+ All Categories
Home > Documents > OLTC Failure

OLTC Failure

Date post: 14-Oct-2015
Category:
Upload: vtps
View: 112 times
Download: 20 times
Share this document with a friend
Description:
OLTC Failure
Popular Tags:

of 18

Transcript
  • -------------------------------------------------------------------------------------------------------------

    P.O.Box 87

    Mayfield, NSW, 2304

    Tel 02 4928 1511

    Fax 02 4928 1511

    Mob 0425 326 541

    [email protected]

    Power Control Engineers Pty Ltd

    Specialist Electrical Engineers

    ABN 50 103 684 466

    TRANSFORMER FAILURE

    Review and Investigation

    of

    Transformer Failure

    Rev No Description Originator Checked Date

    0 Issued KB MS 23/01/09

  • 23/01/09

    Page 2 of 18

    ----------------------------------------------------------------------------------------------------------------

    ------------------------------------------------------------------------------------------------------------------------------------------------------------

    \\Host\SharedDocs\PCE Work\PCE Projects\Web Site Revamp\Investigation into Transformer Failure due to Failure of

    OLTC.docx

    PCE

    Transformer Failure due to OLTC Fault

    Table of Contents

    1 INTRODUCTION ........................................................................................................................ 3

    2 EXECUTIVE SUMMARY ............................................................................................................ 3

    2.1 Recommendations .............................................................................................................. 3

    3 REVIEW OF REPAIRERS REPORT ......................................................................................... 4

    3.1 Repairer Inspection Findings............................................................................................... 4

    4 INVESTIGATION OF FAULT AND FAILURE MODE .................................................................. 5

    4.1 Fault Current Determination ................................................................................................ 5

    4.1.1 Current waveform analysis. .......................................................................................... 5

    4.1.2 Voltage Waveform Analysis. ........................................................................................ 5

    4.2 Analysis of Fault Recording ................................................................................................ 6

    4.3 Review of Protection Operation ........................................................................................... 8

    4.4 Review of Tap changer Mechanism .................................................................................... 9

    4.5 Review of Winding Physical Layout..................................................................................... 9

    4.6 Winding Open Circuit Voltage ........................................................................................... 11

    4.7 Detailed Failure Mechanism Sequence ............................................................................. 12

    5 CONCLUSION .......................................................................................................................... 13

    6 APPENDICES .......................................................................................................................... 14

    6.1 Appendix 1 Calculations ................................................................................................. 14

    6.2 Appendix 2 Photographs of Failed Transformer ............................................................. 15

    6.3 Appendix 3 Tap Changer Data ....................................................................................... 17

    6.4 Appendix 4 Notice of Failure .......................................................................................... 18

  • 23/01/09

    Page 3 of 18

    ----------------------------------------------------------------------------------------------------------------

    ------------------------------------------------------------------------------------------------------------------------------------------------------------

    \\Host\SharedDocs\PCE Work\PCE Projects\Web Site Revamp\Investigation into Transformer Failure due to Failure of

    OLTC.docx

    PCE

    Transformer Failure due to OLTC Fault

    1 INTRODUCTION

    An industrial site experienced a failure of a 7.5/10MVA 33000V/6600V power transformer. The

    transformer was sent to a repairer for inspection and repair.

    This report reviews the findings of the inspection by the repairer and fault data gathered on site.

    2 EXECUTIVE SUMMARY

    The review of the repairers report and investigation of fault data verify that the transformer failure

    was due to the failure of a connection to the transition resistor in the transformer tap changer. The

    failure caused an open circuit in the delta HV winding leading to high voltages, internal arcing and

    severe damage to the winding.

    Existing protection schemes operated correctly and without delay but were unable to contain the

    damage. No change is recommended to these systems.

    It is possible to install some additional monitoring of the tap changers but direct detection and

    prediction of this particular fault is difficult to achieve. Additional monitoring should be considered.

    The recommended solution is early detection of potential problems through regular planned

    maintenance according to manufacturers recommendations

    2.1 Recommendations

    Recommendation

    1. Highlight this mode of failure and the inspection required to detect it. to

    maintenance personnel

    2. Consider installing additional tap changer monitoring equipment

    3. Ensure tap changer maintenance is carried out at recommended number of

    operations

    4. Ensure transition resistor components are replaced as per manufacturers

    recommendations

    5. Carry out additional offline non-intrusive testing of the tap changers at

    shorter intervals than tap changer maintenance intervals. Testing such as

    contact resistance is included.

