    OptiX RTN 600 Equipment

    Commissioning

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    2/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 1

    Learning Guide

    Before studying this course, you are supposed to complete the

    study on

    Basics of digital microwave communications or related

    knowledge

    OptiX RTN 600 Product Introduction

    OptiX RTN 600 Networking and Protection Mechanism

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    3/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 2

    References

    Digital Microwave Communications Basics

    OptiX RTN 600 Radio Transmission System Configuration

    Guide

    OptiX RTN 600 Radio Transmission System Commissioning

    Guide

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    4/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 3

    Objectives

    Upon completion of this course, you will be able to:

    Finish proper preparations before the commissioning

    Performing NE commissioning of the OptiX RTN 600

    Performing hop commissioning of the OptiX RTN 600

    New introduce slide of V1R2 is remarked by

    R2 New Slide

    Adjust Slide

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    5/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 4

    Contents

    1. Preparations for the OptiX RTN 600 Commissioning

    2. NE Commissioning of the OptiX RTN 600

    3. Hop Commissioning of the OptiX RTN 600

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    6/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 5

    Contents

    1. Preparations for the OptiX RTN 600 Commissioning

    1.1 Determining Commissioning Items

    1.2 Preparing Related Documents

    1.3 Preparing Related Tools

    1.4 Checking Commissioning Conditions

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    7/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 6

    Determining Commissioning Items

    1. NE Commissioning Items

    Commissioning Item Optional/Require

    d

    Remarks

    Powering on the

    equipmentRequired

    If the fan is available in the equipment,

    check whether the fan is working or not

    after power on.

    Testing indicators RequiredCheck whether all indicators work

    normally or not.

    Connecting the Web

    LCTRequired

    -

    Configuring the data Required -

    Performing the service

    loopback testOptional

    If the instruments are available on site, it

    is recommended that you test this item.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    8/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 7

    Determining Commissioning Items (cont.)

    1. NE Commissioning Items (cont.)

    Commissioning Item Optional/Require

    d

    Remarks

    Testing E1 cablesconnections

    Optional It applies to the station where the E1service is accessed.

    Checking the receive

    and transmit power of

    the optical interface

    Optional

    It applies to the station where the SDH

    optical interface service is accessed.

    Testing the RF transmitpower

    Required Use the Web LCT to query the RFtransmit power.

    Testing the

    active/standby cross-

    connect board switching

    Optional

    It only applies to the equipment

    configured with the active and standby

    cross-connect boards.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    9/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 8

    Determining Commissioning Items (cont.)

    Commissioning Item Optional/

    Required

    Remarks

    Aligning the antenna Required -

    Testing the ECC Required -

    Testing the orderwire

    phoneOptional

    It is applicable when there is the order

    wire phone available between stations.

    Testing all services Required Test all service types turned up at thestation like the E1, STM-1, and WS.

    Testing the clock

    tracingRequire

    Check and ensure that the clock source

    can be traced normally.

    2. Hop Commissioning Items

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    10/70

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    11/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 10

    New Add Commissioning Items NE Commissioning Items

    R2 New Slide

    Commissioning Item Optional/RequiredRemarks

    Testing the XPIC Cable

    connectionOptional

    It is applicable when the IFX is

    configured.

    Commissioning ItemOptional/Requir

    ed

    Remarks

    Testing the E3DS3services requiredIt is applicable when the E3 (DS3) service

    is configured.

    Testing XPIC function required It is applicable when the XPIC is configured.

    Testing N+1 protection switching requiredIt is applicable when the N+1 protection is

    configured.

    Hop Commissioning Items

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    12/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 11

    Preparing Related Documents

    The documents that are required include the engineering design

    documents and commissioning guide documents.

    Engineering design documents like

    OptiX RTN 600 Radio Transmission System Network Planning Document

    OptiX RTN 600 Radio Transmission System Engineering Design

    Document

    Commissioning guide documents like:

    OptiX RTN 600 Radio Transmission System Commissioning Guide

    OptiX RTN 600 Radio Transmission System Quick Installation and

    Commissioning Guide

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    13/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 12

    Preparing Tools

    The tools that are required include the common tools, special tools

    and instruments. The recommended list is as follows:

    Type Description

    Common

    tool

    Adjustable wrench, percussion drill, sharp-nose pliers, and

    electric knife

    Special

    tool

    Anti-static glove, ESD-preventive wrist strap, telescope,

    and intercom

    InstrumentMulti-meter, BER tester, and laptop computer (installed

    with the Web LCT), SDH Instrument

    Adjust Slide

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    14/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 13

    Checking Commissioning Conditions

    The NE commissioning conditions to be checked include the

    status of the equipment as well as that of the laptop computer

    used in the commissioning. The NE commissioning conditions are

    listed as follows:

    The hardware installation of the equipment must be complete, and it

    should pass the installation check.

