FiT for new PV solar plants

    In 2010, new legislation (Royal Decrees 1565/2010 and 14/2010) enacted the following changes:

    • The reduction of the FiT for new projects

    • Limits on the duration of current projects

    • Imposed a new tax for use of transmission and distribution lines

    • Limits on the electricity production guaranteed to be purchased at the FiT

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 25

    Agenda

    21

    22

    23

    Company and Business Overview

    Market and Business Environment Analysis

    Valuation

    24 Appendix

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 26

    Valuation

    Methodology

    This valuation was performed in accordance with International Accounting Standard 36 -

    “Impairment of Assets” (hereinafter “IAS36").

    IAS36 requires that the value of an asset be accessed annually or whenever there is a sign

    indicating significant depreciation of the asset. In such events the asset must undergo a

    valuation process which should be compared to its book value. If the book value of the asset exceeds the resulting valuation, an impairment loss is recognized.

    The value of the asset shall be the greater of two amounts:

    • The “fair value less cost to sell”.

    • The “value in use” of the asset.

    “Fair value less cost to sell” represents the amount received from the sale of an asset at an

    acceptable market price less the costs incurred by the transaction.

    “Value in use” is the present value of future cash flows expected to be derived from the asset.

    Due to CNE’s notification of the provisional suspension of the Feed in Tariff for which Olmeda

    is eligible, there has been an event of significant impact on the expected future cash flows derived from the subject of this valuation.

    The calculations and assumptions, presented herein, were performed in order to reflect the

    “value in use” as defined under IAS36.

    Additionally the option to dismantle and sell the PV plant in parts was considered, with the

    resulting net value corresponding to the “fair value less cost to sell”.

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 27

    Valuation

    Methodology (Cont.)

    Valuation Methods:

    • Discounted Cash Flow (DCF) - Value of asset equated to present value of expected future cash flows

    generated by the asset.

    • Comparable-based - Value of asset derived from pricing of 'comparable' assets generally calculated by

    multipliers of relevant financial figures (i.e. earnings, cash flows, book value or sales).

    • Net Asset Value (NAV) – Value of asset equated to the sum the net value of its components.

    This work utilizes the DCF valuation method, which is most appropriate for this situation.

    The valuation is calculated in Euros, in nominal terms (in gross terms) for the purpose of asset impairment examination (according to IAS 36) of “Olmeda” as of 31/03/2011, based on the financial reports of 2010 and Q1/2011.

    Theoretically, the same results should be obtained by discounting pre-tax cash flows at a pre-tax discount rate or post-tax cash flows at a post-tax discount rate, as long as the post-tax discount rate is properly adjusted for the future tax expenses. This valuation was based on the latter. The pre-tax discount rate may be calculated as the value which equates in present value terms pre-tax cash flows with the valuation.

    The current complex regulatory situation with the Spanish authority has created a high level of uncertainty regarding the future results of the company, and the corresponding cash flows.

    Following current accepted valuation methodologies for cases where likely scenarios for future cash flows are highly divergent, the approach taken in this report is the scenario based methodology.

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 28

    Valuation

    Methodology (Cont.)

    The scenario based approach is widely accepted in the relevant professional literature as the favorable alternative for the valuation of assets under high uncertainty:

    Source: Damodaran, Copland, Koller & Murrin, McKinsey & Company, Inc.

    “Uncertainty is the hardest part of valuing high-growth technology companies, and the use of probability –weighted scenarios is a simple and straightforward way to deal with it.”

    “We capture cash-flow risk through the probability-weighting of scenarios, so that the cost of equity applied to each of them shouldn’t include any extra premium; it can consist of the risk-free rate, an industry-average beta, and general market risk premium.”

    (“Valuation- Measuring and Managing the Value of Companies” p. 315-325, by Copland, Koller & Murrin,

    McKinsey & Company, Inc.)

    “The expected cash flows that we use to value risky assets can be estimated in one or two ways. They can represent a probability-weighted average of cash flows under all possible scenarios or they can be the cash flows under the most likely scenario. While the former is the more precise measure, it is seldom used simply because it requires far more information to compile.”

    (“Probabilistic Approaches: Scenario Analysis, Decision Trees and Simulations” by Aswath Damodaran.)

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 29

    Valuation

    Methodology (Cont.)

    In an attempt to minimize the possibility of deviation in determining the additional risk imposed by regulatory uncertainty, this valuation is based on expected cash flows that may result from the different possible regulatory decision outcomes (scenarios).

    The scenarios were defined by the different Feed in Tariffs that the company may receive as a result of the Ministry of Energy’s decision as well as other changes that are derived from the decision about the tariff:

    • “Original Feed-in Tariff” Scenario: Assumes that “the Partnership” will be able to restore the park’s previous status under Royal Decree 661/2007 and thus receive the corresponding higher FiT

    • “New Feed-in Tariff” Scenario: Assumes that “the Partnership” is not granted the FiT it previously enjoyed, thus it is required to apply and receives the lower FiT currently offered (2011), which is still above market prices

    • “No Feed-in Tariff” Scenario: Assumes a situation in which “the Partnership” is not granted any FiT and must sell all of the electricity produced at free market rates

    Each scenario was assigned a probability of occurrence - the probabilities were defined based on the expert opinion of the company’s lawyers about the likelihood of the legal process decision.

    The final valuation is calculated based on the weighted average of the DCF of each scenario weighted by the appropriate probability.

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 30

    Valuation

    WACC - Methodology

    Weighted Average Cost of Capital - represents the weighted cost of the capital used to finance a company’s activity.

    The WACC incorporates the cost of the capital provided by each funding source according to the relative weight of it in the total funding.

    It is customary to divide the WACC into two factors: the cost of debt (external capital) and the cost of equity (own capital).

    Equity Weight in total capital

    Debt Weight in total capital

    Tax Shield on financing expenses

    Cost of Debt: return on capital required by third party lenders

    Cost of Equity: return on capital required by stockholders

    CAPM

    WACC

    Risk Free Rate - generally associated with Government long-term bonds

    Risk Factor representing the relation of returns with theseof the financial market as a whole

    Market Risk Premium

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 31

    Parameter Value

    Cost of Equity (Ke) 12.4%

    Cost of Debt (Kd) 8.5%

    D/(D+E) 35.2%

    Tax 25%

    WACC 10.3%

    Valuation

    WACC Calculation

    Cost of Equity WACC

    Source: Damodaran, Bloomberg, Company Reports(1) Sunflower’s leverage ratio stands around 30% as of May, 2011

    Parameter Value

    Risk Free Rate (Rf) 5.3%

    Market Beta (Unlevered) 0.64

    Levered Beta 0.90

    Market Risk Premium 5.2%

    Liquidity/Small Cap Premium 2.5%

    Cost of Equity (Ke) 12.4%

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 32

    Valuation

    Main Assumptions

    Source: “Economic update Spain”, Rabobank Economic Research Department, May 2011, Inflation.eu, Company’s documents(1) 2011 - 2.75%; 2012 - 1.25%; Long term - 2.87%

    Electricity Production

    Expected electricity production is based on “the Partnership’s” assumptions, which are derived from

    production in previous years and along with the opinions of their technical advisors

    Annual degradation of ~0.5% is expected due to production line exhaustion. This assumption is in-line with a

    benchmark of similar PV projects

    Electricity Tariff

    The electricity generated is sold according to two separate tariffs

    • Feed in Tariff (guaranteed rate) are provided up to a defined quota

    • The remainder is sold at free market rates negotiated daily

    With regards to Olmeda Park, the Feed in Tariff (FiT) quota was calculated by "the Partnership" based on

    Royal Decree 661/2007 and the amendments made in RD 165/2010 and RD 14/2010 and the plant’s specific

    characteristics (size and location)

    Currently, there is uncertainty regarding the Feed in Tariff rate for Olmeda Park as it is currently under review.

