Options for Possible Sector Test
Mike Lamont
LHC sector test 24-3-2008
LHC sector test 34-3-2008
LHC sector test 44-3-2008
LHC sector test 54-3-2008
Outline
Motivation Options
Space & Time Access Pre-requisites Cold checkout Impact Schedule Conclusions
LHC sector test 64-3-2008
Baseline 1 week with beam Pilot Beam for the most part:
single bunch of 5 - 10 x 109 protons Total intensity:
2 - 3 x 1013 protons
LHC sector test 74-3-2008
Motivation
Beam tests form a integral part of full beam commissioning
This has got to be done anyway but gives lead time for problem resolution, improvements etc.
Beam: Polarity of magnetic elements Aperture in the cold machine Response of key beam instrumentation Magnet field quality
Very Visible Milestone
LHC sector test 84-3-2008
Integration Full test of a majority of subsystems over more
than one eighth of the ring Allows staged approach to the full problem space Time to fully resolve problems before the real
thing Analysis, improvements, resolution, adjustment
The lessons learnt will reduce the time needed for full commissioning
Breathing space if there are any serious problem(less true now perhaps)
LHC sector test 94-3-2008
Integration & commission with beam:
Full-blown system wide integration testFull-blown system wide integration test
LHC sector test 104-3-2008
Option 1
layout
LHC sector test 114-3-2008
Option 1: Injection R8 – A78 – R7
No temporary dump to be installed at IR7 - use collimators instead (3 primaries, 5 secondaries for the single beam).
No temporary installation of beam instrumentation at IR7.
Need small part of 8-1, all 7-8 hardware commissioned to 450 GeV+.
Minimal Impact Solution
LHC sector test 124-3-2008
Option 1: Pros and Cons
Minimal requirements on Cryogenics & HWC 2 sectors
Less area classified by RP Less impact on other systems
BI, LBDS
Only one sector test - less systems tested BI, LBDS, collimators missed
BI configuration not perfect Rely on in situ instrumentation Not ideal – no BCT – some implications for measurements
LHC sector test 134-3-2008
Option 2
LHC sector test 144-3-2008
Option 2: Injection R8 – A78 – A67 – Dump
Use TCDQ and TCS to block down stream aperture – safeguard only - no installation of temporary dump. RP approval/study required
Beam onto TDE Can use correctors to steer into dump channel - so
should be able to guarantee very little beam goes onto TCDQ etc.
Rely on in situ instrumentation (BCT in dump line etc.). No temporary installation required.
Need small part of 8-1, all 7-8, all 6-7 hardware commissioned to 450 GeV+.
LHC sector test 154-3-2008
Option 2: Pros & Cons
Test beam dump and related systems Don't irradiate ring - beam onto TDE (beam dump block) Check IR7 optics, performance of warm magnets Beam through 3 IRs, 2 full sectors Full suite of Beam Instrumentation in place
FBCT, Screens, BLMs
Support required for 3 cold sectors cold while work in progress elsewhere in ring - clearly test has more of an impact.
Favoured Solution
LHC sector test 164-3-2008
Option 3 – Injection point 2
Outside possibility – would imply problems elsewhere Need partial 1-2, complete 2-3 Dump on collimators in IR3
LHC sector test 174-3-2008
TestsPriority Duration Intensity # shots Intensity Comments
12 p+ p+0 Re-commission TI8 1 12 5E+09 500 2.5E+12
1End TI8, Injection Steering, commission BDI, timing
1 12 5E+09 500 2.5E+12 TDI in, protecting LHCb
2Trajectory acquisition commissioning, trajectory correction, threading, energy matching
1 24 5E+09 100 5.0E+11 Mostly to arc
3Linear Optics from kick/trajectory, coupling, BPM polarity checks, corrector polarity checks
1 12 1E+10 400 4.0E+12 To IR7 or beam dump
4 Check BLM system 1 Parasitic
5 Aperture limits, acceptance 1 18 5E+09 800 4.0E+12 Oscillations, p bumps, BLMs, BCT
6 Momentum aperture 1 6 5E+09 100 5.0E+11 Move energy of SPS beam
7Determination of quench level - calibrate BLMs. Commission multi-bunch injection as necessary
1 36 1E+11 40 4.0E+12 Start with pilot and work slowly up
9Effects of magnetic cycle, variations during decay, reproducibility including energy variation on flat bottom
1 24 1E+10 300 3.0E+12 10 cycles
10 Field errors (high statistics) 2 12 2E+10 200 4.0E+12 Collect data, off-line analysis
TOTAL 144 2.5E+13DAYS 6.0
LHC sector test 184-3-2008
Access – closing the whole ring Pre-preparation, DSO tests
2 months Closing the ring: patrols etc
3-4 days Experiments out for a week
“a disturbance but acceptable” Access during test possible
to areas that don’t see beam Supervised areas after test
Given analysis, and measurements during and after the test, it is envisaged that:
Certain areas might be declared controlled areas for the first few days after the test;
Thereafter these areas would join the rest of the sectors involved as supervised areas
LHC sector test 194-3-2008
Monitoring
Radiation monitoring RAMSES operational LHCb: 4-5 monitors planned under RAMSES
Beam Loss Monitors Sensitive to losses at 1% level with pilot bunch intensity
Beam Intensities Beam extracted, injected (and to dump) to be logged
RPG survey after the event and perhaps during the test to ensure that activation remains low. Careful survey afterwards planned after the test near the
injection dump and dump itself.