    The power supply of the equipment must be available.

    The service signal cables connected to other equipment must be

    routed well.

    The laptop computer must be installed with the Web LCT, and

    applications should work normally.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    15/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 14

    Checking Commissioning Conditions (cont.)

    The hop commissioning items to be checked include the NE

    commissioning status as well as the weather conditions. The hop

    commissioning conditions are listed as follows:

    The NE commissioning of the radio equipment at both ends of the

    same radio link must be complete.

    The weather should be suitable, and there should no rain or fog

    between stations.

    The on-site conditions and the personnel in charge of antennacommissioning must meet the requirement on the operation at a high

    altitude.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    16/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 15

    Summary

    This chapter describes the following contents:

    NE commissioning items and hop commissioning items

    Documents and tools prepared before the commissioning

    Commissioning conditions

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    17/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 16

    Contents

    1. Preparations for the OptiX RTN 600 Commissioning

    2. NE Commissioning of the OptiX RTN 600

    3. Hop Commissioning of the OptiX RTN 600

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    18/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 17

    Contents

    2. NE Commissioning of the OptiX RTN 600

    2.1 Powering On the Equipment

    2.2 Testing Indicators

    2.3 Accessing the Web LCT

    2.4 Configuring the Data

    2.5 Performing the Service Loopback test

    2.6 Testing the Connections of the E1 Cables

    2.7 Testing the Transmit and Receive Optical Power

    2.8 Testing the RF Transmit Power

    2.9 Testing the Active/Standby Cross-Connect Board Switching

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    19/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 18

    Powering On the Equipment

    Prerequisites The hardware installation of the equipment must be complete, and it

    should pass the installation check.

    The input power must be available.

    The power switch of the input power (such as the power box of the

    cabinet) must be turned off.

    Tools and Instruments

    Multi-meter

    Procedure

    Set the SYS-PWR switch on the PXC board to O.

    Set the ODU-PWR switch on the IF board to O.

    Turn on the input power switch of the cabinet.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    20/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 19

    Powering On the Equipment (cont.)

    testing the voltage and polarization of the input power at the accesspoint (such as the output terminal of the power box on the cabinet) by

    multi-meter. The voltage should range from -38.4 V to -72 V.

    Set the SYS_PWR switch on the PXC board to I.

    If the fan is available, first check it is working normally after power on.

    Wait for about 20 seconds, and then observe indicators of each boardinstalled in the IDU.

    The PROG indicator on the SCC board should be first on. After it

    blinks and is lit green for some time, it should be off.

    For details on the board indicators, refer to the OptiX RTN 600 Radio

    Transmission System Product Description. Set the ODU-PWR switch on the IF board to I.

    Note: The SYS-PWR and ODU-PWR switches on PXC and IF boards have

    the locking device. They need to be slightly pull out before switch them.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    21/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 20

    Testing Indicators

    Prerequisites The equipment must be powered on for

    more than five minutes.

    Tools and Instruments

    None.

    Procedure

    Press the LAMP TEST button on the

    SCC board, and indicators of all boards

    should be on.

    Release the LAMP TEST button, and

    indicators of all boards should recover

    to the status before the LAMP TEST

    button is pressed.

    LAMP

    TEST

    button

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    22/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 21

    Accessing the Web LCT

    Prerequisites

    The equipment must be powered on.

    Tools and Instruments

    Laptop computer installed with the Web LCT

    Network cable

    Procedure

    Start the laptop computer, and log in to the

    operating system. Run the Web LCT program.

    Connect the network port on the laptopcomputer to the ETH interface on the SCC

    board through the network cable. The green

    indicators of the ETH interface and network

    port should be on.

    NM interface

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    23/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 22

    Accessing the Web LCT (Cont.)

