+ All Categories
Home > Documents > Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

Date post: 17-Dec-2015
Category:
Upload: suzan-cunningham
View: 215 times
Download: 0 times
Share this document with a friend
Popular Tags:
24
Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st , 2013
Transcript
Page 1: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

Overview: Hurricane Sandy

1st Quartile Insights Conference

August 21st, 2013

Page 2: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

2

Exelon at a Glance

Generation Companies• Nuclear, Fossil, Wind, Solar

Utility Companies • PECO, ComEd & BGE• 7.9M customers - 6.7M elect.&1.2M gas ( 2nd largest in U.S.)

Shared services including HR, IT and Finance

A founding member of the PJM Interconnection• PJM Interconnection is a regional

transmission organization (RTO) that manages the high-voltage electric grid and the wholesale electricity market that serves 13 states and the District of Colombia

Exelon Corporation is one of the largest electric companies in North America with more than $23 billion in annual revenues. Exelon's family of companies includes energy generation, power marketing, transmission and energy delivery

Page 3: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

33

PECO PROFILE Subsidiary of Exelon Corporation Serving the greater Philadelphia Pennsylvania area for over 100 years 2,100 square miles (5,400 km2) service territory Population Density 3.8 Million in retail service territory (2.3 Million In

Philadelphia) Electric and Gas Utility

• 1.6 M Electric Customers (677,000 in Philadelphia) • 8,984 megawatt peak load• 500K Gas Customers

Page 4: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

44

PECO PROFILE

Primary Distr. Circuit Miles - 21,800 Total (13,000 O/H & 8,800 U/G) Voltages (Distribution) 34kV, 13kV, 4kV, 2.4kV Transmission Miles - 1,063 (including 69 kV) Voltages (Transmission) 500kV, 230kV, 138 kV, 69kV Substations 450 (18,468 MVA Installed Capacity) Circuits (Distribution) 2,200 Distribution Transformers 177,000 Poles 400,000 Reclosers 1,600 Manholes 28,500

Page 5: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

The Forecast

5

Page 6: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

6

Overview of Hurricane Sandy Hurricane Sandy caused widespread

damage along the East Coast

• Overall, more than 9 million customers lost power during the event

• While the New Jersey and New York coast lines were the hardest hit, there was significant impact to southeastern Pennsylvania

• The Pennsylvania Department of Transportation reported that more than 200 bridges and roads were closed because of downed trees, power lines and flooding,

Page 7: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

7

Overview of Hurricane Sandy

In excess of 1.2M PECO customers lost power. Over 840,000 customers experienced a sustained outage and 465,000 were out of service concurrently at the storm peak.

Sandy was the most damaging storm in company history.

Sandy caused approximately 3,500 primary events, 90% more events than Hurricane Irene

Page 8: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

8

Overview of Hurricane Sandy Over 4,700 employees and

contractors worked around-the-clock to repair damage and restore service

Workers from as far away as Louisiana, Mississippi, Florida, Tennessee and Kentucky, as well as ComEd and BGE crews, helped with the PECO effort

Safety, as always, is PECO’s highest priority. We worked closely with our local emergency responders and communicated with our customers regarding safety through multiple communications channels

Coordination between PECO and governmental entities was essential to our emergency response strategy

Page 9: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

Preparation During the week of 10/22, PECO recognized the

potential of the storm and began developing a specific storm response strategy• Modeled on previous Hurricane responses, including

Irene of 2011• Work schedules and accommodations for essential staff

were put in place• Foreign crew resources were identified and secured• Operations sub-centers were opened and staffed• Materials and supplies were staged• The distribution system configuration was normalized• All IT system work was suspended and systems stabilized

On October 26 Governor Tom Corbett declared a state of emergency on October 26 to speed overall preparations• All travel limited to essential personnel only

9

Page 10: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

10

Preparation Initiated Pre-Event Planning and Preparations Five Days Prior to Storm

• Held Pre-Event Conference Calls to Discuss Preparations and Planning

• Around the Clock Staffing Strategy was Organized• Mobilized 1,670 PECO Operations and Support Personnel

Secured More Than 3,030 Additional Personnel for Assistancewith Restoration and Tree Trimming

Conducted Interviews and Briefings with Media to Discuss Storm Preparations, Planning and Customer Outage Expectations

Conducted Outreach with Elected Officials and Local Governments• State Regulatory and Elected Officials• County 911 Centers Outreach and Staffing• Municipal and County Governments

Page 11: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

11

Using Lessons Learned from Irene

Utilization of Established Hurricane Plan

• Utilized a 200 point plan produced as a result of Lessons Learned from Hurricane Irene

Advanced Planning Keys• Activated EOC (Emergency

Operation Center) on Thursday morning (10/25) and remained open through 11/16 for system restoration and recovery work

• Early identification and requests for external support.

