47 Agenda – Ordinary Meeting 25 May 2016 - #5097313 ORDINARY MEETING 25 MAY 2016 4 PROJECT LAUNCH APPROVAL FOR CONSTRUCTION OF STAGE 2 WALKER ROAD SPORTING FACILITY - SOCCER AND CRICKET FIELDS AND ASSOCIATED SERVICES Wayne Dagleish | 1/3/81-31 | #5081919v1 RECOMMENDATION: That Council: 1. Approves the construction of Stage 2 Walker Road Sporting Facility project with an overall Project Launch Budget of $5,650,836 and approves the end date of 22 July 2017; and 2. Delegates authority to the Chief Executive Officer in accordance with the Local Government Act 2009 to: a. Approve expenditure up to the value of the project launch budget of $5,650,836 b. Enter into contracts, negotiate and finalise any and all matters relating to this project. EXECUTIVE SUMMARY: Stage 2 is the second construction stage of the Council approved Walker Road Sporting and Recreation Precinct Master Plan located at Edmonton. Four new fields will be constructed consisting of two soccer fields and a senior standard cricket field with turf wicket and an adjacent junior cricket field. Associated services will be provided including an access road, car parking, water sewer and electrical services, irrigation, landscaping and field lighting. Consultation and design of Stage 2 civil and electrical works is now complete and construction project management is to be progressed by Capital Projects Delivery. The construction works will be undertaken by Cairns Works Construction in order to achieve the earliest possible site start and final handover as a three month maintenance period is required for turf establishment beyond the civil works programmed for December completion. The proposed handover completion date is 31 March 2017. Cairns Works have recently completed the adjacent Stage 1 Softball and Baseball facility with a final cost of $7,500,000 anticipated, which will be $431,000 below that approved PLA budget of $7,931,000. This report seeks Project Launch Approval (refer Attachment 1) for the above Stage 2 project works.
Transcript
Page 1: ORDINARY MEETING 4 - Cairns Regional Council · ordinary meeting 25 may 2016 4 project launch approval for construction of stage 2 walker road sporting facility - soccer and cricket

47

Agenda – Ordinary Meeting 25 May 2016 - #5097313

ORDINARY MEETING

25 MAY 20164

PROJECT LAUNCH APPROVAL FOR CONSTRUCTION OF STAGE 2 WALKER ROAD SPORTING FACILITY - SOCCER AND CRICKET FIELDS AND ASSOCIATED SERVICES

Wayne Dagleish | 1/3/81-31 | #5081919v1

RECOMMENDATION:

That Council:

1. Approves the construction of Stage 2 Walker Road Sporting Facility project with an overall Project Launch Budget of $5,650,836 and approves the end date of 22 July 2017; and

2. Delegates authority to the Chief Executive Officer in accordance with the Local Government Act 2009 to:a. Approve expenditure up to the value of the project launch budget of

$5,650,836b. Enter into contracts, negotiate and finalise any and all matters relating

to this project.

EXECUTIVE SUMMARY:

Stage 2 is the second construction stage of the Council approved Walker Road Sporting and Recreation Precinct Master Plan located at Edmonton. Four new fields will be constructed consisting of two soccer fields and a senior standard cricket field with turf wicket and an adjacent junior cricket field. Associated services will be provided including an access road, car parking, water sewer and electrical services, irrigation, landscaping and field lighting.

Consultation and design of Stage 2 civil and electrical works is now complete and construction project management is to be progressed by Capital Projects Delivery. The construction works will be undertaken by Cairns Works Construction in order to achieve the earliest possible site start and final handover as a three month maintenance period is required for turf establishment beyond the civil works programmed for December completion. The proposed handover completion date is 31 March 2017.

Cairns Works have recently completed the adjacent Stage 1 Softball and Baseball facility with a final cost of $7,500,000 anticipated, which will be $431,000 below thatapproved PLA budget of $7,931,000.

This report seeks Project Launch Approval (refer Attachment 1) for the above Stage 2project works.