    Set the IP address information of the computer, and log in to the NE.The IP address should comply with the following conditions:

    IP address: The IP address should be in the 129.9.0.0 network section

    and should be different from the default IP address of the NE

    (129.9.191.240).

    Subnet mask: 255.255.0.0. Default gateway: Null.

    Double click the shortcut of Web LCT on the desktop. The login

    interface of the Web LCT is displayed.

    In the login interface of the Web LCT, enter the user name and

    corresponding password. Click Login. The default user name is

    admin, and the default password is T2000. If the user name and

    password are correct, the NE List page is displayed in the IE.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    24/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 23

    Configuring the Data

    Prerequisites

    The documents that are required by data configuration must be

    available.

    Tools and Instruments

    Web LCT

    Procedure

    Before configuring the NE data, create the NE, log in and modify the

    ID settings of the NE according to the requirements in the Network

    Planning Document. The OptiX RTN 600 can be configured in two modes, General Mode

    and Wizard Mode. Users can choose the proper configuration mode

    depending on the specific configuration scenarios. For details, refer to

    the OptiX RTN 600 Radio Transmission System Configuration Guide.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    25/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 24

    Testing Transmit and Receive Optical

    Power

    Prerequisites

    The service data must be configured.

    The 15-minute performance monitoring of the NE must be started.

    The fiber connections must be normal.

    Tools and Instruments Web LCT

    Fixed optical attenuator or variable optical attenuator

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    26/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 25

    Testing the Transmit and Receive Optical

    Power (cont.)

    Procedure Disable the automatic laser shutdown (ALS) function of the laser, and

    ensure that transmission of the laser is enabled.

    Query the 15-minute performance by using the Web LCT to obtain the

    values of the transmit and receive optical power. Based on the queried values along with the specifications of optical modules,

    judge whether they are within the normal value range.

    If the values are beyond the normal range, adjust the optical power by

    increasing or decreasing the number of attenuators to ensure that the receive

    and transmit optical power is within the normal value range.

    Perform the loopback test for the services upon the completion of the

    optical power test. Ensure that no bit errors occur in five minutes.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    27/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 26

    Performing the Service Loopback Test

    Prerequisites

    The Web LCT must be logged in to successfully and its connection to

    the NE must be normal.

    The board must work normally.

    Tools and Instruments

    Web LCT

    BER tester or SDH analyzer

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    28/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 27

    Performing the Service Loopback Test

    (cont.)

    Procedure

    Connect the board to be tested to the test instrument.

    Issue the loopback command and observe the instrument for five

    minutes.

    Repeat the above two steps to test each board. The service loopback for the IF board can only be implemented by

    testing the services of other service boards.

    Adopt different loopback mode depending on the actually used

    instrument.

    If the SDH analyzer is used to test the optical interface board, first usethe optical power meter to test the optical power before the test and

    use the attenuator to ensure that the optical power is within the normal

    range. This can protect the instrument and the board.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    29/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 28

    Testing E1 Cable ConnectionsUsing a BER Tester

    Prerequisites

    The E1 port must be transferred through the DDF.

    The service data must be configured.

    Tools and Instruments

    Web LCT

    BER tester

    Procedure

    Connect the BER tester to the first E1 port of the OptiX RTN 600 at

    the DDF.

    Set the corresponding E1 port to outloop by using the Web LCT.

    Observe the BER tester. The AIS alarm displayed on the BER tester

    should be cleared.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    30/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 29

    Testing E1 Cable ConnectionsUsing a BER Tester (cont.)

    Release the outloop of the E1 port by using

    the Web LCT.

    Observe the BER tester. It should report the

    AIS alarm.

    Repeat the above five steps to test other E1ports.

    Tip

    Connect all E1 ports in a serial manner and set all

    of them to outloop by using the Web LCT. In this

    way, you can check whether all E1 ports arenormal at the same time. If any fault occurs, you

    also need to locate it segmentally.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    31/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 30

    Testing the Connections of E1 Cables Through PRBS

    1. At the DDF, use an E1 cable to loop back the services over the first E1port towards the tributary board.

    2. On the Web LCT, select the E1 interface board in the Object Tree.

    3. In the function tree, choose Configuration > PRBS Test.

    4. Select the first E1 port, and then set the PRBS-related parameters.

    Direction: Tributary

    Duration: 5

    Measured in Time: s

    5. Click Start to Test. The system displays a prompt dialog box.

    6. Click OK.

    R2 New Slide

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    32/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 31

    Testing the Connections of E1 Cables Through PRBS

    7. When the Progress column is 100%, click Query to check the testresult. The Total PRBS column should be 0, and the curve diagram

    should be green.

