Ops. AGENDA
• Status of open Action ItemsMetcalfe
• Science Operations Status Metcalfe
• Instrument Operations Buenadicha
• EPIC MonitoringStuhlinger/Smith
1Science Operations & Data Systems Division Research & Scientific Support Department
Page 1
XMM-NewtonXMM-Newton
Meeting/action Status Subject Actionee Due
EPIC TTD-0014/3 Open Explain increases in pn offset variance in the 840 M. Smith 2005-03-03 to 870 plus revolution range
EPIC TTD-0014/5 Open Provide an agenda draft for a hypothetical OBSW G. Buenadicha 2005-03-03 contract meeting addressing all concerns raised
during the presentation EPIC TTD-0014/9 Open Make MOS2 CCD5 effect public M. Stuhlinger 2005-03-03 EPIC TTD-0015/2 Open Identify what is needed for testing and preparing M. Casale 2005-11-03
for the use of redundancies EPIC TTD-0015/3 Open Subsequently to evaluate and decide which of the A. Abbey 2005-11-03
items resulting from action 15/2 can be delivered
EPIC TTD-0016/1 Open Investigate the possibility of MOS small window A. Abbey 2006-05-29 mode in peripheral ccds M. Casale
EPIC TTD-0016/2 Open Provide SOC with the sequence for MOS extended A. Abbey 2006-05-29 small window mode.
2Science Operations & Data Systems Division Research & Scientific Support Department
Page 2
XMM-NewtonXMM-Newton
ACTIONS
SCIENCE OPERATIONS STATUSfor
EPIC TTD MEETING
PALMA de MALLORCA
26 October 2006
L. Metcalfe SCI-SDX
XMM-Newton Science Support Manager
3Science Operations & Data Systems Division Research & Scientific Support Department
Page 3
XMM-NewtonXMM-Newton
CONTENTS
• Significant meetings and dates
• Operations: Status & Modes
• General Calibration Points
• Data Processing - SSC
• Miscellaneous
4Science Operations & Data Systems Division Research & Scientific Support Department
Page 4
XMM-NewtonXMM-Newton
SIGNIFICANT MEETINGS
AND
DATES
5Science Operations & Data Systems Division Research & Scientific Support Department
Page 5
XMM-NewtonXMM-Newton
SIGNIFICANT MEETINGS
• Users Group Meeting #7 18/19 May 2006
• SAS Workshop 2006 30 May-02 Jun. 2006
• ICWG meeting, Iceland 14-16 Jun. 2006
• Variable & Broad Fe Lines around Black Holes 26-28 Jun. 2006
• EPIC Background Working Group @ Palma 25 Oct. 2006
• EPIC Cal./Ops. Meeting @ Palma de Mallorca 26-27 Oct. 2006
• SSC Consortium Meeting @ Potsdam 13-15 Nov. 2006
(incl. SAS Wk. Group Meeting)
• OM Cal. & TTD meeting @ ESAC late 2006
• EPIC Cal. Workshop @ ESAC 18-19 Jan. 2007
• Inter-mission X-ray cross-calibration 08-11 May 2007
Intnl. Working Group on cross-cal. & the defn. of X-ray standards no.II.
• ESAC Science Workshop 2007: Legacy Science modes 04-06 Jun. 2007
• Users Group meeting #8 07-08 Jun. 2007
• SAS Workshop 2007 18-21 Jun. 2007
SIGNIFICANT DATES I
Proceedings of 2005 conference (“The X-ray Universe 2005”)
• Distributed Mar. 2006
Calibration
• Progress, especially with RGS (t dept.) vs EPIC, at UG#7 May 2006
• EPIC Background Working Group tools Apr. & June 2006
SAS
• SAS 7.0 release (+ RGS vs EPIC cal. Improvements) 30 June 2006
• to be used for the reprocessing
7Science Operations & Data Systems Division Research & Scientific Support Department
Page 7
XMM-NewtonXMM-Newton
SIGNIFICANT DATES II
XSA
• XSA 2.9 Querying other Archives Apr. 2006
• XSA 3.0 Release of the Slew Survey Catalogue 03 May 2006
• XSA 3.5 2XMM-beta 28 Aug. 2006
2XMM-beta
• Released by SSC 24 July 2006
• and through XSA 3.5 28 Aug. 2006
8Science Operations & Data Systems Division Research & Scientific Support Department
Page 8
XMM-NewtonXMM-Newton
SIGNIFICANT DATES III
AO6 Call
• AO6 Call 28 Aug. 2006
• Closed Phase I 06 Oct. 2006
595 valid proposals yielding an over-subscription of 6.91
• Open phase II 15 Jan. 2007
• Close XRPS 09 Feb. 2007
• Begin AO6 observations May 2007
9Science Operations & Data Systems Division Research & Scientific Support Department
Page 9
XMM-NewtonXMM-Newton
OPERATIONS
10Science Operations & Data Systems Division Research & Scientific Support Department
Page 10
XMM-NewtonXMM-Newton
STATUS and MODES
All instruments essentially stable
Slew Mode tests on rev.1242 (Sept.19-21) went well
essentially ready with EPIC (pn & MOS) and RGS instruments
but SOC systems need to handle slew scheduling less manually
also OM mode
RGS2 ADC-problem glitch
now better understood
see dedicated splinter on contingency preparation
Slewing / re-pointing ‘mode’ for RGS !
implementation requirements/plan by end-year ??