    Each of the scenario in the valuation model assumes a different outcome of the Feed in Tariff review

    For the purposes of the model, free market electricity rates follow the technical advisors’ estimations relying

    on historical average market prices

    Electricity tariffs are expected to grow during the model period. We assumed that it will grow with inflation,

    thus adjustments to inflation were made according to relevant inflation forecast1

    For Feed in Tariffs, the adjustment is reduced by 0.25 percentage points in 2011-2012 and 0.5 percentage

    points for each following year, in accordance with Royal Decree 661/2007

    All of the scenarios consider revenues based on the original FiT until April 2011

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 33

    Valuation

    Main Assumptions (Cont.)

    Source: Company

    Expenses

    All expense items are derived from 2011 expected values adjusted annually based on each item’s specific characteristics

    Power transmission expenses - Estimated at €0.01 per kWh for 2011 and are expected to decrease according management expectation regarding a contract with a new supplier as of the beginning of 2012

    Land lease, insurance, O&M and supplier bonus expenses - Calculated based on information provided by "the Partnership", in accordance with current supplier contracts. These expenses items vary per scenario

    Insurance expenses - Based on 2011 expected values and are assumed to remain constant over time due as on the one hand, prices are increasing due to inflation, and on the other hand insurance premiums are expected to decrease

    G&A expenses - Assumed to be €10,000 in 2011, with annual growth equal to inflation

    Tax

    Tax expenses were calculated based on tax rate of 25%, which is the appropriate tax rate for "the Partnership"

    "The Partnership" enjoys several tax benefits:

    • Accelerated depreciation of assets

    • Tax benefits stemming from environmental investments

    Impact of tax benefits are calculated in accordance with the views of "the Partnership“

    “Fair Value Less Cost to Sell”

    According to “the Partnership’s” technical consultants, the net value of the park’s equipment, sold in parts is ~€7M (see Appendix G). This value was measured against the “value in use” under each scenario with the greater of the two considered in the total value calculation.

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 34

    Valuation

    Main Assumptions - Scenarios

    “Original FiT” Scenario “New FiT” Scenario “No FiT” Scenario This scenario assumes no Feed-in Tariff

    is awarded to “the Partnership”, thus the whole of the electricity produced is sold at the free market rateO&M cost - under this scenario, the

    current model would lead to values lower than acceptable by suppliers. Therefore, the model assumes costs at €30k per MW (maintenance only) , based on company’s assumption and in-line with market This scenario doesn’t have regulatory

    limitations about the project duration and was modeled considering 30 years of activity

    This scenario assumes that “the Partnership” will be awarded a new FiT in accordance with RD 1578/2008, equal to the current rate at the time of approval –The current rate now stands at €0.13 and decreases by 2.6% per quarterA delay period (time to recover tariff) is

    incorporated to reflect the time until the new FiT is set - during this period electricity is sold at the market rateO&M cost - under this scenario, the

    current model would lead to values lower than acceptable by suppliers. Therefore, the model assumes fixed costs of €30k per MW (maintenance only) , based on company’s assumption and in-line with market prices Based on the amendment to RD

    1578/2008, the project will be eligible for the FiT for 25 years

    This scenario assumes the full restoration of the originally applied FiT, according to Royal Decree 661/2007Under this scenario, any delay in

    restoring the tariff will be compensated retroactive in a manner that compensates for the timing of the paymentsO&M expenses (including insurance and

    land lease) are priced at 10% of revenues after transmission costs in 2011 and are expected to be reduced to 8% in 2012 Based on the amendment to Royal

    Decree 14/2010, the project will be eligible for the FiT for 28 more years after 2011 (for a total of 30 years)

    Parameter Value

    Feed-in Tariff (2011) € 0.4756

    Market Tariff (2011) € 0.0400

    Time to recover tariff (months) 0

    Project Duration (years, from 2011) 28

    Feed-in Tariff Duration (years, from 2011) 28

    Maintenance Costs (2011) 10%

    Parameter Value

    Feed-in Tariff (2011) € 0.1346

    Market Tariff (2011) € 0.0400

    Time to recover tariff (months) 12

    Project Duration (years, from 2011) 26

    Feed-in Tariff Duration (years) 25

    Maintenance Costs (2011) € 180,000

    Parameter Value

    Feed-in Tariff (2011) N/R

    Market Tariff (2011) € 0.0400

    Time to recover tariff (months) N/R

    Project Duration (years, from 2011) 30

    Feed-in Tariff Duration (years) N/R

    Maintenance Costs (2011) € 180,000

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 35

    Valuation

    Valuation Results - “Original FiT” Scenario

    Key Results Forecast1

    Main AssumptionsValuation

    (1) Detailed Cash flows are presented in Appendix C; (2) Profit Before Taxes after accelerated depreciation, not accounting depreciation

    Original Feed-In Tariff (€, '000) Q2-Q4/2011 2012 2013 2014 2015 2020 2030

    AC kWh Produced 8,161,728 10,325,715 10,274,087 10,222,716 10,171,603 9,919,843 9,434,863

    Revenues 2,628 3,772 3,799 4,507 4,588 5,147 6,476

    Operating Costs 328 334 336 392 398 438 526

    EBITDA 2,300 3,438 3,463 4,115 4,190 4,709 5,950

    Profit Before Taxes (896) (824) (799) (147) (72) 4,709 5,950

    Project CF 2,296 3,433 3,458 4,110 4,185 3,938 4,458

    NPV (31/3/2011) 38,419

    Parameter Value

    Feed-in Tariff (2011) € 0.4756

    Market Tariff (2011) € 0.0400

    Time to recover tariff (months) 0

    Project Duration (years, from 2011) 28

    Feed-in Tariff Duration (years, from 2011) 28

    Maintenance Costs (2011) 10%

    2

    (€, '000)

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 36

    Valuation

    Valuation Results - “New FiT” Scenario

    Key Results Forecast1

    Main AssumptionsValuation

    (1) Detailed Cash flows are presented in Appendix C; (2) Profit Before Taxes after accelerated depreciation, not accounting depreciation

    New Feed-In Tariff (€, '000) Q2-Q4/2011 2012 2013 2014 2015 2020 2030

    AC kWh Produced 8,161,728 10,325,715 10,274,087 10,222,716 10,171,603 9,919,843 9,434,863