    8. Release the loopback set in 1.

    9. Repeat 2 through 7 and check the test result. The curve diagram should

    be yellow.

    10. Repeat 1 through 9 to test all other E1 ports.

    R2 New Slide

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    33/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 32

    Testing XPIC Cable

    Prerequisites

    The NE is running normal.

    The IFX board is working normal.

    Procedure

    The XPIC Enabled parameter must be set to Enabled (default value) for the

    IFX boards. Using an XPIC cable to loop back the XPIC IN port and XPIC OUT port for the

    IFX board. Then check the color of the XPIC indicator.When the XPIC indicator

    show green, it means the XPIC cable is normal.

    R2 New Slide

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    34/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 33

    Testing the RF Transmit Power

    Prerequisites

    The service data must be configured and the performance monitoring

    of the NE must be started.

    The ATPC function must be disabled.

    Tools and Instruments Web LCT

    Procedure

    In the NE Explorer, select the ODU that requires querying the RF

    transmit power and query RF Transmit Powerin the performance

    events.

    Browse the performance events in the window. The difference

    between the queried value of the RF transmit power and the preset

    value should be less than 0.1 dB.

    If the tested value is abnormal, contact Huawei for solutions.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    35/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 34

    Testing Active/Standby Cross-connect

    Board Switching

    Prerequisites

    The service data must be configured.

    The 15-minute performance monitoring of the NE must be started.

    The equipment must be configured with the active and standby cross-connect boards.

    Tools and Instruments

    Web LCT

    BER tester

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    36/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 35

    Testing Active/Standby Cross-connect

    Board Switching (Cont.)

    Procedure Confirm the current working status of active and standby PXC

    boards and no abnormal alarms by using the Web LCT.

    Perform active/standby PXC board switching by Web LCT.

    Query the working status of the active and standby PXC boards to

    check whether the switching is performed normally.

    Query the current and history alarms to check whether any alarm is

    generated during the switching process.

    After the test, restore the PXC board in slot 1 to the active board.

    Query the alarms and ensure that the cross-connect board works

    normally.

    If you use the BER tester to monitor the services, few bit errors may

    occur during the switching process. The services, however, can

    recover immediately after the switching is complete.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    37/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 36

    Questions

    What is the procedure to access Web LCT?

    How should the E1 port be set and connected for testing the connections

    of E1 cables? What method can we adopt for testing this item quickly?

    Why the ATPC function is disabled when the RF transmit power is tested?

    What are the two modes in data configuration? What are the differences

    between them?

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    38/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 37

    Summary

    This chapter describes the prerequisites, tools and instruments, and

    procedure for the NE commissioning items:

    Powering on the equipment

    Testing indicators

    Accessing the Web LCT

    Configuring the data

    Testing the transmit and receive optical power

    Performing the service loopback test

    Testing the connections of E1 cables Testing the XPIC Cables

    Testing the RF transmit power

    Testing the active/standby cross-connect board switching

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    39/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 38

    Contents

    1. Preparations for the OptiX RTN 600 Commissioning

    2. NE Commissioning of the OptiX RTN 600

    3. Hop Commissioning of the OptiX RTN 600

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    40/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 39

    Table of Contents

    3. Hop Commissioning of the OptiX RTN 600

    3.1 Aligning the Antenna

    3.2 Testing the ECC

    3.3 Testing the E1 Service

    3.4 Testing the WS Service

    3.5 Testing the order wire

    3.6 Testing the Clock Tracing

    3.7 Testing the IF 1+1 Switching

    3.8 Testing the SNCP Switching

    3.9 Testing the 24-Hour BER

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    41/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 40

    Aligning the Antenna

    Prerequisites The NE commissioning of the radio equipment at both ends of the same radio

    link must be complete.

    During the commissioning, the weather should be suitable and there should be

    no rain/fog between stations.

    The on-site conditions and personnel in charge of the antenna commissioning

    must meet the requirements of operation at a high altitude.

    The ATPC function is disable.

    Tools and Instruments

    Wrench, multi-meter and intercom.

