Tembikai Non-Associated Gas (TNAG) Pipeline Project
In March 2019 Vestigo Petroleum Sdn Bhd (VPSB) awarded Alam Maritim Sdn Bhd (Alam), in partnership with Cortez Subsea (Cortez) the Tembikai Nag (TNAG) pipeline system contract.
• New wellhead platform to be tied back to existing Berantai FPSO
• 58km 12-inch rigid pipeline
• 70m water depth
©2016 AFGlobal Corporation. All rights reserved.
QUICKER, SAFER,
CLEANER
Elastic strain and surface friction makes joints stronger that steel.
An expanded end is forcefully inserted into a ‘pin’ end to provide an
interference fit.
Lay 3.5 – 5km of pipeline per day resulting inless vessel time and reduced crew for a cost-effective approach, up to 30 per cent cheaperthan traditional methods.
A reduction on the reliance of vessels andman-power means we reduce our carbonfootprint.
This alternative to welding takes advantage ofsemi-automation to result in a safer workenvironment, free from hot-work andradiography.
Used on standard line-pipe 2” to 16” in up to 300m
water-depth.
Technologies – Zap-Lok™ Mechanical Connector
©2016 AFGlobal Corporation. All rights reserved.
Technologies – Stinger Deployed Diverless Connector
QUICKER, SAFER,
CLEANER
This application removes the need fordivers to connect the pipeline which canreduce the overall pipeline installationand tie-in costs by over 30%.
A reduction on the reliance ofvessels and man-power meanswe reduce our carbonfootprint.
This alternative to diving reduces the riskto our people.
Cortez and AF Global have jointly developed the
application of the diver-less connector for shallow water
pipeline tie-ins.
The pipelines are installed using mechanical
connectors and the tie-ins undertaken using the
diver-less connection in a deployment frame.
Using an ROV, the connection is made
from the pipeline to the host facility with flexible
pipe risers and flowlines.
©2016 AFGlobal Corporation. All rights reserved.
Technologies – Stinger Deployed Diverless Connector
Key Components
• Retlock™ Clamp
• Guidance System
• ROV Tooling
Installation Animation
©2016 AFGlobal Corporation. All rights reserved.
SDDC Installation Animation
Animation
©2016 AFGlobal Corporation. All rights reserved.
Challenging the Conventional
• Pipeline being installed now!
• Proven technologies used in different applications
• 20% cost saving compared to conventional diver installed pipeline
• Savings can be increased beyond 30% using construction vessel with Modular Pipelay System