First Version
1
Abstract—This paper presents an open loop synchronization
strategy for connecting an islanded Micro-grid to system. This
strategy adopts the impedance pre-insertion method to reduce
the synchronizing transients to be within an acceptable level, as
long as both the Micro-grid side and system side are operating
within the power quality requirements. To verify the feasibility of
the method, it is applied to a sample case study. The results have
shown that the size of impedance can be designed properly to
effectively mitigate the transient phenomenon, and at the same
time, the impacts to the stability of the generating units are
within the normal limit.
Index Terms—microgrids, islands, open loop synchronization,
impedance Pre-insertion
I. INTRODUCTION
UE to electricity market deregulations and the need to
reduce environmental footprints from centralized electric
power plants, distributed generations (DG) and
renewable resources have been gaining enormous support in
both research and industrial applications. A Micro-grid is
formed by an aggregation of DG units and local loads that is
in complete autonomous operation (as an island) from the rest
of the power grid [1]-[2]. A fundamental component of the
Micro-grid is the existence of a synchronizer, which allows
the connection of the Micro-grid to the rest of the bulk grid.
This process of connecting two operating electric systems is
known as synchronization. Usually, there are 3 common
synchronization scenarios to consider:
- A single synchronous machine synchronizes to grid
- Micro-grid (islanded system) synchronizes to grid
- A grid synchronizes with another grid (During system
restoration)
Similar to a single synchronous machine to system
synchronization, Micro-grids synchronization must be done
carefully. If the synchronization criteria are not met at the
moment when breaker closes, a high transient may occur,
which will result in equipment damage and power quality
concerns [9]-[10]. Faulty synchronization can:
- Damage transformer and synchronous generator
windings primarily due to the peak inrush current,
which may also lead to misoperation of feeder relays
[3].
Y. Zhou is with the Electrical Engineering Department in University of
Alberta, Edmonton, T6G 1H9 Canada (e-mail: [email protected]).
- Damage the generator due to the sudden mechanical
stresses experienced by the generator shaft and prime
mover [11].
- Cause generators to become unstable or unable to
maintain in synchronism with the system primarily due
to an initial out-of-step closing of breaker, which may
lead to the relay tripping of generators [13].
From the synchronization concerns addressed above,
the problem of synchronization is to reduce switching
transients and ensure stability of all generators.
The standard synchronization practice is to adjust the
voltage difference ∆V, angle difference ∆θ, and frequency
difference ∆f into an acceptable range before the synchronism
check relay sends the signal to close the breaker [5]. If the
acceptable range is not met, the generators within one system
are tuned based on remote sensing and feedback control of the
frequency and voltage signals from the breaker location. Case
studies of Micro-grid to system synchronizations based on
feedback control strategies have been presented in literature
[6], [7]. Active synchronization strategy that takes into
account of voltage unbalances and harmonic distortions is
presented in [4].
In order to implement such feedback control systems in
reality, infrastructure support such as communication links
must be built to carry the signals from remote sensing to local
machines. The cost of this infrastructure support can be quite
high especially when the Micro-grids are in remote areas,
where it is located far away from the point of interconnection
to the main grid. In addition, synchronizing a Micro-grid to
system is more difficult than synchronizing a single generating
unit to system due to the fact that the Micro-grid’s voltage and
frequency are determined by multiple DG units and local
loads. In other words, for Micro-grid to system
synchronization, multiple communication links would have to
be built to allow the tuning of individual DG units. Therefore,
synchronizing a Micro-grid to system by feedback control can
not only drive up the cost of infrastructure support, but also
may increase the time and effort to synchronize the two
islands. Especially during system restoration process, the
coordinated control of multiple generators within one system
through feedback may delay the time required to synchronize
any surviving islands [8].
Various transient mitigation methods have been
implemented in practice in different industrial applications.
The feedback control method used in generator
synchronization to reduce the voltage difference across the
Open Loop Synchronization of Micro-grid to
System Based on Impedance Pre-insertion
First A. Author, Fellow, IEEE, Second B. Author, and Third C. Author, Jr., Member, IEEE
D
First Version
2
breaker is only one of them. Other methods include:
impedance pre-insertion has been widely used in industry for
reducing the capacitor switching transients [14]; Point-on-
wave switching used in capacitor or transformer energization
[15]; Silicon-Controlled Rectifier (SCR) based soft starter
used in motor starting to reduce inrush current [16]; and
Sequential phase energization for transformer [17].
This paper proposes an impedance pre-insertion
based synchronization strategy that can connect the Micro-grid
to system in an open loop manner. The main advantage of this
strategy is that the synchronization can be performed without
any feedback controls, i.e. reduces the cost and time required
for Micro-grids synchronization.
The rest of the paper is organized as follows. Section
II presents the proposed method for open loop synchronization
in detail. In Section III, the issues to consider for the proposed
open loop scheme are addressed. Simulation results are shown
in Section IV and the paper concludes in Section V.
II. PROPOSED METHOD – OPEN LOOP SYNCHRONIZATION
The open loop synchronization scheme is to design the
impedance pre-insertion value such that the peak transients are
acceptable, when the two parties are operating within the
power quality limits (PQ limits) as shown in Fig. 1. As
shown, impedance is inserted in series with breaker 1 (BRK1).
This impedance is purely an inductor. After breaker 1 is closed
and system has reached a new steady state, the impedance is
bypassed by closing breaker 2 (BRK2).
It is important to realize that both parties typically operate
within their power quality limits (PQ limits) before the
synchronization process. They are also the pre-established
operating regions. The operating regions [19] (i.e. the power
quality requirements) are established by the utility to ensure
the grid operates safely and reliably during acceptable system
disturbances. If both sides of the breaker are not operating
within their normal operating range, the synchronization
process is not permitted.
Based on Fig. 1, once BRK1 is closed, a transient current
will flow through the impedance, which will propagate to the
DG units within the Micro-grid. This transient current is
composed of an AC and a DC component similar to the case
of a three-phase fault at the generator terminal. The influence
of the DC component on the peak transient current can be
taken into account by applying a factor K to the AC
component [18]. The peak current is reduced as the size of
𝑋𝑖𝑛𝑠𝑒𝑟𝑡 increases as shown by (1). The peak current 𝐼𝑝𝑒𝑎𝑘 is
proportional to:
"
| | | |peak
total insert d eq
V VI
X X X X
(1)
where ∆𝑉 is the rms voltage across breaker before it closes.
𝑋𝑖𝑛𝑠𝑒𝑟𝑡 is an inductor inserted at the breaker location as shown
in Fig. 1. 𝑋𝑑′′ and 𝑋𝑒𝑞 are the synchronous machine’s direct
axis subtransient reactance and equivalent circuit impedance
respectively. 𝑋𝑒𝑞 includes any transformer leakage reactances,
series line impedance (positive sequence) and system
impedance.
Pre-established
Operating Region
Bulk Grid Generator,
Microgrid
( )gV pu
( )gf Hz
60.2
59.7
1.10.9 Pre-established Operating Region ( )sV pu
( )sf Hz
60.05
59.95
1.10.9
1 2
BRK 1
BRK 2
Circuit Breaker
Z insert
Fig. 1. Power quality requirements for open loop synchronization
The open loop synchronization procedure is
developed in Fig. 2. As shown, all the measurements including
voltage, angle and slip are performed at the circuit breaker
location. In addition, if both parties are not operating within
their respective PQ limit, then it implies that the power system
potentially has a power quality issue, which should be
resolved first before synchronization is performed. When both
sides are naturally within PQ limits under the normal system
condition, breaker can be closed at a small angle difference.
This angle difference is explained in more detail in the Section
III. Once the circuit breaker is closed, the impedance could be
bypassed shortly by closing BRK2 after system stabilizes and
reaches a new steady state operation.
Fig. 2. Procedure for performing open loop synchronization
In order to implement the open loop synchronization
scheme, there are some fundamental issues, which have to be
considered. These issues will be addressed in the next section.
III. ISSUES TO SOLVE
The issues that need to be solved in this section include:
- What is the acceptable level of transients?
- How to determine the proper impedance value?
- Can the Micro-grid maintain stability with the designed
impedance?
- Are the impedance bypass transients acceptable?