    Note: If there are two antennas at each site, it needs to align the mainantennas and diversity antennas at both ends respectively. First align the

    main antennas and then the diversity antennas. Both antennas at local site

    should be aligned with the main antenna at opposite end.

    R2 New Slide

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    42/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 41

    Aligning the Antenna

    Aligning the antennas is the most important activity in the HOP commissioning,and its result has a direct effect on the performance of the radio link. There are two

    types of antenna Single-Polarized Antenna, dual-Polarized Antenna .

    When you align the single-polarized antennas, you need to align the main lobe of

    the antenna signals by adjusting the azimuth angle and elevation angle of the

    antennas at both ends.

    When you align the dual-polarized antennas, you need to align the main lobe of the

    antenna signals by adjusting the azimuth angle and elevation angle of the

    antennas at both ends. You also need to adjust the feed booms of the antennas

    and ensure that the Cross-Polarization Discrimination (XPD) meets the specified

    requirements.

    R2 New Slide

    Adjust Slide

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    43/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 42

    Aligning the Single-Polarized Antennas

    Procedure

    1. According to the designed received signal level (RSL) along with the

    relationship curve between the VBNC and RSL described in the user

    documents (shipped with the equipment) of the ODU reference

    documents, read the designed value of the VBNC.

    2. Align the antennas at both ends approximately by using the specific tool

    (telescope) or instrument (COMPASS or GPS). If the antennas at bothends are not aligned approximately, the VBNC cannot be adjusted to the

    designed value.

    3. Fix the antenna at the opposite end, and adjust the azimuth (elevation) of

    the antenna at the local end in a wide range. Use the multi-meter to

    observe the VBNC value of the ODU at the local end. At least three peaksignals should be detected and the voltage of the peak signal in the

    middle should be maximum. When the VBNC reaches the maximum value,

    tighten the antenna. When the antenna is being tightened, keep that the

    VBNC is always the maximum.

    Adjust Slide

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    44/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 43

    Aligning the Single-Polarized Antennas (cont.)

    4. As step 3, adjust the elevation (azimuth) of the antenna. And tighten it.

    5. Tighten the antennas at the local end. Repeat steps 3 and 4 to adjust

    the antennas at the opposite end and tighten them.

    6. Repeat steps 3 to 5 for two to four times. When the RSL of the

    antennas at the local end and the remote end reach the maximum

    value, tighten the antennas at both ends.

    7. Test VBNC of ODUs at both ends by multi-meter. Read the actual

    receive power level (RSL) by referring to the relationship curve between

    the VBNC and RSL for the ODUs at both ends. The difference between

    actual RSL value and its designed value should be ranged from -3 dB

    to +3 dB.

    8. If the VBNC does not meet the above requirements, check whether the

    antennas at both ends are approximately aligned by referring to the

    step2. Also you can refer to the OptiX RTN 600 Radio Transmission

    System Maintenance Guide for solutions.

    9. After antennas aligning is complete, tighten all screws of the antennas.

    R2 New Slide

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    45/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 44

    Aligning the Dual-Polarized Antennas

    Step 1: Power off the vertically polarized ODUs at both ends of the radiolink, power on the horizontally polarized ODUs at both ends of the radio

    link, and thus ensure that the antennas transmit horizontally polarized

    signals.

    Step 2: Adjust the azimuth angle and elevation angle of the antennas at

    both ends by referring to Aligning the Single-Polarized Antennas, andensure that the main lobe of the horizontally polarized signals is aligned

    with the antenna.

    Step 3: Measure the RSL (P1) of the horizontally polarized signals at the

    local end.

    Use a multimeter to measure the signal level on the RSSI port of the

    horizontally polarized ODU.

    Calculate the RSL (P1) of the horizontally polarized received signals

    by referring to the curve diagram in the ODU box.

    R2 New Slide

    R2 New Slide

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    46/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 45

    Aligning the Dual-Polarized Antennas (cont.)

    Step 4: Adjust the feed boom at the local end, and ensure that the RSL ofthe vertically polarized signals reaches the lower threshold (P2).

    Power on the vertically polarized ODU at the local end.

    Use a multimeter to measure the signal level on the RSSI port of the vertically

    polarized ODU.

    Release the holder of the feed boom a little bit, and turn the feed boom slightly

    until the signal level reaches the lower threshold.

