+ All Categories
Home > Documents > OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 ·...

OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 ·...

Date post: 29-Jun-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
25
OPEN UNIVERSITY OF MALAYSIA PhD Viva Voce BY JOSEPH TEYE IGNATIUS BUERTEY BSc., MSc. TOPIC: ESTIMATING COST CONTINGENCY FOR ENGINEERING CONSTRUCTION PROJECTS: INTEGRATING RISK MODELLING TO IMPROVE BUDGETARY RELIABILITY JULY 2015
Transcript
Page 1: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

OPEN UNIVERSITY OF MALAYSIA

PhD Viva Voce

BY

JOSEPH TEYE IGNATIUS BUERTEY BSc., MSc.

TOPIC:

ESTIMATING COST CONTINGENCY FOR ENGINEERING CONSTRUCTION PROJECTS:

INTEGRATING RISK MODELLING TO IMPROVE BUDGETARY RELIABILITY

JULY 2015

Page 2: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

Purpose of the Study

• The study developed and validated a conceptual framework for determining realistic cost contingency margins for Engineering projects.

Page 3: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

.

.

Coordinated and integrated national

database on Engineering Projects in

Ghana is non-existent

The substructure, engineering

services installations and finishes

were prone to high scope changes,

system failure and severity

effect on cost overruns

The effect of systemic uncertainty

on project cost overruns is very

high compared to project specific risk

Engineering Professional’s

knowledge about risk management

processes is very low

The Financial impact of scope and

design related risk on cost growth is

very high

SIGNIFICANCE OF STUDY

Practical Implication: The need

to review the curricula of tertiary

institutions and provide CPD

Orientation by Professional bodies

Policy Implications: The need to

establish an Engineering Industry

regulatory body in Ghana

Theory Implications :

Risk partition according to the

DST combination rule

Practical Implication

The need to enhance design

management effort by

practitioners

Practical Implication

The need to research to improve

the estimation process of Cost

contingency margins

Page 4: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

Research Problem PROBLEM

SITUATION

No

standardised

methods

High risk

characterization

of industry

High Cost and

Schedule

overruns

Increased cost

uncertainty

Increased

system

engineering

failure

Addressing the Gap is very important because it forms the

basis for informed decision making in the study area and

boost efforts at minimizing cost overruns and client

confidence in Project cost management and serves as a

basis for contingency management

RESEARCH GAP:

HOW TO ESTIMATE RELIABLE COST CONTINGENCY

MARGINGS FOR ENGINEERING PROJECTS

PREVIOUS RESEARCH

• Touran (2003b) and Baccarini (2004): Contingency margins

is estimated as a percentage (10%) of the contract value

• Ali (2005): Proposed that cost contingency estimation must be

undertaken using the integration of risk management process

hence was recommended for further research

• Gunhan and Arditi (2007): Held that Deterministic models are

unrealistic hence risk modelling was required

• Keith (2011): Held that uncertainty in cost growth decreases as

one travels along the project trajectory with significant risk

unveiling. Hence recommended risk integration for modelling

cost contingency

Page 5: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

Literature Review Item Reference Key Points from Review

1 Patrascu (1988) Contingency is an amount of money for cost required but uncertain. These

uncertain cost includes design changes, design growth, variations due to

method of construction, scope creep and specification changes.

2 Malik (1994) Used quantitative methods to determine uncertainty of project cost. Thus

BOQ items and usage resources and their prices were presented as

moments . The method did factor risk items

3 Touran (2003a) Presented a probabilistic model that considers the random nature of

change orders and their impact on the cost and schedule overruns. He

used poison correlation for design stage budgeting

4 Baccarini (2004) A 3-tier contingency model was developed. The model was based on

project variables such as project size, bid variability, bids received, project

duration, project location, year of execution, etc

5 Sonmez et al (2007) Reviewed the financial impact of risk factors at the bidding stage . Used

the Pearson Correlation Coefficient

6 Nasirzadeh et al

(2008)

Developed a model for the expected cost of the project . The risk outcome

was deduced by multiplying the probability of occurrence by the maximum

expected cost (expected value)

7 Keith (2012) Proposed a 3-tier risk modelling must be used. as risk identification;

qualitative risk analysis. Type III a quantitative risk analysis and active

contingency management

Page 6: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

Literature Review-Contingency Methods

. Traditional

Method

Detailed

Percentages

with Probability

of occurrence

Risk Analysis

and Modelling

Detailed

Percentages

• Method of moments (Diekmann, 1983), (Moselhi, 1997), (Yeo, 1990)