    Revenues 813 1,043 1,049 1,183 1,202 1,341 1,665

    Operating Costs 276 277 280 284 289 323 402

    EBITDA 537 766 769 899 914 1,017 1,264

    Profit Before Taxes (2,659) (3,496) (3,493) (3,363) (3,348) 1,017 1,264

    Project CF 533 761 764 894 908 1,012 1,259

    NPV (31/3/2011) 9,074

    Parameter Value

    Feed-in Tariff (2011) € 0.1346

    Market Tariff (2011) € 0.0400

    Time to recover tariff (months) 12

    Project Duration (years, from 2011) 26

    Feed-in Tariff Duration (years) 25

    Maintenance Costs (2011) € 180,000

    (€, '000)

    2

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 37

    No Feed-In Tariff (€, '000) Q2-Q4/2011 2012 2013 2014 2015 2020 2030

    AC kWh Produced 8,161,728 10,325,715 10,274,087 10,222,716 10,171,603 9,919,843 9,434,863

    Revenues 813 424 428 434 442 496 626

    Operating Costs 276 277 280 284 289 324 402

    EBITDA 537 147 148 150 152 172 224

    Profit Before Taxes (2,659) (4,115) (4,114) (4,112) (4,109) 172 224

    Project CF 533 142 143 144 147 167 219

    Valuation

    Valuation Results - “No FiT” Scenario

    Key Results Forecast1

    Main AssumptionsValuation

    Parameter Value

    Feed-in Tariff (2011) N/R

    Market Tariff (2011) € 0.0400

    Time to recover tariff (months) N/R

    Project Duration (years, from 2011) 30

    Feed-in Tariff Duration (years) N/R

    Maintenance Costs (2011) € 180,000

    (1) Detailed Cash flows are presented in Appendix C; (2) Profit Before Taxes after accelerated depreciation, not accounting depreciation

    2

    "Value in Use" NPV (31/3/2011) 2,043

    Dismantlement Net Value 7,000

    NPV (31/3/2011) 7,000

    (€, '000)

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 38

    Valuation

    Scenario Based Valuation - Summary

    Scenario Probability Valuation Summary

    The probability of the scenarios described was calculated based on the expert opinion of the company’s lawyers in Spain (see Appendix E).

    The lawyers estimated the likelihood of recovering the original Feed-in Tariff to be “HIGHLY PROBABLE”.

    After reviewing innumerous interpretations of this term, we considered it to be equivalent to about 75% probability (see Appendix F).

    In addition, we estimate a probability of 15% for the scenario in a new FiT is imposed and of 10% for the case in which no FiT is approved. These are conservative estimations, based on conversations with the company’s legal advisors and management.

    Valuation Probability

    "Original FiT" € 38,419 75%

    "New FiT" € 9,074 15%

    "No FiT" € 7,000 10%

    Total

    Valuation€ 30,875

    This paper estimates the value of Olmeda Park as of 31 March, 2011 at € 30,875k

    (€, '000)

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 39

    Valuation

    Sensitivity Analysis

    WACC

    Regulatory Influence

    Scenario Probabilities

    A Sensitivity analysis was performed in order to examine the impact of variations in the WACC, Scenario Probabilities, and Regulatory influence on the total value of Olmeda Park

    WACC Valuation

    8.7% € 35,281

    9.0% € 34,316

    9.3% € 33,395

    9.7% € 32,516

    10.0% € 31,677

    10.3% € 30,875

    10.6% € 30,109

    11.0% € 29,376

    11.3% € 28,674

    11.6% € 28,002

    11.9% € 27,358

    0.0020 0.0010 0.0005 0.0001 0.0000

    -1.0% € 30,495 € 30,581 € 30,624 € 30,662 € 30,667

    -0.5% € 30,621 € 30,707 € 30,750 € 30,788 € 30,792

    0.0% € 30,747 € 30,832 € 30,875 € 30,914 € 30,918

    0.5% € 30,873 € 30,958 € 31,001 € 31,040 € 31,044

    1.0% € 30,998 € 31,084 € 31,127 € 31,165 € 31,170

    Transmission Tax (€/kWh)

    Gu

    ara

    nte

    ed

    Pu

    rch

    ase

    "Original FiT" Valuation

    65.00% € 27,941

    70.0% € 29,408

    75.0% € 30,875

    80.0% € 32,343

    85.00% € 33,810

    (€, '000) (€, '000)

    (€, '000)

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 40

    Valuation

    Notes on Previous Valuation

    According to The Israel Securities Authority standards, a valuation shall include details pertaining to previous

    valuations that were performed regarding the asset in question

    Sunflower Gmbh & CO.kg has received a valuation of the Olmeda Park conducted by Giza-Singer-Even Ltd. In

    March 2011. The valuation was in the capacity of impairment testing as of 31 December, 2010 and was

    required due to legislative changes in Spain (Royal Decrees 14/2010 and 1565/2010)

    Below is a comparison of key results in the two valuations:

    There is a minor difference in the WACC assumed (see Appendix D for further clarification)

    There is a difference of over 20% in the value of Olmeda Park as calculated in the two valuations

    This dissimilarity is a result of changes in the park’s status (due to the provisional suspension of the FiT) that

    occurred in the beginning of May 2011, and created uncertainty as to the future FiT and cash flow of the park

    Our model was designed to represent this uncertainty through the use of the scenario approach

    The “Original FiT” scenario in our model is most similar to the Giza-Singer-Even valuation, as it incorporates

    the assumption made by Giza-Singer-Even that Olmeda Park shall continue to be eligible for the historic FiT

    The difference between the value calculated under the “Original FiT” scenario, and the one reflected in the

    Giza-Singer-Even valuation is minimal (under 2%) and is a result of changes in the inflation rate1 expected in

    Spain for 2011 and 2012 (updated estimations)

    (1) As of Jan.2011, expected inflation in Spain for 2011 was 1% ; updated data from May/2011 forecasts inflation rates in Spain for 2011 at 2.75%-4%

    (€, '000) Giza Trigger-Foresight

    WACC 10.23% 10.31%

    Value € 37,769 € 30,875

    Source: “Economic update Spain”, Rabobank Economic Research Department, May 2011, Inflation.eu,