  • 23/01/09

    Page 4 of 18

    ----------------------------------------------------------------------------------------------------------------

    ------------------------------------------------------------------------------------------------------------------------------------------------------------

    \\Host\SharedDocs\PCE Work\PCE Projects\Web Site Revamp\Investigation into Transformer Failure due to Failure of

    OLTC.docx

    PCE

    Transformer Failure due to OLTC Fault

    3 REVIEW OF REPAIRERS REPORT

    The data reviewed includes the following

    Repairer Fault Investigation Report

    Fault Disturbance Recording from power monitoring equipment

    Fault records and notes by site personnel

    3.1 Repairer Inspection Findings

    The findings of the inspection report by the repairer are summarised below

    The lead to the tap changer transition resistance contact of HV Winding-A was burned off.

    Flash marks were evident on the tap changer fixed and change over contacts for Winding-A.

    The top of HV Winding-A had failed due to interturn fault and flashover.

    The bottom of HV Winding-A was damaged mechanically.

    The LV winding B showed signs of slight distortion

  • 23/01/09

    Page 5 of 18

    ----------------------------------------------------------------------------------------------------------------

    ------------------------------------------------------------------------------------------------------------------------------------------------------------

    \\Host\SharedDocs\PCE Work\PCE Projects\Web Site Revamp\Investigation into Transformer Failure due to Failure of

    OLTC.docx

    PCE

    Transformer Failure due to OLTC Fault

    4 INVESTIGATION OF FAULT AND FAILURE MODE

    PCE investigations included

    Review of the fault recordings captured by the substation Power Monitor to further verify the

    mode of failure.

    Gathering additional fault data from site personnel.

    Review of repairer report

    Literature search

    Calculations

    Available literature indicated that that failure of tap changers is the second most common cause of

    failure of transformers, second only to insulation deterioration and failure. The type of failure which

    occurred with this transformer is fairly common and typical of this type of OLTC failure.

    4.1 Fault Current Determination

    The fault current was initially of the order of 2100A (3 x 700A) for the first two cycles and then it

    increased beyond the range of the power monitor. However, the fault currents in this range could be

    determined from the data available as follows.

    4.1.1 Current waveform analysis.

    Inspection of the steady fault current waveform indicated a ratio along the x axis of a half cycle to

    the truncated section of the waveform equal to 52:35 where 52 equates to 180 degrees. The

    truncated level of the current waveform was 1250A and thus the peak value of the Sine wave is

    calculated to be approximately 2545A. This equates to an RMS current of 1799A. The fault

    recording is for one of three feeders supplying the bus to which the failed transformer was

    connected and thus the transformer fault current would have been of the order of 5397A

    4.1.2 Voltage Waveform Analysis.

    The level to which the voltage waveform collapsed provides a second means of estimating the level

    of fault current. Knowing the supply impedance at the bus to which the transformer is connected it is

    possible to calculate the current flowing which would result in the voltage dropping to the level

    recorded. The recording shows that the voltage collapsed from 17700V to 1180V. The fault current

    required to cause this collapse is calculated to be 7030A (See Appendix 1 Calculations)

    The known Supply Utility fault levels at the 33kV busbar are 8kA line to line and 3.8kA line to

    ground. Based on these magnitudes, the initial fault could have been a single line-to-ground fault.

    As the fault current eventually exceeded the 3.8kA line to ground fault level, the final fault is

    confirmed as comprising a line-to-line fault or line-to-line-to-ground fault.

  • 23/01/09

    Page 6 of 18

    ----------------------------------------------------------------------------------------------------------------

    ------------------------------------------------------------------------------------------------------------------------------------------------------------

    \\Host\SharedDocs\PCE Work\PCE Projects\Web Site Revamp\Investigation into Transformer Failure due to Failure of

    PCE

    Transformer Failure due to OLTC Fault

    4.2 Analysis of Fault Recording

    The fault recording is shown below:

    Figure 1 Fault Trace from Power Monitor

    An analysis of this recording verifies the failure mode of the transformer.

    Prefault conditions at point A indicate the system operating at a voltage of 25kV(peak) =

    17.7kV(rms) line to ground and 100A pk (approx 210A rms total - 3 feeders)

    At point B the fault is initiated. The fault is not a direct short circuit but develops as

    evidenced by the recorded initial fault current peak of 650A developing to a steady state

    peak of 2500A after 2 cycles (Note these are the fault currents seen by 1 of 3 feeders).