First Version
3
A. Acceptable Transient Level
Acceptable transient level is calculated based on the
synchronization criteria from the standard IEEE C50.12 for
salient-pole synchronous generators [20]. The standard
specifies, “Generators shall be designed to be fit for service
without inspection or repair after synchronizing that is within
the limits listed…”. The limits are:
- Angle ±10° - Voltage 0 to 5% (of nominal)
- Slip ±0.067𝐻𝑧
In other words, the current and torque transients
experienced by the generator under the above conditions are
considered acceptable. The IEEE limits established above can
be illustrated by an acceptable transient region shown in Fig.
3.
The worst acceptable transient is obtained based on
examining the peak current incurred due to the conditions
specified by the four corners of the region in Fig. 3. Based on
the short circuit theory, higher voltage difference across
breaker leads to higher transients, thus, only the right two
corners are remained to examine. The worst case lies in the
case ∆𝑉 = +0.05𝑝. 𝑢. , ∆𝑓 = +0.067𝐻𝑧 due to the fact that
higher machine frequency than system immediately after the
closing of breaker tends to advance the rotor angle and the
transient torque.
Fig. 3. Determine the worst acceptable transient level
B. Impedance Value Design
The method to effectively design the appropriate size of
impedance to limit the worst transients under the open loop
scheme is developed in this section. Firstly, possible worst
case transients have been identified based on the PQ limits.
Secondly, the peak current as a function of impedance is
determined.
Prior to synchronization, each party is expected to operate
within their established power quality requirements, i.e.
voltage and frequency are within their normal operating range
as specified in Fig. 4. Although the angle requirement is 10
degrees based on IEEE standard, but an IEEE industrial
survey reported that the maximum closing angle can reach up
to 20 degrees when synchronized manually by an operator
[11]. Therefore, for open loop synchronization, a worst case
angle difference of 20 degrees is used throughout this paper.
1V
1f
60.2Hz
59.7Hz
1.1pu0.9pu
2V
2f
60.05Hz
59.95Hz
1.1pu0.9pu
1 2
43
43
21
Micro-grid Side Operating Range System Side Operating Range
Fig. 4. Worst case transients based on open loop synchronization
It is intuitively clear based on Fig. 4 that the largest voltage
and frequency mismatch will result in the largest
synchronizing transients. As a result, there are four
combinational cases to consider, which are case (2, 3), case (4,
1), case (3, 2) and case (1, 4). The first number refers to the
operating point in the Micro-grid side, and the second number
refers to the system side.
Although the peak current due to closing of breaker 1 can
be obtained by repeated dynamic simulations, but the
analytical expression has the advantage of simplifying the
design process. Therefore, analytical expression for
calculating the peak transient current as a function of the
impedance value is derived.
Analytically, the Micro-grid is modelled as a synchronous
generator with a load connected to its terminal. Before the
breaker is closed, the current through the impedance is zero.
However, the stator current of the synchronous machine
consists of a steady state flow of load current as shown in Fig.
5(a). At the instant of breaker switching, this switch can be
represented by two opposing voltage sources in series, as
shown in Fig. 5(b). By using the superposition theorem, the
circuit shown in Fig. 5(b) can be split into two equivalent
circuits, as shown in Fig. 5(c).
SGLI
jXsys
V Vgrid
insertjX
SG
V Vgrid
V
LI
SG
V
VgridLI
V
''
djX
(a) (b)
(c)
jXsys
jXsys jXsys
insertjX
insertjX insertjX
Fig. 5. Equivalent circuit representation of closing breaker 1. (a) Circuit
before breaker 1 is closed. (b) Circuit after breaker 1 is closed. (c) Equivalent circuits after breaker 1 is closed.
The circuit on the left side of Fig. 5(c) represents the
same circuit before breaker is closed. The current in this
circuit represents the steady state component. The right side
circuit can be used to calculate the transient resulting from the
switching. The steady state component of the stator current
equals to the load current. Assuming ∆𝑓 = 0, the analytical
expression for the transient component based on Kirchhoff’s
Voltage Law (KVL) for the circuit is:
Acceptable TransientRegion
f (Hz)
V (pu)
(+0.05pu, +0.067Hz)
Worst Acceptable Transient
(+0.05pu, -0.067Hz)(-0.05pu, -0.067Hz)
(-0.05pu, +0.067Hz)
First Version
4
( )( ) 2 sin( )
di tL Ri t V wt
dt
(2)
where, L and R are the equivalent inductance and resistance
seen by the breaker, respectively. 𝑤 is the angular frequency
at 60𝐻𝑧. is the voltage difference phase across breaker. The
solution to the differential equation (2) is:
/
2 2
2( ) sin( ) sin( ) Rt L
eq
Vi t wt e
X R
(3)
where, eqX includes the series impedances 𝑋𝑑
′′, 𝑋𝑖𝑛𝑠𝑒𝑟𝑡
and𝑋𝑠𝑦𝑠. equals 𝑡𝑎𝑛−1(𝑋𝑒𝑞/𝑅) is the impedance angle.
The peak transient stator current becomes the sum of
load current and the synchronizing current computed
analytically in time domain by (3). It is worth mentioning that
this analytical expression is derived on the basis ∆𝑓 = 0 .
However, the effects due to ∆f from the PQ limits can be
neglected in calculating the peak current. An intuitive
explanation is realized by considering two voltage sources
connected together with different frequencies. If one voltage
source is taken as a reference running at angular frequency 𝑤1,
the instantaneous voltage difference when the breaker is
closed at t=0 is dictated by:
1 1( )
1 2| | | |j w t jw tj wtV V e e V e
(4)
∆𝑤 represents the angular frequency difference between the
two voltage phasors having magnitudes 1V and
2V ,
respectively.
Based on the time window of sub-transient, the peak
inrush current typically occurs within t < 2 cycles from the
initial start of synchronization. Therefore, the impact of ∆𝑓 on
∆𝑉 across the breaker is negligible since ∆𝑤𝑡 ≈ 0.
C. Transient Stability Evaluation
The section is to investigate the transient stability of
the generator due to the impact of open loop synchronization.
It is well known that the power transfer capability or the
stability margin between a generator and the system decreases
due to a fault on one of the parallel transmission lines. As the
line trips, the equivalent impedance between the generators to
the system are increased, thus the stability margin is
decreased. A similar phenomenon occurs when the impedance
is inserted at the synchronizing breaker location. Therefore,
the goal is to ensure that the worst case maximum rotor angle
reached does not go beyond the stability limit of a generator.
Furthermore, the effect of high Micro-grid loading levels may
aggravate the impacts on stability, so it should also be
considered in the analysis.
1) Generator to system synchronization
The synchronization phenomenon from a transient
stability point of view can be explained by a generator to
system synchronization example in Fig. 6. The power angle
curve (P-δ curve) is widely used for conducting transient
stability analysis, e.g. application of equal area criterion based
on power angle curves to find the critical fault clearing time to
ensure generators remain in synchronism with the system.
Similarly, power angle curves and equal area criterion can be
applied accordingly to analyze the synchronization
phenomenon after breaker is closed as shown in Fig. 7.
'E 'jXdtjX
sysZ
Infinite Bus
1 2
1 2
1 2
V V V
f f f
Synchronizing
Breaker
Fig. 6. Generator to system synchronization example
Before the closing of synchronizing breaker, the
electric power transfer between the generator and system is
zero. As the breaker is closed, the generator experiences a
sudden loading condition primarily due to the relative phase
difference to the grid. If the Micro-grid frequency is higher
than the system prior to synchronization, the rotor angle is
going to increase further until the synchronous frequency (i.e.
the system frequency) is reached after breaker closes. This
point where maximum rotor angle occurs is denoted by 𝛿𝑚𝑎𝑥
in Fig. 7. The rotor during this time period is dissipating the
kinetic energy offset stored initially. After 𝛿𝑚𝑎𝑥 is reached,
the rotor begins to swings in the opposite direction.
Eventually, the electromechanical oscillation will stabilize due
to the effects of damping.
-90 0 90 180Power Angle (deg)
Pe
o
max o
min o
Kinetic energy dissipation
due to f1>f2Pm
maxPe
o Initial angle difference
across breaker
Fig. 7. Power angle curve for generator to system synchronization
Based on the classical definition of the swing
equation with damping ignored, the motion of the rotor
dynamics are [21],
2
2
2 ( )
( )( )
m e
syn
syn
H d tP P
w dt
d tw t w
dt
(5)
The electrical power transfer from the internal voltage of
generator to the system after breaker is closed can be
expressed as: '
'sin( )s
e
d t sys
E VP
X X X
(6)
where, 𝐸′ represents the internal voltage behind direct axis
transient reactance, sV is the voltage magnitude of the system,
First Version
5
and 𝛿 is the power angle between E’ and sV . The first
equation of (5) by taking integral can be expressed as:
maxmax
00
2
( )
m e
syn
H dP P d
w dt (7)
For generator synchronization, since the mechanical power
𝑃𝑚 ≈ 0 , equation (7) can be integrated and expressed in a
closed form to obtain the value 𝛿𝑚𝑎𝑥 in the first swing:
1 2
max 0 1 2'cos cos( ) [2 ( )]
T
s syn
HXf f
EV w (8)
where, 𝑋𝑇 is the total series reactance, H is the machine inertia
constant, and 𝛿0 = ∆𝜃 is the initial angle difference when
breaker is closed.
2) Micro-grid to system synchronization
In the case of Micro-grid to system synchronization,
an equivalent diagram for stability analysis is shown in Fig.
8(a). Before the breaker closes, the power is mainly consumed
by the load as shown in Fig. 8(b). After the breaker closes in
Fig. 8(c), the power produced by the generator is exchanged
with the grid.
'E 'jXdLjX sysjX
Infinite Bus
LZ
Z insert
1 2
1 2
1 2
V V V
f f f
'E 'jXd
LZLI
0Vt 'E 'jXd eqjX
Infinite Bus
LZ
(a)
(b) (c)
sV
sV
Fig. 8. Circuits for transient stability analysis (a) Micro-grid to system
synchronization schematic diagram. (b) Before closing breaker (c) After breaker is closed.
The load is modelled as constant impedances for transient
stability studies. Y-∆ transformation is used to eliminate the
node Vt of Fig. 8(c) such that the nodes retained are shown in
Fig. 9, which are only the internal voltage 𝐸′, the infinite bus,
and the reference node to ground.
'E 12Z
10Z20Z
Y 1 2
Fig. 9. Equivalent circuit for one machine with load to an infinite bus
From network theory, the real power at node 1 of Fig.
9 is given by *
1Re EI or expressed as:
'2 '
_ 11 11 12 12cos( ) cos( )e after sP E Y E V Y
(9)
where,11 10 12Y Y Y ,
10 101/Y Z , and 12 121/Y Z .
12Z is the
series impedance of the transmission network, including
transformers, lines and the value of impedance pre-insertion.
10Z is the equivalent shunt impedance connected to the
machine terminal, which includes any local loads.11 and
12
are the impedance angle corresponding to 11Y and
12Y ,
respectively.
Similar to synchronization of generators, the
theoretical 𝛿𝑚𝑎𝑥 for the first swing when Micro-grid
synchronizes to system can be obtained by substituting (9) into
(7), which gives a non-linear equation:
12 12 max 12
2
1 2 max
' [sin( ) sin( )]
/ [2 ( )] ( )( ) 0
s o
syn m c o
E V Y
H W f f P P
(10)
where,'2
11 11cos( )cP E Y represents the power dissipation in
the network from first part of (9). Due to the impact of
loading, the initial power angle 𝛿0 in this case is the sum of
the initial angle difference across breaker and the loading
angle before synchronization.
The impacts of load and impedance pre-insertion on
the power-angle characteristic are shown in Fig. 10 and Fig.
11, respectively. Both figures examine the case where Micro-
grid frequency is higher than the synchronous frequency.
-50 0 50 100 150-1
0
1
2
3
4
5
Load Angle (deg)
Ele
ctr
ic P
ow
er
(pu)
Before Breaker Close
After Breaker Close
Pm
max o
min o o
Fig. 10. Impact of load to Micro-grid synchronization
-50 0 50 100 150-1
0
1
2
3
4
5
Load Angle (deg)
Ele
ctr
ic P
ow
er
(pu)
Before Breaker Close
After (X Insert = 0)
After (X Insert = 0.1 pu)
After (X Insert = 0.3 pu)
Pmax
max 0
min 0
0
Pm
Fig. 11. Impact of impedance pre-insertion to Micro-grid synchronization
According to Fig. 10, increasing the loading level of
Micro-grid reduces the stability margin, where the margin is
defined as the ratio of the difference (𝑃𝑚𝑎𝑥 − 𝑃𝑚 ) to 𝑃𝑚𝑎𝑥 .
Furthermore, by increasing the impedance size, the stability
margin is decreased significantly. Therefore, it is true that both
factors negatively impact the power transfer capability
between the Micro-grid to the system. However, the maximum
First Version
6
rotor angle reach is mainly affected by the loading level of the
Micro-grid and the phase difference across the breaker.
Based on the open loop synchronization requirements
and transient stability analysis, the worst case that should be
examined in terms of maximum rotor angle advancement is
based on the peak loading level and the designed impedance
value. In addition, the voltage levels (Micro-grid and system
sides) should be at the lowest of the PQ limits according to
(9). The frequency difference should be positive (i.e. higher
Micro-grid frequency than system) to result in higher rotor
advancement within the first swing. As a result, the worst case
open loop synchronization scenario from a transient stability’s
point of view is case (1, 3) from Fig. 4.
D. Impedance bypass consideration
Similar to the first breaker switching, impedance
bypass also produces a second transient effect on the system.
Therefore, the peak current from the second transient must be
evaluated to ensure an acceptable disturbance level.
According to the principal of superposition, bypass
switching can be represented by two opposing voltage sources
as shown in Fig. 12, which is equivalent to a single voltage
source in the transient circuit. This circuit is quite similar to
synchronization but with ∆𝑓 = 0 . The voltage difference
across the impedance before the bypass depends on both the
impedance value and the amount of current flow through the
impedance.
Impedance Insertion
Micro-grid,Generators Bulk Grid
Superposition
Impedance InsertionV1 V2 V1 V2
V
Fig. 12. Representing impedance bypass by equivalent voltage source
In the impedance design section, an acceptable
transient level is determined based on the IEEE C50.12.
Similar approach can be taken for impedance bypass. If the
voltage across the impedance before bypass is lower than the
acceptable bypass voltage, the bypass peak current will not be
a concern. The acceptable voltage level for bypass according
to IEEE C50.12 and Fig. 3 is computed to be 0.1855 p.u.
The actual voltage across the impedance in steady
state can be computed through load flow studies. The
initializations to load flow study should consider the
Automatic Voltage Regulation (AVR) and Governor Control
settings because it will affect both the reactive and active
power output from the synchronous machine. As a
consequence, the machine controls can affect directly the
power flow through the impedance, which may result in
higher bypass voltage.
Based on the open loop power quality limits in Fig. 1,
the voltage range for all busses in the system is typically
between 0.9-1.1 p.u. The AVR of synchronous generator
generally maintains the terminal voltage of the machine at a
preset level. After the impedance switching, since the grid
voltage is stiff, the busses near the point of interconnection
tend to follow the system voltage. However, due to the nature
of open loop synchronization, the voltage set-point of AVR is
not adjusted during the process of synchronization, which
means it is regulating the terminal voltage to the level prior to
synchronization. Therefore, there exists a reactive power (Q)
flow at the impedance in steady state. In addition, Q can flow
in either direction through the impedance.
Normally in a Micro-grid, when there is more than
one generator, the speed governors are operating in droop
control mode to assure proper load sharing between the DG
units. From synchronization point of view, before the
impedance bypass in steady state, the Micro-grid frequency
becomes the system frequency. The governor responds to the
change in frequency by a percentage change in the mechanical
torque or output power [21] as in (11). Therefore, real power
(P) flow also exists through the impedance.
(%) 1
( )microgrid sys
m
nom
f ffP pu
R f R
(11)
where, R is the droop constant andnomf is the rated machine
frequency.
