    OVER-THE-RHINE

  • 8/3/2019 OTR Workgroup - October 18

    3/56

    RESIDENTIAL SALES

    Gateway I , I I , I I I & IV : 152 of the 186 condos (82%) are sold

    (8 were sold since July)

  • 8/3/2019 OTR Workgroup - October 18

    4/56

    RESIDENTIAL LEASING

    Gateway I , I I , I I I & IV : 68 of the 68 apartments (100%) are leased

  • 8/3/2019 OTR Workgroup - October 18

    5/56

    COMMERCIAL LEASING

    69% of space leased (62,720 SF of 91,038 SF). Currently negotiatingmultiple leases.

  • 8/3/2019 OTR Workgroup - October 18

    6/56

    COMMERCIAL LEASING

    Opening soon

    Abigail Street, 1216 Vine Street

    Bakersfield, 1213 Vine Street

    Harper Sloane, 1216 Vine Street

    On The Run Cleaners, 1332 Vine Street

    1215, Taza Mia Coffee Shop, 1215 Vine Street

    Currently negotiating 4 letters of intent

    Would bring total leased SF to 85% of available space

  • 8/3/2019 OTR Workgroup - October 18

    7/56

    Saengerhalle Office Building, home of 3CDC

    COMMERCIAL LEASING

  • 8/3/2019 OTR Workgroup - October 18

    8/56

    COMMERCIAL LEASINGSaengerha l le

    Saengerhalle Tenants SF Business TypeProjected

    Employees3CDC - Leased 7,485 Developer 26Northpointe - Leased 1,650 Developer 6Necco Leased 6,520 Foster Parenting 15SampleSaint - Leased 3,300 Mobile Media 15Kurt Platte - Leased 1,650 Architect 8Four Entertainment Group - Leased 2,510 Entertainment 8Office Space - Available

    3,100 12Vitrue Leased3,300

    Social Media and Branding

    Restaurant Space - Available 2,730 --- ---Total 32,265 90

    --- ---

  • 8/3/2019 OTR Workgroup - October 18

    9/56

    Parvis, 1400 Block of Vine

    COMMERCIAL LEASING

  • 8/3/2019 OTR Workgroup - October 18

    10/56

    PARVIS TENANTS

  • 8/3/2019 OTR Workgroup - October 18

    11/56

    ST. PAULS CHURCH

  • 8/3/2019 OTR Workgroup - October 18

    12/56

  • 8/3/2019 OTR Workgroup - October 18

    13/56

    Mercer Commons

    $53.5 million project

    2.695 acres 19buildings and 26

    vacant parcels 96 market rate apts.

    30 affordable apts.