• Range estimating, (Curran, 1989)

• Analytical hierarchy process (Dey, Tabucanon & Ogunlana, 1994)

• Fuzzy sets/logic (Peak, Lee, Ock, 1993)

• Monte Carlo simulation (Lorance & Wendy, 1999), (Clark, 2001)

• Influence diagrams (Diekmann & Featherman, 1998)

• Factor rating (Hackney, 1985; Oberlander & Trost, 2001)

• Regression Analysis (Merrow & Yarossi, 1990; Aibinu & Jagboro, 2002)

• Artificial neural network (Chen & Hartman, 2000; Williams, 2003)

• Theory of constraints (Leach, 2003)

• Risk Analysis(Touran, 2003a; Rashed, 2005; Gunhan& Arditi, 2007, Kaith

(2012)

Page 7: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

Literature Review- Theories

Dempster Shafer

Theory AP Dempster (1967) &

G. Shafer (1976)

Probability

Theory Gerolamo Cardano

(1657-game of Chance)

Fuzzy Set

Theory Nasir Zadeh (1965)

Decision Theory

Random variables, stochastic process and event.

Focused on goal-directed behavior in the presence of options

Uncertainties related to uncertainties, vagueness and ambiguity

Belief function allows one to base degrees of

belief for one question on the probabilities for

related questions- mass, belief and plausibility

Evidence is associated with multiple event at a

higher level of abstraction

In Summary:

• The process of cost contingency estimation needs further exploration.

• Previous studies have focused on how to improve errors in the existing deterministic methods at the expense of bringing out new ideas to overcome its unreliability.

• The need to introduce into the cost-risk equation a combinatorial matrix of qualitative and quantitative risk modelling in relation to detectability of risk factors and work sections

• These gaps have been addressed by undertaking an integrated risk studies using the FMEA and belief function of DST combination model

Page 8: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

Methodology-Philosophy

Realism Positivist

Approximation towards Idealism Facts and values are distinct

The rationale for using realism is that the varied bases for estimating

contingency Margins for construction project exist but the systematic

risk procedure to be adopted for the estimating process is lacking

The Positivist position was chosen with the belief that the intriguing

process of estimating cost contingencies could be explored further

through a systematic and cognitive approach

Page 9: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

METHODOLOGY- RESEARCH PROCESS

. Research Approach: Deductive: Application of

DST

Inductive: Develop CCM

Framework design

Testing and validation

Instrument:

Questionnaires

Distribution &

unstructured interviews

Research Design:

Cross-section:

observation of how cost

Contingency is

estimated in the industry

Data Gathering

Method

Primary and

Secondary Data

Research Strategy

Qualitative

(Interviews/

Content Analysis)

Quantitative methods

Sampling Method:

Kish (1965) & Clarke

(1998)

Findings and

Conclusion

Data Analysis:

Qualitative and

Quantitative

Page 10: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

Research Methodology (Data Analysis)

RQ Research Question Analysis Method Reasons

RQ1 How do construction professionals

allow for contingency margins in the

engineering and construction

industry

Univariate

Statistical

Analysis

To determine ethnographical

practices of Built Environment

professionals

RQ2 Why do practitioners adopted the

current methods to estimate cost

contingency

Content Analysis To evaluate the enterprise

environmental factors of built

environment professionals

RQ3 What is the level of knowledge of risk

management by Engineering and

construction professionals?

Content Analysis Measure risk orientation in the

built environment

RQ4 How can risk factors affecting project

cost contingency be categorised

qualitatively ?

Content Analysis Risk categorisatioin for a RBS

RQ5 Which risk factors significantly affect

project cost contingency

Multivariate

statistical analysis

FMEA

Qualitative Risk analysis for

further quantitative modelling

RQ6 Which construction work sections are

prone to high scope changes?

Multivariate

statistical analysis

FMEA

To measure risk severity and

impact of the various work

sections

Page 11: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

Research Methodology (Data Analysis)

RQ Research Question Analysis Method Reasons

RQ7 What is the approximate probability

of occurrence of the risk factors

affecting contingency margins?

Multi-variate

statistical analysis &

Risk Modelling

To assess the mass, belief

and plausibility of the

Dempster’s combination

RQ8 To what extent does the risk factors

associated with contingency

margins, financially impact the

project?

