CHALLENGES IN DESIGN & MAINTENANCE OF TRACK STRUCTURE
FOR MIXED TRAFFIC REGIME ON IR
- Vipul Kumar, ED/Track-I- Ajay Kumar, Director/Track-II
RDSO
INTRODUCTION
Operation upto 25 t axle load at 100 kmph in mixed traffic regime is being envisaged by IR.
These operations shall be on the same track having/planned for semi high speed passenger operation.
Further, some of the routes are being planned for upgradation to 200 kmph passenger operations
SEMI HIGH SPEED OPERATIONSBasic Requisites from Track
1. Much more accurate track geometry in comparison to that for 110-120 kmph to provide at least same degree of ride comfort and stability to stocks
2. Considerable reduction in rail-weld failures ( should preferably be zero) as these may lead to devastating consequences at higher speeds
Basic requirements of rolling stock
Small track - vehicle interaction force/accelerations• responsible for distortion of the track geometry and effecting
fatigue failures of rails and welds
i.e. Track friendly design in line with international standards
UIC Leaflet 724-R
(track equipment for 25t axle load on ballasted track) International study and literature indicate that - Best way to decrease the deteriorating effects on track when operating
with high axle load is through reduction in dynamic wheel loads
Pre-conditions for reducing dynamic wheel loads include:- Good track geometry quality- Adapted speed- Good wheel quality- Track friendly vehicle design However, there are limitations as regards to maintenance of good
track geometry and good wheel quality. So, the track friendly vehicle design becomes most important factor
REQUIREMENTS FOR HEAVY AXLE LOAD WAGON
Comparison Of Acceptance Criteria (Freight Stocks)
SN Parameters IR Limits UIC-518/EN-14363 Limits British Standards
1 Vertical acceleration Not specified 0.5g 0.25g (mean)
0.44g (max.)
2 Lateral acceleration Not specified 0.3g 0.2g (mean)
0.33g (max.)
3 Vertical Ride Index 4.5 NA 4.25 (mean)
5.0 (max )4 Lateral Ride Index 4.5 NA
5Track loading Limit
(Q lim) – track fatigue criteria
Not Specified ( 90 + Q0 )
Max 210 KN Not Available
6 Lateral Force (Hy2m)
0.85(1+P/3) t P=axle load
0.85(10+Po/3) kN Po=axle load
0.85(1+2Q/3) t 2Q= nominal wheel load
Problems With Existing Heavy Axle Load Designs Track loading (dynamic forces on rail ) are not known
High acceleration values much beyond the international norms• High vibrations imparted to track in the high stress state due to
high axle load causes increased incidences of fatigue as well as sudden failures
Smaller wheel dia : • higher contact stress, increased rate of surface crack propagation• increased risk of fatigue failure• Increased cycles of impact on track in case of wheel flat/deformed wheel, increasing chances of failure when coupled with track & other vehicle defects of higher degree
Acceleration values of existing stocks25 T AXLE LOAD WAGONS
LOADED CONDITIONWAGON SPEED MAX LAT.ACC (g) MAX.VER. ACC.(g) C&M-I
VOL-I Or OTHER
REPORT NO. REMARKS
Detailed run
Long run
Detailed run
Long run
BOBSNM1 60/80 0.48 0.65 0.45 0.49 Other 726/2006
BOXN 25M 125 0.23 0.25 0.69 0.81 C&M-I 1217/2012 (i) UN-A0 (ii) 2 degree curve at 80kmph
BLC 25M 125 0.21 0.25 0.47 0.51 C&M-I 1288/2013 UN-A0, TW-A0, AL-A0
BOXNHL 25T 85 0.51 0.38 0.36 0.41 Other 1427/2015
0.47 0.4 0.42 0.37 Other
BOXNEL 90 0.66 0.31 0.72 0.65 Other 1437/2016
BOYEL 90 0.74 0.57 0.73 0.76 Other 1439/2016
BOXNS 100 0.19 0.42 0.76 0.87 Other 1463/2016
Acceleration values of existing stocks22.9 T AXLE LOAD WAGONS
LOADED CONDITIONWAGON SPEED MAX LAT.ACC (g) MAX.VER. ACC.(g) C&M-I
VOL-I Or OTHER
REPORT NO. REMARKS
Detailed run
Long run Detailed run
Long run
BOXNHL 110 0.64 0.66 0.78 0.73 C&M-I 929/2009
BOXNHL (PU TYPE CCSB PAD)
110 0.53 0.47 0.45 0.41 C&M-I 936/2009
BCNHL 110 0.48 0.57 0.57 0.61 C&M-I 1007/2009
BOXNHL (Series 1)
85 0.23 0.31 0.56 0.56 Other 1341/2014
BOXNHL (Series II)
85 0.25 0.33 0.5 0.64 Other 1342/2014
Effect Of Increased Axle Load Studies reported in ORE, D/141/RP 1:
For increase in axle load from 20t to 22t, the fatigue failure in rails will increase based on the relative increase in mean axle load raised to a power of 3 to 4
- for increase from CC to CC+ 8+2 loading - It culminates into 40-60% increase in fatigue failure of rails
- Further increase from 22.9 t to 25 t - the expected further increase in fatigue failure of rails may be 30-40%
Studies reported in ORE, D/141/RP 5: 10% increase in axle load – increase in maintenance cycle by 33 % Study by ZETATECH Ass 10% increase in axle load may cause damage to track higher by 20%
Experience Of Heavy Axle Load Operation On IR Operation of 22.9t at 75 kmph & limited operation of 25t at 50 kmph
Based on limited data captured and provided by ECOR, SCR & SECR , the track related issues may be summarized as under:
• Excessive wear in switches and crossings• Crossing zone requires frequent packing• CMS crossings required frequent replacement/repair • Excessive wear of outer rails of curve and flattening of inner rails• Increased cases of glued joint failure and fish plate fracture• Stretches on weak formation/black cotton soil causing frequent ballast