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 41

    Agenda

    21

    22

    23

    Company and Business Overview

    Market and Business Environment Analysis

    Valuation

    24 Appendix

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 42

    Appendix

    Appendix A - 63 SPVs

    1 OLMEDA SONNIG 1, S.L. 17 OLMEDA SONNIG 17 S.L. 33 OLMEDA SONNIG 33 S.L. 49 OLMEDA SONNIG 49, S.L.

    2 OLMEDA SONNIG 2 S.L. 18 OLMEDA SONNIG 18 S.L. 34 OLMEDA SONNIG 34 S.L. 50 OLMEDA SONNIG 50, S.L.

    3 OLMEDA SONNIG 3 S.L. 19 OLMEDA SONNIG 19 S.L. 35 OLMEDA SONNIG 35 S.L. 51 OLMEDA SONNIG 51, S.L.

    4 OLMEDA SONNIG 4 S.L. 20 OLMEDA SONNIG 20 S.L. 36 OLMEDA SONNIG 36 S.L. 52 LLANOS SOLEIL 19, S.L.U.

    5 OLMEDA SONNIG 5 S.L. 21 OLMEDA SONNIG 21 S.L. 37 OLMEDA SONNIG 37 S.L. 53 LLANOS SOLEIL 20, S.L.U.

    6 OLMEDA SONNIG 6 S.L. 22 OLMEDA SONNIG 22 S.L. 38 OLMEDA SONNIG 38 S.L. 54 LLANOS SOLEIL 21, S.L.U.

    7 OLMEDA SONNIG 7 S.L. 23 OLMEDA SONNIG 23 S.L. 39 OLMEDA SONNIG 39 S.L. 55 LLANOS SOLEIL 22, S.L.U.

    8 OLMEDA SONNIG 8 S.L. 24 OLMEDA SONNIG 24 S.L. 40 OLMEDA SONNIG 40 S.L. 56 LLANOS SOLEIL 23, S.L.U.

    9 OLMEDA SONNIG 9 S.L. 25 OLMEDA SONNIG 25 S.L. 41 OLMEDA SONNIG 41, S.L. 57 LLANOS SOLEIL 24, S.L.U.

    10 OLMEDA SONNIG 10 S.L. 26 OLMEDA SONNIG 26 S.L. 42 OLMEDA SONNIG 42, S.L. 58 LLANOS SOLEIL 25, S.L.U.

    11 OLMEDA SONNIG 11 S.L. 27 OLMEDA SONNIG 27 S.L. 43 OLMEDA SONNIG 43, S.L. 59 LLANOS SOLEIL 26, S.L.U.

    12 OLMEDA SONNIG 12 S.L. 28 OLMEDA SONNIG 28 S.L. 44 OLMEDA SONNIG 44, S.L. 60 LLANOS SOLEIL 27, S.L.U.

    13 OLMEDA SONNIG 13 S.L. 29 OLMEDA SONNIG 29 S.L. 45 OLMEDA SONNIG 45, S.L. 61 LLANOS SOLEIL 28, S.L.U.

    14 OLMEDA SONNIG 14 S.L. 30 OLMEDA SONNIG 30 S.L. 46 OLMEDA SONNIG 46, S.L. 62 LLANOS SOLEIL 29, S.L.U.

    15 OLMEDA SONNIG 15 S.L. 31 OLMEDA SONNIG 31 S.L. 47 OLMEDA SONNIG 47, S.L. 63 LLANOS SOLEIL 30, S.L.U.

    16 OLMEDA SONNIG 16 S.L. 32 OLMEDA SONNIG 32 S.L. 48 OLMEDA SONNIG 48, S.L.

    Source: Company Documents

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 43

    Appendix

    Appendix B - Comparable Companies

    Due to "the Partnership's” distinctive characteristics, the choice of the suitable peer group in the same environment with similar operational structure posed some difficulty.

    The search for peer companies was extended to adjacent markets and the peer group is based on relevant publicly traded companies in the solar power market.

    The peer group was analyzed for the calculation of the market beta (unlevered) and for comparison to the company’s long term leverage levels.

    Source: Damodaran, Bloomberg

    Company Beta(L) Beta(U) D/EV

    Alter Energy AG 0.92 0.92 0%

    Conergy AG 0.93 0.53 61%

    EDP Renovaveis 0.83 0.53 45%

    Iberdrola Renovables SA 0.63 0.44 37%

    Phoenix Solar AG 0.95 0.78 23%

    Sechilienne-Sidec 0.87 0.48 50%

    Solar Millenium 0.79 0.79 0%

    Solaria Energia 1.18 0.65 45%

    Average 0.89 0.64 35%

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 44

    Appendix

    Appendix C - Valuation Results

    “Original FiT” Scenario

    (EUR, '000)

    Inflation Rate

    Accumulated Inflation

    Production:

    AC kWh Produced

    Guaranteed Purchase

    Excess Production

    Revenues

    Garanteed Price

    Market Price

    Total Revenues

    Costs

    Energy Cost per kWh

    Energy Cost

    Rent cost

    Insurance

    Maintenance

    Supplier Bonnus

    G&A

    Total Operating Costs

    EBITDA

    New Energy Tax

    Depreciation for Tax

    Profit Before Taxes (tax calculation)

    Accumulated Profit Before Taxes

    Tax Credit for environmental investments

    Use of Tax Credit

    Nominal Tax

    Effective Tax

    Project CF

    Q2-Q4/2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

    2.8% 1.3% 1.8% 2.3% 2.9% 2.9% 2.9% 2.9% 2.9% 2.9%

    2.8% 4.0% 5.9% 8.4% 11.5% 14.7% 18.0% 21.4% 24.8% 28.4%

    8,161,728 10,325,715 10,274,087 10,222,716 10,171,603 10,120,745 10,070,141 10,019,790 9,969,691 9,919,843

    5,284,125 7,500,000 7,500,000 8,952,000 8,952,000 8,952,000 8,952,000 8,952,000 8,952,000 8,952,000

    2,877,603 2,825,715 2,774,087 1,270,716 1,219,603 1,168,745 1,118,141 1,067,790 1,017,691 967,843

    0.476 0.487 0.491 0.497 0.507 0.519 0.531 0.543 0.556 0.570

    0.040 0.041 0.042 0.042 0.043 0.045 0.046 0.047 0.049 0.050

    2,628 3,772 3,799 4,507 4,588 4,695 4,804 4,915 5,030 5,147

    0.0100 0.00125 0.00125 0.00125 0.00125 0.00125 0.00125 0.00125 0.00125 0.00125

    81.62 12.91 12.84 12.78 12.71 12.65 12.59 12.52 12.46 12.40

    12.75 17.47 17.69 18.00 18.42 18.95 19.49 20.05 20.63 21.22

    35.25 47.00 47.00 47.00 47.00 47.00 47.00 47.00 47.00 47.00

    187.51 242.06 243.47 299.07 304.11 310.88 317.79 324.85 332.07 339.44

    3.44 4.56 4.62 4.71 4.82 4.96 5.11 5.26 5.42 5.57

    7.50 10.28 10.40 10.59 10.84 11.15 11.47 11.80 12.14 12.48

    328 334 336 392 398 406 413 421 430 438

    2,300 3,438 3,463 4,115 4,190 4,289 4,390 4,494 4,600 4,709

    88% 91% 91% 91% 91% 91% 91% 91% 91% 91%

    4.1 5.2 5.1 5.1 5.1 5.1 5.0 5.0 5.0 5.0

    3,196 4,262 4,262 4,262 4,262 4,262 4,262 4,262 902 0

    (896) (824) (799) (147) (72) 27 128 232 3,698 4,709

    (896) (1,720) (2,519) (2,666) (2,738) (2,711) (2,582) (2,350) 1,348 6,056

    1,705 1,705 1,705 1,705 1,705 1,705 1,705 1,705 1,705 1,587

    0 0 0 0 0 0 0 0 118 412

    0 0 0 0 0 0 0 0 337 1,177

    0 0 0 0 0 0 0 0 219 765

    2,296 3,433 3,458 4,110 4,185 4,284 4,385 4,489 4,376 3,938

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 45

    2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

    2.9% 2.9% 2.9% 2.9% 2.9% 2.9% 2.9% 2.9% 2.9% 2.9%

    32.1% 35.9% 39.8% 43.8% 47.9% 52.2% 56.5% 61.0% 65.7% 70.4%

    9,870,244 9,820,892 9,771,788 9,722,929 9,674,314 9,625,943 9,577,813 9,529,924 9,482,274 9,434,863

    8,952,000 8,952,000 8,952,000 8,952,000 8,952,000 8,952,000 8,952,000 8,952,000 8,952,000 8,952,000