Page 2: ORDINARY MEETING 4 - Cairns Regional Council · ordinary meeting 25 may 2016 4 project launch approval for construction of stage 2 walker road sporting facility - soccer and cricket

48

Agenda – Ordinary Meeting 25 May 2016 - #5097313

BACKGROUND:

The “Walker Road Sports and Recreation Master Plan” final report datedSeptember 2013 (#4162100) was approved by Council at the Ordinary Meeting on 30 October 2013 (#3981701, #4166133).

The 19.8 hectare Lot 304 Council development site presently has the leased Edmonton Leisure Centre at the south western portion of the site on Walker Road. The balance of the vacant land (approximately 18 hectares) is to be progressively developed based on the approved updated Concept Master Plan and Staging Plan detailed in Attachment 2 (#4752347).

The first development “Stage 1A Sporting Fields for Softball and Baseball” is complete and hand over occurred in April 2016.

This second development “Stage 2” Sporting Fields for Soccer and Cricket” formalises the western central portion of the site adjacent to the existing Edmonton Leisure Centre.

Stage 2 scope includes the provision of:

A new internal access road link with 63 carparks and lighting18,000 m3 of bulk earthworks, shaping and topsoiling Additional 114 carparks with lighting adjacent to the Edmonton Leisure Centre 100m of 375mm diameter trunk sewer modificationsExtension of trunk water, electrical and communications conduit and cableTwo rectangular soccer fields with automated irrigation and field lightingOne senior turf wicket cricket field with manual irrigation, feature picket fence and field lightingOne junior cricket fieldTurfing, landscaping, fencing and signageTemporary 45 bay carpark centrally located adjacent to the future shared soccer/cricket amenities building.

COMMENT:

Construction is programmed to commence immediately to take advantage of dry conditions for construction and provide for the oval line planted turf establishment to coincide with the next wet season. Mulgrave Cricket Club requires their transition to Walker Road to happen as soon as possible. The building platform and services for the future shared soccer/cricket amenities building needs to be constructed in Stage 2 prior to letting that future public tender building contract work (Stage 3).

In ground electrical and irrigation services have been designed in Stage 2 to the ultimate Master Plan requirements ensuring underground capacity is available for future upgrades.

The new fields will be of a high standard with superior infrastructure and lighting for night play and training, increased parking that is fully lit and located adjacent to the future 600m2 shared soccer/cricket amenities building.

Page 3: ORDINARY MEETING 4 - Cairns Regional Council · ordinary meeting 25 may 2016 4 project launch approval for construction of stage 2 walker road sporting facility - soccer and cricket

49

Agenda – Ordinary Meeting 25 May 2016 - #5097313

The central senior cricket oval is designed for multipurpose use providing two junior rectangular fields to service hockey, football, Oztag and touch football. This will be suitable for day and night use in coordination with cricket.

The western smaller cricket field adjacent to Isabella School is suitable for vigoro use. The two adjacent soccer fields fronting Walker Road are also suitable for junior hockey, Oztag and touch football.

The Stage 2 project will be overseen by Capital Projects Delivery and construction works will be undertaken by Cairns Works Construction who have significant experience in the delivery of such projects as demonstrated by the previous Endeavour Park upgrade and Stage 1 sporting fields at Walker Road. With an immediate construction start, the civil works will be completed by December followed by a three month (wet season) landscaping and turfing establishment period resulting in a 31 March 2017 project handover date.

OPTIONS:

That Council approves the Project Launch Approval for an amount of $5,650,836 with an approved end date of 22 July 2017.

Or

Council does not approve the Project Launch Budget.

Ray PlastoManager Capital Projects Delivery

Linda KirchnerGeneral Manager Community Sport and Cultural Services

Page 4: ORDINARY MEETING 4 - Cairns Regional Council · ordinary meeting 25 may 2016 4 project launch approval for construction of stage 2 walker road sporting facility - soccer and cricket

50

Agenda – Ordinary Meeting 25 May 2016 - #5097313

1. Details

Name of Project or Program Walker Road Stage 2 – (Soccer & Cricket fields)

Project Code PCC15143-02 Contract No.