The larger the frequency and voltage differences
prior to synchronization, the larger the power flowing through
the impedance due to AVR and governor controls. Based on
the open loop power quality limits, possible worst case bypass
voltages can be identified as case (2, 3), case (4, 1), case (3, 2)
and case (1, 4).
IV. SIMULATION RESULTS
The system under study consists of one 6.6 MVA
synchronous generator connected in a 30 mile (25kV) feeder
to the main substation. A peak loading of 6MW is evenly
distributed along the feeder as shown in Fig. 13. The three-
phase short circuit level at the point of interconnection is 346
MVA. The system and synchronous generator data can be
found in Appendix. The impedance pre-inserted at the circuit
breaker location is purely an inductor.
15 miles 15 miles
25/4.16kVYg/Yg
SGSGSUB
25kV
346MVA
CB
6.6MVA
+
AVR
2.0MW
0.65MVAr
V1,f1V2,f2
Impedance
Insertion
2.0MW
0.65MVAr
2.0MW
0.65MVAr Fig. 13. Single line diagram of case study
Determination of the acceptable transient level is
illustrated through the case study presented in Fig. 13. Based
on the EMTP simulations in MATLAB/Simulink, current and
torque peaks under the operating point specified in Fig. 3 are
found to be 1.5 and 1.7 p.u., respectively. Their time-domain
simulation results are shown in Fig. 14.
First Version
7
Fig. 14. Time domain simulation to obtain acceptable transients
Possible worst case synchronizing transients based on
Fig. 4 will take place in the following 4 cases shown in Fig.
15, where the operating point of both parties deviate the most.
The worst transient of all occurs in case (2, 3). This is because
prior to synchronization, the Micro-grid side voltage is
maintained at 1.1 p.u. and the Micro-grid frequency is
+0.25Hz higher than the system frequency.
Fig. 15. Worst case transients based on power quality limits
Since the worst transients are identified in case (2, 3), then
the size of impedance can be chosen either by repetitive
EMTP simulations or by the analytical expression shown in
(3). A comparison of the two approaches is shown in Fig. 16.
The analytical method provides an upper bound for the peak
stator current. For this case study, the impedance value
determined analytically is 0.6 p.u. or 56.82 Ω.
Fig. 16. Peak currents versus sizes of impedance pre-insertion for case (2, 3)
For transient stability analysis, the worst case occurs
in case (1, 3). The theoretical prediction of the maximum rotor
angle reached is obtained by simplifying the circuit in Fig. 13
to Fig. 9 using repetitive Y-∆ transformations. Therefore, the
maximum swing angle can be calculated by using (10). From
Fig. 17, it can be seen that increasing the inserted impedance
does not have a significant effect on the maximum rotor angle.
Based on the acceptable stability limit and the designed
impedance value, a feasible impedance range is within 0.6p.u.-
1.1p.u.
Fig. 17. Feasible impedance range based on short circuit and stability analysis
In order to evaluate the severity of bypass transients,
load flow study is used to find the worst bypass voltage among
the four possible cases. Case (4, 1) is the worst case as shown
in Fig. 18 because it results in the largest complex power |S|.
This |S| through the designed impedance (0.6p.u.) incurs a
voltage difference of 0.178p.u. across the bypass breaker,
which is lower than the acceptable level of 0.1855p.u.
Therefore, the bypass transient is acceptable.
-0.1 -0.05 0 0.05 0.1 0.15-0.4
-0.3
-0.2
-0.1
0
0.1
0.2
0.3
0.4
Real Power Flow (p.u.)
Reactive P
ow
er
Flo
w (
p.u
.)
maxS
Case (4, 1)
Case (2, 3)
Case (3, 2)
Case (1, 4)
Fig. 18. Worst possible power flows through the impedance computed by
load flow studies
V. CONCLUSION
The purpose of this work is to propose an open loop
synchronization strategy for a Micro-grid to system, which can
be applied to practical Micro-grid implementations. An
impedance pre-insertion method has been proposed to reduce
synchronizing transients. Based on this idea, an open loop
scheme to synchronize Micro-grids to grid has been
developed. Methods to design the open loop scheme are
established. Study results have shown that the proposed
scheme is highly feasible. The potential uses of the proposed
scheme include reducing cost of Micro-grid synchronization
and support fast restoration of power systems.
APPENDIX
TABLE I THEVENIN EQUIVALENT (SUB) DATA
Short circuit power (MVA) 346
Nominal voltage (kV) 25
0 0.5 1 1.5-2
-1
0
1
2
time (s)
Sta
tor
Curr
ent
(pu)
0 0.5 1 1.50.5
1
1.5
2
time (s)
Torq
ue T
e (
pu)
Breaker closes to begin synchronization
Acceptable torque transient
Acceptable current transient
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.81
1.5
2
2.5
Impedance Size (pu)
Peak C
urr
ent
(pu)
EMTP
Analytical
Acceptable
Z Insertion = 0.6 pu
Acceptable transient level
First Version
8
X/R Ratio 7
TABLE II SYNCHRONOUS GENERATOR DATA
Nominal Power (MVA) 6.6
Nominal Voltage (kV) 4.16
Pair of poles 2
Inertia constant (s) 2.52
Stator resistance (pu) 0.00
𝑋𝑑(pu) 1.26
𝑋𝑑′ (pu) 0.26
𝑋𝑑′′ (pu) 0.18
𝑋𝑞(pu) 1.24
𝑋𝑞′′ (pu) 0.21
𝑇𝑑𝑜′ (pu) 1.4446
𝑇𝑑𝑜′′ (pu) 0.0218
𝑇𝑞𝑜′′ (pu) 0.0690
TABLE III EXCITATION SYSTEM DATA
AVR IEEE Type 1
𝑇𝑟 5ms
𝐾𝑎 300
𝑇𝑎 50ms
𝐾𝐸 1.0
𝑇𝐸 0.65s
𝐾𝑓 0.048
𝑇𝑓 0.95s
𝐸𝑓𝑚𝑖𝑛 -5
𝐸𝑓𝑚𝑎𝑥 8
REFERENCES
[1] F. Katiraei, M. R. Iravani, and P. W. Lehn, “Micro-grid Autonomous
Operation During and Subsequent to Islanding Process,” IEEE Trans. Power Del., vol. 20, no. 1, Jan. 2005.
[2] W. Kohn, Z. B. Zabinsky, and A. Nerode, “A Micro-grid Distributed
Intelligent Control and Management System,” IEEE Trans. Smart Grid, Aug. 2015.
[3] H. Laaksonen, D. Ishchenko, and A. Oudalov, “Adaptive Protection and
Micro-grid Control Design for Hailuoto Island,” IEEE Trans. Smart Grid, vol. 5, no. 3, May. 2014
[4] F. Tang, J. M. Guerrero, J. C. Vasquez, D. Wu, and L. Meng,
“Distributed Active Synchronization Strategy for Micro-grid Seamless Reconnection to the Grid Under Unbalance and Harmonic Distortion,”
IEEE Trans. Smart Grid, Mar. 2015
[5] M. J. Thompson, “Fundamentals and Advancements in Generator Synchronizing Systems,” 65th Annual Conference for Protective Relay
Engineers, pp. 203-214, Apr. 2012.
[6] T. M. L. Assis, G. N. Taranto, “Automatic Reconnection From Intentional Islanding Based on Remote Sensing of Voltage and
Frequency Signals,” IEEE Trans. Smart Grid, vol. 3, no. 4, Dec. 2012.
[7] C. Cho, J. Jeon, J. Kim, S. Kwon, K. Park, and S. Kim, “Active
Synchronizing Control of a Microgrid,” IEEE Trans. Power Electron,
vol. 26, no. 12, Dec. 2011.
[8] Ontario Power System Restoration Plan, IESO, Ontario, 2015 [9] L. C. Gross, L. S. Anderson, and R. C. Young, “Avoid Generator and
System Damage Due to a Slow Synchronizing Breaker,” proceedings of the 24th Annual Western protective Relay Conference, Spokane, WA,
Oct. 1997.
[10] IEEE Guide for AC Generator Protection, IEEE standard C37.102-2006.
[11] W. M. Strang, C. J. Mozina, B. Beckwith, T. R. Beckwith, S. Chhak, E.
C. Fennell, E. W. Kalkstein, K. C. Kozminski, A. C. Pierce, P. W.
Powell, D. W. Smaha, J. T. Uchiyama, S. M. Usman, and W. P.
Waudby, “Generator synchronizing, industry survey results,” IEEE
Trans. Power Del., vol. 11, no. 1, pp. 174-183, Jan. 1996. [12] J. V. Mitsche and P. A. Rusche, “Shaft torsional stress due to
asynchronous faulty synchronization,” IEEE Trans. Power App. Syst.,
vol. PAS-99, no. 5, pp. 1864-1870. Sep. 1980. [13] K. Malmedal, P. K. Sen, and J. P. Nelson, “Application of out-of-step
relaying for small generators in distributed generation,” IEEE Trans.
Ind. Appl., vol. 41, no. 6, pp. 1506-1514, Nov./Dec. 2005. [14] R. P. O’leary, R. H. Harner, “Evaluation of Methods for Controlling the
Overvoltages Produced by the Energization of a Shunt Capacitor Bank,”
International Conference on Large High Voltage Electric Systems, Paris, Aug. 1988.
[15] R. W. Alexander, “Synchronous Closing Control For Shunt Capacitors,”
IEEE Trans. Power App. Syst., vol. PAS-104, no. 9, Sep. 1985. [16] A. Nied, J. Oliverira, R. F. Campos, R. P. Dias, and L. C. S. Marques,
“Soft Starting of Induction Motor With Torque Control,” IEEE Trans.
Ind. Appl., vol. 46, no. 3, May/June. 2005. [17] Y. Cui, S. G. Abdulsalam, S. Chen, and W. Xu, “A Sequential Phase
Energization Technique for Transformer Inrush Current Reduction –
Part I: Simulation and Experimental Results,” IEEE Trans. Power Del., vol. 20, no. 2, Jan. 2005.
[18] A. J. Rodolakis, “A comparison of North American (ANSI) and
European (IEC) fault calculation guidelines.” IEEE Trans. Ind. Appl., vol. 29, no. 3, pp. 515-521, May/Jun. 1993.
[19] Technical Requirements for Connecting to the Alberta Interconnected Electric System (IES) Transmission System, ESBI, Alberta, 1999.
[20] IEEE standard for Salient-Pole 50 Hz and 60 Hz Synchronous
Generators and Generator/Motors for Hydraulic Turbine Applications Rated 5 MVA and Above, IEEE Standard C50.12-2005.
[21] P. Kundur, “Power System Stability and Control”, in McGraw-Hill,
1994, pp. 581-600.
Final Version
9
Abstract—This paper proposes a novel method to enable open-
loop synchronization of a microgrid to the main grid. The idea is
to pre-insert an impedance to reduce the synchronization
transients and then bypass it after the initial transients are over.
With this method, infrastructure cost and complexity of
synchronization can be reduced significantly since the
communication link between the breaker and the microgrid
generators is no longer required. In addition, the extra effort
required for generator adjustments, especially for multiple units,
can be avoided. Technical considerations and design method for
the selection of pre-insertion impedance size is presented. A
simulation study is conducted to evaluate the performance of the
method. The results prove that the transient levels can be
effectively reduced and open-loop synchronization is indeed
achievable.
Index Terms—Impedance insertion, islanding, microgrid,
open-loop synchronization.
VI. INTRODUCTION
ICROGRIDS are becoming an integral feature of the
power systems due to their environmental and
economical benefits. A microgrid includes a variety of
distributed energy resource (DER) units (including distributed
generation (DG) and energy storage devices and different
types of load. Improved reliability and sustainability are some
of the desired characteristics affecting the distribution level
provided by the implementations of microgrids [22].
Microgrids are able to operate in both grid-connected and
islanded modes. For effective operation in islanded mode,
several methods have been proposed for controlling the
microgrid [2-4].
Among the various types of distributed generators proposed
for microgrids, the synchronous generators (SG) are actually
the most common type. Examples are combined heat and
power (CHP), internal combustion engine, and small hydro
[26]. Each time the microgrid switches from islanded to grid-
connected operation mode, the grid and its SGs need to be
synchronized with the main grid. Precaution is necessary to
make sure that synchronization criteria are met to avoid
equipment damage and power quality concerns [27], [28].
In the traditional synchronizing practices, voltage across the
The authors are with Electrical and Computer Engineering Department of
University of Alberta, Edmonton, AB T6G 1H9, Canada (e-mail:
breaker at the substation location is monitored and sent to the
operator at the generation site. The operator then uses these
measurements to adjust governor and exciter settings to meet
the synchronization criteria [29]. Automatic synchronization
methods based on feedback control strategies have been
presented in literature [30], [31]. Recently, an active
synchronization strategy that takes into account voltage
unbalances and harmonic distortions is presented in [32]. In
order to implement such feedback control systems in practice,
infrastructure support such as communication links are
necessary to carry the signals from the breaker location
(substation) to the local machines as shown in Fig. 1. The
problem is that the microgrid might be located in a rural or
forestry area far away from the point of connection to the main
grid. For example, in [30] it is stated that these rural
microgrids are becoming common in Brazil. In such cases, the
cost of communication infrastructure can be prohibitively
high.
Additional difficulties arise when there are multiple DG
units in the microgrid. In this case, multiple communication
links are necessary to allow the tuning of individual DG units.
Therefore, synchronizing by feedback control can drive up the
cost of infrastructure support and increase synchronization
effort.
~
Microgrid
Synchronizing
Controls
Communication Link
Main Grid
Machine
Controls
CB
Fig. 1. Schematic of the synchronization methods with feedback control
In response to the above challenges, a novel open-loop
synchronization method is proposed in this paper. As the name
implies, the method does not require a communication link
between the DG units and the breaker location. The proposed
method is inspired by the practices of controlling switching
transients, since synchronization is an event where switching
transients is the main concern. The idea here is to pre-insert an
impedance to reduce the synchronization transients. With this
method, infrastructure cost and complexity of synchronization
A Method to Enable Open-Loop
Synchronization of a Microgrid to Main Grid
Yaxiang Zhou, Student Member, IEEE, Wilsun Xu, Fellow, IEEE, Moosa Moghimi Haji, Student Member,
IEEE, Jing Yong, Member, IEEE
M
Final Version
10
can be reduced significantly since the communication link
between the breaker and the microgrid generators is no longer
required.
The rest of the paper is organized as follows. The proposed
scheme is presented in Section II. The impedance design
method is explained in Section III. A case study is conducted
in Section IV to evaluate the effectiveness of the proposed
method. Finally, the conclusion is presented in Section V.
VII. PROPOSED OPEN-LOOP SYNCHRONIZATION METHOD
The main concern on synchronizing two systems or a
generator with a system is the transients produced when the
synchronizing circuit breaker is closed. Excessive transients
can lead to large inrush current and transient torque, damaging
generator and other equipment [33], [34]. The current practice
of reducing synchronization transients is to limit the voltage,
angle, and frequency differences between the two parties.
There are other ways to reduce switching transients [35]. A
good example is the impedance insertion/bypass scheme used
to limit capacitor switching transients. In this scheme, the
inserted impedance increases the total circuit impedance and
thus reduces the inrush current. The impedance is bypassed
after the system has reached the steady-state. In view of the
excellent performance of this scheme on reducing switching
transients, one may wonder if it can be used to simplify the
synchronization of a microgrid to a system.
Before synchronization, the microgrid and the system are
expected to operate within their respective power quality
limits. This means that each party has a known operating
region of voltage and frequency at the synchronization point.
The proposed idea is to establish a value of the pre-insertion
impedance such that the resulting transient is always within
acceptable limit as long as the two parties are operating within
their power quality limits at the time of synchronization.
Consequently, feedback control is not needed to adjust the
microgrid operating point. Fig. 2 illustrates the proposed
scheme.
It is clear that a larger Zinsert will result in more reduction of
inrush currents. However, it may increase the transient when
the impedance is bypassed. In addition, larger Zinsert will
weaken the synchronizing power between the microgrid and
the system so instability may occur. Therefore, the following
issues must be addressed for the proposed scheme:
a) What is the acceptable synchronization transient level?
b) What is the minimum value of Zinsert which can lead to
acceptable synchronization transients?
c) What is the maximum value of Zinsert that can maintain
system stability and results in acceptable bypass
transients?
In the following section, the above issues are addressed one
by one. A method to design the proposed scheme is developed
accordingly.
VIII. IMPEDANCE SIZE DESIGN
Current surges and power oscillations should be taken into
account for designing the impedance size. The first step is to
find the maximum acceptable surge level and power
oscillation. Maximum surge level could be expressed by
maximum current and maximum torque. These values are
calculated based on the synchronization criteria from the
standard IEEE C50.12 for salient-pole synchronous generators
[38]. The limits are:
- Angle ±10° - Voltage 0 to 5% (of nominal)
- Slip ±0.067𝐻𝑧
These limits are established to ensure an acceptable
transient level experienced by the generator in terms of stator
current and shaft torque. In order to find the worst transient,
the limits have been transformed into an acceptable region
shown in Fig. 3. As the synchronizing condition moves away
from the origin, the transient level will increase due to an
increase in the voltage across the breaker. As a result, the four
corners of the region should be examined through simulations
to determine the maximum acceptable current and torque,
since they are farthest from the origin.
Fig. 3. Acceptable transient region defined by standard
The maximum power oscillation level is expressed by the
maximum rotor angle which usually happens at the first
swing. A limit is required to ensure that the synchronous
generator of the DG unit will successfully be synchronized
with the grid and will not become unstable. The industry
practice is to consider 45 degrees as the maximum rotor angle
for transient stability studies [39]. The same value is used in
this paper as the maximum acceptable rotor angle.
The current transients and transient stability of the
Fig. 2. The scheme of the proposed method and power quality limits of the
both sides
Final Version
11
microgrid during the open-loop synchronization are analyzed
in the next subsections. Then the impedance design method is
presented.
A. First switching surges
As mentioned before, the method is meant to enable open-
loop synchronization of the micro grid at any normal operating
point of the microgrid and the main grid shown in Fig. 4. To
make sure that the current and torque transients are both lower
than their acceptable limits, all of the operating points of the
two systems should be examined. However, it is evident that
the largest voltage and frequency mismatch will result in the
largest synchronizing transients. Therefore, there are four
combinational cases to consider: case (2, 3), case (4, 1), case
(3, 2) and case (1, 4). Where, the first number refers to the
operating point in the microgrid side, and the second number
refers to the system side shown in Fig. 4. It should be
mentioned that 10 degrees angle difference is used to find the
transient limits according to IEEE standard [38]. In practice,
according to an IEEE industrial survey [40], the maximum
closing angle can reach up to 20 degrees when
synchronization is done manually by an operator. Therefore, a
worst case angle difference of 20 degrees is used for
impedance design.
The worst (highest) transient current and torque could be
determined by simulating the four aforementioned cases.
However, to have a better insight, an analytical expression is
derived for the case of having only one synchronous
generator.
The microgrid is modelled as a synchronous generator with
a load connected to its terminal. Before the breaker is closed,
the current through the impedance is zero. However, the stator
current of the synchronous machine consists of a steady state
flow of load current as shown in Fig. 5(a). At the instant of the
first breaker switching, this switch can be represented by two
opposing voltage sources in series, as shown in Fig. 5(b). By
applying the superposition theorem, the circuit shown in Fig.
5(b) can be split into two equivalent circuits shown in Fig.
5(c).
The circuit on the left side of Fig. 5(c) represents the same
circuit before breaker is closed. The current in this circuit
represents the steady state component. The right side circuit
can be used to calculate the transient resulting from the
switching. Assuming ∆f is equal to zero, the analytical
expression for the transient component based on Kirchhoff’s
voltage law (KVL) for the circuit is
( )( ) 2 sin( )
di tL Ri t V wt
dt (1)
where, L and R are the total equivalent inductance and
resistance, respectively. is the angular frequency and is
the voltage phase difference across the breaker. The solution
to the differential equation (1) is
/
2 2
2( ) sin( ) sin( ) Rt L
eq
Vi t wt e
X R
(2)
where, eqX includes the series impedances X”d, Xinsert, and Xsys.
is the impedance angle given by tan-1
(Xeq/R).
The peak stator current is the sum of load current and the
synchronizing current, where the synchronizing current is
given by (2). It is worth mentioning that (2) is derived on the
basis ∆f=0 because the frequency difference effect on the
transient current is negligible. An explanation is realized by
considering two voltage sources connected together with
different frequencies. If one voltage source is taken as a
reference running at angular frequency 1 , the instantaneous
voltage difference when the breaker is closed at t=0 is given
by
1 1( )
1 2| | | |j w t jw tj wtV V e e V e
(3)
where, ∆ω represents the angular frequency difference
between the two voltage phasors having magnitudes V1 and V2,
respectively.
Based on the time window of subtransient, the peak inrush
current typically occurs within t < 2 cycles from the
synchronization instant. Since ∆wt is almost zero, the impact
of ∆f on ∆V across the breaker will be negligible.
B. Transient Stability Evaluation
Every time the microgrid has to be synchronized with the
main grid, transient stability is one of the main concerns. The
effect of inserting the impedance on the transient stability will
be evaluated in this section. Then, the worst case which causes
the maximum rotor angle will be identified. The ultimate goal
is to ensure that the maximum rotor angle in the worst case
does not exceed the transient stability limit of the generator.
Fig. 4. Operating regions of the microgrid and main grid
Fig. 5. Equivalent circuit representation of closing breaker 1. (a) Circuit before
breaker 1 is closed. (b) Circuit after breaker 1 is closed. (c) Equivalent circuits
after breaker 1 is closed.
Final Version
12
First, a simple case including a single generator shown in
Fig. 6 is considered. The rotor dynamics can be expressed by
the classical definition of the swing equation with damping
ignored [41] 2
2
2 ( )
( )( )
m e
syn
syn
H d tP P
w dt
d tw t w
dt
(4)
where, Pm and Pe are mechanical and electrical power,
respectively. H is the machine inertia constant. ω(t) and ωsys
are the generator and system angular frequency, respectively.
After breaker is closed, the electrical power transfer from
the internal voltage of generator to the system can be
expressed as '
'sin( )s
e
d t sys
E VP
X X X
(5)
where, E' represents the internal voltage behind direct axis
transient reactance, Vs is the voltage magnitude of the system,
and δ is the power angle between E' and Vs. The following
equation can be derived from the first equation of (4) max
max
00
2
( )m e
syn
H dP P d
w dt
(6)
For generator synchronization, since the mechanical power
is close to zero, (6) can be integrated and expressed in a closed
form to obtain the value of δmax in the first swing
1 2
max 0 1 2'cos cos( ) [2 ( )]T
s syn
HXf f
EV w
(7)
where, XT is the total series reactance.
In the case of microgrid to system synchronization, an
equivalent diagram for stability analysis is shown in Fig. 7(a).
Before the breaker is closed, the power is mainly consumed by
the load as shown in Fig. 7(b). After the breaker is closed, the
power is exchanged with the main grid, as shown in Fig. 7(c).
By modeling the loads as constant impedances and applying
Y-∆ transformations, the circuit shown in Fig. 7(c) is
transformed to the circuit shown in Fig. 8. From network
theory, the real power at node 1 of Fig. 8 is given by
*
1Re EI or
'2 '
_ 11 11 12 12cos( ) cos( )e after sP E Y E V Y (8)
where,11 10 12Y Y Y ,
10 101/Y Z , and 12 121/Y Z .
12Z is the
series impedance of the transmission network, including
transformers, lines and the inserted impedance. 10Z is the
equivalent shunt impedance connected to the machine
terminal, which includes any local loads.11 and
12 are the
impedance angle corresponding to 11Y and
12Y , respectively.
Similar to synchronization of single generator, the
theoretical δmax for the first swing when microgrid
synchronizes to system can be obtained by substituting (8) into
(6), which gives a non-linear equation
12 12 max 12
2
1 2 max
' [sin( ) sin( )]
/ [2 ( )] ( )( ) 0
s o
syn m c o
E V Y
H W f f P P
(9)
where,'2
11 11cos( )cP E Y represents the power dissipation in
the network from first term of (8).
