1 Produced by IRC as a contribution to the One WaSH National Program Produced byIRC as a contribution to the One WaSH National Program ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW SALOMON/YGRY in partnership with AMEN Consulting, ACA Raising Consultants and Zenas Engineering 22-9-2016 Produced by SALOMON with Partners
Transcript
Page 1: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

1Produced by IRC as a contribution to the One WaSH National ProgramProduced byIRC as a contribution to the One WaSH National Program

ONEWASH PLUS

Urban Wash Project – 8 Towns

MID TERM REVIEWSALOMON/YGRY in partnership with AMEN Consulting,

ACA Raising Consultants and Zenas Engineering

22-9-2016

Produced by SALOMON with Partners

Page 2: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

2Produced by IRC as a contribution to the One WaSH National Program

Phase I: Phase I elapsed from August 2014 to April 2015 and included four

Components:

Component A. Development of a Sanitation master plan - including

solid and health care waste management taking into consideration

And a minimum package for sanitation in urban and peri-urban areas

comprising:

Construction of CGD friendly school toilets,public toilets,landfill

sites,sludge drying beds going on in 7 cities

Construction of composting and plastic bottles grinding pilot units

to be constructed in Jigjiga

Push Carts and Garbage bins provided by UNICEF

Garbage and Vaccum Trucks to be provided

Produced by SALOMON with Partners

Page 3: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

3Produced by IRC as a contribution to the One WaSH National Program

Phase I

Component B: Design Report including the preparation of comprehensive bill of quantities, drawings and technical specifications for improvement works including for: water source, water intake and treatment works and storage reservoirs and hydraulic design of the pressure line and completed distribution network

Component C: Studies on affordability and willingness to pay, Business Plan preparation (based on the principle of cost recovery and in coordination with the Water Resources Development Fund) and (pro-poor) tariff setting.

Component D. Environmental Impact Assessment of the proposed project water and sanitation activities in the selected towns

Produced by SALOMON with Partners

Page 4: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

4Produced by IRC as a contribution to the One WaSH National Program

Phase IIPhase II started by July 2015 and comprehends the

Supervision of construction works (water supply and sanitation facilities) shall be undertaken both at Urban and Rural level:

• Supervision of Sanitation Works shall focus on institutional, public/communal, solid & liquid waste management in 8 towns. In line with the technical designs, BoQs and technical specifications provided, complete engineering services and contract management shall be provided for related construction activities, in consultation with UNICEF.

• Supervision of Water Works shall focus on 7 towns’ water supplies and resilience water supplies in 25 satellite villages.

Produced by SALOMON with Partners

Page 5: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

5Produced by IRC as a contribution to the One WaSH National Program

SUPERVISION TEAM:

Salomon: Team Leader (1)

• Water Supply Expert (1)

• Water Resources Expert (1) – (partial time)

• Design and AutoCad Team (3 Engineers)

• Field Hydrogeologist (2 -Wellinchiti and Abomsa)

YGRY Consulting Engineers:

• Hydrogeologist Expert (1)

• Sanitary Engineer Expert (1)

AMEN – Oromia (3 Towns) + ACA (2 Towns + Zenas (1 Town):

• Coordinator

• Per Town:

• Resident Engineer

• Field Techncian Engineer (only for AMEN)