    After one cycle the fault current has increased to a level which causes the voltage to

    collapse as seen at point C.

    Points C and D on the recording show a number of spikes on the voltage waveform. These

    are probably due to instability of the developing arcing fault across the HV Winding-A of the

    transformer with some arcing to the tank of the transformer. At this stage the fault current

    reaches its maximum level.

    Point E which is 3 to 4 cycles from the start of the fault is where the fault has developed to a

    full phase to phase fault as a result of the interturn failure and arcing across the top of the

    HV Winding-A.

    At point F the vacuum circuit breaker feeding the transformer clears the fault. The fault

    current is cleared and there is indication of a recovery voltage transient. The time from the

    A B C D E F

  • 23/01/09

    Page 7 of 18

    ----------------------------------------------------------------------------------------------------------------

    ------------------------------------------------------------------------------------------------------------------------------------------------------------

    \\Host\SharedDocs\PCE Work\PCE Projects\Web Site Revamp\Investigation into Transformer Failure due to Failure of

    PCE

    Transformer Failure due to OLTC Fault

    start to the clearing of the fault is approximately 90ms or 4.5 cycles. The transformer

    differential protection would have initiated a trip signal in 20 to 30ms and the breaker

    clearing time would be in the order of 60ms. This confirms the correct operation of the

    protection scheme.

    The current and voltage levels for the duration of the fault captured in Figure 1 Fault Trace from

    Power Monitor above are shown in Figure 2 - Transformer Fault Current and Voltage Levels below

    Figure 2 - Transformer Fault Current and Voltage Levels

    0.0

    1000.0

    2000.0

    3000.0

    4000.0

    5000.0

    6000.0

    7000.0

    0 50 100 150 200 250

    Cu

    rre

    nt

    (Am

    ps)

    Time (ms)

    Amps

    0.00

    5.00

    10.00

    15.00

    20.00

    25.00

    30.00

    35.00

    40.00

    45.00

    0 50 100 150 200 250

    Vo

    lta

    ge

    (k

    V)

    Time (ms)

    kV

  • 23/01/09

    Page 8 of 18

    ----------------------------------------------------------------------------------------------------------------

    ------------------------------------------------------------------------------------------------------------------------------------------------------------

    \\Host\SharedDocs\PCE Work\PCE Projects\Web Site Revamp\Investigation into Transformer Failure due to Failure of

    OLTC.docx

    PCE

    Transformer Failure due to OLTC Fault

    4.3 Review of Protection Operation

    Site personnel advised that the following protection operated:

    1. O/C Instantaneous on phase 1 and 2 (alarm flag #4) (SPAJ140C on Transformer 33kV

    feeder with a trip recorded at 24x setpoint, or 6480A)

    2. Bucholz on main tank (2 stage type with oil surge and gas detection though it is not known

    which operated)

    3. Oil explosion vent (rupture disk) failed on main tank expelling oil

    4. Oil vent on tap changer tank remained intact

    5. Differential relay type 4C21 with A & B phases flagged

    The settings for the SPAJ140C on Transformer 33kV feeder are as follows:

    Feeder Transformer

    Relay SPAJ140C

    CT Ratio 200 / 1

    Overcurrent Settings Earth Fault Settings

    Curve Very Inverse Curve Definite Time

    Plug I>/In 1.35 (270A) Io>/In 0.20 (40A)

    Time Dial t> 0.21 to> 0.10

    Inst I>>/In 9.00 (1800A) Io>>/In Set off

    Inst t>> 0.04 to>> - - - -

    No earth fault was flagged on this relay. This is because the instantaneous operating time t>> of

    0.04s is faster than the earth fault definite time of 0.1s.

  • 23/01/09

    Page 9 of 18

    ----------------------------------------------------------------------------------------------------------------

    ------------------------------------------------------------------------------------------------------------------------------------------------------------

    \\Host\SharedDocs\PCE Work\PCE Projects\Web Site Revamp\Investigation into Transformer Failure due to Failure of

    PCE

    Transformer Failure due to OLTC Fault

    4.4 Review of Tap changer Mechanism

    Figure 3 Transformer Tap Changer

    4.5 Review of Winding Physical Layout

    There was observed mechanical and flashover damage to the top of the HV winding and

    mechanical movement at the bottom of the winding. The leads to the tap changer come out at the

    top of the winding.

    Figure 4 below shows diagrammatically one phase of the HV winding and tap take-offs 2 15.