    Calculate the RSL (P2) of the vertically polarized signals by referring to the

    curve diagram in the ODU box. The calculated XPD1 (XPD1 = P1 P2) should

    not be less than 30 dB.

    R2 New Slide

    R2 New Slide

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    47/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 46

    Aligning the Dual-Polarized Antennas (cont.)

    Step 5: Record the angle (D1) of the current feed boom. Step 6: Power off the horizontally polarized ODUs at both ends of the

    radio link, power on the vertically polarized ODUs at both ends of the

    radio link, and thus ensure that the antennas transmit vertically polarized

    signals.

    Step 7: Measure the RSL (P3) of the vertically polarized signals at the

    local end by referring to 3.

    Step 8: Power on the horizontally polarized ODU at the local end, and

    calculate the level (P4) of the horizontally polarized signals received at

    the local end by referring to 4. The calculated XPD2 (XPD2 = P3 P4)

    should not be less than 30 dB.

    R2 New Slide

    R2 New Slide

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    48/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 47

    Aligning the Dual-Polarized Antennas (cont.)

    Step 9: Record the angle (D2) of the current feed boom.

    Step 10: Repeat 3 through 9 to adjust the feed boom slightly (ranging

    from D1 to D2), and ensure that XPD1 and XPD2 are not less than 30 dB.

    Step 11: Tighten all the screws of the antennas.

    Note: In the actual situation, you can align the dual-polarized antennas by

    measuring only the vertically polarized signals

    R2 New Slide

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    49/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 48

    Testing the ECC

    Prerequisites

    Antenna alignment must be complete.

    The NE must have access to the Web LCT.

    Tools and Instruments Web LCT

    Precautions

    Test the ECC at one end of the radio link.

    Procedure

    In the NE List page, click Add NE.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    50/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 49

    Testing the ECC (cont.)

    In the Add NE page, set the following attributes of the opposite NE: ID: ID of the opposite NE

    Name: name of the opposite NE

    Extended ID: extended ID of the opposite NE

    Gateway Type: IP gateway

    Gateway IP Address: IP address of the local NE

    User Name: root (default)

    Password: password (default for the user root)

    Click OK. In this case, a row of data for the newly added NE is added

    in the NE List page.

    Observe Login Status of the newly added NE. Login Status should

    be displayed as Logged In.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    51/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 50

    Testing the E1 Service

    Prerequisites The E1 service must be available between stations and the service

    configuration at each station must be correctly delivered.

    Antenna alignment must be complete.

    Tools and Instruments

    BER tester and Web LCT

    Procedure

    At local site, connect the BER tester to the first E1 port.

    At remote site, loopback the first E1 port by cable. If cable loopback is

    unfeasible, set the software inloop for the first E1 port by Web LCT.

    Test the BER for 5 to 10 minutes by BER tester. No bit error should

    occur.

    Release all loopbacks.

    Repeat the above four steps to test other E1 ports one by one.

    R2 New Slide

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    52/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 51

    Testing E3 (DS3) Services

    Prerequisites

    The E3 (DS3) service must be configured between stations.

    Aligning the antennas must be complete.

    Tools, Instruments, and Materials

    SDH Analyser Web LCT

    Procedure

    Connect the SDH Analyser to the first E3 (DS3) port of the equipment on the local side.

    On the equipment on the opposite side, use an E3 (DS3) cable to loop back the services

    over the first E3 (DS3) port towards the tributary board, that is, hardware inloop over the

    E3 (DS3) port. If the hardware inloop fails, perform software inloop over the E3 (DS3) port

    by using the Web LCT.

    Test the BER for 5 to 10 minutes by using the SDH Analyser . There should be no biterrors.

    Release the loopback.

    Repeat 1 through 4 to test other E3 (DS3) ports

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    53/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 52

    Testing the WS Service

    Prerequisites

    The WS service must be configured.

    Antenna alignment must be complete.

    Tools and Instruments

    BER tester

    Procedure

    At local site, connect the BER tester to the WS port.

    At remote site, perform the hardware inloop for the WS port.

    Test the BER for 5 to 10 minutes by BER tester. No bit errors shouldoccur.

    Release the loopback.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    54/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 53

    Testing the order wire

    Prerequisites The order wire phone must be correctly installed at the station.

    The data of the order wire must be configured.

    Antenna alignment must be complete.

    Tools and Instruments

    None.