Division Div 2 Branch Parks & Leisure

Department CS & CS Function Code 2756

Unit Sporting Facilities Budget Submission Ref No. 3501172 (M/plan)

Asset Class Recreation Facilities Internal/External Internal

New/Renewal/Upgrade New Document No. #5081919

2. RecommendationIt is recommended that Council:

1. Approves the construction of Stage 2 Walker Road Sporting Facility project with an overall Project Launch Budget of $5,650,836 and approves the end date of 22 July 2017; and

2. Delegates authority to the Chief Executive Officer in accordance with the Local Government Act 2009 to:

a. Approve expenditure up to the value of the project launch budget of $5,650,836b. Enter into contracts, negotiate and finalise any and all matters relating to this project.

PLB (Project Launch Budget) – refer section 9. $5,650,836

AED (Approved End Date) – refer section 4. 22/07/2017

3. Executive Summary

Stage 2 is the second construction stage of the Council approved Walker Road Sporting and Recreation Precinct Master Plan located at Edmonton. Four (4) new fields will be constructed consisting of two soccer fields and a senior standard cricket field with turf wicket and an adjacent junior cricket field. Associated services will be provided including an access road, lit car parking, water, sewer and electrical services, irrigation, landscaping and field lighting.

Consultation and design of Stage 2 civil and electrical works is now complete and construction project management is to be progressed by Capital Projects Delivery. The construction works will be undertaken by Cairns Works Construction in order to achieve the earliest possible site start and final handover as a three month maintenance period is required for turf establishment beyond the civil works programmed for December completion. The proposed handover completion date is 31 March 2017. Cairns Works have recently completed the Walker Road Stage 1 softball and baseball

Page 5: ORDINARY MEETING 4 - Cairns Regional Council · ordinary meeting 25 may 2016 4 project launch approval for construction of stage 2 walker road sporting facility - soccer and cricket

51

Agenda – Ordinary Meeting 25 May 2016 - #5097313

facility with an anticipated final cost of $7,500,000 which will be $431,000 below the approved PLA budget of $7,931,000 for that project.

This report seeks Project Launch Approval (refer Attachment 1) for the above Stage 2 project works.

4. Approved End Date (AED)

Milestone DateDesign Complete 15/5/2016

Construction Start 20/6/2016

Construction Practical Completion 30/3/2017

Approved End Date (AED) 22/7/2017

5. Project Funding Sources

Source Amount ($)

Revenue $5,650,836

Grants $0

Developer Contributions $0

Other (please specify) $0

Project Launch Budget $0

6. Risks (Outline the major risks associated with the project which may impact on delivery of the scoped project on time and on budget.)

Description of Risk Impact of Risk Proposed Solution / How to Mitigate the Risk

Cost to Mitigate ($)

Areas of poor subgrade quality or wet areas

Delays and cost increases

Contingency fund and some time allowed post construction practical completion

Project Contingency

10%

Wet weather delays AED not achieved Proposed AED allows suitable allowances

Ergon Energy delays AED not achieved Proposed AED allows suitable allowances

Comment Council officers have made every attempt to identify risks and mitigate them in the design and planning of these works.

7. Responsible Officers

Project Sponsor Linda Kirchner – General Manager Community Sport and Cultural Services

Owner’s Representative Tim Dendle – Coordinator Leisure Services

Project Manager Wayne Dagleish – Capital Project Delivery PreconstructionLeigh Gniel – Capital Projects Delivery –Superintendents Representative

Other Ray Plasto - Superintendent

Page 6: ORDINARY MEETING 4 - Cairns Regional Council · ordinary meeting 25 may 2016 4 project launch approval for construction of stage 2 walker road sporting facility - soccer and cricket

52

Agenda – Ordinary Meeting 25 May 2016 - #5097313

8. Minimum Energy Performance Standards for New Capital Works ProjectsDoes the project involve the design or installation of any high usage energy consuming equipment or the design or construction of any buildings?

Yes (complete below) No (continue to section 9)

Does the design deviate from Council’s Minimum Energy Performance Standards?