puncture resulting into abrupt cross level variation• Fish plate of stock rail joints getting battered, leading to failure of fish
plates
Experience Of Heavy Axle Load Operation On IRK – K Line9944 no. of 25t axle load trains in 9 years- approx 1100 trains/yearGMT of the section is 25substantial increase in rail /weld failure under heavy axle load
Year No of 25 t axle load trains
Total RF + WF
Year No of 25 t axle load trains
Total RF + WF
2008 - 09 829 3 2012 - 13 1843 82009 - 10 832 7 2013 - 14 1997 182010 - 11 796 11 2014 - 15 1398 572011 - 12 1134 12
Experience Of Heavy Axle Load Operation On IR
South East Central Railway
Total 222 IMR detected in Bilaspur division in the year 2014-15
• 100 IMR were detected in the 1st round i.e. without being classified as OBS in previous round
• 112 IMR upgraded from OBS
• In spite of above detection, 138 rail fractures
• The trend is almost same in 2015-16
The rate of detection of IMR and rail fracture in the route under operation of CC+8+2 loads is too high
Issues In Heavy Axle Load Operation On IR
(A) Issues in design of track structure Most critical parameters for track design i.e. Track loading is not
known• Design with old data of obsolete wagons measured at lower
speed and on different track structure
Even with these old values• rail stress in 60 kg/90UTS rails are exceeding the limits at 100
kmph for 25t axle load• close to limit at 75 kmph The wagon having reduced wheel diameter (780mm
condemning)• Higher contact stress on rail – increased rate of surface crack
propagation
Issues In Heavy Axle Load Operation On IR
(A) Issues in design of track structure
High DA permitted during operation - Critical WILD alarm at 35t ( 280% DA for 25t axle load)
• rail stress of 55.28 Kg/mm2 against the permissible limit of 46.8 Kg/mm2 in 60 kg/90 UTS rail
• No track structure can be designed for such high dynamic load
High values of accelerations of present heavy axle load wagons; • high vibrations imparted to rail under high stress condition,
reduced fatigue life, increased chances of fatigue and sudden failures
Issues In Heavy Axle Load Operation On IR
(B) Major issues in operation Indiscipline in zonal railways in monitoring and remedial action on impact loading on track
• Meagre availability of WILDs – no monitoring of 90% of loads
• Poor response of zonal railways on WILD alarms – hardly 7 to 8% detachment
• Alarms up to 50 t are generally ignored and allowed to run
• Instantaneous wheel load upto 59t (DA – 400%) are recorded – indicating poor maintenance
Limitations: 60 kg rail has safety limit of approx. 21t, AT welds are having even less
Issues In Heavy Axle Load Operation On IR(B) Major issues in operation Poor monitoring of overloading and corrective action by zonal
railways Inadequate powering – stalling, damage to rail
Impact: Unusually high number of rail fractures and IMRs as reported in BSP division, KK line - enormous cost of replacement and track down time, safety hazard
Issues In Heavy Axle Load Operation On IR(B) Major issues in operation Required enhanced maintenance blocks and resource
But the situation is grim – corridor blocks have vanished, severe resources constraints putting lot of pressure on infrastructure
maintenance arrears, in-service failures, passengers safety at risks, downtime
Problem of corrosion of rails and fastenings due to human excreta from coaches
reduced sectional area at critical locations as foot, sudden breakage of rail
CONCLUSION & WAY FORWARD
Increase in through-put with increased axle loads and introducing semi-high speed on the same track can be justified to cater to the needs of ever burgeoning population, assuming certain risks.
Mostly, these risks are associated with the high rail-wheel forces.
Keeping the rail-wheel forces low is the only way for economically sustainable heavy axle load operations along with safer semi-high speed passenger operations.
CONCLUSION & WAY FORWARD For reducing these risks, various elements and regime of
heavier axle loads and semi-high speed operations needs to be conceived and implemented meticulously. Main elements are
• Proper design of track structure - needing real time measurement of dynamic forces on track
• world class freight suspension system with limited dynamic loading
• Regime of clearing rolling stocks in line with international std- in order to ensure that rolling stock passes through the track
with worn out limits having low dynamic forces
CONCLUSION & WAY FORWARD• Enhanced monitoring and maintenance of rolling stocks: - way side monitoring equipment, Installation of WILD at all important/specified
locations required
• Enhanced monitoring and maintenance of track: - high speed TRC, Vehicular USFD, Broken rail detection system,
completely mechanized maintenance
• Timely maintenance and replacement of both aged rolling stock and fixed infrastructure
• Well laid maintenance regime: 4 hrs corridor block, enhanced funds and material arrangement, better mobility (MMU, RCRV etc)
THANKS