Lubrication of Fasteners
NO OK: During Assembly of Nacelle & Rotor Bolts Lubrication of Fasteners were done, but only a portion of threads was covered with Lubrication oil.
OK: As per Assembly procedure EA2000001-R4 the entire friction area of the fastener needs to be lubircated.
Thread portion not Lubircated Completely
Thread portionLubircated Completely& Uniformly
3/3 IBE-1-006-R01Ed 2
8/12/2011
X
One Point LessonLeccion Puntual
SUBJECTTEMA
DateFecha AUTHOR
AUTORLesson NºLección Nº
Area who makes the OPL / Área que realiza la LP
S: SafetySeguridad
E: Environ menntMedio Ambiente
Q: QualityCalidad
SO: SupportSoporte
Lubrication of Fasteners
Date / Fecha: Instructor / Instructor:
RecipientsReceptores
Date / Fecha: Instructor / Instructor:
RecipientsReceptores
NO OK: During Assembly of Nacelle & Rotor Bolts Lubrication of Fasteners were done, but only a portion of threads was covered with Lubrication oil.
OK: As per Assembly procedure EA2000001-R4 the entire friction area of the fastener needs to be lubircated.