    918,244 868,892 819,788 770,929 722,314 673,943 625,813 577,924 530,274 482,863

    0.583 0.597 0.611 0.625 0.640 0.655 0.671 0.687 0.703 0.720

    0.051 0.053 0.054 0.056 0.058 0.059 0.061 0.063 0.064 0.066

    5,266 5,389 5,514 5,642 5,773 5,908 6,045 6,185 6,329 6,476

    0.00125 0.00125 0.00125 0.00125 0.00125 0.00125 0.00125 0.00125 0.00125 0.00125

    12.34 12.28 12.21 12.15 12.09 12.03 11.97 11.91 11.85 11.79

    21.83 22.46 23.10 23.76 24.45 25.15 25.87 26.61 27.38 28.16

    47.00 47.00 47.00 47.00 47.00 47.00 47.00 47.00 47.00 47.00

    346.97 354.67 362.53 370.56 378.77 387.15 395.71 404.46 413.39 422.52

    5.74 5.91 6.08 6.26 5.19 3.94 2.62 1.23 0.00 0.00

    12.84 13.21 13.59 13.98 14.38 14.79 15.22 15.65 16.10 16.57

    447 456 465 474 482 490 498 507 516 526

    4,820 4,933 5,050 5,169 5,292 5,418 5,546 5,678 5,813 5,950

    92% 92% 92% 92% 92% 92% 92% 92% 92% 92%

    4.9 4.9 4.9 4.9 4.8 4.8 4.8 4.8 4.7 4.7

    0 0 0 0 0 0 0 0 0 0

    4,820 4,933 5,050 5,169 5,292 5,418 5,546 5,678 5,813 5,950

    10,876 15,809 20,859 26,028 31,319 36,737 42,283 47,962 53,775 59,725

    1,175 753 321 0 0 0 0 0 0 0

    422 432 321 0 0 0 0 0 0 0

    1,205 1,233 1,262 1,292 1,323 1,354 1,387 1,420 1,453 1,488

    783 802 941 1,292 1,323 1,354 1,387 1,420 1,453 1,488

    4,032 4,127 4,104 3,872 3,964 4,058 4,155 4,254 4,355 4,458

    Appendix

    Appendix C - Valuation Results (Cont.)

    “Original FiT” Scenario

    (EUR, '000)

    Inflation Rate

    Accumulated Inflation

    Production:

    AC kWh Produced

    Guaranteed Purchase

    Excess Production

    Revenues

    Garanteed Price

    Market Price

    Total Revenues

    Costs

    Energy Cost per kWh

    Energy Cost

    Rent cost

    Insurance

    Maintenance

    Supplier Bonnus

    G&A

    Total Operating Costs

    EBITDA

    New Energy Tax

    Depreciation for Tax

    Profit Before Taxes (tax calculation)

    Accumulated Profit Before Taxes

    Tax Credit for environmental investments

    Use of Tax Credit

    Nominal Tax

    Effective Tax

    Project CF

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 46

    Appendix

    Appendix C - Valuation Results (Cont.)

    “Original FiT” Scenario

    (EUR, '000)

    Inflation Rate

    Accumulated Inflation

    Production:

    AC kWh Produced

    Guaranteed Purchase

    Excess Production

    Revenues

    Garanteed Price

    Market Price

    Total Revenues

    Costs

    Energy Cost per kWh

    Energy Cost

    Rent cost

    Insurance

    Maintenance

    Supplier Bonnus

    G&A

    Total Operating Costs

    EBITDA

    New Energy Tax

    Depreciation for Tax

    Profit Before Taxes (tax calculation)

    Accumulated Profit Before Taxes

    Tax Credit for environmental investments

    Use of Tax Credit

    Nominal Tax

    Effective Tax

    Project CF

    2031 2032 2033 2034 2035 2036 2037 2038

    2.9% 2.9% 2.9% 2.9% 2.9% 2.9% 2.9% 2.9%

    75.3% 80.3% 85.5% 90.8% 96.3% 101.9% 107.7% 113.7%

    9,387,689 9,340,750 9,294,046 9,247,576 9,201,338 9,155,332 9,109,555 9,064,007

    8,952,000 8,952,000 8,952,000 8,952,000 8,952,000 8,952,000 8,952,000 8,952,000

    435,689 388,750 342,046 295,576 249,338 203,332 157,555 112,007

    0.737 0.754 0.772 0.791 0.809 0.828 0.848 0.868

    0.068 0.070 0.072 0.074 0.076 0.079 0.081 0.083

    6,627 6,780 6,938 7,099 7,264 7,432 7,605 7,781

    0.00125 0.00125 0.00125 0.00125 0.00125 0.00125 0.00125 0.00125

    11.73 11.68 11.62 11.56 11.50 11.44 11.39 11.33

    28.97 29.80 30.66 31.54 32.44 33.37 34.33 35.32

    47.00 47.00 47.00 47.00 47.00 47.00 47.00 47.00

    431.84 441.36 451.09 461.03 471.18 481.55 492.13 502.95

    0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

    17.04 17.53 18.03 18.55 19.08 19.63 20.19 20.77

    537 547 558 570 581 593 605 617

    6,090 6,233 6,379 6,529 6,683 6,839 7,000 7,164

    92% 92% 92% 92% 92% 92% 92% 92%

    4.7 4.7 4.6 4.6 4.6 4.6 4.6 4.5

    0 0 0 0 0 0 0 0

    6,090 6,233 6,379 6,529 6,683 6,839 7,000 7,164

    65,815 72,048 78,427 84,957 91,639 98,479 105,479 112,643

    0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0

    1,522 1,558 1,595 1,632 1,671 1,710 1,750 1,791

    1,522 1,558 1,595 1,632 1,671 1,710 1,750 1,791

    4,563 4,670 4,780 4,892 5,007 5,125 5,245 5,369

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 47

    Q2-Q4/2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

    2.8% 1.3% 1.8% 2.3% 2.9% 2.9% 2.9% 2.9% 2.9% 2.9%

    2.8% 4.0% 5.9% 8.4% 11.5% 14.7% 18.0% 21.4% 24.8% 28.4%

    8,161,728 10,325,715 10,274,087 10,222,716 10,171,603 10,120,745 10,070,141 10,019,790 9,969,691 9,919,843

    1,115,891 7,500,000 7,500,000 8,952,000 8,952,000 8,952,000 8,952,000 8,952,000 8,952,000 8,952,000

    7,045,837 2,825,715 2,774,087 1,270,716 1,219,603 1,168,745 1,118,141 1,067,790 1,017,691 967,843