LHC sector test 204-3-2008
BICBIC
BICBIC
BICBIC
3/16 of LHC Beam Interlock System
SPS Extr.
Kicker
BICBIC
BICBIC
BICBIC
BICBICBICBIC
SPS Extraction Lines
Interlock System
Radiation levels BLM Powering Interlock Warm Magnet Interlock Vacuum LHCb
Access system will provide input to BIS which will inhibit SPS extraction. Configurable if the case of extraction required & LHC not ready (e.g. extraction tests)
BIS
Required circuits
• Beam 2 Circuits only
• For limited recycling, it would be preferable for listed circuits to be available to, say, the equivalent 1-2 TeV level.
LHC sector test 224-3-2008
Injection
RQ5.R8 Q5 quadrupole
RQ4.R8 Q4 quadrupole
RD2.R8 D2 recombination dipole
RD1.R8 D1 recombination dipole
LHC sector test 234-3-2008
Triplets & LHCb
RQX.R8 Inner triplet
RQX.L8 Inner triplet
RD1.L8 D1 recombination dipole
LHC sector test 244-3-2008
LL5 & DS.L5
RQ7.L8 2*MQM
RQ8.L8 MQML
RQ9.L8 MQM MQMC
RQ10.L8 MQML
RQTL11.L8B2 MQTLI
RQT12.L8B2 MQT
RQT13.L8B2 MQT
LHC sector test 254-3-2008
A78
Circuits No. of circuits Priority
Main bends MB RB.A78 1 1
Main quads MQ RQF, RQD 2 1
Skew quads MQS RQS [B2] 1 1
Trim quads MQT RQTF,RQTD [B2] 2 1
Orbit correctors MCB RCB [B2] 23 H & 24 V 1
Lattice sextupoles MS RSF,RSD [B2] 4 2
Lattice octupoles MO ROD, ROF [B2] 1 -
Skew sextupoles MSS RSS [B2] 1 3
b3 spool MCS RCS [B2] 1 3
b4 spool MCO RCO [B2] 1 -
b5 spool MCD RCD [B2] 1 -
LHC sector test 264-3-2008
MR4
RQT13.R7B2 QT
RQT12.R7B2 QT
RQTL11.R7B2 QTLI
RQTL10.R7B2 QTLI
RQTL9.R7B2 QTLI
RQTL8.R7B2 QTLI
RQTL7.R7B2 QTLI
RQ6.R7B2 6* QTLH
LHC sector test 274-3-2008
6-7
LHC sector test 284-3-2008
Other systems Injection elements: septa, kickers Collimators Machine Protection Beam Instrumentation:
BPMs, BLMs, BTV, BCT, BST Magnet Model Controls Software/tools Access system Radiation Protection Radiation Monitoring Optics, aperture model
See Chamonix 2006
Test preparation largely orthogonal to HWC
LHC sector test 294-3-2008
Near test schedule
Phase Time
Sectors checkout, interlock & machine protection tests etc.
