Director – Ticketing Planning & Development: TfNSWDOUG HOWE
Opal Transformational PMO
1
TRISH STOCKTON - Principal Manager Program Services – TfNSW
www.pm-partners.com.au
© PM-Partners group. All rights reserved
Transport ticketing prior to Opal» Sydney was one of the remaining large cities in the world not to be using an
electronic ticketing system
» Each transport mode had it’s own ticketing products distributed through it’s own
channels with only some products available for use on more than one transport
mode. Customers generally carried more than one ticket type in their wallet
» Tickets were purchased at time of travel, daily or periodically resulting in extensive
queuing for ticket sales and customer travel delays
» Most customers paid more for their travel
» If a ticket was lost, the customer also lost the outstanding investment in that ticket
» Transport Operators maintained ticket sales facilities
» Transport Operators each had their own fare collection and reconciliation facilities,
systems and staff
» Information regarding customer travelling desires, patterns and challenges was
limited to non-existent impeding ability to better forecast supply and demand
2
www.pm-partners.com.au
© PM-Partners group. All rights reserved
ETS Vision“To transform the public transport
experience for customers.
Opal will provide a better customer ticketing experience,
contribute to an increase in the overall uptake of public
transport use and act as an enabler towards a truly
integrated transport system.”
3
www.pm-partners.com.au
© PM-Partners group. All rights reserved
A TICKETING SOLUTION THAT MEETS CUSTOMER NEEDS
» An improved ticketing system that is easy to use
» Simpler and faster access to the public transport network
» Enables operator staff to deliver better customer service
AT THE INDIVIDUAL LEVEL, CUSTOMERS ENJOY BENEFITS SPECIFIC TO
THEIR NEEDS, TO TRULY MAKE OPAL AN IMPROVED TICKETING SYSTEM
» Opal provides flexibility for customers who only want to pay for the travel
they use
» Opal provides rewards to customers who use public transport often
» Opal provides security for customers where value counts
What we aimed to deliver for our customers
4
www.pm-partners.com.au
© PM-Partners group. All rights reserved
$1.8 billion budget
45 ICT systems
Understanding our touchpoints - complexity
5
www.pm-partners.com.au
© PM-Partners group. All rights reserved 6
Opal puts the customer at the
centre of transport ticketing
www.pm-partners.com.au
© PM-Partners group. All rights reserved
GEOGRAPHIC SCALE OF OPAL COMPARED TO OTHER SMARTCARD ROLLOUTS
DOUG HOWE
OPAL IS THE SMARTCARD CUSTOMERS USE TO
PAY FOR THEIR TRAVEL ON PUBLIC TRANSPORT
Customers keep the
card and reuse it
every time they
travel.
Opal is
replacing
paper tickets.
Opal Geographic Footprint
7
www.pm-partners.com.au
© PM-Partners group. All rights reserved
Key learnings and insights
WHAT WORKED FOR US
» Choosing a vendor that offered proven technology – and then
collaborating closely
» Working with operators in a partnership – from start to finish
» Progressive rollout – one mode at a time, one product at a time
» Asking our stakeholders how we were doing – whether or not
we liked the answer!
» Strong program management – focus on people, not just
technology
8
www.pm-partners.com.au
© PM-Partners group. All rights reserved
PEARL CONSORTIUM
» Led by Cubic Transportation Systems – global and local experience
» With Parkeon, CBA, Downer EDI, ePay
DESIGN, BUILD, OPERATE AND MAINTAIN MODEL
AUGMENTATION
» Internal expert team supplementing Consortium capabilities
» Collaborative approach for testing and implementation
» Independent Certifier to ensure the Program delivered obligations in
the Contract Deed
Proven Vendor
9
www.pm-partners.com.au
© PM-Partners group. All rights reserved
» Inclusion from the requirements stage all the way through
» Funding support for business readiness, implementation and operational
support
» ETS funded support across change dimensions (process development,
capability building, training, communication, infrastructure change, operational
support)
» Operator Executives part of governance structure
» Strong support to ensure continuity of business operations
Harbour City Ferries
Sydney Trains
NSW TrainLink
State Transit buses
16 private bus operators
Transdev Light Rail
Transport Operator Partnerships
10
www.pm-partners.com.au
© PM-Partners group. All rights reserved
PROGRESSIVE ROLLOUT BY:
» Mode
» Product
» Acquisition channel
BENEFITS:
» A smoother change for customers
» Continuous improvement
» Operator readiness
» Proactive management of hiccups
SCHEDULE RESPONSIVENESS
» Accelerated ferry rollout
» Accelerated train rollout
Progressive rollout
11
www.pm-partners.com.au
© PM-Partners group. All rights reserved
Stakeholder Feedback
OVERALL CUSTOMER
SATISFACTION
OVERALL STAFF
ACCEPTANCE & READINESS
» Conducted regular stakeholder and customer engagement to track our
progress
» Ensured we listened to Operator concerns and provided escalation paths
» Customer and Operator feedback measured at regular intervals
» Results used as ongoing continuous improvement
AND THE RESULT?
