11
OriginsSpaceTelescope(OST)MissionConcept1
Open Issues
Face-to-Face#5June1-2,2017
11
22
Concept1DesignStatus/Issues• Concept1massis~2,000kgoverthelaunchvehicle(VulcanAces5m
fairing)liftcapability– Massfor5instrumentsis2643kg
• Far-IRImager/Polarimeter (FIP):781kg• HighResolutionSpectrometer(HRS):935kg• MediumResolutionSurveySpectrometer(MRSS):435kg• HeterodyneInstrument(HI):383kg• Mid-IRSpectrometer/Imager/Coronagraph(MISC):108kg
• Opticalraytracesforinstrumentsarestillinprogressandsomearenearcompletion– Eliminationofanyoftheseinstrumentswillresultinreworkofraytracesand
packagingforremaininginstruments• Fairingvolumeisextremelytightanduncertain,overallpackagingis
uncertainanddeploymentisstillTBD
• CurrentConcept1istooheavytobelaunchedona5mfairing– Volumeistightanduncertain
33
Solution:LargerLaunchVehicle(LV)
• NASASpaceLaunchSystem(SLS)haslargermassandvolumecapabilitiestoaccommodatecurrentOSTConcept1– FairingSizes: 8.4x19m,10mx31m
• SLSwillbeavailablein2030’swhenOSTwillbereadytolaunch– BothLUVOIRandHabEx missionconceptsincludeSLS
• SLSisadevelopmentprogramanditisyettohaveafirstlaunch– Higherriskiteminmissiondevelopment
• LargerLVcostwillbehigher,howeverlargervolumemayallowflightsystemdesigntobelesscomplex,resultinginlowermissioncostoverall
44
StudyOfficePlanandRequest
• Plantoworkwithinstrumentteamstoscaledowninstrumentvolume,massandpowertofitintoa5meterfairing
• Intheeventthatthescaleddowninstrumentsresultsinexceeding5mfairingcapabilities,weneeddesignflexibilitytoassumealargerLV– InordertocompleteConcept1designby9/30/17,weneed
designflexibility
• StudyOfficerequestsSTDTpermissiontogotoalargerlaunchvehicle,ifnecessary– Needadecisionby6/15/2017,5pm
55
StudyScheduleOriginsSpaceTelescopeDecadalMissionStudySchedule
Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar
Milestone
F2FMeetings
StudyDeliverables
NASAHQApD
Science
Technology
Med-ResolutionSurvey
Specctrogarph
(MRRS)
Far-IRImager/Polarimeter
(FIP)
High-Resolution
Sepectrograph(HRS)
HeterodyneInstrument
(HI)
Mid-IRImager
Spectrometer
(MISC)
InstrumentAccommodation
Module
(IAM)
TelescopeSystem
MissionDefintion,Design,
&Development
CY2017 CY2018 CY2019
f2f #43/21-22
f2f #56/TBD
'Strawman'Telescope design,aperturesizes
Decadal MisssionEnablingTechnology
TRLAssessmentsTRL AssessmentUpdatePrep
Definemissionrequirements,minimumsuccesscriteria,
Defineinstsrumentinterfaces, criteria,
configuration,instrumentplacmentsinIAM
Defineoptical reqrm'ts
Defineoptical reqrm'ts
Instrument def.,reqr,'ts,
HRSIDL(5/1-5)
Instrument def.,reqr,'ts, interfaces,
prepforIAMIDLMRRSI/F f2fMtg
HII/F f2fMtg
MISCI/F f2fMtg
Defineoptical reqrm'ts
Defineoptical reqrm'ts
Instrument def.,reqr,'ts,
interfaces,prepforIAMIDL
Instrument def.,reqr,'ts, interfaces,prep
forIAMIDL
TelescopeIDL#1(8/14-18)
Telescopetypedef.,reqr,'ts, interfaces, prepforTelescopeIDL
MDL#1(9/18-22)
TRL Assessment UpdateReporttoHQ(6/30)
InterimReporttoHQ(12/5)
2MissionConcepts, mission duration, LVselections, ConOps,
prepforMDL,Developend-to-end (ETE)missionschedule
PrelimMissionDesignITR
10/18
f2f #6CANReleased:1/26
Partner
On-Board
Prepare/draft interim report forsubmittal toHQ,Develop sciencecasesforinterimreport
ScienceDefinition, Sciencerequirments, minimumscience, sciencecases
Prep missiondesignforInterimRpt
Mission Design