• Topographic Surveyor

TOTAL: 24 Professionals

Produced by SALOMON with Partners

Page 6: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

6Produced by IRC as a contribution to the One WaSH National Program

Maksegnit Town and 4 Satellite Villages – Jaraye, Aroge

Maksegnit, Tsion and Aguash Water Supply and Sanitation

Project and Bahir Gimb and Chinchaye Project

Tigray

AfarAmhara

Somali

Oromia

HaririAddis Ababa

Dire Dawa

Southern Nations

Nationalities,

and Peoples

Gambela

Benishangui-

Gumaz

Produced by SALOMON with Partners

Page 7: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

7Produced by IRC as a contribution to the One WaSH National Program

Maksegnit Town and 6 Satellite Vilages –Water Supply and

Sanitation Project

Produced by SALOMON with Partners

PROJECT: Maksegnit Town & 4 SVsBahir Gimb and Chinchaye

EMPLOYER Ahmara Water Resources Bureau

CONSULTANT:Salomon Lda/YGRY/Zenas Engineering

CIVIL CONTRACTOR: Abebe Negash - Lead Contractor Ahmara Water Works

DRILLING CONT. Tis Esat - Sub-contractor

CONSTRUCTION CONTRACT SUMMARY

DATE SIGNATURE: 24 June 2015 12 February 2016

CONTRACT VALUE w/ VAT: 55,487,866.55 10,021,080.02

VARIATIONS: Being negotiated -

TOTAL AMOUNT with VAT: 55,487,866.55 10,021,080.02

CONTRACT TIME: 14 Months 7 Months

COMMENCEMENT DATE: 05 August 2015 25 April 2016

COMPLETION DATE: 15 November 2016 25 November 2016

EXTENSION OF TIME: To be negotiated -

% OF PHYSICAL WORK DONE: 80%50%

ADVANCE SUM TAKEN: 16,646,359.97 with VAT 3,006,324.01 w/ VAT

PAYMENT CERTIFIED: 20,472,644.00 with VAT 1,471,180.40 w/ VAT

Page 8: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

8Produced by IRC as a contribution to the One WaSH National Program

Maksegnit Town and 4 Satellite Vilages Water

Supply and Sanitation Project - Fotos

Produced by SALOMON with Partners

MAKSEGNIT TOWN and JARAYE, AROKE MAKSEGNIT, TSION AND AGUASH

PHYSICAL EXECUTION: % Executed Remarks

WATER SUPPLY:

Water source 98% 4 BHs producing 34 l/s

Transmision Main 98% 6.7 Kms Pressure and Gravity HDPE pipes

Reservoirs 120 M3 CCH 60% No access

Reservoir 400M3 95% Pipe work missing

Distribution Network 80% 8 Kms installed

Operational Compounds 80% Finishing works

Electromechanical Equi. 0% Pumps and Generators on site

Overall 80%

Access to Operational Compouds to install pumps and generators and

transformers not possible

SANITATION

Public Toilets 60% Roof and finishing works missing

School Toilets 80% Finishing works missing

Sludge Drying Bed 30%Right of way problems not yet solved

Sanitary Land Fill 40%

Overall 60% Not possible to access the SDB & SLF site

Overall 60%

Compensations to be paid and Works to be re-started - if conditions permit 3-4 months

to conclude

BAHIR GIMB & CHINCHAYE

PHYSICAL EXECUTION:% Executed Remarks

WATER SUPPLY:

Transmision Main 99%7.634 Kms Pressure and

Gravity HDPE pipes

Reservoirs 2x25 M3 0% To be started soon

Reservoirs 2x10 M3 0% To be started soon

Distribution Network - Water Points 85% On going

Overall 50%Possible to conclude until end

of 2016

Page 9: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

9Produced by IRC as a contribution to the One WaSH National Program

WUKRO Town and 4 Satellite Vilages -Abahawi, Maitewaru,

Dengole, Maiyani –Water Supply and Sanitation Project

Tigray

AfarAmhara

Somali

Oromia

HaririAddis Ababa

Dire Dawa

Southern Nations

Nationalities,

and Peoples

Gambela

Benishangui-

Gumaz

Produced by SALOMON with Partners

Page 10: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

10Produced by IRC as a contribution to the One WaSH National Program

Abahawi Satelitte Village

Produced by SALOMON with Partners

Page 11: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

11Produced by IRC as a contribution to the One WaSH National Program

WUKRO Town & 4 Satellite Villages

Water Supply and Sanitation Project–Wukro Town & 4 Satellite Villages

PROJECT: Wukro Town & 4 Satellite Villages

EMPLOYER Tigray Water Resources Bureau

CONSULTANT: Salomon Lda/YGRY/ACA

CONTRACTOR: Civil Contractor: Raycon Construction and Machinery Rental

Drilling Contractor: Collar Engineering

CONSTRUCTION CONTRACT SUMMARY

DATE SIGNATURE: 25/06/2015

CONTRACT VALUE: 87,674,914.18 Birr

VARIATIONS: 20,881,684.02 Birr

TOTAL AMOUNT BIRR 108,556,598.20 Birr

CONTRACT TIME: 547Days/18months

COMMENCEMENT DATE: 25 July 2015

COMPLETION DATE: 16 January 2017

EXTENSION OF TIME: Requested but still not approved

% OF WORK DONE: 60% water supply and 70 % sanitation

ADVANCE SUM TAKEN: 26,302,474.25 ETB with VAT

PAYMENT CERTIFIED: 25,921,888.04 ETB with VAT

TIME ELAPSED IN DAYS: 411Days (75.13%)

Produced by SALOMON with Partners

Page 12: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

12Produced by IRC as a contribution to the One WaSH National Program

Wukro Town and 4 Satellite Vilages Water

Supply and Sanitation Project

Produced by SALOMON This can

be the title

Produced by SALOMON with Partners

WUKRU TOWN and ABAHAWI, MAITEWARU, DENGOLE AND MAIYANI

PHYSICAL EXECUTION: % Executed Remarks

WATER SUPPLY:

Water source 98% 3 BHs producing 54 l/s

Pressure Transmision Main 80%

Missing only TM from BHs to CCH1 (1895 mts) - 80% from CCH1 to CCH2 (1463 mts) - completed for CCH2 to Arato (2569 mts)

Gravity Transmision Main 93%Gravity Transmission Main (4830 mts) almost completed -

missing fittings

Collection Chamber One 85%96% of 150 M3 Reservoir completed + 84 % Booster Station

and 80% of Operator Dweling

Collection Chamber Two 90% 97% of 50 Mr res + 87% booster station

Arato Reservoir 92% Finishing works

Dengole Reservoir 80% Chlorination and 300 M3 Reservoir - 80% completed

500 M3 New Reservoir 95% Finishing Works

Distribution Network 10% 1.3 Km distribution pipe is completed

Operational Compounds 65% BH10 and BH11 - 85 % completed

Electromechanical Equip. 0%EM selected: Surface Pumps: Kirloskar; Submersible Pumps:

Lowara; Generators: Cummins (shipped)

Abahwi SV water supply 0% Contractor to be instructed soon to start

Overall 60% EM and Distribution Network to be boosted

SANITATION

Public Toilets 98% Finishing Works

School Toilets 99% Finishing Works

Sludge Drying Bed 50% Works interrupted since June 2016 due to heavy rain and works to resume as soon as possibleSanitary Land Fill 40%

Overall 70%Works progress visible - EM plus Distribution network are

the two main working components to be boosted

Page 13: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

13Produced by IRC as a contribution to the One WaSH National Program

ADISHAU Town & 5 Satellite Villages Water Supply

and Sanitation Project–

Produced by SALOMON This can

be the title

Produced by SALOMON with Partners

Page 14: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

14Produced by IRC as a contribution to the One WaSH National Program

ADISHAU Town & 5 Satellite Villages Water Supply

and Sanitation Project–

Produced by SALOMON with Partners

PROJECT:Adishehu Town & 4 Satellite

Villages

EMPLOYER Tigray Water Resources Bureau

CONSULTANT: Salomon Lda/YGRY/ACA

CONTRACTOR: Civil Contractor: Remhay Construction

CONSTRUCTION CONTRACT SUMMARY

DATE SIGNATURE: 09/03/2016

CONTRACT VALUE: 6,394,204.70 Birr

CONTRACT TIME: 180 Days/ 6 months

COMMENCEMENT DATE: 24 March 2016

COMPLETION DATE: 24 September 2016

EXTENSION OF TIME: Under negotiation

% OF WORK DONE: 62% (91.66% planned)

ADVANCE SUM TAKEN: 1,918,261.41 with VAT

PAYMENT CERTIFIED:

TIME ELAPSED IN DAYS: 176 Days

Page 15: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

15Produced by IRC as a contribution to the One WaSH National Program

ADISHAU Town & 5 Satellite Villages Water Supply

and Sanitation Project

Produced by SALOMON with Partners

Adishehu Town & 5 Satellite VillagePHYSICAL EXECUTION: % Executed Remarks

WATER SUPPLY:

Shallow water wells Drilling & complete construction for Adishuhu Satellite villages (TahitayAtsela, Kola sesat, LaelayAtsela , AdiAwlie, Melaiso, Gena)

95%On going development last shallow well and hand

pump installation

Overall Water Supply 95%

SANITATION

Public Toilet 85% On going

Septic Tank for Public Toilet 87% On going

School Toilet 86% On going

Septic Tank for School Toilet 87% On going

Second Public Toilet 0%To be started soon - dumped material removal

solved

Sludge Drying Bed 0%Right of way problem - change of location - need design modification under processSanitary Land Fill 0%

Overall Sanitation 60%

Overall Contract 70%

Public Toilet and the SDB & SLF missing - works to be extended to be able to finish if no more

problems are encountered

Page 16: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

16Produced by IRC as a contribution to the One WaSH National Program

Sheno Town and 2 Satellite Vilages –Adadi

Mato and Chimisse

Produced by SALOMON with Partners

Page 17: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

17Produced by IRC as a contribution to the One WaSH National Program

Hamusgabeya and Adadi

Produced by SALOMON with Partners

Page 18: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

18Produced by IRC as a contribution to the One WaSH National Program

SHENO Town & 4 Satellite Villages

Water Supply and Sanitation Project–PROJECT: Sheno Town & 5 Satellite Villages

EMPLOYER Oromia Water Mineral Energy Bureau

CONSULTANT: Salomon Lda/YGRY/AMEN Consulting

CONTRACTOR:

Civil Contractor: GTB Engineering

EMU GENERAL IMPORTER Drilling Contractor: TAM Geo-Engineering

Capacity Building:

CONSTRUCTION CONTRACT SUMMARY

DATE SIGNATURE: 13 January 2016

CONTRACT VALUE CIVIL WORKS: 27,017,149.65

PIPE AND FITTINGS ETB 28,213,421.50 + USD 499,127.78

DRILLING CONTRACTOR ETB 6,742,105.00

ELECTROMECHANICAL ETB 3,277,513.79 + EU 326,159.85

CAPACITY BUILDING ETB 1,323,650

TOTAL AMOUNT 66,573,839.94 ETB + 576,262.04 USD +

326,159.85 EURO

CONTRACT TIME: 16 Months

COMMENCEMENT DATE: 10 February 2016

COMPLETION DATE: 15 June 2017

ADVANCE SUM TAKEN: 17,367,089.00 - 30% of ETB Component

PAYMENT CERTIFIED: None

TIME ELAPSED IN DAYS: 210 Days

Produced by SALOMON with Partners

Page 19: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

19Produced by IRC as a contribution to the One WaSH National Program

Sheno Town and 4 Satellite Vilages Water

Supply and Sanitation Project

SHENO TOWN and HAMUSGABEYA, ADADI MATO, CHIMISSE AND ADADI

PHYSICAL EXECUTION: % Executed Remarks

WATER SUPPLY:

Water source 80% 2 BHs completed and 1 BH being finalysed

Pressure Transmision Main 0% LC not opened

Operational Compounds 0%

Drilling delay + right of way problem and compensation

150 M3 Elevated Reservoir 5% On going and heavy rainy season

2x200 M3 New Reservoir 60% On going and heavy rainy season

Distribution Network 14%

On going delayed due ot right of way problem and heavy rainy season

Electromechanical Equip. 0% Waiting for the drilling

Hamusgabeya water supply 4% Started as per the work schedule

150 M3 Ground Reservoir 15% On going and heavy rainy season

Overall Water Supply 20%

Heavy rainy season hampered the civil construction and LC delay is hampering the

Transmission Main and EM

SANITATION

Public Toilets 23% On going and heavy rainy season

School Toilets 19% On going and heavy rainy season

Sludge Drying Bed 0% Location decision and Heavy rainy season obliged to be postponed to October 2016 Sanitary Land Fill 0%

Overall Sanitation 8%

Heavy rainy season hampered the sanitation as well as location selection

Project Overall 19%

Initial delay in mobilysing and performance capacity of the Lead Contractor had a negative impact in the beginning and the present heavy

rainy season

Produced by SALOMON with Partners

Page 20: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

20Produced by IRC as a contribution to the One WaSH National Program

Wellinchiti Town and 4 Satellite Vilages Water

Supply and Sanitation Project

Produced by SALOMON with Partners

Page 21: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

21Produced by IRC as a contribution to the One WaSH National Program

Dengore Tyio Satellite Village

Produced by SALOMON with Partners

Page 22: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

22Produced by IRC as a contribution to the One WaSH National Program

WELLINCHITI Town & 4 Satellite Villages Water Supply

and Sanitation Project–

PROJECT: Wellinchiti Town & 5 Satellite Villages

EMPLOYER Oromia Water Mineral Energy Bureau

CONSULTANT: Salomon Lda/YGRY/AMEN Consulting

CONTRACTOR:

Civil Contractor: GTB Engineering

EMU GENERAL IMPORTER

Drilling Contractor: TAM Geo-Engineering

Capacity Building:

CONSTRUCTION CONTRACT SUMMARY

DATE SIGNATURE: 13 January 2016

CONTRACT VALUE CIVIL WORKS: 32,799,010.89

PIPE AND FITTINGS 23,136,728.89 ETB + 277,064.90 USD

DRILLING CONTRACTOR 9,286,505.88 ETB

ELECTROMECHANICAL 3,380,703.97 + 377,522.80 EURO

CAPACITY BUILDING 1,323,650.00 ETB

TOTAL AMOUNT 69,926,599.63 ETB + 277,064.90 USD +

377,552.80 EURO

CONTRACT TIME: 14 Months

COMMENCEMENT DATE: 15 February 2016

COMPLETION DATE: 14 April 2017

ADVANCE SUM TAKEN: 13,985,320.00

PAYMENT CERTIFIED: Being Processed 16,000,000.00 ETB

TIME ELAPSED IN DAYS: 210 Days

Produced by SALOMON with Partners

Page 23: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

23Produced by IRC as a contribution to the One WaSH National Program

Wellinchiti

and 4 Satellite Vilages Water Supply and

Sanitation Project

Produced by SALOMON This can

be the title

WELLINCHITI TOWN and DENGORE TYIO, DENGALU WANGA AND FETO PHYSICAL EXECUTION: % Executed Remarks

WATER SUPPLY:

Wellinchti Water Supply

Water source 0% Weak performance of the Drilling Contractor

Pressure Transmision Main 0% LC not opened

Operational Compounds 22%One Operational Compound on going and others

waiting for the drilling results

500 M3 Elevated Reservoir 1 90% On going

500 M3 Elevated Reservoir 2 75% On going

Feto 50 M3 Reservoir 98% On going

Distribution Network 81% On going

Water Points 95% On going

Water Kisoks 0%

Electromechanical Equip. 0% Waiting for the drilling results

Dengore Tyio water supply 0% Just started

Overall 26%Weak performance of the Drilling Contractor + LC

opening delay

SANITATION

Public Toilets 90% On going

Public Toilets 0% Site selection problem solved recently

School Toilets 95% On going

School Toilets 95% On going

Sludge Drying Bed 50% Clay material seal delayed

Sanitary Land Fill 90% On going

Overall 70%

Project Overall 30%

Weak performance of the Drilling Contractor + LC opening delay and the present heavy rainy season

