Wilkes Elementary School Bainbridge Island School District. Opened: 2012 Gross Square Feet: 70,509 Construction Bid: $21,359,000 Construction Final Cost: $21,714,411 Cost per Square Foot: $308 Architect: Mahlum General Contractor: Spee West Construction. - PowerPoint PPT Presentation
Popular Tags:
8
Wilkes Elementary School Comparable Schools from Neighboring School Districts Opened: 2012 Gross Square Feet: 70,509 Construction Bid: $21,359,000 Construction Final Cost: $21,714,411 Cost per Square Foot: $308 Architect: Mahlum General Contractor: Spee West Construction Wilkes Elementary School Bainbridge Island School District
Transcript
Page 1: Opened:   2012 Gross Square Feet:   70,509 Construction Bid:  $21,359,000

Wilkes Elementary School – Comparable Schools from Neighboring School Districts

Opened: 2012

Gross Square Feet: 70,509

Construction Bid: $21,359,000

Construction Final Cost: $21,714,411

Cost per Square Foot: $308

Architect:Mahlum

General Contractor:Spee West Construction

Wilkes Elementary SchoolBainbridge Island School District

Page 2: Opened:   2012 Gross Square Feet:   70,509 Construction Bid:  $21,359,000

Wilkes Elementary School – Comparable Schools from Neighboring School Districts

Opened: 2012

Gross Square Feet: 76,950

Construction Bid: $22,349,000

Construction Final Cost: $22,838,769

Cost per Square Foot: $297

Architect:NAC Architecture

General Contractor:Bayley Construction

Cherry Crest Elementary SchoolBellevue School District

Page 3: Opened:   2012 Gross Square Feet:   70,509 Construction Bid:  $21,359,000

Wilkes Elementary School – Comparable Schools from Neighboring School Districts

Opened: 2011

Gross Square Feet: 70,370

Construction Bid: $20,045,867

Construction Final Cost: $21,355,894

Cost per Square Foot: $303

Architect:NAC Architecture

General Contractor:Graham Construction

Machias Elementary SchoolSnohomish School District

Page 4: Opened:   2012 Gross Square Feet:   70,509 Construction Bid:  $21,359,000

Wilkes Elementary School – Comparable Schools from Neighboring School Districts

Opened: 2012

Gross Square Feet: 66,580

Construction Bid: $20,674,700

Construction Final Cost: $21,720,911

Cost per Square Foot: $326

Architect:NAC Architecture

General Contractor:Spee West Construction

Carl Sandburg Elementary SchoolLake Washington School District

Page 5: Opened:   2012 Gross Square Feet:   70,509 Construction Bid:  $21,359,000

Wilkes Elementary School – Comparable Schools from Neighboring School Districts

Opened: 2008

Square Feet: 56,506

Construction Bid: $16,100,000

Construction Cost: $17,500,000

Cost per Square Foot: $310

Architect:Integrus Architecture

General Contractor:Kassel Construction

Rachel Carson Elementary SchoolLake Washington School District

Page 6: Opened:   2012 Gross Square Feet:   70,509 Construction Bid:  $21,359,000

Wilkes Elementary School – Comparable Schools from Neighboring School Districts

Opened: 2008

Square Feet: 55,000

Construction Bid: Not available

Construction Final Cost: $19,500,000

Cost per Square Foot: $355

Architect:Bassetti Architects

General Contractor:Sellen Construction

St. Thomas SchoolMedina, Washington

Page 7: Opened:   2012 Gross Square Feet:   70,509 Construction Bid:  $21,359,000

Wilkes Elementary School – Comparable Schools from Neighboring School Districts

Opened: 2013

Square Feet: 67,250

Construction Bid: $23,765,374

Construction Cost:$24,873,086

Cost per Square Foot: $370

Architect:Integrus Architecture

General Contractor:Mortenson Construction

Benjamin Rush Elementary SchoolLake Washington School District

Page 8: Opened:   2012 Gross Square Feet:   70,509 Construction Bid:  $21,359,000

Wilkes Elementary School – Energy Consumption Comparison

Old School New School

2010 2013

Comparative Period Nov. 6-Dec. 7 Nov. 6-Dec. 7

PSE KWH 41,852 72,600Propane KWH 71,315 0

Total Monthly KWH 113,167 72, 600

Invoice Amount PSE $4,700 $9,320Invoice Amount Propane $4,348 0Total Invoice Amounts $9,047 $9,320

Heated Square Footage 44,958 63,462 Cost per Square Foot $ 0.201 $0.147

Today’s Relative Cost $14,528 $9,320

= Percent Savings 36%

Wilkes Elementary SchoolENERGY CONSUMPTION COMPARISON


Recommended