forInterimRpt
Sciencecases
forInterimRpt
AAS f2f #7 f2f #8
TRL Assessment UpdateReporttoHQ(6/30)
FinalReporttoHQ
OSTPresentation
toDecadal
Committee
Address ITRComments
Mission costing, PrepforMDL#2,
prep forCR
Address ITRComments
Address ITRComments
UpdateTelescopsedesigns, requirements, interfaces,PrepforTelescope IDL #2
UpdateIAMdesignconcept,ceriteria, interfaces,
IAM IDL#2(3/TBD)
TelescopeIDL#2(4/TBD)
MDL#2(5/TBD)
AddressIAM Comments,CRcomments, Finalreport draftandreview
FinalizeScienceRequirments, Scicence Cases,ScienceInstrument operation scenarios
AddressCRcomments, adjustmissioncost, preparefinalreport
MissionDesignITR,CR
Refine ETEmissionschedule andcost
Draft FinalRpt&Review
UpdateMisssionEnablingTechnologyTRLAssessments,DevelopTechnology
Roadmapfortechnology enhancementTRL Assessment Update
Prep&review
DraftTechnologyRoadmap, estimatecostfor technologyenhancement
f2f #9
InstrumentI/Ff2fMtgs(6/13)
Update instrument, requirements, design,interface definitions
Update instrument, requirements, design,interface definitions
Update instrument, requirements, design,interface definitions
Update instrument, requirements, design,interface definitions
Address ITRComments
Address ITRComments
Address ITRComments
Address ITRComments
Address ITRComments
instrument costestimatesreview,finalreviewofinstrument req.criteria,
boundarycondition, operation scenarios
instrument costestimatesreview,finalreviewofinstrument req.criteria,
boundarycondition, operation scenarios
instrument costestimatesreview,finalreviewofinstrument req.criteria,
boundarycondition, operation scenarios
instrument costestimatesreview,finalreviewofinstrument req.criteria,
boundarycondition, operation scenarios
IAMcostestimatesreview,finalreviewofinterfaces, boundary
condition, instrument postionallocations
Telescopecostestimatesreview,interfaces,
boundarycondition, deploymentschemes,
Inputto
IAM IDL#2
Inputto
Inputto
IAM IDL#2
Inputto
IAM IDL#2
Inputto
IAM IDL#2
DetermineSciCaseforCoronagraph(MISC)
IAM#1(7/17-21)
Defineoptical reqrm'ts
Update instrument, requirements, design,interface definitions
instrument costestimatesreview,finalreviewofinstrument req.criteria,
boundarycondition, operation scenarios
FIP IDL(4/17-21)
Instrument def.,reqr,'ts,
interfaces, prepforIDL
Address ITRComments, enablingtechnologies
TeamX
77
OSTConcept1DesignParameters
• 9meterdiameterprimarymirror– Segmented,Off-AxisTelescope
• 5scienceinstruments– Far-IRImager/Polarimeter (FIP)– HighResolutionSpectrometer(HRS)– MediumResolutionSurveySpectrometer(MRSS)– HeterodyneInstrument(HI)– Mid-IRSpectrometer/Imager/Coronagraph(MISC)
• InstrumentAccommodationModule(IAM)• 8cryo-coolerstocoolandmaintainTelescopeandIAMat
4Kelvin• Launchona5meterfairinglaunchvehicle
– VulcanAcesassumed• MissionOperationsOrbitisSunEarthL2
88
5mFairingDesignChallenges1. Massexceedsallowable.2. StowinganddeployingSunshadeandBaffle:
- Mightbeenoughspacetodoitincurrentconfiguration– TBD.Stowedstack-uponlyallowsfor.75minheightforstowingSunshade.
- Engineer,within-depthknowledgeofJWSTSunshadedesign,isjuststartingtolookatit.
- Cableharnessesandcryo lines(volumeTBD)needtostowinsameareaasSunShade.Maynotbeenoughroomforitall.
- Howtodeploythecableharnessesandcryo linesANDtheSunshadewhentheyallstowinsamelocationmaybeunworkable.