Multi-variate

statistical analysis &

Risk Modelling

To determine probability

impact matrix for the

Dempster’s combination

RQ9 What risk management process

should one follow in the

determination of an adequate

contingency margin?

Risk Modelling To determine a cohesive and

systematic method of

determining and evaluating

contingency drivers

RQ10 How can the process of cost

contingency estimation be

improved?

Risk Modelling To develop a frame framework

for the cost risk management

RQ11 What steps should be considered

when developing a model for the

determination of contingency

margins for construction projects in

Ghana?

Risk Modelling To validate and confirm a

systematic process for the

cost risk modelling

Page 12: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

ANALYSIS • Based on objective data source which is representative and free from bias, DST

calculus is estimated by means of mapping

m:2 Ω →[0,1]; With m(A) > 0 called the focal element.

• The function m is called the basic assignment and fulfills: ∑AϚΩm(A)=1

• Bel (A)= ∑AϚA; B≠ØΩ m(B) AND Bel (¬A) = 1- Pl (A), Pl (A)= 1- bel (¬A)

With bel (¬A)≤ pl (¬A)

• Where uncertainty is construed as the difference between pl (¬A) and bel (¬A)

Pl(A)= ∑A∩B≠Ø m(B)=1

• The measure of pl(A) is not understood as the complement of bel (A).

Only AϚΩ|m(A)>0≠Ø→bel (A)≤ pl (A)

• For any set of defined hypotheses, represented by a set Ω= a1, a2, a3

• 2Ω = Ø, h1, h2, h3, h1,h2 , h1, h3,, h2, h3 , h1,h2, h3, Ω

• Based on data entry and transfer, several algebraic equations were be generated

Y1= a1x1+b1x2+c1x3+d1x4+α1 ………………………………………………..(1)

Yn= a1xn+bnx2+cnx3+dnx4+αn ………………………………………………..(n)

• With the above frame of discernment, an m x n matrix would be deduced

Page 13: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

ANALYSIS • 71% of built environment professionals have no knowledge about risk management theories

and techniques.

• Only 7.07% of professionals had ever applied a risk management tool in practice

• There are no standardised methods for estimating cost contingency.

• Approximately 90.06% of respondents used deterministic tools based on self-intuition,

experience and organisational process asset to estimate cost contingency

• There are no coordinated and integrated national database on Engineering Projects

• Approximately 64% of the cost drivers were systemic in nature whilst projects specific risk

accounted for 36% of the risk impact.

• 8 out of the 31 Risk factors significantly affected the cost contingency and 4 work sections

were identified as prone to high scope changes.

• Based on categorisation, design and Economic risk had the highest likelihood of occurrence

• Design and financial risk had the highest financial impact

• Natural and financial risk had the highest Hideability

• The substructure and services had the highest likelihood of occurrence

• Services and finishes had the highest financial cost impact

• Substructure and services were the most hideable work sections

Page 14: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

ANALYSIS

• Based on the basic assignments of the DST combinatorial matrix, the likely cumulative financial impact of the most significant risk were determined.

• The estimated overall cost growth ranges from 13.1% to 17.88% using 4 work sections and 8 risk factors

Substructure

( 3.8%),

Finishes

( 2.8%),

Electrical

engineering

work (3.3%)

mechanical

installations

(3.2%)

Incomplete

scope

definition

(0.261%)

Changes in

scope

(0.242%)

Inflation and

micro

economic

instability

(0.176%)

Changes in

specification

(0.128%)

Delayed

payment

problems

(0.164%)

Differing site

conditions

(0.171%)

Page 15: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

.

.

ANALYSIS: CONCEPTUAL COST RISK EVOLUTION PROCESS

Page 16: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

.

.