    0.476 0.124 0.124 0.126 0.128 0.131 0.135 0.138 0.141 0.144

    0.040 0.041 0.042 0.042 0.043 0.045 0.046 0.047 0.049 0.050

    813 1,043 1,049 1,183 1,202 1,229 1,256 1,284 1,312 1,341

    0.0100 0.00125 0.00125 0.00125 0.00125 0.00125 0.00125 0.00125 0.00125 0.00125

    81.62 12.91 12.84 12.78 12.71 12.65 12.59 12.52 12.46 12.40

    12.75 17.47 17.69 18.00 18.42 18.95 19.49 20.05 20.63 21.22

    35.25 47.00 47.00 47.00 47.00 47.00 47.00 47.00 47.00 47.00

    135.00 184.95 187.26 190.61 195.06 200.65 206.41 212.34 218.43 224.70

    3.44 4.56 4.62 4.71 4.82 4.96 5.11 5.26 5.42 5.57

    7.50 10.28 10.40 10.59 10.84 11.15 11.47 11.80 12.14 12.48

    276 277 280 284 289 295 302 309 316 323

    537 766 769 899 914 933 954 975 996 1,017

    66% 73% 73% 76% 76% 76% 76% 76% 76% 76%

    4.1 5.2 5.1 5.1 5.1 5.1 5.0 5.0 5.0 5.0

    3,196 4,262 4,262 4,262 4,262 4,262 4,262 4,262 902 0

    (2,659) (3,496) (3,493) (3,363) (3,348) (3,328) (3,308) (3,287) 94 1,017

    (2,659) (6,156) (9,648) (13,011) (16,360) (19,688) (22,996) (26,283) (26,189) (25,172)

    1,705 1,705 1,705 1,705 1,705 1,705 1,705 1,705 1,705 1,705

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    533 761 764 894 908 928 949 970 991 1,012

    Appendix

    Appendix C - Valuation Results (Cont.)

    “New FiT” Scenario

    (EUR, '000)

    Inflation Rate

    Accumulated Inflation

    Production:

    AC kWh Produced

    Guaranteed Purchase

    Excess Production

    Revenues

    Garanteed Price

    Market Price

    Total Revenues

    Costs

    Energy Cost per kWh

    Energy Cost

    Rent cost

    Insurance

    Maintenance

    Supplier Bonnus

    G&A

    Total Operating Costs

    EBITDA

    New Energy Tax

    Depreciation for Tax

    Profit Before Taxes (tax calculation)

    Accumulated Profit Before Taxes

    Tax Credit for environmental investments

    Use of Tax Credit

    Nominal Tax

    Effective Tax

    Project CF

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 48

    2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

    2.9% 2.9% 2.9% 2.9% 2.9% 2.9% 2.9% 2.9% 2.9% 2.9%

    32.1% 35.9% 39.8% 43.8% 47.9% 52.2% 56.5% 61.0% 65.7% 70.4%

    9,870,244 9,820,892 9,771,788 9,722,929 9,674,314 9,625,943 9,577,813 9,529,924 9,482,274 9,434,863

    8,952,000 8,952,000 8,952,000 8,952,000 8,952,000 8,952,000 8,952,000 8,952,000 8,952,000 8,952,000

    918,244 868,892 819,788 770,929 722,314 673,943 625,813 577,924 530,274 482,863

    0.148 0.151 0.155 0.159 0.162 0.166 0.170 0.174 0.178 0.182

    0.051 0.053 0.054 0.056 0.058 0.059 0.061 0.063 0.064 0.066

    1,370 1,400 1,431 1,462 1,494 1,527 1,561 1,595 1,630 1,665

    0.00125 0.00125 0.00125 0.00125 0.00125 0.00125 0.00125 0.00125 0.00125 0.00125

    12.34 12.28 12.21 12.15 12.09 12.03 11.97 11.91 11.85 11.79

    21.83 22.46 23.10 23.76 24.45 25.15 25.87 26.61 27.38 28.16

    47.00 47.00 47.00 47.00 47.00 47.00 47.00 47.00 47.00 47.00

    231.15 237.78 244.61 251.63 258.85 266.28 273.92 281.78 289.87 298.19

    5.74 5.91 6.08 6.26 5.19 3.94 2.62 1.23 0.00 0.00

    12.84 13.21 13.59 13.98 14.38 14.79 15.22 15.65 16.10 16.57

    331 339 347 355 362 369 377 384 392 402

    1,039 1,062 1,084 1,108 1,132 1,158 1,184 1,211 1,238 1,264

    76% 76% 76% 76% 76% 76% 76% 76% 76% 76%

    4.9 4.9 4.9 4.9 4.8 4.8 4.8 4.8 4.7 4.7

    0 0 0 0 0 0 0 0 0 0

    1,039 1,062 1,084 1,108 1,132 1,158 1,184 1,211 1,238 1,264

    (24,133) (23,071) (21,987) (20,879) (19,747) (18,589) (17,405) (16,194) (14,957) (13,693)

    1,705 1,705 1,705 1,705 1,705 1,705 1,705 1,705 1,705 1,705

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    1,034 1,057 1,079 1,103 1,128 1,153 1,179 1,206 1,233 1,259

    Appendix

    Appendix C - Valuation Results (Cont.)

    “New FiT” Scenario

    (EUR, '000)

    Inflation Rate

    Accumulated Inflation

    Production:

    AC kWh Produced

    Guaranteed Purchase

    Excess Production

    Revenues

    Garanteed Price

    Market Price

    Total Revenues

    Costs

    Energy Cost per kWh

    Energy Cost

    Rent cost

    Insurance

    Maintenance

    Supplier Bonnus

    G&A

    Total Operating Costs

    EBITDA

    New Energy Tax

    Depreciation for Tax

    Profit Before Taxes (tax calculation)

    Accumulated Profit Before Taxes

    Tax Credit for environmental investments

    Use of Tax Credit

    Nominal Tax

    Effective Tax

    Project CF

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 49

    2031 2032 2033 2034 2035 2036

    2.9% 2.9% 2.9% 2.9% 2.9% 2.9%

    75.3% 80.3% 85.5% 90.8% 96.3% 101.9%

    9,387,689 9,340,750 9,294,046 9,247,576 9,201,338 9,155,332

    8,952,000 8,952,000 8,952,000 8,952,000 8,952,000 8,952,000

    435,689 388,750 342,046 295,576 249,338 203,332

    0.187 0.191 0.196 0.200 0.205 0.210

    0.068 0.070 0.072 0.074 0.076 0.079

    1,702 1,739 1,777 1,816 1,855 1,896

    0.00125 0.00125 0.00125 0.00125 0.00125 0.00125

    11.73 11.68 11.62 11.56 11.50 11.44

    28.97 29.80 30.66 31.54 32.44 33.37

    47.00 47.00 47.00 47.00 47.00 47.00

    306.74 315.55 324.60 333.92 343.50 353.36

    0.00 0.00 0.00 0.00 0.00 0.00

    17.04 17.53 18.03 18.55 19.08 19.63

    411 422 432 443 454 465

    1,290 1,317 1,345 1,373 1,402 1,431

    76% 76% 76% 76% 76% 75%

    4.7 4.7 4.6 4.6 4.6 4.6

    0 0 0 0 0 0

    1,290 1,317 1,345 1,373 1,402 1,431

    (12,403) (11,085) (9,740) (8,367) (6,965) (5,534)

    1,705 1,705 1,705 1,705 1,705 1,705

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    1,286 1,313 1,340 1,369 1,397 1,426

    Appendix

    Appendix C - Valuation Results (Cont.)