Page 12: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

12

Using Lessons Learned from Irene

Staging of Crews• Followed Sub Center model: Staffed

centers, mobilized storm kits and material, accommodation arrangements, etc.

• 240 Crews were on the ground and ready to mobilize before the storm hit

Communications to Employees• Media and communications positions

were double-staffed and followed protocol established during Irene.

Page 13: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

13

Using Lessons Learned from Irene Road Closures

Dedicated External and Operations Coordinators, and up to 8 field teams. PECO cleared 305 roads (~200% over Irene)

Used new system event codes to accelerate ID and dispatch

Customer Communications Regarding Restorations Proactive outbound calls to most impacted customers Four On-Site Command Centers to provide face-to-face communications

opportunities and information sheets for customers in most impacted areas Launched website to provide customers with outage information on mobile

devices

Permitting for Foreign Crews PECO coordinated with PEMA, PENNDOT, the Governor’s Office and the

Turnpike Authorities, as well as officials in other states, to expedite the ability of crews to reach the PECO service territory and support restoration efforts

Page 14: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

14

Hurricane Sandy Statistics

• Start Time – Monday 10/29/12 @ 05:59 • End Time – Tuesday 11/6/12 @ 23:13• Storm Size – Extreme (>1000 Primary Events)• Opcon Level 6 - All Hands• Major Event Days (MED) – 7 days• Primary Events - 3,535• 2.5 beta CAIDI – 177 (2.95 hours)• All-in CAIDI -1,638 (27.3 hours)

Page 15: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

15

Hurricane Sandy Statistics

• Sustained Customer Outage - 843,007• Secondary Non-Outage events (WTR, WDN,WSA) –

3,150 • Customers restored prior to ETR - 48.2%• ETR Reach - 68.9%• Service Level - 92.6%• PECO Field and Gas Mechanics/Foreman - 868• Foreign Crews/Contractors – 2,055• Tree Trimmers – 849• Office - 928

Page 16: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

16

Sandy Outages and Restoration Specific Issues Impacting Restoration

• High winds resulting in down trees• Road closures• 40+ MPH winds that required crews to

stand down for 5 hours• Some localized flooding

Damage to Distribution System (as compared to Irene)• Cross Arms – 2,875 (+37%)• Fuses – 16,522 (+31%)• Poles – 750 (+141%)• Transformers – 390 (+57%)• Wire and Cable – 141 miles (+60%)

Responded to almost 2,600 police, fire and wire down jobs

Polling locations• Due to pending election on Teas. 11/6,

approximately 2,100 polling locations had to be verified to determine outage status, and expedite response as required.

Page 17: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

17

Number and Percentage of Customers Restored

Restored within 24 hours of outage 524,000 62.4%

Restored within 48 hours of outage 678,468 80.6%

Restored within 72 hours of outage 764,801 90.8%

Restored within 7 days of outage 849,830 99.98%

Sandy Outages and Restoration

Customer Restoration Timeline

Restoration Strategy• Restore service to any affected substations/unit substations• Perform switching to re-route power to customers when possible• Restore power to critical care customers • Restore customers with attention given to circuits based on number of affected

customers – cut and run initially• Restore power to smaller neighborhoods and individual services

Page 18: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

18

Lessons Learned from Sandy

A full review of our Hurricane Sandy preparations and response was conducted within departments and as an organization

Successes to be Replicated:• Pre-Planning and early activation set us up for success• Utility Mutual Assistance again played an essential role in ensuring our

ability to respond to the event - PECO joined S.E.E. after Irene• AMR meter pinging prevented approximately 6,100 truck rolls,

accelerating our restoration efforts by 2 to 3 days• Effective communications focused on safety • Our sourcing strategy fully met our needs - No significant material issues• Having ALM’s, Supervisors, and Asplundh at Sub-Centers was very

effective

Page 19: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

19

Lessons Learned from Sandy

New Opportunities (Sandy Lessons learned, in conjunction with Emergency Preparedness Standardization Initiatives, through Exelon Utilities):

• ETR determination and communication strategy review• Sub-Center/Sub-Station process review• Sub-Center communications and dispatch capabilities review• Damage Assessment best practice review• More “seamless” sharing of Exelon resources