To consider the transient stability in designing the
impedance, first the worst case should be identified. Then
stability of the system under the worst case should be ensured.
The effect of increasing the loading level on the transient
stability is shown in Fig. 9. As it can be seen, increasing the
loading level of microgrid reduces the stability margin, where
the margin is defined as (Pmax-Pm)/Pmax. The reason is that the
initial angle of the rotor will be higher as the load is increased.
The effect of inserted impedance on the transient stability is
shown in Fig. 10. As it was expected, the inserted impedance
will reduce Pmax and consequently reduce the transient stability
margin. As it will be seen in the case study, since the
frequency difference between the two grids is small, the
inserted impedance will only have a small impact on the
maximum rotor angle.
To sum up, the worst case that should be examined in terms
of maximum rotor angle is based on the peak loading level and
the designed impedance value. In addition, the voltage levels
(microgrid and system sides) should be at the lowest of the
Fig. 6. Generator to system synchronization example
Fig. 7. Circuits for transient stability analysis (a) microgrid to system
synchronization single line diagram. (b) Before closing breaker (c) After
breaker is closed.
Fig. 8. Simplified equivalent circuit of the microgrid after applying Y-∆
transformations
Final Version
13
power quality limits according to (6) and (8). The frequency
difference should be positive (i.e. higher microgrid frequency
than system) to result in higher rotor angle within the first
swing. As a result, the worst case open loop synchronization
scenario from a transient stability point of view is case (1, 3)
shown in Fig. 4.
C. Second Switching Surges
Similar to the first breaker switching, impedance bypass
also produces a transient effect on the system which must be
evaluated to ensure an acceptable disturbance level. According
to the principal of superposition, bypass switching can be
represented by two opposing voltage sources as shown in Fig.
11, which is equivalent to a single voltage source in the
transient circuit. This circuit is quite similar to the first
switching circuit, but with ∆f=0. The voltage difference across
the impedance before the bypass depends on both the
impedance value and the amount of current flowing through
the impedance.
The active and reactive power flowing through the
impedance after closing the first breaker depend on the
governor and AVR settings of the synchronous generator. The
reason is that due to the nature of open loop synchronization,
the voltage set-point of AVR is not adjusted during the
process of synchronization. Therefore, the AVR is regulating
the terminal voltage to the level prior to synchronization. As a
result a reactive power flow is expected which can flow in
either direction depending on the voltage levels of the
synchronous generator and the main grid.
Active power flow through the inserted impedance is also
expected. The speed governors of the synchronous generators
are operating in droop control mode to assure proper load
sharing between the DG units. When the system reaches the
steady-state before impedance bypass, the microgrid
frequency becomes equal to the system frequency. The
governor responds to the change in frequency by a percentage
change in the mechanical torque or output power [41] as in
(10). Therefore, a real power exchange between the microgrid
and the main grid exists which can be in either direction
depending on the pre-synchronization frequencies of the both
sides.
(%) 1( )
microgrid sys
m
nom
f ffP pu
R f R
(10)
where, R is the droop constant and fnom is the rated machine
frequency.
The larger the frequency and voltage differences prior to
synchronization, the larger the power flowing through the
impedance. The worst case caused by the highest voltage
difference should be identified to make sure that the worst
possible transient is lower than the acceptable limit. Possible
worst case bypass voltages can be identified as case (2, 3),
case (4, 1), case (3, 2) and case (1, 4) shown in Fig. 4. The
voltage across the impedance can be found through load flow
studies. Then the highest voltage difference is compared to the
acceptable voltage limit. If the maximum voltage is lower than
the limit, the bypass is realized in one step. Otherwise, more
bypass steps are required. The voltage difference limit is
0.1855 p.u. based on standard IEEE C50.12 [38].
D. Impedance Design Summary
The design method for the pre-insertion impedance size can
be summarized as follows:
- The acceptable transient current and torque limits are
determined.
- The four possible worst cases identified before are
established to find the case with the worst transient.
- The worst case is then used to determine the minimum
impedance size through analytical approach or
Fig. 9. Impact of load to microgrid synchronization
Fig. 10. Impact of impedance pre-insertion to microgrid synchronization
Fig. 11. Representing impedance bypass by equivalent voltage source
Final Version
14
simulation.
- Analytical approach or simulation is then used to find
the maximum acceptable impedance to maintain the
transient stability of the generators.
- An acceptable impedance range is now developed
according to transient current and transient stability
limits. This impedance size is selected in the lower
range in this paper to have the maximum transient
stability margin.
- Power flow studies are utilized to find the case causing
the highest voltage across the inserted impedance
among the four cases identified before. The highest ∆V
is then compared to the maximum acceptable value to
find how many steps are required to bypass the inserted
impedance.
IX. CASE STUDY
To evaluate the effectiveness of the method, it is applied to
a system shown in Fig. 12. The system consists of one 6.6
MVA synchronous generator connected through a 30 mile
(25kV) feeder to the main substation. A total load of 6MW is
distributed along the feeder as shown in the figure. The system
and synchronous generator data can be found in Appendix.
The impedance pre-inserted at the circuit breaker location is
considered to be purely inductive.
The system is simulated in MATLAB/Simulink. Based on
EMTP simulations, maximum acceptable transient current and
torque are found to be 1.5 p.u. and 1.7 p.u., respectively. The
respective simulation results are shown in Fig. 13.
A. Impedance Design
The 4 possible worst cases for the first switching discussed
in Section III are simulated. The Peak current and torque for
these cases are presented in Fig. 14. As it can be seen, the
worst transients occur in case (2, 3). Now that the worst case
is identified, the minimum size of impedance required to limit
the transients can be found either by EMTP simulations or by
the analytical expression given in (2). A comparison of the
two approaches is shown in Fig. 15. The analytical method
provides an upper bound for the peak stator current. For this
case study, the impedance value determined analytically is 0.6
p.u. or 56.82 Ω.
For transient stability analysis, the worst case occurs in case
(1, 3). Similar to the previous step, either EMTP simulations
or analytical approach could be used to determine the
predicted maximum rotor angle. The theoretical prediction of
the maximum rotor angle is obtained by simplifying the circuit
in Fig. 12 to Fig. 8 using Y-∆ transformations. The maximum
swing angle can then be calculated by (9). The maximum rotor
angles found by simulation and analytical approaches for
different impedance sizes are compared in Fig. 16. It can be
seen that the results of the two methods are close to each
other. In addition, increasing the inserted impedance size does
not have a significant effect on the maximum rotor angle.
According to the maximum acceptable transient level and
stability limit, the feasible impedance range is within 0.5p.u.-
1.1p.u. However, to ensure a high stability margin, 0.6pu is
chosen as the required impedance size.
The last design step is to evaluate the severity of bypass
transients. Load flow studies are used to find the worst bypass
voltage among the four possible cases mentioned in Section III
and the results are presented in Fig. 17. As it can be seen, case
Fig. 12. Single line diagram of the case study
Fig. 13. Time domain simulation to obtain acceptable transient limits
Fig. 14. Worst case transients based on power quality limits
Fig. 15. Peak current versus impedance size for the worst case
2.01 2.00 1.90 1.93
2.34 2.332.22 2.26
0.00
0.50
1.00
1.50
2.00
2.50
3.00
case (2, 3) case (4, 1) case (3, 2) case (1, 4)
Pea
k S
tato
r C
urr
ent
an
d
To
rqu
e (
pu
)
I_peak Te_max
Worst Case transient
Final Version
15
(4, 1) has the highest complex power which leads to the
highest voltage across the impedance. For the selected
impedance size (0.6p.u.), this complex power incurs a voltage
difference of 0.178 p.u., which is lower than the acceptable
level of 0.1855p.u. Therefore, the impedance can be bypassed
in one step while the transient level is acceptable.
B. Simulation Results
To better show the performance of the proposed method,
the whole synchronization process using the designed
impedance is shown in Fig. 18 to Fig. 20. For these
simulations it is assumed that the synchronization is done
under case (2, 3) which has the worst transient at the
synchronization instance. The voltage angle difference across
the breaker is assumed to be 20 degrees. For comparison, the
synchronization under the same condition but without the
inserted impedance is also shown in these figures.
