21st Century Non-Paved Roads OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMS 2019 OGRA Conference Roozbeh Rashedi, Ph.D., P.Eng. VP-Technology, Infrastructure Solutions Inc.
Transcript
Page 1: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

21st Century Non-Paved Roads

OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMS

2019 OGRA Conference

Roozbeh Rashedi, Ph.D., P.Eng.VP-Technology, Infrastructure Solutions Inc.

Page 2: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

Gravel Roads –Who cares?

Page 3: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

GRAVEL ROADS

60% of public roads in Canada are gravel - 626,000 km

53% of the national road network in the U.S. is gravel -2.6 million km

Routinely, gravel road segments have up to 400 vehicles per day

They are the poor cousin and typically receive less management attention compared to paved roads.

They are critical for product transport; the lifeblood of agricultural communities; only access to remote communities and recreation areas; serve mining and forestry; and serve local residents, especially in semi-urban and rural areas.

Page 4: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

ALL SEASON GRAVEL ROADS ARE OPENING UP NORTHERN CANADA

Existing Trans-Taiga Road (Quebec) – 666 km North Road (Quebec) – 406 km Inuvik to Tuktoyaktuk (Northwest Territories) – 137

kmUnder Construction Shoal Lake 40 First Nation – Freedom Road

(Manitoba) – 24 km East Side of Lake Winnipeg (ESLW) Road (Manitoba)

– 1,000 kmPlanning East-West All Season Road (Ontario) – 400 km Bathurst Inlet Port and Road (BIPAR) Project

(Nunavut) – 227 km James Bay Coastal All Season Road (Ontario) – 390

km James Bay to Hwy 17 All Season Road (Ontario) -

200 to 350 km Tlicho, All Season Road to Whati (NWT) – 97 km

James MacKenzie/Canadian Press

Page 5: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

GRAVEL ROAD MANAGEMENT

Maintaining gravel roads is a major activity for many municipalities and requires regular interventions to provide safe and smooth roads for users

Municipalities spend millions of dollars every year on gravel road maintenance and rehabilitation activities

Is this money spent effectively?

Do we know?

Page 6: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

What is the current state of Gravel Road Management?

Page 7: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

2017 SURVEY OF GRAVEL ROAD MANAGEMENT PRACTICES

GOAL: To capture state of practice of gravel road management in Canada

97 Canadian municipalities responded

Representing 40,000 km of gravel roads

Published 2017

Page 8: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

STATE OF GRAVEL ROAD MANAGEMENT IN CANADA

The majority of municipalities do not collect condition data about their gravel roads.

A perceived lack of benefit from a time and cost investment perspectives

Lack of a simple gravel road management system to help with condition assessment and data collection

Page 9: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

RECORD KEEPING IS

GOOD

The maintenance history records can be used within a gravel road management system to monitor deterioration rates and

inform management and maintenance strategies.

Page 10: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

STATE OF GRAVEL ROAD MANAGEMENT IN CANADA

Other Findings

Gravel road management highly depends on individual and local knowledge

Frequency of maintenance activities varies based on traffic volumes, local conditions, user complaints and subgrade strength

Almost all municipalities with more than 50 km of gravel roads saw a great value in having software tools to assist with gravel road management

Page 11: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

STATE OF GRAVEL ROAD MANAGEMENT IN CANADA

Other Findings

Gravel road management highly depends on individual and local knowledge

Frequency of maintenance activities varies based on traffic volumes, local conditions, user complaints and subgrade strength

Almost all municipalities with more than 50 km of gravel roads saw a great value in having software tools to assist with gravel road management

Page 12: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

STATE OF GRAVEL ROAD MANAGEMENT IN CANADA

Other Findings

Gravel road management highly depends on individual and local knowledge

Frequency of maintenance activities varies based on traffic volumes, local conditions, user complaints and subgrade strength

Almost all municipalities with more than 50 km of gravel roads saw great value in having software tools to assist with gravel road management

Page 13: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

What should a gravel road network management tool look like?

Page 14: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

Desired Features of a GRMS

manage inventory, condition data, and maintenance history of their gravel roads in conjunction with their paved roads;

establish refined priority policies using network-wide priority settings based on various physical attributes, in addition to socio-economic factors for individual road segments;

specify detailed routine maintenance polices based on local knowledge or pre-set schedules;

incorporate robust gravel loss models to allow prediction of the need for and extent of re-graveling operations;

identify when gravel roads should be upgraded to surface treated;

compare the longer-term impacts of multiple scenarios with different policy and budget settings; and

generate a 10-year capital plan with road lists, budgeted costs, annual schedules, and map visualizations.

Page 15: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

GRAVEL ROAD MANAGEMENT SYSTEM (GRMS)

Page 16: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

CONDITION SURVEYS – RECORDING THE DATA

Page 17: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

Predicting Deterioration Rates

Predicted Annual Gravel Loss (mm/year)=𝑓𝑓(𝑡𝑡𝑟𝑟𝑎𝑎𝑓𝑓𝑓𝑓𝑖𝑖𝑐𝑐, 𝑝𝑝𝑟𝑟𝑒𝑒𝑐𝑐𝑖𝑖𝑝𝑝𝑖𝑖𝑡𝑡𝑎𝑎𝑡𝑡𝑖𝑖𝑜𝑜𝑛𝑛, 𝑚𝑚𝑎𝑎𝑖𝑖𝑛𝑛𝑡𝑡𝑒𝑒𝑛𝑛𝑎𝑎𝑛𝑛𝑐𝑐𝑒𝑒, 𝑟𝑟𝑜𝑜𝑎𝑎𝑑𝑑 𝑔𝑔𝑒𝑒𝑜𝑜𝑚𝑚𝑒𝑒𝑡𝑡𝑟𝑟𝑦𝑦)

Page 18: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

UPGRADE DECISIONS

Other Considerations: Structural Capacity Drainage Traffic

Characteristics Road Geometry Opinion of Local

Residents

Page 19: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

Optimized Gravel Road Management Using DOT

Page 20: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

DOT: Dashboard Visualizations

Page 21: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

DOT: GIS visualization and data analytics

Page 22: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

DOT: Optimization & Scenario Comparison

Page 23: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

DOT: Optimization & Scenario Comparison

Page 24: OPTIMIZED GRAVEL ROAD MANAGEMENT SYSTEMSograconference.ca/wp-content/uploads/2016/02/3-Roozbeh_Rashedi... · Under Construction Shoal Lake 40 First Nation – Freedom Road (Manitoba)

Thank Youfor more information on DOT (Decision Optimization Technology) ™ and gravel road survey please contact: