Open Plan Download to 1 st Update
Transcript

Open Plan

Download to 1st Update

Default password is PASSWORD

PDM Drafting Conventions

• Logic relationships between activities may be:– finish to start -- (Default)– start to start– finish to finish– start to finish– and variations of each

SS5

FS2

1000Activity #1 6 days

1005Activity #2 6 days

1010Activity #3 2 days

1015Activity #4 10 days

1020Activity #5 3 days

1025Activity #61 day

1030Activity # 7 4 days

1035Activity #8 4 days

1040Activity #9 5 days

1045Activity #10 6 days

FF2

SS0

Activity B

20

Activity A

15

FF 10

SS 5

PDM Drafting Conventions

• Lag Durations Between Activities• may delay the START or FINISH of the subsequent activity beyond

the START or FINISH of the specified preceding activity

Activity A- 10 days Activity B- 10 daysNo Activity - 10 days

Activity B

15

Activity A

20

FF 10

SS 5

Activity A- 20 days Lag - 10 days

Lag=5 Activity B- 15 days?

PDM Drafting Conventions

• Interpretation of Finish to Start relationship– what is meant by finish to start?– what is meant if Lag < 0 (negative Lag)?– what part of Activity A is not yet complete?– what part of Activity A is complete?

•SS+7 vs FS-3•what would be meant by FS-12?

Activity A 10 days

Activity B 15 days

PDM Drafting Conventions

• Interpretation of Start to Start relationship– what is meant by start to start?– start Activity B when Activity A is 50% complete

– which 50%? -- if the scope cannot be explained, the % is suspect

Activity A 10 days

Activity B 15 days

PDM Drafting Conventions

• Interpretation of Start to Start relationship– what is meant by start to start?– start Activity B when Activity A has 2 days Remaining Duration

– what scope during last two day? -- if unknown, lag duration is suspect

Activity A 10 days

Activity B 15 days

PDM Drafting Conventions

• Interpretation of Start to Start relationship– what is meant by start to start?– start Activity B when 3 days of Activity A’s OD has been performed

– this may be what we mean to say -- is it what we told the computer?

Activity A 10 days

Activity B 15 days

PDM Drafting Conventions

• Interpretation of Start to Start relationship– what is meant by start to start?– start Activity B when 3 days have passed since Activity A was started– or start Activity B when 3 days of Activity A have been performed

Activity A 10 days

Activity B 15 days

Activity A 10 days

Activity B 15 days

versus

3 days

3 days

PDM Drafting Conventions

• Interpretation of Start to Start relationship– what is meant if Lag > OD of Activity A?

Activity A 10 days

Activity B 15 days

Activity A 10 days

Activity B 15 days

versus

12 days

12 days?

Default password is PASSWORD