As it can be seen in Fig. 18 and Fig. 19, without the inserted
impedance the current and torque could reach as high as 2 p.u.
and 2.34 p.u., respectively, which are higher than the
acceptable limits. After inserting the impedance, the peak
current for the first and second switching are 1.37 p.u. and
1.38 p.u. which are within the acceptable limit. Also the peak
torque for the first and second switching are 1.54 p.u. and 1.36
p.u., respectively, which are below the maximum acceptable
limit.
Comparing the rotor angles in Fig. 20 shows that although
inserting the impedance increases the oscillations, the
oscillations will not causing the rotor to pass the maximum
stability limit and the generator will be stable after the
synchronization.
X. CONCLUSION
An impedance insertion method has been proposed in this
paper to enable open-loop synchronization of a microgrid.
Since the primary concern in synchronization is the switching
transients, the idea is to pre-insert an impedance before the
breaker closing to reduce the transients to an acceptable level.
The impedance is then bypassed using a second breaker. The
necessary requirements are considered in the impedance
design to ensure acceptable transient level and transient
stability. Using the open-loop scheme, both synchronization
Fig. 16. Feasible impedance range base d on short circuit and stability analysis
Fig. 17. Worst possible power flows through the impedance from load flow
studies
Fig. 18. Stator current during synchronization with and without impedance
insertion
Fig. 19. Torque during synchronization with and without impedance
insertion
Fig. 20. Rotor angle during synchronization with and without impedance
Final Version
16
cost and effort is reduced because feedback control is not
necessary. The proposed scheme has been evaluated through a
case study. The results demonstrated that the transient levels
can be effectively reduced and the microgrid can be
successfully synchronized in an open-loop manner. This
scheme presents an attractive solution to synchronizing remote
microgrids.
APPENDIX
TABLE I
THEVENIN EQUIVALENT (SUB) DATA [30]
Short circuit power (MVA) 346
Nominal voltage (kV) 25
X/R Ratio 7
TABLE II
SYNCHRONOUS GENERATOR DATA [30]
Nominal Power (MVA) 6.6
Nominal Voltage (kV) 4.16
Pair of poles 2
Inertia constant (s) 2.52
Stator resistance (pu) 0.00
𝑋𝑑(pu) 1.26
𝑋𝑑′ (pu) 0.26
𝑋𝑑′′ (pu) 0.18
𝑋𝑞(pu) 1.24
𝑋𝑞′′ (pu) 0.21
𝑇𝑑𝑜′ (pu) 1.4446
𝑇𝑑𝑜′′ (pu) 0.0218
𝑇𝑞𝑜′′ (pu) 0.0690
TABLE III
EXCITATION AND GOVERNOR-TURBINE DATA [41]
AVR IEEE
Type 1
Governor- Turbine
System
Type: Hydro
𝑇𝑟 5ms 𝑅𝑝 0.05
𝐾𝑎 300 𝑇𝑔 0.2s
𝑇𝑎 50ms 𝑇𝑤 1.0s
𝐾𝐸 1.0 𝑅𝑡 0.38
𝑇𝐸 0.65s 𝑇𝑟 5.0s
𝐾𝑓 0.048
𝑇𝑓 0.95s
𝐸𝑓𝑚𝑖𝑛 -5
𝐸𝑓𝑚𝑎𝑥 8
ACKNOWLEDGMENT
The authors wish to thank the supports from the NSERC
Smart Microgrid Research Network (NSMG-Net) during the
course of this project.
REFERENCES
[22] A. Bidram and A. Davoudi, “Hierarchical Structure of Microgrids
Control System,” IEEE Trans. Smart Grid, vol. 3, no. 4, pp. 1963-1976, Dec. 2012.
[23] M. Savaghebi, A. Jalilian, J. C. Vasquez, and J. M. Guerrero,
“Secondary Control Scheme for Voltage Unbalance Compensation in an Islanded Droop-Controlled Microgrid,” IEEE Trans. Smart Grid, vol. 3,
no. 2, pp. 797-807, Jun. 2012
[24] M. S. Golsorkhi Esfahani and D. D. C. Lu, “A Decentralized Control
Method for Islanded Microgrids under Unbalanced Conditions,” IEEE
Trans. Power Del., doi: 10.1109/TPWRD.2015.2453251.
[25] P. Sreekumar and V. Khadkikar, “A New Virtual Harmonic Impedance
Scheme for Harmonic Power Sharing in an Islanded Microgrid,” IEEE Trans. Power Del., doi: 10.1109/TPWRD.2015.2402434.
[26] N. W. A. Lidula and A. D. Rajapakse, “Microgrids research: A review
of experimental microgrids and test systems,” Renewable Sustainable Energy Rev., vol. 15, no. 1, pp. 186-202, Jan. 2011.
[27] L. C. Gross, L. S. Anderson, and R. C. Young, “Avoid Generator and
System Damage Due to a Slow Synchronizing Breaker,” proceedings of the 24th Annual Western protective Relay Conference, Spokane, WA,
Oct. 1997.
[28] IEEE Guide for AC Generator Protection, IEEE standard C37.102-2006. [29] M. J. Thompson, “Fundamentals and Advancements in Generator
Synchronizing Systems,” 65th Annual Conference for Protective Relay
Engineers, pp. 203-214, Apr. 2012. [30] T. M. L. Assis, G. N. Taranto, “Automatic Reconnection From
Intentional Islanding Based on Remote Sensing of Voltage and
Frequency Signals,” IEEE Trans. Smart Grid, vol. 3, no. 4, pp. 1877-1884, Dec. 2012.
[31] C. Cho, J. Jeon, J. Kim, S. Kwon, K. Park, and S. Kim, “Active
Synchronizing Control of a Microgrid,” IEEE Trans. Power Electron, vol. 26, no. 12, pp. 3707-3719, Dec. 2011.
[32] F. Tang, J. M. Guerrero, J. C. Vasquez, D. Wu, and L. Meng,
“Distributed Active Synchronization Strategy for Micro-grid Seamless Reconnection to the Grid Under Unbalance and Harmonic Distortion,”
IEEE Trans. Smart Grid, vol. 6, no. 6, pp. 2757-2769, Nov. 2015 [33] H. Laaksonen, D. Ishchenko, and A. Oudalov, “Adaptive Protection and
Micro-grid Control Design for Hailuoto Island,” IEEE Trans. Smart
Grid, vol. 5, no. 3, pp. 1486- 1493, May. 2014 [34] K. Malmedal, P. K. Sen, and J. P. Nelson, “Application of out-of-step
relaying for small generators in distributed generation,” IEEE Trans.
Ind. Appl., vol. 41, no. 6, pp. 1506-1514, Nov./Dec. 2005 [35] R. C. Dugan, M. F. McGranaghan, H. W. Beaty, “Electrical Power
Systems Quality”, in McGraw-Hill, 1996, pp. 100-103.
[36] Technical Requirements for Connecting to the Alberta Interconnected Electric System (IES) Transmission System, ESBI, Alberta, 1999.
[37] A. J. Rodolakis, “A comparison of North American (ANSI) and
European (IEC) fault calculation guidelines.” IEEE Trans. Ind. Appl., vol. 29, no. 3, pp. 515-521, May/Jun. 1993.
[38] IEEE standard for Salient-Pole 50 Hz and 60 Hz Synchronous
Generators and Generator/Motors for Hydraulic Turbine Applications Rated 5 MVA and Above, IEEE Standard C50.12-2005.
[39] N. Mohan, "Electric Power Systems: A First Course", in John Wiley &
Sons Inc., 2012, pp. 159-160. [40] W. M. Strang, C. J. Mozina, B. Beckwith, T. R. Beckwith, S. Chhak, E.
C. Fennell, E. W. Kalkstein, K. C. Kozminski, A. C. Pierce, P. W.
Powell, D. W. Smaha, J. T. Uchiyama, S. M. Usman, and W. P. Waudby, “Generator synchronizing, industry survey results,” IEEE
Trans. Power Del., vol. 11, no. 1, pp. 174-183, Jan. 1996.
[41] P. Kundur, “Power System Stability and Control”, in McGraw-Hill, 1994, pp. 581-600.