    28 condominiums

    17,600 SFcommercial

    359 parking spaces

  • 8/3/2019 OTR Workgroup - October 18

    14/56

  • 8/3/2019 OTR Workgroup - October 18

    15/56

    Building Legend

    Existing Buildings tobe Renovated

    Existing Buildings tobe Removed

    14TH STREET

    VINE

    ST

    REET

    WALN

    UT

    STREET

    MERCER STREET

    13TH STREET

    PROJECT SUMMARY

  • 8/3/2019 OTR Workgroup - October 18

    16/56

    Building Legend

    Existing Buildings tobe Renovated

    Existing Buildings tobe Removed

    Alleys to be Restored

    14TH STREET

    VINE

    ST

    REET

    WALN

    UT

    STREET

    MERCER STREET

    13TH STREET

    PROJECT SUMMARY

  • 8/3/2019 OTR Workgroup - October 18

    17/56

    Building Legend

    Existing Buildings tobe Renovated

    Existing Buildings tobe Removed

    Alleys to be Restored

    New Mixed-Use andMulti-FamilyBuildings

    14TH STREET

    VINE

    ST

    REET

    WALN

    UT

    STREET

    MERCER STREET

    13TH STREET

    PROJECT SUMMARY

  • 8/3/2019 OTR Workgroup - October 18

    18/56

    Building Legend

    Existing Buildings tobe Renovated

    Existing Buildings tobe Removed

    Alleys to be Restored

    New Mixed-UseMulti-FamilyBuildings

    New Townhomes

    14TH STREET

    VINE

    ST

    REET

    WALN

    UT

    STREET

    MERCER STREET

    13TH STREET

    PROJECT SUMMARY

  • 8/3/2019 OTR Workgroup - October 18

    19/56

    Building Legend

    Existing Buildings tobe Renovated

    Existing Buildings tobe Removed

    Alleys to be Restored

    New Mixed-UseMulti-FamilyBuildings

    New Townhomes

    New CommunityParking Garage

    14TH STREET

    VINE

    ST

    REET

    WALN

    UT

    STREET

    MERCER STREET

    13TH STREET

    PROJECT SUMMARY

  • 8/3/2019 OTR Workgroup - October 18

    20/56

    Building Legend

    Existing Buildings tobe Renovated

    Existing Buildings tobe Removed

    Alleys to be Restored

    New Mixed-UseMulti-FamilyBuildings

    New Townhomes

    New CommunityParking Garage

    New Green Spaces

    14TH STREET

    VINE

    ST

    REET

    WALN

    UT

    STREET

    MERCER STREET

    13TH STREET

    PROJECT SUMMARY

  • 8/3/2019 OTR Workgroup - October 18

    21/56

    PROJECT SUMMARY

  • 8/3/2019 OTR Workgroup - October 18

    22/56

    28 for-sale units126 apartments (30 affordable)17,600 SF commercial space

    Phase 1

    4 Restored Buildings 11 for-sale units

    5 New Townhomes 5 for-sale units

    1 New Mixed-Use Building12 for-sale units; 3,900 SFcommercial

    1 New Parking Garage 340 spaces

    Phase 2

    13 Restored Mixed-Income Buildings 46 apartments; 8,000 SF commercial1 New Mixed-Income Building 21 apartments; 5,700 SF commercial

    Phase 3

    2 Restored Buildings 8 apartments

    8 New 3-Story Townhomes 16 apartments

    1 New Building 35 apartments

    PROJECT SUMMARY

  • 8/3/2019 OTR Workgroup - October 18

    23/56

  • 8/3/2019 OTR Workgroup - October 18

    24/56

  • 8/3/2019 OTR Workgroup - October 18

    25/56

  • 8/3/2019 OTR Workgroup - October 18

    26/56

  • 8/3/2019 OTR Workgroup - October 18

    27/56

  • 8/3/2019 OTR Workgroup - October 18

    28/56

  • 8/3/2019 OTR Workgroup - October 18

    29/56

  • 8/3/2019 OTR Workgroup - October 18

    30/56

  • 8/3/2019 OTR Workgroup - October 18

    31/56

    WASHINGTON PARKProgramming

    3CDC and the Park Board are holding Washington Park soundingsessions to brainstorm about programming.

    Past Sessions September 29, Lavomatic October 13, Know Theater

    Upcoming Sessions October 25, Emmanuel Community Center

    October 27, Neons

  • 8/3/2019 OTR Workgroup - October 18

    32/56

  • 8/3/2019 OTR Workgroup - October 18

    33/56

    The new City Gospel Mission facility will provide expandedspace currently unavailable at their landlocked Elm St. location

    76 emergency beds for men (double the current total per H2H plan)

    36 transitional beds to support CGMs Exodus recovery program (doublethe current total per H2H plan)

    Full-Day Services Provide programming and counseling that engagesresidents and eliminates forced exit of the facility during daytime hours

    Including an increased ratio of case workers to residents, providingmore one-to-one interaction

    Share facilities with partnering organizations that provide

    complementary programming and services for the homeless (LordsGym & Jobs Plus)

    Improved Sleeping Arrangements Plan calls for 10 or fewer beds in eachroom, which will provide more privacy and reduce health concernsassociated with congested sleeping quarters. Exodus residents in separatesleeping area than homeless-shelter guests

    HOMELESS TO HOMESC i t y G o s p e l M i s s i o n

    http://www.google.com/imgres?imgurl=http://media.gamedaypr.com/2011%20FPM%20Charity%20Logos/City%20Gospel%20Mission.JPG&imgrefurl=http://media.gamedaypr.com/ft2.php?dir=/2011%20FPM%20Charity%20Logos&usg=__tcE4TPiilRx-XtdxkOX4_U-gL8g=&h=600&w=1500&sz=155&hl=en&start=4&zoom=1&um=1&itbs=1&tbnid=60jV-znctHKyHM:&tbnh=60&tbnw=150&prev=/search?q=city+Gospel+mission&um=1&hl=en&sa=N&biw=1003&bih=615&tbm=isch&ei=UJnlTfv2LcnPgAeDmpS6Bg
  • 8/3/2019 OTR Workgroup - October 18

    34/56

    HOMELESS TO HOMESC i t y G o s p e l M i s s i o n

    Project Update: Site has been selected and we purchased the property onJuly 19th.

    Zoning: City Gospel Mission has received zoning approval from the City ofCincinnati

    Architect Drawings: Design Development drawings are completed.Construction drawings should be completed by October 2011.

    Bidding: November 2011

    Construction Start Date: December 2011

    Estimated Completion: Year end 2012

  • 8/3/2019 OTR Workgroup - October 18

    35/56

    HOMELESS TO HOMESC i t y G o s p e l M i s s i o n

    http://www.google.com/imgres?imgurl=http://media.gamedaypr.com/2011%20FPM%20Charity%20Logos/City%20Gospel%20Mission.JPG&imgrefurl=http://media.gamedaypr.com/ft2.php?dir=/2011%20FPM%20Charity%20Logos&usg=__tcE4TPiilRx-XtdxkOX4_U-gL8g=&h=600&w=1500&sz=155&hl=en&start=4&zoom=1&um=1&itbs=1&tbnid=60jV-znctHKyHM:&tbnh=60&tbnw=150&prev=/search?q=city+Gospel+mission&um=1&hl=en&sa=N&biw=1003&bih=615&tbm=isch&ei=UJnlTfv2LcnPgAeDmpS6Bg
  • 8/3/2019 OTR Workgroup - October 18