    Figure 4- Schematic of A Phase Winding

    Open Circuit

    occurs here

    momentarily

    These wires connect the contacts

    to the transition resistor. A failure

    of one of these wires resulted in

    the open circuiting of the

    transformer HV winding during a

    tap changing operation

    Transition Resistor

    Barrier Plate

  • ----------------------------------------------------------------

    ----------------------------------------------------------------

    \\Host\SharedDocs\PCE Work\PCE Projects\

    PCE

    Transformer Failure due to OLTC Fault

    Figure 5 below shows an approximate physical representation of the HV winding viewed horizontally

    as a cross section of half the winding.

    there are approximately 10 such layers.

    photos and the nameplate data.

    Figure 5- Physical Represen

    The tap take-offs are at approximately mid winding (from nameplate diagram). Between tap 3 and

    tap 13 is approx 10% of the winding (based on known tap range of 13%). Each layer is

    approximately 10% of the winding (since there are 10 laye

    offs are in one layer with tap leads brought out the top of the winding, so possibly passing close to

    the top of layer 4 (at tap takeoff position 2).

    A 2 3 4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    To B

    Tap changer

    --------------------------------------------------------------------------------

    ----------------------------------------------------------------------------------------------------------------------------

    \Web Site Revamp\Investigation into Transformer Failure due to Failure of

    Transformer Failure due to OLTC Fault

    below shows an approximate physical representation of the HV winding viewed horizontally

    as a cross section of half the winding. Each vertical line represents a layer of turns. From photos

    there are approximately 10 such layers. This layout is not known for certain but is deduced from

    Physical Representation of Winding

    offs are at approximately mid winding (from nameplate diagram). Between tap 3 and

    tap 13 is approx 10% of the winding (based on known tap range of 13%). Each layer is

    approximately 10% of the winding (since there are 10 layers). This could mean most of the tap take

    offs are in one layer with tap leads brought out the top of the winding, so possibly passing close to

    the top of layer 4 (at tap takeoff position 2).

    To C

    14

    15

    A1

    Tap changer Open Cct

    23/01/09

    Page 10 of 18

    ----------------

    ----------------------------

    Investigation into Transformer Failure due to Failure of

    below shows an approximate physical representation of the HV winding viewed horizontally

    Each vertical line represents a layer of turns. From photos

    This layout is not known for certain but is deduced from

    offs are at approximately mid winding (from nameplate diagram). Between tap 3 and

    tap 13 is approx 10% of the winding (based on known tap range of 13%). Each layer is

    rs). This could mean most of the tap take-

    offs are in one layer with tap leads brought out the top of the winding, so possibly passing close to

  • 23/01/09

    Page 11 of 18

    ----------------------------------------------------------------------------------------------------------------

    ------------------------------------------------------------------------------------------------------------------------------------------------------------

    \\Host\SharedDocs\PCE Work\PCE Projects\Web Site Revamp\Investigation into Transformer Failure due to Failure of

    PCE

    Transformer Failure due to OLTC Fault

    4.6 Winding Open Circuit Voltage

    With the transformer operating normally delivering load, the supply L-L voltage appears across the

    HV windings distributed across the windings. If the tap changer fails open circuit and there is no

    current flowing in the HV winding then the full Line voltage is seen between the open circuited

    sections and is no longer distributed evenly across the whole winding.

    In addition if there is a residual current and voltage in the secondary this will be transformed to

    corresponding voltages in the open circuited sections of the primary winding and may add to the L-L

    voltage further increasing the overall voltage which may appear between adjacent turns and tap

    changer leads. (Note that the load current in the secondary winding may continue to flow for a

    number of cycles after the primary winding is open circuited due to inductance and the load

    effectively becomes a source to this phase with the secondary voltage transforming back to the

    primary windings.) This is shown in Figure 6 Illustration of voltages across open circuited HV

    windings .

    Figure 6 Illustration of voltages across open circuited HV windings

    HV Amps LV Amps

    Source Load

    Source HV2

    HV Winding LV Winding

    HV1 LV

    Transformer Healthy Condition - No OC in HV winding Voltage Vectors

    HV1

    HV1 Winding LV Amps

    Source Load

    Source

    HV2 Winding

    LV

    HV2 Voltage Vectors

    Transformer with OC HV Winding with residual current in secondary

  • 23/01/09

    Page 12 of 18

    ----------------------------------------------------------------------------------------------------------------

    ------------------------------------------------------------------------------------------------------------------------------------------------------------

    \\Host\SharedDocs\PCE Work\PCE Projects\Web Site Revamp\Investigation into Transformer Failure due to Failure of

    OLTC.docx

    PCE

    Transformer Failure due to OLTC Fault

    4.7 Detailed Failure Sequence

    This review and investigation verifies that the transformer failed as a result of a failure in the tap

    changer open circuiting a high voltage winding.