ANALYSIS: INFORMATION FLOW FOR IMPLEMENTED RISK MODEL

CLIENT BREIF

CONCEPT FORMATION

FEASIBILITY STAGE

PROJECT INITIATION

PRELIMINARY DEFINITION STAGE

DETAILED DESIGN/SCOPE DEFINITION

DESIGN MANAGEMENT

DESIGN DOCUMENT

DESIGN REVIEW

CONTRACT STRATEGY

PROJECT CHARTER

COST PLANNING

COST FORCASTING

COST ESTIMATE

COST BUDGETING

DETAILED DESIGN/SCOPE DEFINITION

COST MODELLING

FINANCIAL TREATMENT

COST RESERVE

PROJECT PLANNING STAGE

RISK IDENTIFICATION

QUALITATIVE RISK ANALYSIS

QUANTITATIVE RISK ANALYSIS

FINANCIAL IMPACT

RISK RESPONSE PLANNING

RISK UPDATE REVIEW

ENDOGENOUS

EXOGENOUS

SYSTEMIC

PROJECT SPECIFIC

INPUT PROJECT PHASE

RISK MANAGEMENT PROCESS OUTPUT

RISK EVALUATION

RISK QUANTIFICATION

Page 17: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

TESTING AND VALIDATION OF MODEL

. This was to verify the usability and

reality of the model results obtained

based on the Evidential reasoning

Theory. Users propounded their own

basic belief assignment and defined

their own hypothesis

PILOT TESTING OF

MODEL FOR QS, COST

ENGINEERS & PM

• Data of completed project was used

• Planed contingency and Actual Contingency.

• Actual average of cost overruns was 49.61%

with ranging from 1.62% to 332.52%. With Most

of the values higher than the modal figures

• An average of 5.1% had 10% contingency

• Another 76.5% had 26.43%, with the rest higher

• The modal contingency was 17% with a range of

8% to 29%.

• Comparing actual cost to model figures were

very close with variability of 0.5% to 5.25%

VALIDATION OF

MODEL

• An action research

method

• A focus group of 12

QS & CE was used

for the validation

exercise

Page 18: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

DISCUSSIONS OF THE STUDY RESULTS

Research Findings Deductions from the Results

RF1: Most professionals and respondents in the industry

used deterministic tools based on self-intuition, experience

and organizational process asset

RF2: There are not standardised tools or methods to be

adopted. No National historical data on cost

This could be attributed to the lack of

coherent methods of determining cost

contingency.

Practitioners may adopted the easier way

of determining the cost contingency

RF3: Most built environment professionals have no

knowledge about risk management theories and

techniques, only an insignificant proportion have ever

applied a risk management tool in their professional

practice

The background training of the

professional has resulted in the use of

unreliable methods resulting in project cost

overruns.

Guestimating and deterministic models

may be the only option in practice with

unreliable project output

RF4: Risk factors may be categorised based on orientation

in the RBS as drivers.

RF5: Based on FMEA, Scope related design risk had the

highest Risk Priority categorisation. This was followed by

economic, financial risk and technical risk.

A cogent risk breakdown structure may be

the first step to cost risk estimation

Risk identification using brain storming

and Delphi techniques, an effective

qualitative and quantitative method

required

Page 19: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

DISCUSSIONS OF THE RESULTS

Research Findings Deductions from the Results

R6: Using FMEA, 4 work sections were identified as prone to

high scope changes. These are Substructure, Electrical and

Mechanical installations and Finishes.

Critical review of scope definition

and Integrated Design

management may be considered

RF7: Design and Financial risk accounted for the highest

probability of occurrence of cost risk driver affecting cost

contingency

RF8: Design risk had the highest risk impact categorisation

followed by financial risk. Systemic risk had the highest

Financial Impact Matrix

The need to review the effect of

systemic risk on project cost

overruns

An effective Risk response

planning process required to

mitigate the effect of these risk

RF9: Qualitative Risk analysis using FMEA and

Quantitative risk analysis using DST by means of probability

impact matrix

RF10: Conceptual cost risk evolution onions was developed

following risk management planning, Risk identification;

qualitative risk planning, quantitative risk analysis, risk

response planning, risk review, risk update

The impact of financial risk may

be mitigated through risk

modelling

The use of the DST was exploited

Page 20: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

DISCUSSIONS OF THE RESULTS CONT Relationship of Research Findings to Other Research

.

RESEARCH

FINDING

PREVIOUS RESEARCH CORRELATION BETWEEN PREVIOUS

RESEARCH

RF 1,2 & 3 Gunhan and Arditi (2007); Estimating contingency

margins for construction projects using percentages

Ford (2002): there is no evidence of formal standardized

models for estimating Cost Contingency

There are no formal process of estimating project

cost contingency contingencies in Ghana

Practitioners use deterministic models

RF 4 & 5 Rifat et al (2007): established that differing site

conditions, safety, defective design, changes in work,

delayed payment of the contractor, and quality of work

as the high important risk factors.