• Lock Out / Tag Out consistency between the 3 utilities• Ability to view circuit maps between companies• Electronic Work Packages• Enhanced utilization of GPS

• Further enhancements to Road Closure process• Expand use of social media • Further enhancing our Storm Center website

Page 20: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

20

Lessons Learned from Sandy

Additional opportunities:- Electronic work packages

o GPS prints on CD or flash drive- Clarify and communicate the “sub-center” process

o Enhance sub-centers to be self-sufficient- Improve process for PECO material clean-up after work is

complete- Establish air card process- Lock Out / Tag Out for Annuitants- Create PECO service territory information booklet for

contractors and foreign crews

Page 21: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

21

Appendices

Location# Company # of FTEs # of Crews Date Time Date Time # of FTEs # of Crews1 MJ (ComEd COC) 56 12 28-Oct 20:00 28-Oct 15:00 56 12 Coatsville2 Henkels (ComEd COC) 8 2 28-Oct 20:00 28-Oct 15:00 8 2 G&L3 Intren #1 (ComEd) 40 9 28-Oct 17:00 28-Oct 17:00 40 9 North Wales4 Blue Grass (KY) 32 7 28-Oct 18:00 28-Oct 18:00 32 7 West Grove5 M&M Elec. (KY) 25 4 28-Oct 18:00 28-Oct 18:00 25 4 West Grove6 ComEd #1 111 35 28-Oct 18:00 28-Oct 18:00 111 35 New Hope7 Pike (Group 1-Gulf) 38 9 28-Oct 18:00 28-Oct 18:00 38 9 Warminster8 T&D Solutions 8 2 28-Oct 18:00 28-Oct 18:00 8 2 Emilie9 Meade #1 17 5 28-Oct 18:00 28-Oct 18:00 21 6 North Wales

10 Chain Electric (Gulf) 30 5 28-Oct 18:00 28-Oct 18:00 30 5 North Wales 11 PECO COCs 167 39 29-Oct 6:00 29-Oct 6:00 169 3912 Fischel (Tampa) (Group 1) 50 11 29-Oct 15:00 29-Oct 15:00 50 11 Essington13 Entergy (Group 1) 171 44 30-Oct 13:00 30-Oct 13:00 171 44 N Wales,Warminster14 Southern - Gulf Power 70 18 30-Oct 13:00 30-Oct 13:00 70 18 Plymouth15 Southern - Mississippi 62 10 30-Oct 13:00 30-Oct 13:00 62 10 Plymouth16 Pike (Group 3 -FPL) 12 3 30-Oct 22:00 30-Oct 22:00 12 3 Warminster17 FPU (FL) 11 3 31-Oct 9:00 30-Oct 23:00 11 3 Warminster18 Fischel (Group 2) 13 3 30-Oct 22:00 30-Oct 23:30 13 3 West Grove20 Duke Florida (VA) 156 24 31-Oct Late 31-Oct 22:00 156 24 Warminster21 Duke COC (Pike #4) 62 29 31-Oct Late 31-Oct 22:00 69 29 Emilie22 Sumter (Duke COC-NC) 27 5 31-Oct 22:00 31-Oct 22:00 27 5 Plymouth23 MB Haynes (Duke COC-NC) 23 5 31-Oct 21:00 31-Oct 22:00 23 5 Plymouth24 Pike #5 59 15 1-Nov 12:00 1-Nov 14:00 59 15 Essington25 Mastec 22 3 1-Nov 14:00 1-Nov 21:00 22 3 Essington26 (Miss Power #2) Southern 19 3 2-Nov 12:00 1-Nov 22:00 19 3 Plymouth27 MJ (ComEd COC) 25 6 1-Nov 18:00 1-Nov 22:00 26 6 Coatsville28 Intren #2 (ComEd) 89 21 1-Nov 22:00 1-Nov 22:00 89 21 Willow Grove29 ComEd #2 114 41 2-Nov 11:00 2-Nov 11:00 114 41 New Hope30 Davis Elliot (BGE COC) 111 18 2-Nov 11:00 2-Nov 11:00 89 18 Upper Makefield31 Pike #6 (BGE) 109 23 2-Nov 11:00 2-Jan 11:00 105 20 Berwyn32 Entergy (Group 2) 58 7 2-Nov 12:00 2-Nov 11:00 58 7 Coatsville33 BGE Utility (#1) 46 11 3-Nov 11:00 3-Nov 10:00 40 10 Upper Makefield34 Davis Elliot 2 (BGE COC) 93 20 3-Nov 11:00 3-Nov 10:00 99 22 Berwyn35 Pike #7 (BGE COC) 47 10 3-Nov 11:00 3-Nov 10:00 47 10 Willow Grove36 Henkels (BGE COC) 3 1 3-Nov 11:00 3-Nov 10:00 3 1 G&L37 Riggs 2 (BGE COC) 36 12 3-Nov 10:00 3-Nov 10:00 40 9 Essington38 East Coast Util. 14 2 3-Nov 15:00 3-Nov 15:00 14 2 Upper Makefield39 Rock Creek 10 2 4-Nov 9:00 4-Nov 9:00 10 2 Upper Makefield40 BGE Utility (#2) 24 10 4-Nov 23:00