8.21 10 1 108.1
12
www.pm-partners.com.au
© PM-Partners group. All rights reserved
Strong Program Governance» Clear governing structure, reporting and escalation channels
» Committed and available Sponsors including Minister
» Dates that were not allowed to move
» Effective decision making
› Materials tailored for the audience
› Agile, risk based approach
» Clear accountability
» MoU’s defined obligations for Operators and ETS
» Strong Program leadership
» Heavy emphasis on collaboration
» TfNSW team of all contractors and specialists in their fields
» Relentless focus on controlling and managing complexity
» Effective Media and Public Relations management
13
www.pm-partners.com.au
© PM-Partners group. All rights reserved
Strong Program Governance – Programme Controls
Operations &
Service
Management
ETS Programme
Management Plan
Safety &
Environment
Management
Programme
Financial
Management
Schedule
Management
Programme
Status
Reporting
Legislative &
Regulatory
Management
Contract
Management
Programme
Governance
Implementation/
Delivery
Management
Benefits &
Modelling
Management
Resource
Management
Programme
Services
Solution Design,
Contract
Management
Implementation
Management
Scope and
Deliverables
Management
Pro
gra
mm
e M
an
ag
em
en
t M
eth
od
olo
gy
Security
Management
Solution
Design and
developmentPrivacy
Management
Compliance
Customer
Experience
Management
Operator/TfNSW
Transition
Management
Operations
Management
Assurance
& Audits
Procurement
Management
Opal Revenue
Management
Business
and
Stakeholder
Readiness
CED Product
Development
CED Marketing &
Communications
Customer
Experience
Testing
Verification
Quality
Management
Change Request
Management
Risk
ManagementIssue
Management
Records
Management
& GIPA
14
www.pm-partners.com.au
© PM-Partners group. All rights reserved
Strong Program Governance LEADERSHIP TEAM
Programme Services glues the whole Programme together
‘This Program marches to the beat of a drum and
Trish Stockton is the drummer’ – Greg Ellis
15
www.pm-partners.com.au
© PM-Partners group. All rights reserved
Program Services
16
www.pm-partners.com.au
© PM-Partners group. All rights reserved
Fit for Purpose Controls
Controls needed to be:» Pragmatic
» Adaptable and always cognisant of the business context – sufficient control without being bureaucratic
» Supported by easy to use tools and low administration
» Readily usable by anyone recruited
» Suitable to a 5 year Program of Work not necessarily an ongoing Portfolio of projects
» Well understood with clear accountability
» Auditable
» Regularly assessed, improved and adjusted where required
17
www.pm-partners.com.au
© PM-Partners group. All rights reserved
Key learnings and insightsKEY CHALLENGES» Applying effective Project level and integrated scheduling in
fast paced environment
» Managing an effective decision making pipeline across a vast
number of key impacting technical, strategic and policy
considerations
» Working with simple tools suited for a single Programme
delivery
» Always looking into the future to remove potential blockages
across all aspects of the Programme
» Continuous improvement to adapt to changing direction of
project
18
www.pm-partners.com.au
© PM-Partners group. All rights reserved
Success and Awards!Winner 2013 – Three major design awards
including the Powerhouse Museum Design
Award for the free standing Opal card reader
Winner - 2014 – Opal card project won
the 2014 SMART Infrastructure Award
from Infrastructure Partnerships Australia
19
Winner 2015 – Sydney Design Awards for
Opal Revenue Protection Mobile Application
www.pm-partners.com.au
© PM-Partners group. All rights reserved
2014 NSW Premier’s Award, Building and Infrastructure
20
www.pm-partners.com.au
© PM-Partners group. All rights reserved
Thank you
21
Sydney (Head Office) Melbourne Office Singapore
Level 2, Bank of NSW House
228 Pitt Street
Sydney NSW 2000
Phone: 1300 70 13 14
Rialto South Tower
Level 27, 525 Collins Street
Melbourne VIC 3000
Phone: 1300 70 13 14
Level 39,
Marina Bay Financial Centre
Tower Two
10 Marina Boulevard
Singapore 018983
Phone: +65 6818 6074
Stay connected
P3O Foundation & Practitioner PRINCE2 AgileMSP Foundation & Practitioner
More info
AGILE COACHING