Burroughs & Juntima (2004) established project

definition, use of technology, process complexity,

contracting and execution strategy, equipment

percentage

31 risk descriptors categorised into 8 risk

groupings. Key risk factors affecting project cost

contingency are scope and design related .

Systemic risk significantly affected cost overruns .

Substructure the key project specific risk indicator

RF 6 Kim, An & Kang (2004) established that Gross floor area,

storeys, total units, duration, roof types, foundation type,

basement, finishing grade affected cost growth

Using the FMEA, the work section prone to high

scope changes are substructure, services and

finishes

RF 7 & 8 Ali (2005) modeled cost contingency using probability,

Monte Carlo simulation and triangular cost distribution by

integrating the floor Area per building component

Design and financial risk has the highest likelihood

and impact. Environmental and natural risk was

the most difficult to detect

RF 9,10,11 Keith (2007) proposed with various tools, a risk

management framework of risk identification, risk

analysis, risk mitigation and plan, risk allocation and risk

monitoring and control for the risk cost risk management

process

A 7-step risk management process was

developed using the Dempster combination rule.

The Mass belief and plausibility of the various

work sections and risk were determined for the

purpose of the Cost contingency model

Page 21: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

CONCLUSIONS AND SUMMARY Research Objective Research Finding Research Implication

1. Identifying and documenting the

current methods adopted by

construction professional in the

determination of project cost

contingencies

There is no structured models or prescriptive

methods adopted except for their reliability on

historical data, organizational process asset and

reliance on expert knowledge

PRACTICE: The findings can contribute to

restructuring of the curricula for higher

education in Ghana and CPD orientation by

the professional bodies in Ghana

2. Identify rate and rank the most

significant factors that affect

contingency levels of construction

projects

Systemic risk factors were identified to have the

highest severity affect the cost contingency. These

are mainly design, scope, economic risk. Natural

risk had highest pproject specific indicators

POLICY: The result can contribute to the

need for the establishment of Construction

Industry Regulatory body in Ghana

3. Determine the works sections that

are prone to high scope changes and

likely impact of these changes

Substructure, services and finishes were identified

as work sections which were prone to high scope

changes

PRACTICE: it would serve as a driver for an

enhanced design management effort for Built

environment professionals

4. To estimate the likely probability

of occurrence and financial impact of

the combined risk factors and work

sections using evidential reasoning

methods.

Using FMEA and DST, basic belief assignments

were developed, with mass and plausibility. Design

and Economic risk had the highest likelihood of

occurrence and severity impact Substructure,

finishes and services had the highest likelihood and

impact

THEORY: The findings can form a basis for

theoretical partitioning of the cost risk drivers

based on the Dempster’s combination

5. Develop, document and validate a

conceptual framework for

construction cost contingency

estimation.

A matrix of the risk factors matched with work

sections based on the basic belief assignments was

developed. Forthwith, multi-stage CCC risk

management model was developed for the purpose

of cost contingency estimation

PRACTICE: The findings can serve as a

basis for regulating risk and actuarial studies

on project prior to commencement by

Engineering and designs actors

6. Develop a computer based model to

test the practicability of the

conceptual framework for

construction cost contingency

estimation.

A Cost Contingency model, PROCOM Model was

developed and tested and be could be accessed via

www.costcontingencycalculator.com

PRACTICE: these could help review the

Cost contingency estimation method by using

basic belief functions

Page 22: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

CONTRIBUTION TO KNOWLDGE. The GAPS in knowledge have been filled by the study as follows:

• It has filled a theoretical gap by providing a structured method of determining cost risk for

construction projects • A tabulated financial impact of various risk and their indices has as well been developed

as a guide during cost contingency estimation. The research has filled the gap in term of the extent of contingency definition a professional can influence in the form of systemic risk.

• Using evidential reasoning, an innovative model has been developed for the estimation of construction cost contingency with much variability. This uniquely models the likelihood, impact and detectability of risk factors using FMEA and DST. The matrix of the major risk factors and work section have been combined to develop basic belief assignments. To enhance uniformity of the model, the key characteristics of the construction industry was used as permissible parameters. Users would be required to input a set of hypothesis based on their belief and pieces of evidence based on risk and work section. This method provides a higher level of detail and reliability in the risk definition of contingency estimating

• The estimated cost of contingency for a project may not necessarily 10% but depending on the project design definition and risk parameters being modeled. Analysis of field studies with qualitative and quantitative risk analysis revealed an approximate cost contingency range of 13.1% to 17.88%, this could be higher or lower depending on the extent to systemic risk could me managed. Thus the above accounts for the high cost growth, project failure and system engineering failure in most Engineering projects.