    The following sequence of events fits all the known facts.

    1. There was a possible pre-existing poor connection on a lead to the tap changer transition

    resistor in HV Winding-A.

    2. Constant tap changing caused the connection wire to the transition resistor to fatigue and fail

    strand by strand at the poor connection near the lug.

    3. Eventually, as a tapping occurs the last strand(s) break or burn off due to the transition

    current (from the momentarily shorted turn).

    4. The HV load current immediately arcs across the open circuit tap changer contacts as the

    induced voltage and supply voltage keep the load current flowing. The load current is

    relatively low and this loacalised arcing is not severe.

    5. The arc extinguishes at the first current zero so that there is no current flowing in the HV

    winding at the next AC cycle.

    6. With no current flowing in the HV winding the voltage between sections of the winding

    separated by the open circuit in the tap changer increase to line voltage. This voltage may

    increase beyond line voltage due to the superimposed transformation voltages from the LV

    side of the transformer back to the open circuited sections of the HV winding. The voltage

    may reach twice line voltage.

    7. The level of voltage between open circuited sections of the winding (including the tap take

    off leads) exceeds the interturn insulation level resulting in failure of the insulation in the

    winding and subsequent flashover.

    8. The failure and arcing across the section of winding results in the current through the

    affected winding rising to a level high enough to saturate the core.

    9. With the core saturated, the HV Winding-A impedance is drastically reduced allowing very

    high currents to flow in the winding damaging it further by distorting the top and bottom turns

    due to the high interturn magnetic forces.

    10. In addition, the arcing across sections of the winding propagates to adjacent layers of the

    winding as the insulation is damaged by the combined effects of arcing, voltage stress and

    mechanical distortion.

    11. The tap changer closes onto the faulted winding resulting in fault currents flowing through

    the tap changer contacts causing burning and damage to these contacts

    12. The fault effectively develops into a line to line fault. (Refer Figure 1 Point D) 13. The distortion of the winding under high fault currents results in some of the leads to the tap

    changer breaking off and arc from these leads to the transformer tank. 14. The fault current and arcing continue until cleared by the transformer circuit breaker.

  • 23/01/09

    Page 13 of 18

    ----------------------------------------------------------------------------------------------------------------

    ------------------------------------------------------------------------------------------------------------------------------------------------------------

    \\Host\SharedDocs\PCE Work\PCE Projects\Web Site Revamp\Investigation into Transformer Failure due to Failure of

    OLTC.docx

    PCE

    Transformer Failure due to OLTC Fault

    5 CONCLUSION

    The problem occurs because an open circuit in the tap changer results in high voltages between

    sections of the HV windings and connection leads to the tap changer. This results in insulation

    break down in the HV windings.

    In conclusion,

    1. A failure of a connecting lead in the transformer tap changer resulted in an open circuit of the

    HV Winding-A

    2. The open circuit of the HV winding resulted in voltages of at least line voltage (and possibly

    up to 2x line voltage) between the open circuited sections of the winding, (ie effectively

    interturn) causing winding insulation failure and flash over of the winding.

    3. The initial fault developed in to a full phase to phase fault due to arc fault propagation,

    saturation of the transformer core and mechanical distortion of the windings.

    4. The HV Winding-A and the tap changer were both severely damaged by the fault

    5. Circuit breaker protection is not fast enough to limit this damage once this occurs. There

    appears to be no practical way to monitor during operation the onset of this particular

    condition.

    It is recommended that tap changers should be inspected when transformer maintenance is

    undertaken to ensure that other similar problems do not occur. Manufacturers replacement

    recommendations should be followed especially for transition resistor components.

    Possible non intrusive testing or monitoring of main power transformers should also be investigated

    such as:

    Tap changer Motor current monitoring

    Tap change speed of operation (offline test)

    Tap contact resistance monitoring (offline test)

  • 23/01/09

    Page 14 of 18

    ----------------------------------------------------------------------------------------------------------------

    ------------------------------------------------------------------------------------------------------------------------------------------------------------

    \\Host\SharedDocs\PCE Work\PCE Projects\Web Site Revamp\Investigation into Transformer Failure due to Failure of

    PCE

    Transformer Failure due to OLTC Fault

    6 APPENDICES

    6.1 Appendix 1 Calculations

    33kV POWER TRANSFORMER FAILURE ANALYSIS

    Fault Current Calculation from Current Waveform

    Half cycle units (180 degrres) 52

    Units of truncated sinewave 35

    Equivalent degrees of truncated section 121.2 deg

    Phase angle at start of truncation 29.4 deg 0.514 radians

    Truncated current level 1250 Amp

    Peak Value of sinewave 2545 Amp

    RMS fault current (3 feeders) 5399 Amp

    Conclusion Fault was Line-Line not SLG (SLG FL =3.8kA only)

    Fault Current Calculation from Voltage Sag

    Voltage Sag L-N V sag 16520 V

    Base voltage L-L Vb 33000 V

    Base MVA Pb 292 MVA

    Source Imped (pu) Zsource pu 0.1137+0.6198i pu

    Base Imped Zb 3.73 (Vb2 / Pb)

    Source Imped (complex) Zsource 0.424038698630137+2.31151438356164i Ohm Z=Zpu*Zb

    Source Imped Zsource 2.35 Ohm

    Fault Current (complex) Ifault 1268.37525723914-6914.15113840647i A

    Fault Current Ifault 7030 A

    Conclusion Fault was Line-Line not SLG (SLG FL =3.8kA only)

  • 23/01/09

    Page 15 of 18

    ----------------------------------------------------------------------------------------------------------------

    ------------------------------------------------------------------------------------------------------------------------------------------------------------

    \\Host\SharedDocs\PCE Work\PCE Projects\Web Site Revamp\Investigation into Transformer Failure due to Failure of

    PCE

    Transformer Failure due to OLTC Fault

    6.2 Appendix 2 Photographs of Failed Transformer

  • 23/01/09

    Page 16 of 18

    ----------------------------------------------------------------------------------------------------------------

    ------------------------------------------------------------------------------------------------------------------------------------------------------------

    \\Host\SharedDocs\PCE Work\PCE Projects\Web Site Revamp\Investigation into Transformer Failure due to Failure of

    PCE

    Transformer Failure due to OLTC Fault

  • 23/01/09

    Page 17 of 18

    ----------------------------------------------------------------------------------------------------------------

    ------------------------------------------------------------------------------------------------------------------------------------------------------------

    \\Host\SharedDocs\PCE Work\PCE Projects\Web Site Revamp\Investigation into Transformer Failure due to Failure of

    PCE

    Transformer Failure due to OLTC Fault

    6.3 Appendix 3 Tap Changer Data

  • 23/01/09

    Page 18 of 18

    ----------------------------------------------------------------------------------------------------------------

    ------------------------------------------------------------------------------------------------------------------------------------------------------------

    \\Host\SharedDocs\PCE Work\PCE Projects\Web Site Revamp\Investigation into Transformer Failure due to Failure of

    OLTC.docx

    PCE

    Transformer Failure due to OLTC Fault

    6.4 Appendix 4 Notice of Failure

    Notice to Site Electrical Personnel

    10MVA 33/6.6kV Transformer Failure

    This site has experienced a failure of a 7.5/10MVA 33000V/6600V power transformer .

    An inspection of the transformer and investigation into the failure has revealed that the root cause of

    the failure was due to a connecting lead in the tap changer failing to an open circuit condition

    resulting in an open circuit near the middle of one of the delta connected HV windings.

    The failure occurred as follows

    1. A failure of a connecting lead in the transformer tap changer resulted in an open circuit of the

    HV winding.

    2. The open circuit of the HV winding resulted in voltages of at least line voltage (and possibly

    up to 2x line voltage) between the open circuited sections of the winding, (ie effectively

    interturn) causing winding insulation failure and flash over of the winding.

    3. The initial fault developed in to a full phase to phase fault due to arc fault propagation,

    saturation of the transformer core and mechanical distortion of the windings.

    4. The HV winding and the tap changer were both severely damaged by the fault

    5. Circuit breaker protection is not fast enough to limit this damage once this occurs.

    6. There appears to be no practical way to monitor during operation the onset of this particular

    condition, and the only remedy is regular and thorough maintenance.

    The transformer has been sent for a rewind and will probably be out of service for 3 months.

    This failure highlights the importance of regular planned maintenance according to manufacturers

    recommendations to prevent similar failures in the future.


Recommended