Yes (If yes, provide details and rationale) No

9. Procurement Arrangements

Cairns Works provided Stage 2 price on the 4th May 2016 to undertake earthworks, drainage, sewer, water, electrical services, roadworks, car parking, oval lighting, fencing, irrigation and landscaping. Prices are considered competitive, fair and reasonable to progress with an immediate start of works. An additional 2 months would have to be added to the start date if external tenders are required for pricing these works. Cairns Works are experienced to deliver the works as demonstrated by the previous successfully completed Walker Road Stage 1.

Stage 1 was successfully delivered by Cairns Works under the forecast budget.

10. Project Launch Budget (PLB)Outline the details for the main project phases.

Project Phase Status Costs ITD ($)

Phase Estimate($)

Updated master planning and Stage 2 civil and electrical design

In Progress $215,630 $360,836

Project Management To be Commenced $0 $115,000

Authorities - Ergon, Telstra, Water & Waste

To be Commenced $0 $60,000

Stage 2 Construction To be Commenced $0 $4,650,000

Total $5,185,836

Contingency amount and Comments (basis for contingency required): $465,000

Project Launch Budget (PLB) required: $5,650,836

11. Allowances in the Original Budget vs PLB

2015/16

($)2016/17

($)

Other years

($)

TOTAL($)

Original Budget – Project or Program – Stage 2

$0 $5,500,000 $0 $5,500,000

Page 7: ORDINARY MEETING 4 - Cairns Regional Council · ordinary meeting 25 may 2016 4 project launch approval for construction of stage 2 walker road sporting facility - soccer and cricket

53

Agenda – Ordinary Meeting 25 May 2016 - #5097313

PLB $254,0000 $5,396,836 $0 $5,650,836

Variance or Project Budget remaining

-$254,000 $103,164 $0 -$150,836

Comments

This PCC15143-02 funding PLA is for Stage 2 works as detailed here with all future works to be undertaken as budget becomes available. The recently completed Walker Road Stage 1 project was delivered under budget in the order of $431,000.

12. Attachments:Concept Master Plan #5039574Master Plan Staging #5039577Lease Boundaries Plan #5039583

13. Approval:All necessary planning and other statutory approvals have been identified and/or responsibility for obtaining such approvals has been allocated.

Yes No

14. Legal Review of Underlying ContractsHave the major underlying contracts been reviewed by Council’s legal advisors?

Yes No (If no, outline below how contracts have been drafted)

Cairns Works will be undertaking the construction works

Page 8: ORDINARY MEETING 4 - Cairns Regional Council · ordinary meeting 25 may 2016 4 project launch approval for construction of stage 2 walker road sporting facility - soccer and cricket

54

Agenda – Ordinary Meeting 25 May 2016 - #5097313

Submitted for Approval by:

Name: Ray Plasto

Position: Manager Capital Projects Delivery

Signature: ____________________________

Date:

Endorsed by (as per Capital Expenditure Delegations):

Name: Linda Kirchner

Position: General Manager Community Sport and Cultural Services

Signature: ____________________________

Date:

Approved by Council (as per Capital Expenditure Delegations):

Submitted to: Peter Tabulo - CEO

Date:

To be ratified at the Ordinary Council Meeting

Date:

Page 9: ORDINARY MEETING 4 - Cairns Regional Council · ordinary meeting 25 may 2016 4 project launch approval for construction of stage 2 walker road sporting facility - soccer and cricket

55

Agenda – Ordinary Meeting 25 May 2016 - #5097313

Page 10: ORDINARY MEETING 4 - Cairns Regional Council · ordinary meeting 25 may 2016 4 project launch approval for construction of stage 2 walker road sporting facility - soccer and cricket

56

Agenda – Ordinary Meeting 25 May 2016 - #5097313

Page 11: ORDINARY MEETING 4 - Cairns Regional Council · ordinary meeting 25 may 2016 4 project launch approval for construction of stage 2 walker road sporting facility - soccer and cricket

57

Agenda – Ordinary Meeting 25 May 2016 - #5097313


Recommended