- Maynotbeenoughroominbustostoreeverything.ManydeploymentboomsareneededforSunshade.Largeproptanktakesupalotofroom,aswell.LayoutofBusisTBD.
3. CurrentlyHRSinstrumentinterfereswithlowercornerofstowedPrimaryMirror• PackagingofHRSmightnotallowforremovalofinterference– TBD.• RemovingonehexsegmentofPMrequiredifHRSinterferenceremains.
4. CGifstowedassemblywillberatherhigh.HighCGandhighmassmayprecludeusingthislaunchvehicle.
1010
142”
57”Areaofredtriangle=1/2[(142-57)/2]^2=903in^2
AreaofDTA=PixD^2/4=Pix40in^2/4=1256in^2
AreaofbustopshapewithoutDTAarea=142^2– 4(903”)– 1256=20,164in^2– 3,612in^2– 1256in^2=15,296in^2(9.8m^2)
Volumeavailableforsunshadestowageandcableharnessesandcryo lines=9.8m^2x.75m=7.35m^3Areaofsunshade=TBD
BusVolume
1212
PotentialLaunchVehicles
LaunchVehicle ManufacturerCountry
ofOrigin
CostperlaunchFairingSizeDia.byLength
PayloadtoGTO(kg)
PayloadtoL2(3)
Status LaunchSites
Falcon9FullThrust(FT)(1)
SpaceX U.S.A. $62Million 5.2mx13.1m 8,300 3,370(4) FT:Active CapeCanaveralSLC-40KennedySpaceCenterLC-39AVandenbergSLC-4E
DeltaIVHeavy ULA U.S.A $375Million(2014) 5mx19.1m 14,220 10,695 Active SLC-37B,CapeCanaveralSLC-6VandenbergAFB
AtlasV500Series ULA U.S.A NotAvailable 5.4mx20.7m5.4mx23.5m
4,750–8,900 2125-6,165 Active CapeCanaveralSLC-41VandenbergAFBSLC-3E
FalconHeavy SpaceX U.S.A $90Millionforupto8,000kgtoGTO
5.2mx13.1m (27˚)22,200 NotAvailable Indevelopment KennedyLC-39AVandenbergAFBSLC-4E
SpaceLaunchSystem
Boeing,ULA,OrbitalATK,AerojectRocketdyne
U.S.A $500Million 5mx19m8.4mx19m10mx31m
Notavailable NotAvailable Indevelopment LC-39B,KennedySpaceCenter
Ariane5 AirbusDefenseandSpace Europe $165-$220Million(20ESAmemberstates)
5.4mx17m (27˚)ECA(2):10,500 NotAvailable Active GuianaSpaceCentreELA-3,FrenchGuiana
H-llB MitsubishiHeavyIndustries
Japan NotAvailable 5.1mx15m 8,000 NotAvailable Active TanegashimaSpaceCenter,Japan
U.S.A./In
de
velopm
ent
Foreign/
Activ
eU.S.A./Active
Notes:1) FT – Full Thrust is the latest version of the Falcon 9; versions v1.1 and v1.0 are retired from service.2) ECA - The Ariane 5 ECA (Evolution Cryotechnique type A), first successfully flown in 2005, uses an improved Vulcain 2 first-stage engine with alonger, more efficient nozzle with a more efficient flow cycle and denser propellant ratio. The Ariane 5 ECA has a GTO launch capacity of 9,100 kg(20,100 lb.) for dual payloads or 9,600 kg (21,200 lb.) for a single payload. ES - the Ariane 5 ES (Evolution Storable) has an estimated LEO launchcapacity of 21,000 kg (46,000 lb.). Ariane versions A5 G, A5 G+, and A5 GS are retired from service.3) L2 - Lagrange point 2 named after Joseph Lagrange, an 18th century mathematician, who found the solution to the “three-body problem”. Inastrodynamics, the characteristic energy (C3) is a measure of the excess specific energy over that required to just barely escape from a massive body.The units are length2/time2, i.e., energy per mass. In this case an initial C3 estimate of -0.5 km2/sec2 to L2 was assumed.4) Assumes the Drone recovery option for the Falcon 9 FT 1st Stage and launch from SLC-41 at CCAFS.