• An innovative model has been proposed, tested and validated for cost contingency definition based on the degree uncertainty such as known known, known unknown, unknown unknown. Again the work redefined contingency in terms of categorization as: construction, design, management or financial contingency.

Page 23: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

7 NUMBER SCIENTIFIC PUBLICATIONS .

SP1 Buertey, J. T.I, Abeere-Inga, E., Adjei Kumi, T. (2012). Construction cost contingency

estimating in Ghana: a review of work sections prone to scope changes, International

Journal of Management, Volume 3, Issue 1, pp. 237-253. ISSN 0976 – 6367(Print), ISSN

0976 – 6375(Online)

SP2 Buertey, J. T.I, Abeere-Inga, E, Adjei Kumi, T. (2012), Practical application of risk

management techniques in infrastructural delivery: a case study of the Ghanaian

Construction Industry. Journal of Construction Project Management and Innovation, Vol 2,

No. 1, ISSN 2223 7852

SP3 Buertey, J. T.I, Abeere-Inga, E., Adjei Kumi, T. (2012), Estimating cost contingency for

construction projects: the impact of systemic and project specific risk. Journal of

Construction Project Management and Innovation, Vol 2, No. 1, ISSN 2223 7852

SP4 Buertey, J. T.I, Abeere-Inga, E.; Adjei Kumi, T. (2012). Successful delivery of Infrastructural

Projects: Epistemic overview of cost risk and uncertainties, Journal of Civil Engineering and

Architecture, ISSN 1934-7359, Volume 6, No. 2 (Serial No. 51), pp. 121–131, USA

SP5 Buertey, J. T.I, Abeere-Inga, E.; Adjei Kumi, T. (2012). Project Cost contingency estimation

in Ghana, an integrated Approach. Science Journal of Civil Engineering and Architecture,

ISSN, 227-6332

SP6 Buertey, J. T.I, Abeere-Inga, E.; Adjei Kumi, T. (2013). The financial impact of risk factors

affecting project cost contingency: evidential reasoning method. (Journal of Engineering,

Project, and Production Management). ISSN 2221-6529 (Print), ISSN 2223-8379 (Online)

SP7 Buertey Joseph Teye (2014), Project Cost Risk and Uncertainties: Towards a Conceptual

Cost Contingency Estimation Model, International Journal of Construction Engineering and

Management 2014, 3(5): 144-155 DOI: 10.5923/j.ijcem.20140305.02

Page 24: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

5 NO. CONFERENCE PAPERS .

CP1 Buertey, J. T.I, Abeere-Inga, E.; Adjei-Kumi, T. Successful Delivery of Infrastructural

Projects: Epistemic Overview of Cost Risk and Uncertainties, Proceedings of 1st

International Conference on Infrastructure Development in Africa at KNUST, Kumasi,

22nd – 24th March 2012

CP2 Joseph T.I. Buertey, T. Adjei-Kumi: “Modelling cash flow prediction in Ghana: A Case

Study of the District Assembly Common Funded Projects”. West Africa Built Environment

Conference, University of Reading. 27th- 28th June 2010

CP3 Buertey, J. T.I, Abeere-Inga, E.; Adjei-Kumi, T. Successful Delivery of Infrastructural

Projects: Epistemic Overview of Cost Risk and Uncertainties, Proceedings of 1st

International Conference on Infrastructure Development in Africa at KNUST, Kumasi,

22nd – 24th March 2012

CP4 Buertey, J. T. I, Abeere-Inga, E.; Adjei-Kumi, T, Project cost risk and uncertainties:

towards a conceptual cost contingency estimation model. Proceedings of WABER 2013

Conference in Accra, Ghana, British Council, 12th-14th August 2013

CP5 Buertey J.T.I (Accepted). A conceptual cost contingency estimation model: a risk

modelling approach. Accepted for presentation at the West Africa Built Environment

Conference, 10th -12 August 2015 at the University of Ghana

Page 25: OPEN UNIVERSITY OF MALAYSIAait-open.net/elearning/file.php/1/RESOURCE/Joseph... · 2016-06-25 · open university of malaysia phd viva voce by joseph teye ignatius buertey bsc., msc.

.

THANK YOU


Recommended