APOGEE GAP & SANTIAGO COVERAGE
Santiago provided coverage across Kourou-Perth gap
• allowed continuous coverage throughout complete revolution
Gap shrinking through years & closes by end 2007
By end 2006:
• the gap in telecommanding is as little as 35 minutes
• and telemetry gap totally disappeared
Decided to discontinue Santiago as of 1 Dec. 2006
Plot shows evolution of apogee gap from 2006 to 2010
13Science Operations & Data Systems Division Research & Scientific Support Department
Page 13
XMM-NewtonXMM-Newton
In the graph the TC gap on 01/12/2006 is ~1300 sec (22 min) to which a little margin (say 10 min) is added for acquisition of signal, carrier sweeping, etc.
APOGEE GAP & SANTIAGO COVERAGE
In the 810 revs. from 450 to 1259 there were 5 cases of instrument
closure due to soft protons (detected by the instruments themselves)
at the time of the Santiago pass around apogee -/+ 2 h
1) Rev-614 : instruments were closed for 35 min
2) Rev-621 : instruments were closed for 2 h 20 min
3) Rev-628 : instruments were closed for 20 min
4) Rev-873 : instruments were closed for 1 h 30 min
5) Rev-1149 : instruments were closed for 1 h 35min
The probability of having an alert at that point in the revolution is, for the
period considered, about 0.62 % (note also that three cases were very close
together in rev-614 to 628 due to exceptionally high solar activity, so this
could actually bias a bit the statistics and make it slightly worse).
14Science Operations & Data Systems Division Research & Scientific Support Department
Page 14
XMM-NewtonXMM-Newton
Science Operations & Data Systems Division Research & Scientific Support Department
Page 15
XMM-NewtonXMM-Newton
Science Operations & Data Systems Division Research & Scientific Support Department
Page 16
XMM-NewtonXMM-Newton
Science Operations & Data Systems Division Research & Scientific Support Department
Page 17
XMM-NewtonXMM-Newton
Science Operations & Data Systems Division Research & Scientific Support Department
Page 18
XMM-NewtonXMM-Newton
Science Operations & Data Systems Division Research & Scientific Support Department
Page 19
XMM-NewtonXMM-Newton
Science Operations & Data Systems Division Research & Scientific Support Department
Page 20
XMM-NewtonXMM-Newton
Science Operations & Data Systems Division Research & Scientific Support Department
Page 21
XMM-NewtonXMM-Newton
Science Operations & Data Systems Division Research & Scientific Support Department
Page 22
XMM-NewtonXMM-Newton
GENERAL CALIBRATION POINTS
23Science Operations & Data Systems Division Research & Scientific Support Department
Page 23
XMM-NewtonXMM-Newton
CCF RELEASE NOTES IN PERIOD
XMM-CCF-REL-220 RGS1 CCD9 node1 CTIX scale factor 11 Aug 2006
XMM-CCF-REL-218 RGS cool pixels 29 Jun 2006
XMM-CCF-REL-217 RGS background spectra templates 28 Jun2006
XMM-CCF-REL-216 A new model for RGS effective area 29 Jun2006
XMM-CCF-REL-215 RGS per.-CCD sens. 2&3 order gr.eff. 29 Jun 2006
XMM-CCF-REL-214 Revision of the RGS CCD gains 27 Jun2006
XMM-CCF-REL-213 Evolution of the RGS CTI 29 Jun 2006
XMM-CCF-REL-212 Tuning RGS Instr. MgF2 abs. Mkn421 27 Jun 2006
XMM-CCF-REL-207 Update of EPIC MOS Gain 17 May 2006
XMM-CCF-REL-206 Update of EPIC MOS CTI 24 May 2006
XMM-CCF-REL-204 EPIC PN Bad Pixels 06 Mar2006
XMM-CCF-REL-203 Long term EPIC-pn CTI refinement 05 Apr 2006
NRCOs
59 RGS long- response & MOS CTI with Vela 2006-01-25
48 Refinement of pn-CTI corr. (follow-up NRCO 34) 2005-02-25
51 Establishing X-ray stdrds: RGS and RXJ 1856-3754 2005-04-20
54 The RGS response to the Crab X-ray standard 2005-08-23
55 RGS CTI calibration 2005-09-01
56 Verification of the EPIC high energy resolution 2005-11-11
57 Investigation of the random EPIC-pn gain scatter 2005-11-11
58 Verification of the EPIC-pn relative timing 2005-11-11
59 RGS long- response & the MOS CTI with Vela 2006-01-25
62 EPIC-pn Burst mode energy calibration refinement 2006-05-17
DATA PROCESSING - SSC
26Science Operations & Data Systems Division Research & Scientific Support Department
Page 26
XMM-NewtonXMM-Newton
Science Operations & Data Systems Division Research & Scientific Support Department
Page 27
XMM-NewtonXMM-Newton
Turn-around time between data acquisition and GO (PIPE) delivery as of 31-March-2006
MISCELLANEOUS
PUBLICATIONSOTHER …
28Science Operations & Data Systems Division Research & Scientific Support Department
Page 28
XMM-NewtonXMM-Newton
29Science Operations & Data Systems Division Research & Scientific Support Department
Page 29
XMM-NewtonXMM-Newton
Oct. 09 2006 1224
30Science Operations & Data Systems Division Research & Scientific Support Department
Page 30
XMM-NewtonXMM-Newton
XSA
31Science Operations & Data Systems Division Research & Scientific Support Department
Page 31
XMM-NewtonXMM-Newton