    “New FiT” Scenario

    (EUR, '000)

    Inflation Rate

    Accumulated Inflation

    Production:

    AC kWh Produced

    Guaranteed Purchase

    Excess Production

    Revenues

    Garanteed Price

    Market Price

    Total Revenues

    Costs

    Energy Cost per kWh

    Energy Cost

    Rent cost

    Insurance

    Maintenance

    Supplier Bonnus

    G&A

    Total Operating Costs

    EBITDA

    New Energy Tax

    Depreciation for Tax

    Profit Before Taxes (tax calculation)

    Accumulated Profit Before Taxes

    Tax Credit for environmental investments

    Use of Tax Credit

    Nominal Tax

    Effective Tax

    Project CF

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 50

    Q2-Q4/2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

    2.8% 1.3% 1.9% 2.4% 2.9% 2.9% 2.9% 2.9% 2.9% 2.9%

    2.8% 4.0% 6.0% 8.6% 11.7% 14.9% 18.2% 21.6% 25.1% 28.6%

    8,161,728 10,325,715 10,274,087 10,222,716 10,171,603 10,120,745 10,070,141 10,019,790 9,969,691 9,919,843

    1,115,891 0 0 0 0 0 0 0 0 0

    7,045,837 10,325,715 10,274,087 10,222,716 10,171,603 10,120,745 10,070,141 10,019,790 9,969,691 9,919,843

    0.476 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

    0.0400 0.0411 0.0416 0.0424 0.0434 0.0447 0.0460 0.0473 0.0486 0.0500

    813 424 428 434 442 452 463 474 485 496

    0.0100 0.0013 0.0013 0.0013 0.0013 0.0013 0.0013 0.0013 0.0013 0.0013

    81.62 12.91 12.84 12.78 12.71 12.65 12.59 12.52 12.46 12.40

    12.75 17.47 17.69 18.03 18.45 18.98 19.53 20.09 20.67 21.26

    35.25 47.00 47.00 47.00 47.00 47.00 47.00 47.00 47.00 47.00

    135.00 184.95 187.26 190.86 195.40 201.01 206.78 212.71 218.82 225.10

    3.44 4.56 4.62 4.71 4.83 4.97 5.12 5.27 5.43 5.58

    7.50 10.28 10.40 10.60 10.86 11.17 11.49 11.82 12.16 12.51

    276 277 280 284 289 296 302 309 317 324

    537 147 148 150 152 156 160 164 168 172

    66% 35% 35% 35% 35% 35% 35% 35% 35% 35%

    4.1 5.2 5.1 5.1 5.1 5.1 5.0 5.0 5.0 5.0

    3,196 4,262 4,262 4,262 4,262 4,262 4,262 4,262 902 0

    (2,659) (4,115) (4,114) (4,112) (4,109) (4,106) (4,102) (4,098) (734) 172

    (2,659) (6,774) (10,888) (15,001) (19,110) (23,216) (27,317) (31,415) (32,149) (31,976)

    1,705 1,705 1,705 1,705 1,705 1,705 1,705 1,705 1,705 1,705

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    533 142 143 144 147 151 155 159 163 167

    Appendix

    Appendix C - Valuation Results (Cont.)

    “No FiT” Scenario

    (EUR, '000)

    Inflation Rate

    Accumulated Inflation

    Production:

    AC kWh Produced

    Guaranteed Purchase

    Excess Production

    Revenues

    Garanteed Price

    Market Price

    Total Revenues

    Costs

    Energy Cost per kWh

    Energy Cost

    Rent cost

    Insurance

    Maintenance

    Supplier Bonnus

    G&A

    Total Operating Costs

    EBITDA

    New Energy Tax

    Depreciation for Tax

    Profit Before Taxes (tax calculation)

    Accumulated Profit Before Taxes

    Tax Credit for environmental investments

    Use of Tax Credit

    Nominal Tax

    Effective Tax

    Project CF

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 51

    2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

    2.9% 2.9% 2.9% 2.9% 2.9% 2.9% 2.9% 2.9% 2.9% 2.9%

    32.3% 36.1% 40.0% 44.1% 48.2% 52.4% 56.8% 61.3% 66.0% 70.7%

    9,870,244 9,820,892 9,771,788 9,722,929 9,674,314 9,625,943 9,577,813 9,529,924 9,482,274 9,434,863

    0 0 0 0 0 0 0 0 0 0

    9,870,244 9,820,892 9,771,788 9,722,929 9,674,314 9,625,943 9,577,813 9,529,924 9,482,274 9,434,863

    0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

    0.0515 0.0529 0.0545 0.0560 0.0576 0.0593 0.0610 0.0627 0.0645 0.0664

    508 520 532 545 557 571 584 598 612 626

    0.0013 0.0013 0.0013 0.0013 0.0013 0.0013 0.0013 0.0013 0.0013 0.0013

    12.34 12.28 12.21 12.15 12.09 12.03 11.97 11.91 11.85 11.79

    21.87 22.50 23.14 23.81 24.49 25.19 25.92 26.66 27.42 28.21

    47.00 47.00 47.00 47.00 47.00 47.00 47.00 47.00 47.00 47.00

    231.56 238.20 245.04 252.07 259.31 266.75 274.40 282.28 290.38 298.71

    5.75 5.92 6.09 6.27 5.20 3.95 2.63 1.23 0.00 0.00

    12.86 13.23 13.61 14.00 14.41 14.82 15.24 15.68 16.13 16.60

    331 339 347 355 362 370 377 385 393 402

    177 181 185 189 195 201 207 213 219 224

    35% 35% 35% 35% 35% 35% 35% 36% 36% 36%

    4.9 4.9 4.9 4.9 4.8 4.8 4.8 4.8 4.7 4.7

    0 0 0 0 0 0 0 0 0 0

    177 181 185 189 195 201 207 213 219 224

    (31,800) (31,619) (31,434) (31,245) (31,050) (30,849) (30,642) (30,429) (30,210) (29,986)

    1,705 1,705 1,705 1,705 1,705 1,705 1,705 1,705 1,705 1,705

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    172 176 180 184 190 196 202 208 214 219

    Appendix

    Appendix C - Valuation Results (Cont.)

    “No FiT” Scenario

    (EUR, '000)

    Inflation Rate

    Accumulated Inflation

    Production:

    AC kWh Produced

    Guaranteed Purchase

    Excess Production

    Revenues

    Garanteed Price

    Market Price

    Total Revenues

    Costs

    Energy Cost per kWh

    Energy Cost

    Rent cost

    Insurance

    Maintenance

    Supplier Bonnus

    G&A

    Total Operating Costs

    EBITDA

    New Energy Tax

    Depreciation for Tax

    Profit Before Taxes (tax calculation)

    Accumulated Profit Before Taxes

    Tax Credit for environmental investments

    Use of Tax Credit

    Nominal Tax

    Effective Tax

    Project CF

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 52

    Appendix

    Appendix C - Valuation Results (Cont.)