affecting the drilling

Produced by SALOMON with Partners

Page 24: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

24Produced by IRC as a contribution to the One WaSH National Program

Abomsa Town and 4 Satellite Vilages Water

Supply and Sanitation Project

Produced by SALOMON with Partners

Page 25: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

25Produced by IRC as a contribution to the One WaSH National Program

ABOMSA Town & 4 Satellite Villages Water Supply and

Sanitation Project–PROJECT: Abomsa Town & 5 Satellite Villages

EMPLOYER Oromia Water Mineral Energy Bureau

CONSULTANT: Salomon Lda/YGRY/AMEN Consulting

CONTRACTOR:

Civil Contractor: Heavy Line

Supply of Pipes and Fittings: Sky Limit

Drilling Contractor: Earth Work and Geo

Electromechanical: ACME Engineering

Capacity Building: Milki Consultant

CONSTRUCTION CONTRACT SUMMARY

DATE SIGNATURE: 14 January 2016

CONTRACT VALUE CIVIL WORKS: 37,334,254.68 ETB

PIPE AND FITTINGS 1,180,849.22 ETB + 525,938.15 USD

DRILLING CONTRACTOR 6,645,424.50 ETB

ELECTROMECHANICAL 4,345,552.18 ETB + 870,037.50 USD

CAPACITY BUILDING 6,337,367.10 ETB

TOTAL AMOUNT 55,843,447.69 ETB + 1,396,575.64 USD

CONTRACT TIME: 16 Months

COMMENCEMENT DATE: 6 February 2016

COMPLETION DATE: 7 May 2017

ADVANCE SUM TAKEN: 16,753,034.31 with VAT

PAYMENT CERTIFIED: 2,369,063.25 with VAT

TIME ELAPSED IN DAYS: 215 days

Produced by SALOMON with Partners

Page 26: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

26Produced by IRC as a contribution to the One WaSH National Program

Abomsa Town and 4 Satellite Vilages Water

Supply and Sanitation Project

Produced by SALOMON This can

be the title

ABOMSA TOWN and HOMBA, GERGELE, FETAN AND TECLAHAIMANOT PHYSICAL EXECUTION: % Executed Remarks

WATER SUPPLY:

Abomsa Water Supply

Water source0%

River Flooding disaster and poor capacity of the Drilling Contractor and weak Sub-Contractors

Pressure Transmission Main 0% LC not opened

Collection Chamber

120 M3 Reservoir 65% On going

Operator Dwelling 52% On going

Pump and Generator House 14% On going

500 M3 Elevated Reservoir 8% On going

Distribution Network 0% LC not opened and HDPE pipes included in the LC

Water Points 0% Location not decided

Water Kiosks 0% Location not decided

Electromechanical Equip. 0% Waiting for the Drilling

Homba water supply 2% Just started

Teclehaimanot water supply 0% Just started

Overall Water Supply 10%No capacity of the Drilling Contractor plus Logistic and

Financial capacity of the Lead Contractor

SANITATION

Public Toilets 65% On going

School Toilets 85% On going

Sludge Drying Bed 0%

Sanitary Land Fill 33%

Overall Sanitation 30% Site selection problem

Overall Contract 15%

River Flooding disaster and poor capacity of the Drilling Contractor and weak Sub-Contractors plus Logistic and

Financial capacity of the Lead Contractor hampered heavily the Work

Operational Compound

500m3 reservoir ground slab re-bar work

Produced by SALOMON with Partners

Page 27: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

27Produced by IRC as a contribution to the One WaSH National Program

Kebridehar Water Supply Project and

Sanitation Works and Jijiga Transfer

Sanitation and Solid Waste Processing

Unit

Produced by SALOMON with Partners

Page 28: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

28Produced by IRC as a contribution to the One WaSH National Program

Kebridehar Town Water Supply and Sanitation

Project

Produced by SALOMON with Partners

Page 29: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

29Produced by IRC as a contribution to the One WaSH National Program

Kebridehar Town Water Supply and Sanitation Project and

Jijiga Transfer Sanitation and Solid Waste Processing Unit

Produced by SALOMON with Partners

Kebridehar Water Supply Project and Sanitation Works and Jijiga Transfer Sanitation and Solid Waste Processing Unit