    Procedure

    Check the status of the order wire at the local equipment side. The

    status of the order wire should meet the following requirements:

    The ringing switch must be set to ON.

    The dialing mode switch must be set to T, that is, the dual-tone dialing

    mode is selected.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    55/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 54

    Testing the Order wire (cont.)

    Dial the order wire of the opposite equipment as follows:

    Pick up the order wire, and press the TALK key on the front panel of the

    phone. The red indicator on the upper right side of the front panel is on,

    accompanied by the dial tone.

    Dial the order wire number of the opposite equipment. Normally, the voice

    quality is good and the voice is clear.

    Answer the order wire.

    The maintenance personnel at the opposite equipment side dials the order

    wire of the local equipment. Normally, the order wire rings and at the same

    time the red indicator on the upper right side of the front panel is on. Pick up the phone, and press the TALK key to talk. The red indicator on

    the upper right side of the phone is on. Normally, the voice quality is good

    and the voice is clear.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    56/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 55

    Testing the Clock Tracing

    Prerequisites The clock tracing priority list must be configured.

    Tools and Instruments

    Web LCT

    Procedure Query the current clock priority table by using the Web LCT.

    According to the clock priority table, query whether the current clock

    tracing source is traced normally.

    If the active and standby PXC boards are configured, perform the

    active/standby switching. This operation can check whether the currentclock source can be traced normally after the switching. After the test

    is complete, restore the PXC boards in slot1 as active board.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    57/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 56

    Testing the IF 1+1 Switching

    Prerequisites

    The equipment must be configured with the IF 1+1 protection.

    Antenna alignment must be complete.

    Tools and Instruments

    BER tester and Web LCT

    Note: The following procedure considers the E1 service between

    stations as an example. If no E1 service is configured between

    stations, perform the test through the configured WS service (only

    applicable in the SDH radio).

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    58/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 57

    Testing the IF 1+1 Switching (cont.)

    Procedure At local site, connect the BER tester to one E1 port.

    At remote site, loopback an E1 port by cable. Or set the software inloop

    on an E1 port by web LCT when cable loopback is unfeasible.

    Test the BER by BER tester. Confirm E1 service is normal.

    View the working status of the protection group by using the Web LCT.

    The Active Board of Device and Active Board of Channel should be

    the active IF board.

    Set the transmission status of the main ODU to mute by using the Web

    LCT or power off the main ODU. This can trigger the IF 1+1 switching.

    View the working status of the protection group after the switching by

    using the Web LCT. The Active Board of Device and Active Board

    of Channel should be the standby IF board. The HSB_INDI or

    HSM_INDI alarm should be reported.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    59/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 58

    Testing the IF 1+1 Switching (cont.)

    View the BER by Web LCT. In the 1+1 HSB protection or 1+1 SD protection, service should recover after a

    transient interruption.

    In the 1+1 FD protection, service just has some bit errors without interruption.

    After switching is complete, test the BER for 5 to 10 minutes. No bit errors

    should occur.

    Set the transmission status of the main ODU tounmute by using the Web LCT

    or powering on the main ODU.

    If the protection mode is set to Revertive mode, test the BER again by using

    the BER tester. When the restore time arrives, the result should indicate that

    the service has recovered after a transient interruption. WTR Time is set to

    600s by default. Test the BER according to the requirements of the actual

    configuration.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    60/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 59

    Testing the SNCP Switching

    Prerequisites The equipment must be configured with the SNCP protection.

    Antenna alignment must be complete.

    Tools and Instruments

    BER tester and Web LCT

    Procedure

    At local site, connect the BER tester to one E1 port.

    At remote site, loopback the corresponding E1 port by cable. Or set

    inloop on the E1 port by web LCT when cable loopback is unfeasible.

    Test the BER by BER tester. Confirm E1 service is normal.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    61/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 60

    Testing the SNCP Switching (cont.)

    Check SNCP status of E1 service by Web LCT. And status should benormal.

    Trigger the SNCP switching by disconnecting the fiber connectors or

    powering off the ODU in the working channel of the E1 SNCP service.

    View the abnormal events of the NE by Web LCT. The abnormalevents of SDH SNCP Switching are displayed in Abnormal Event List.

    View the BER test result. The result should indicate that the service

    has recovered after a transient interruption.

    Reconnect the fiber connector or power on the ODU.