Hurricane Sandy Primary Qualified Resources

Est. Arrival Time Actual Arrival TimeCommited Resources Acquired Resources

Page 22: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

22

Appendices

Thursday, November 1, 2012 Friday, November 2, 2012Time (Hour): 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00 00:00 01:00 02:00 03:00 04:00 05:00 06:00 07:00

BM Crews 34 34 34 34 34 34 34 34 6 6 6 6 6 6 6 6 6DC Crews 44 44 44 44 44 44 44 44 11 11 11 11 11 11 11 11 11PH Crews 17 17 17 17 17 17 17 17 6 6 6 6 6 5 5 5 5

95 95 95 95 95 95 95 95 23 23 23 23 23 22 22 22 22REGIONAL PERSONNEL

TOTAL REGIONAL PERSONNEL SUBCENTER SUPPORT

Contractors (from contractor tab)

BUCKSMONT 212 212 212 212 212 212 212 212 0 0 0 0 0 0 0 0 0

DELCHESTER 64 64 64 64 64 64 64 64 0 0 0 0 0 0 0 0 0

PHILADELPHIA 21 21 21 21 21 21 21 21 0 0 0 0 0 0 0 0 0

297 297 297 297 297 297 297 297 0 0 0 0 0 0 0 0 0

392 392 392 392 392 392 392 392 23 23 23 23 23 22 22 22 22

ETs 83 83 83 83 83 83 83 83 10 10 10 10 10 10 10 10PQTs PR 14 14 14 14 14 14 14 14 0 0 0 0 0 0 0 0Sub. OPS 13 13 13 13 13 13 13 13 7 7 7 7 7 7 7 7Fault Locate PR 19 19 19 19 19 19 19 19 11 11 11 11 11 11 11 11TMen PR 56 56 56 56 56 56 56 56 24 24 24 24 24 24 24 24

DOC Field Resources with ETs Total 185 185 185 185 185 185 185 185 52 52 52 52 52 52 52 52 0DOC Dispatchable Units w/o ETs,

Sub Ops Total PR 89 89 89 89 89 89 89 89 35 35 35 35 35 35 35 35 0SDI 7 7 7 7 7 7 7 7 0 0 0 0 0 0 0 0 0SDII 20 20 20 20 20 20 20 20 0 0 0 0 0 0 0 0 0Net Ops 5 5 5 5 5 5 5 5 0 0 0 0 0 0 0 0 0CID 4 4 4 4 4 4 4 4 0 0 0 0 0 0 0 0 0

221 221 221 221 221 221 221 221 52 52 52 52 52 52 52 52 0

TOTAL DISPATCHABLE UNITS (Regional Crews, Contractor

Crews, Tmen, Fault Locate and PQTs) 481 481 481 481 481 481 481 481 58 58 58 58 58 57 57 57 22

215 215 215 215 215 215 215 215

T&S / F&MS Secondary Crews

Wire Watchers 80 80 80 80 80 80 80 80Non traditional Odor Coverage 20 20 20 20 20 20 20 20Patrollers ERM 38 38 38 38 38 38 38 38Bird Dogs ERMSecondary Screeners (M&DS) 8 8 8 8 8 8 8 8T&S Mechanics (On-System Est.)

DSO

Crews/Personnel On System By the Hour

TOTAL PECO Regional, Foreign & Contractor Crews

Total REGIONAL Crews

Total Contract Crews

TOTAL DSO PERSONNEL

TOTAL PECO/DSO/CONTRACTOR PERSONNEL

VEG. MGMT. CREWS

Page 23: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

https://www.peco.com/CustomerService/OutageCenter/Pages/default.aspx23

Page 24: Overview: Hurricane Sandy 1 st Quartile Insights Conference August 21 st, 2013.

24

Questions?


Recommended