    36/56

  • 8/3/2019 OTR Workgroup - October 18

    37/56

  • 8/3/2019 OTR Workgroup - October 18

    38/56

  • 8/3/2019 OTR Workgroup - October 18

    39/56

    New Facility will support:

    Basic needs for food, shelter, and safety will be immediately met in a state-of-

    the art facility focused on reducing trauma and optimizing womens health Increased capacity of emergency shelter beds from 42 to 60

    Non-dormitory sleeping quarters (1-4 per private room)

    Full day treatment services tailored to each womans specific needs

    Residents will not be forced to exit facility during daytime hours

    High quality individualized case management (1:10 ratio)

    Comprehensive medical services ranging from on site physical and mentalhealth assessment to treatment and referral

    Parking facility that will not only support the demands of the shelter, but alsoprovide support for the neighboring United Way facility

    HOMELESS TO HOMESY W C A E M E R C G E N C Y W O M E N S S H E L T E R

    The regions first womens specific homeless shelterdesigned to meet womens needs and assist in theirtransition out of homelessness

    http://www.google.com/imgres?imgurl=http://www.shapingyouth.org/blog/wp-content/uploads/2008/11/ywca.jpg&imgrefurl=http://www.shapingyouth.org/?p=3571&usg=___8NABm7gZg-QM3mjHO-Ff_ZBdi0=&h=535&w=952&sz=105&hl=en&start=1&zoom=1&um=1&itbs=1&tbnid=fakinTleK8VMrM:&tbnh=83&tbnw=148&prev=/search?q=YWCA&um=1&hl=en&biw=1003&bih=615&tbm=isch&ei=OZ3lTaTcEs7dgQe86IG3Bg
  • 8/3/2019 OTR Workgroup - October 18

    40/56

    Project Update: Site has been selected and we plan to purchase theproperty in the next few months.

    Zoning: YWCA has received zoning approval from the City of Cincinnati and

    has submitted for a Certificate of Appropriateness to demolish the existingstructure.

    Architect Drawings: Conceptual drawings are in development. Constructiondrawings should be completed by November 2011.

    Bidding: December 2011

    Construction Start Date: January 2012

    Estimated Completion: Early 2013

    HOMELESS TO HOMESY W C A E M E R C G E N C Y W O M E N S S H E L T E R

  • 8/3/2019 OTR Workgroup - October 18

    41/56

  • 8/3/2019 OTR Workgroup - October 18

    42/56

    HOMELESS TO HOMESYWCA

  • 8/3/2019 OTR Workgroup - October 18

    43/56

  • 8/3/2019 OTR Workgroup - October 18

    44/56

  • 8/3/2019 OTR Workgroup - October 18

    45/56

    HOMELESS TO HOMESYWCA

  • 8/3/2019 OTR Workgroup - October 18

    46/56

    HOMELESS TO HOMESYWCA

  • 8/3/2019 OTR Workgroup - October 18

    47/56

    THANK YOU

  • 8/3/2019 OTR Workgroup - October 18

    48/56

    Color Building1400 Vine St.

    Project Cost: $4.1 million6,000 SF office3,680 SF restaurant/retail

  • 8/3/2019 OTR Workgroup - October 18

    49/56

    GATEWAY QUARTERPHASE V:

    Prior to renovationover 100,000 grossSF of space

    21 vacant buildingswill be redevelopedinto 98 residentialunits and 8,500 SFstreet levelcommercial space

  • 8/3/2019 OTR Workgroup - October 18

    50/56

    13th and Republic

    12,600 Gross SF9 for sale units1,065 SF of commercial spaceProject cost: $2,579,626

  • 8/3/2019 OTR Workgroup - October 18

    51/56

    Westfalen II1426-1438 Race Street

    32,798 Gross SF30 for sale units5,400 SF of commercial spaceProject Cost: $6,699,554

  • 8/3/2019 OTR Workgroup - October 18

    52/56

    Bakery Lofts Project1421 23 Race St.

    10,402 Gross SF9 for sale unitsProject Cost: $2,344,266

  • 8/3/2019 OTR Workgroup - October 18

    53/56

    Republic Street Project

    6,500 Gross Sf5 for sale units, 17 rentalsProject Cost: $3,846,821

  • 8/3/2019 OTR Workgroup - October 18

    54/56

    Parvis II1406 and 1412 Republic Street

    12,300 Gross Sf13 rentals1,130 SF of commercial spaceProject Cost: $2,550,407

  • 8/3/2019 OTR Workgroup - October 18

    55/56

    Nicolay1401 Republic Street

    13,293 Gross SF9 for sale units1,035 SF of commercial spaceProject Cost: $2,180,202

  • 8/3/2019 OTR Workgroup - October 18

    56/56

    1401 Elm7,290 Gross SF6 for sale unitsProject Cost:$1,522,518


Recommended