    In the Revertive mode, when the restore time arrives, the BER tester

    result should indicate that the service has restored back. WTR Time is

    set to 600s by default.

    Test the BER depending on the requirements of the actual

    configuration.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    62/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 61

    Testing the 24-Hour BER

    Prerequisites Antenna alignment must be complete.

    Tools and Instruments

    BER tester and Web LCT

    Precautions If the 24-hour BER cannot be tested for each hop on the link because

    of the restrictions of the actual situation, choose the E1 service of the

    first node and terminal node of each link to perform this test. This

    operation ensures that the test path covers all the radio links.

    The following test procedure considers the E1 service betweenstations as an example. If no E1 service is configured between

    stations, perform the test through the configured WS service (only

    applicable in the SDH radio).

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    63/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 62

    Testing the 24-Hour BER (cont.)

    Procedure At local site, extract several typical

    E1 services, and perform the

    hardware inloop for the E1 ports. If

    the hardware inloop is unfeasible,

    perform the software inloop for theE1 ports by using the Web LCT.

    At remote site, connect the E1

    services in a serial manner at the

    DDF, and access them to the BER

    tester. Test the 24-hour BER by using the

    BER tester.

    Record the test result. The result

    should indicate that no bit errors

    occur.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    64/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 63

    Testing the 24-Hour BER (cont.)

    Postrequisites

    If bit errors occur in the first 24-hour BER test, remove the fault.

    Perform another 24-hour BER test until the test is passed.

    If bit errors occur in the test for a serial connection, locate the fault by

    using the dichotomizing search or other methods until each channel

    passes the 24-hour BER test independently.

    R2 New Slide

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    65/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 64

    Testing N+1 Protection Switching

    Prerequisites The equipment must be configured with N+1 protection.

    Aligning the antenna must be complete.

    Tools, Instruments, and Materials

    BER tester

    Web LCT

    Precautions

    The following test procedure takes the E1 services between stations

    as an example. If the E1 service is not configured between stations,perform the test through other configured services such as WS

    services.

    R2 New Slide

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    66/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 65

    Testing N+1 Protection Switching (cont.)

    Procedure

    Connect the BER tester to an E1 port of the equipment on the local side.

    On the equipment on the opposite side, perform hardware inloop over the E1

    port. If the hardware inloop fails, perform software inloop over the E1 port by

    using the Web LCT.

    Test the BER by using the BER tester. There should be no bit errors. Check the working status of the board by using the Web LCT.

    Select an NE from the Object Tree in the NE Explorer. Choose

    Configuration > Link Configuration from the Function Tree.

    Select the N+1 Protection tab page, and click Query. The Switching

    Status of the working unit and the protection unit should be Normal.

    Power off the ODU through the power switch on the active IF board that

    transmits E1 services data.

    R2 New Slide

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    67/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 66

    Testing N+1 Protection Switching (cont.)

    Check the BER test result. The service should recover immediately after a

    transient interruption.

    After the switching is complete, perform BER test for 5 to 10 minutes. There

    should be no bit errors.

    Power on the ODU through the switch on the active IF board.

    Test the BER again by using the BER tester. When the WTR time expires, theservice should recover immediately after a transient interruption. WTR Time is

    set to 600s by default. Test the BER depending on the actual configuration.

    Release the loopback set in 2.

    Refer to 1 through 10 to test the N+1 protection switching of the equipment on

    the opposite side.

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    68/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 67

    Questions

    Can you describe the procedure for aligning the antenna?

    How long does it take to test the E1 / WS / E3/ DS3 service respectively by using the

    BER tester?

    What alarms occur after the IF 1+1 switching is complete?

    What alarms occur after the N+1 protection switching is complete?

    How can we ensure that the switching is performed after the SNCP switching is

    complete?

    How should we handle bit errors occurring in the 24-hour BER test?

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    69/70

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 68

    Summary

    The commissioning items in hop commissioning:

    Aligning the antenna

    Testing the ECC

    Testing the E1 service

    Testing the WS service

    Testing the E3 service

    Testing the order wire

    Testing the clock tracing

    Testing the IF 1+1 switching

    Testing the SNCP switching Testing the 24-hour BER

    Testing the N+1 protection switching

  • 7/28/2019 OptiX RTN 600 Equipment Commissioning-20080801-A

    70/70

    Thank You

    www.huawei.com