    “No FiT” Scenario

    (EUR, '000)

    Inflation Rate

    Accumulated Inflation

    Production:

    AC kWh Produced

    Guaranteed Purchase

    Excess Production

    Revenues

    Garanteed Price

    Market Price

    Total Revenues

    Costs

    Energy Cost per kWh

    Energy Cost

    Rent cost

    Insurance

    Maintenance

    Supplier Bonnus

    G&A

    Total Operating Costs

    EBITDA

    New Energy Tax

    Depreciation for Tax

    Profit Before Taxes (tax calculation)

    Accumulated Profit Before Taxes

    Tax Credit for environmental investments

    Use of Tax Credit

    Nominal Tax

    Effective Tax

    Project CF

    2031 2032 2033 2034 2035 2036 2037 2038 2039 2040

    2.9% 2.9% 2.9% 2.9% 2.9% 2.9% 2.9% 2.9% 2.9% 2.9%

    75.6% 80.7% 85.8% 91.2% 96.7% 102.3% 108.1% 114.1% 120.2% 126.5%

    9,387,689 9,340,750 9,294,046 9,247,576 9,201,338 9,155,332 9,109,555 9,064,007 9,018,687 8,973,594

    0 0 0 0 0 0 0 0 0 0

    9,387,689 9,340,750 9,294,046 9,247,576 9,201,338 9,155,332 9,109,555 9,064,007 9,018,687 8,973,594

    0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

    0.0683 0.0702 0.0723 0.0743 0.0765 0.0787 0.0809 0.0832 0.0856 0.0881

    641 656 672 687 704 720 737 755 772 790

    0.0013 0.0013 0.0013 0.0013 0.0013 0.0013 0.0013 0.0013 0.0013 0.0013

    11.73 11.68 11.62 11.56 11.50 11.44 11.39 11.33 11.27 11.22

    29.02 29.85 30.71 31.59 32.50 33.43 34.39 35.38 36.39 37.44

    47.00 47.00 47.00 47.00 47.00 47.00 47.00 47.00 47.00 47.00

    307.29 316.11 325.18 334.51 344.11 353.99 364.15 374.60 385.35 396.41

    0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

    17.07 17.56 18.07 18.58 19.12 19.67 20.23 20.81 21.41 22.02

    412 422 433 443 454 466 477 489 501 514

    229 234 239 244 249 255 260 265 271 276

    36% 36% 36% 36% 35% 35% 35% 35% 35% 35%

    4.7 4.7 4.6 4.6 4.6 4.6 4.6 4.5 4.5 4.5

    0 0 0 0 0 0 0 0 0 0

    229 234 239 244 249 255 260 265 271 276

    (29,757) (29,523) (29,284) (29,040) (28,790) (28,536) (28,276) (28,010) (27,739) (27,463)

    1,705 1,705 1,705 1,705 1,705 1,705 1,705 1,705 1,705 1,705

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    224 229 234 240 245 250 255 261 266 272

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 53

    Appendix

    Appendix D - WACC Comparison

    Source: Damodaran, Bloomberg

    Parameter Giza Trigger-Foresight Remarks

    Risk Free Rate (Rf) 1.7% 5.3%

    Previous model was based on long-term US Government bond yields in real

    terms adjusted for inflation, while the present model is based on long-term

    Spanish Government bond yields in nominal terms.

    Market Beta (Unlevered) 0.67 0.64 Different set of comparable companies.

    D/(D+E) 34.6% 35.2% Different set of comparable companies.

    Market Risk Premium 5.4% 5.2%

    Previous model was based on the equity risk premium for the Spanish market,

    while this model assumes the risk premium of a mature market (the country risk

    premium is embedded in the risk free rate).

    Other Risk Premiums 2.5% 2.5% Different assumptions of excess risk premium.

    Cost of Equity 9.2% 12.4%Reflecting different assumptions in CAPM parameters.

    Previous model was in real terms, while this model is in nominal terms.

    Cost of Debt 5.3% 8.5%This model is based on current debt data received from the company.

    Previous model was in real terms, while this model is in nominal terms.

    Tax 25% 25% No change.

    WACC (Nominal Terms) 10.23% 10.31%

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 54

    Appendix

    Appendix E - Summary of Lawyers’ Opinion

    “In summation, in our opinion, with the reservations derived from the absence of precedents and, therefore, of

    administrative doctrine and case law in relation to RD 1003/2010, it is highly probable that the contestation of

    the Client against the decisions to suspend payment of the subsidized feed in tariff on a precautionary basis and

    that the tariff regime of RD 661/2007 were not applicable to the installations shall be finally accepted by the

    Contentious-Administrative Courts and the installations shall be declared eligible to be paid the subsided feed in

    tariff pursuant to the regime set under RD 661/2001 and consequently the tariff that was suspended/withheld

    from the Client will be repaid together with interest thereon.”

    “Although all documents required by the National Energy Commission were submitted and none of these

    documents lead to conclude that the 63 installations were completed after 29 September 2008, the National

    Commission’s Report on the 63 installations that comprise the plant, concluded that, apparently “installation of

    the necessary equipment for energy production before 30 September 2008 has not been proven””

    “*…+ the large amount of additional evidence filed (listed above), shows beyond doubt that the installations were

    indeed fully completed (with the inverters and modules installed), and all these installations were connected to the

    grid, all before 30 September 2008”

    “All the supplementary documentation now filed in the administrative proceedings show that the 63 installations

    were completed before 30 September 2008”

    Source: Ramón y Cajal Abogados (Company’s lawyers)

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 55

    Appendix

    Appendix F - Translation of Worded Probabilities to Numeric Values

    General

    The estimation of the occurrence of a given event is generally described by a phrase or expression that offers a sense of probability.

    These expressions (known as “Words of Estimative Probability -WEPs”) were originally developed by Sherman Kent in 1964, in relation to Intelligence Analysis.

    The concept of WEPs was later expanded and is currently applied in other areas including accounting.

    Evidence for Interpretation

    A survey conducted among Portuguese statutory auditors revealed that they associate the following range of probability with the expression “Highly Probable”:

    CIA research defines commonly accepted probability ranges for frequently used expressions:

    The expression “Highly Probable” is commonly associated with the probability range of 75%-95%

    We conservatively chose to associate it with a probability of 75%

    Source: “Accounting for Uncertain Tax Positions”, America’s Community Bankers; “The Interpretation of Verbal Probability Expressions used in IAS/IFRS: Some Portuguese Evidence”, by C. Teixeira and A. Fialho Silva; CIA (www.cia.gov)

    “In practice, the “probable" threshold is generally understood to

    mean a 70 to 75 percent confidence level*…+”

    (“Accounting for Uncertain Tax Positions”, America’s Community

    Bankers)

    Expression Mean Median Std Dev Min Max

    Highly Probable 88% 90% 7% 70% 100%

    Definition Probability (%)

    Almost Certainly 80 - 100

    Highly Probable 75 - 95

    Probably 60 - 80

    Unlikely 10 - 30

    Some Slight Chance 0 - 20

  • Confidential. Copyrights Trigger-Foresight, All rights reserved 56

    Appendix

    Appendix G - “Fair Value Less Cost to Sell” Analysis

    Due to the uncertainty of the future FiT, it may be more profitable for “the Partnership” to dismantle the park and sell the parts.

    According to “the Partnership’s” technical advisors there is a market for PV panels, transformers and other parts.

    The following table summarizes the value obtained from selling the parts:

    Source: Novatec Asesoria (Company’s technical consultants)

    Parameter Value

    Actual Price of PV Panels (€/Wp) 1.20

    Plant Size (kWp) 6,986

    Aproximate Net Value (€, '000) 7,000

    Expected Net Income from Sale

    of Parts (€/Wp)1.00

    2011-05-30T22:29:14+0000IsaSig 4 Client


Recommended