Tstart - 2 weeks
Close ring Tstart– 4 day
Access tests & final qualification Tstart – 4 day
Beam to end TI8 Tstart – 1 day
Tests with beam 1 week
Radiation survey Tend + 1 day
Establish supervised areas Tend + 2 day
LHC sector test 304-3-2008
Injectors
LHC sector test 314-3-2008
LHC sector test 324-3-2008
Impact
Sector test makes clear demands on: What is needed to be cold & commissioned and to what level Fairly limited: Beam 2 Circuits & limited recycling,.
Cryogenics, QPS, HWC support required during test In general, low current levels with occasional cycles Interesting possibility of quenches
Access Experiments - “acceptable” HWC – NB that commissioning in other sectors can continue Scheduled access possible (could imagine access/day if we can
guaranteed a reasonable efficient recovery).
LHCb
LHC sector test 334-3-2008
Conclusions
A sector test would be a useful exercise and undoubtedly speed full commissioning with beam most of it has to be done anyway
Could provide a useful buffer if any major problems are discovered.
The impact is not negligible, mainly because the whole ring has to be closed This in itself is a very useful exercise Machine as is or as will be. Work carries on elsewhere. All major installation will have finished and access to the zones
affected after the test will be limited.
This is a back up - to be invoke if delays 3 months Need minimum lead time of some weeks for preparation
LHC sector test 344-3-2008
Thanks…
Magnets Luca Bottura Beam Instrumentation Rhodri Jones, Lars Jensen, Stephen Jackson Injection Brennan Goddard, Jan Uythoven Radiation Protection Doris Forkel-Wirth, Helmut Vincke INB Ghislain Roy Access Pierre Ninin LHCb Rolf Linder HWC Roberto Saban & team Installation Katy Foraz Planning Esther Barbero Soto Vacuum Paul Cruikshank, Miguel Jimenez Controls Robin Lauckner ++ OP/AP Roger Bailey, Verena Kain, Massimo
Giovannozzi, Stephane Fartoukh, Helmut Burkhardt, Alex Koshick, Stefano Raedelli, Ralph Assmann, Frank Zimmerman… and the rest of the commissioning team.
LHC sector test 354-3-2008
Chamonix 2006
Sector test with beam
Overview, motivation and scheduling Mike Lamont
Proposed tests with beam Brennan Goddard
Magnet quenches with beam Alex Koschik
Beam Instrumentation Lars Jensen
Magnet requirements Luca Bottura
Controls requirements Robin Lauckner
Sector test preparation Chair: Pierre Strubin
Planning Esther Barbero Soto
Global Hardware Status Miguel Jimenez
Layout in LSS7 Jan Uythoven
Hardware Commissioning Roberto Saban
State of LHCb for the test Massimiliano Ferro-Luzzi
Radiation Issues Helmut Vincke
Access system Pierre Ninin
LHC sector test 364-3-2008
Reserve slides
LHC sector test 384-3-2008
LHCb Worst case scenario: it is estimated that a total 3 x 1011 protons will be lost in the LHCb region during the whole
test. The losses will be distributed over time. It has to be noticed that this number is quite pessimistic – under “normal” beam conditions the losses are more in the order of 1x10-4.
The aperture in LHCb is large; the injection optics means relatively small beams in the inner triplet to the right of the experiment; the separation and crossing angle bumps will be off; there is therefore no reason to expect significant losses in this region.
RP conclusion (H. Vincke) (Preliminary, based on extrapolations of presently available exemplary calculations):
Dose rates: All 3 x 1011 protons will be lost in carbon surrounded by steel and copper (already existing calculation) at the last
day of the 14 days of tests: maximum 13 uSv/h .
The 3 x 1011 protons will be lost in one point after one week. After the cooling time of another week the maximum dose rate will be 2.8 uSv/h. This scenario can be considered as a more realistic approximation of continuous losses (at the same loss point) over two weeks.
Assuming that the new French law on area classification will not become stricter than the present Swiss one:
Non-designated area: < 2.5 uSv/h for temporary stay (0.5 uSv/h for permanent working places, i.e. assuming 2000 hours/year)
This goal seems to be achievable, even under pessimistic assumptions. In case the dose rates will be higher
(e.g. due to an incident), the area (around the loss point) will have to be classified as supervised area (radiation workers B in the worst case, but most probably VCT status (physicists and technicians from outside institutes will receive dosimeters without medical certificate) will be sufficient – to be checked).