PROJECT: Kebridehar Water Suply Jigjiga Solid Waste Management

EMPLOYER Somali Regional State Water Resources Development Bureau

CONSULTANT:Salomon Lda in association with YGRY Consulting Engineers

PLC

CONTRACTOR: Civil Contractor: Rabah & Sons Private Limited Company

CONSTRUCTION CONTRACT SUMMARY

DATE SIGNATURE: 1 December 2015

CONTRACT VALUE (w/VAT): 90,167,028.89 ETB

VARIATIONS: -

CONTRACT TIME: 18 Months

COMMENCEMENT DATE: January 2016

COMPLETION DATE: June 2017

PERCENTAGE OF WORK DONE:12% Materials on site only

ADVANCE SUM TAKEN: 27,051,108.01

PAYMENT CERTIFIED: 6,689,085.73 with VAT being processed (not yet certified)

TIME ELAPSED IN DAYS: 270 Days

Page 30: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

30Produced by IRC as a contribution to the One WaSH National Program

Kebridehar Town Water Supply and Sanitation Project and

Jijiga Transfer Sanitation and Solid Waste Processing Unit

Produced by SALOMON with Partners

PHYSICAL EXECUTION: % Executed Remarks

WATER SUPPLY:

Kebridehar Water Supply

Water source90%

2 BHs - New BH1 and new BH2 completed -pumping test to be repeated for

determination yield

Transmission Main 0% Pipes to be brought by October/November

Operational Compounds (4) 0% To be started soon

2x500 M3 Reservoir 60% On going

Distribution Network 0% Pipes to be brought by October/November

Water Points 0%

Water Kiosks 0%

Electromechanical Equip. 0% Pumps and Generators on site

Overall Water Supply 15%

SANITATION

Public Toilet 55% On going

School Toilets 80% On going

Sanitary Land Fill 55% On going

Overall Sanitation 60%

Jigjiga Solid Waste Management

Transfer station and Compound 0%

Composting Unit 0%

Plastic Grinding Unit 0%

Overall Solid Waste Mangement 0% Materials on site

Overall Contract 12%Overall works on going despite the difficulities

experienced in the begining of the project

Page 31: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

31Produced by IRC as a contribution to the One WaSH National Program

Challenges/Lessons Learnt Little time allocated for design and site

investigation was limited -» Allocating adequate time to study and design is key for success

Loose site confirmation by local authorities leads to frequent site changes hampering progress

Right of way problems and compensations have slowed the progress

Unsuitable hilly areas for water supply structures and sanitation facilities lead to excessive cost for flood protection and pollution

Excessive abnormal rainy season - lengthy rainy season (El Nino effect) hamper progress

Capacity Limitation on the part of some contractors

Produced by SALOMON with Partners

Page 32: ONEWASH PLUS Urban Wash Project 8 Towns MID TERM REVIEW · DATE SIGNATURE: 09/03/2016 CONTRACT VALUE: 6,394,204.70 Birr CONTRACT TIME: 180 Days/ 6 months COMMENCEMENT DATE: 24 March

32Produced by IRC as a contribution to the One WaSH National Program

Best Practices Consideration of Satellite Villages along with Towns

Consideration of Institutional WaSH facilities along the Town

water supply system

The introduction of Water kiosks

Introducing child, gender and differently abled features in

sanitation facilities

Consideration of solid waste and sludge management

practices (solid waste collection & safe disposal, desludging

and safe disposal) in addition to traditional water supply and

sanitation

BCBT for sustainability of WaSH services

Preparation of Sanitation Master plan prior to recommending

minimum package sanitation facilities that will be scaled up in

the course of the master plan period

Produced by SALOMON with Partners


Recommended