+ All Categories
Home > Documents > Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007...

Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007...

Date post: 10-Jun-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
46
Overview of Cork Docklands Infrastructure Engineers Ireland Presentation 27 January 2009 Seamus Coghlan – Senior Engineer, Docklands Directorate – Cork City Council
Transcript
Page 1: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Overview of Cork Docklands Infrastructure

Engineers Ireland Presentation27 January 2009

Seamus Coghlan – Senior Engineer, Docklands Directorate – Cork City Council

Page 2: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Presentation• Why Cork Docklands?• Framework of South Dock LAP• Access • Flooding• Water Supply• Drainage• District Heating• Seveso

Page 3: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

The N.D.P (2007 – 2013) Vision for the Cork Gateway

• The key challenge identified for Cork during the lifetime of the N.D.P. is 'to significantly accelerate its rate of development and population growth, focussing particularly on the potential of its central area.’

• However the N.D.P. recognised that investment in physical infrastructure to trigger subsequent private investment is necessary. Among the key development and investment priorities identified are roads, water services, port relocation and associated infrastructure to facilitate the regeneration of Cork Docklands and the re-opening of the Cork City-Midleton rail service by 2008.

Page 4: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Cork Gateway

Cork is the second city in the Republic of Ireland and the primary centre of the South West Region;

It is a designated Gateway under the National Spatial Strategy.

Page 5: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Cork Area Strategic Plan: Vision for the Cork Gateway

• A key element of C.A.S.P.'s vision for Cork is that a revitalised City Centre will act as the main economic driver of development in the Region with the redevelopment of the City’s Docklandsseen to form a vital role in the City’s renewal.

• CASP Update reinforces Docklandsas the key development for the city facilitating FDI with suitable 3/4G accommodation within the city centre and increased sustainable population growth.

Page 6: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

CASP - Metro Area

Page 7: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Cork City Council: Vision for the Cork Gateway

Cork Docklands Development Strategy, 2001:

A new urban quarter for Cork that will revitalise the City through high quality contemporary design and a mix of uses

Page 8: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Cork City Council: Development Plan

• Strategy transposed into the Cork City Development Plan 2004.

Page 9: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

North and South Docks Local Area Plans

• Brady Shipman & Martin• O’Mahony Pike Architects• JODA Consulting Engineers• ILTP Transportation

Consultants• AKC Quantity surveyors• UCC Archaeology Dept

Page 10: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Docklands Location

• On the River• Proximate to City centre• Adjacent to Transport Hub

(Kent station and Bus Station)

• Sustainable• Critical Mass• Existing services

Page 11: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Cork Docklands Local Area Plan Boundaries

Page 12: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Key Infrastructural Issues and Constraints

• Access & Movement• Flooding• Water Supply• Drainage• Seveso

Page 13: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Access and Movement

• Traffic Modelling• LAP

– ILTP – Paramics– Atkins – CASP Saturn

• EIS - MVA

Page 14: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

South Docks LAP Framework

• Access• Pedestrians/Cyclists• Vehicles• Public Transport

• Bridges • Road upgrades• District centres – transport stops• Transport Corridor• Southern Access

Page 15: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

South (and North) Docks Zonings

• Mixed Use • Education and R&D• District centres • Commercial

Page 16: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

South Docks Massing

Page 17: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

South Docks Massing

Page 18: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Docklands Key Outcomes

• 25,000 residents• 27,000 jobs• 4km of Quay Amenity• Marina Park 33ha• Multiple opens spaces/pocket parks and plazas• Primary and secondary schools• Cultural and community facilities• 3rd and 4th Level Education• Facilitation of City competitiveness and FDI • District Heating

Page 19: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Spine Road Network• Eastern Gateway Bridge• Water St Bridge• Centre Park Road• Monahan’s Road • Water St N/S Link Rds

Page 20: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Water St Bridge• Bascule “Seagull” Design• Mott McDonald Pettit Consulting Engineers• 50m Opening Span• Facilitate Port Traffic • Single c’way 3 lane (2+buslane)• Iconic• €40 million

• Navigation Simulation

Page 21: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Spine Road Network

• Staged construction

• Facilitate Access to existing Business during Construction

Page 22: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Spine Road Network – Typical Sections

Centre Park Rd • 32m • Single c’way• HQPT Corridor

Monahan’s Road• 29m (min)• 4 Lane• 2 bus lanes

Page 23: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Spine Road Network – Land Acquisition• Minimise impacts

on existing Business

• Temporary Access to existing properties

• Raised levels• Temporary

embankments• Temporary

Retaining Walls

Page 24: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Flooding - Historical Background

• Narrow Channel• Scouring effect• Facilitate port traffic

1774

1801

• Docklands is a polder

Page 25: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Historical Background

• City Park

1832

1841

Page 26: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Historical Background• City Park• Fords

1932

1932

Page 27: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Flooding• Raise or Protect ?• Risk Hierarchy• Raise levels - 3.5mOD – Short term mitigation• Perimeter Protection – 4.5mOD – residual risk – long term

mitigation• Relative impact assessment – no impacts on city centre• 1 in 200 year Joint (spring + surge ) probability Analysis –

3.35mOD• Sea Level Rise – 0.55m (mid range prediction)• Settlement / Wave action – 0.6m• Lee Catchment Flood Risk & Management Study CFRAMS

– due for completion mid 2009 (Halcrow)• DOEHLG Planning Guidance on Flood risk

Page 28: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Flooding Mitigation Strategy

FFL 3.5mOD

Perimeter protection 4.5mOD

Flood Resilience

Temporary demountables

Page 29: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Storm Drainage• Docklands is a Polder• Previously storage proposed – Tobin Gronmij• Raise levels - 3.5mOD • Drain directly to river• Overflow to Lower Level• SUDS

– Quantity – No Attenuation required– Quality – Removal of silts and particulates

Page 30: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Storm Drainage• Docklands is a Polder• Previously storage proposed – Tobin Gronmij• Raise levels - 3.5mOD • Drain directly to river• Overflow to Lower Level

Page 31: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Storm Drainage• Drainage Drawing

Page 32: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Eastern Gateway Bridge – V&H Alignments

• 3 Elements– Railway

Culvert– River Bridge– Marina Bridge

Page 33: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Eastern Gateway Bridge – V&H Alignments

• Marina Clearance 5.3m• River Clearance 6.5m

above HAT.

Page 34: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Eastern Gateway Bridge

Page 35: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Eastern Gateway Bridge

• Single Cable stayed Swing Bridge

• 50m span• €80 million (total inclapproach roads)

Page 36: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Eastern Gateway Bridge - Photomontage

Page 37: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Eastern Gateway Bridge – Protection

Page 38: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Spine Road Network - Status

• EGB Consultancy– Stage 1 completed by ARUP (purchased by negotiation)– Stages 2-5 procured– ARUP successful – awaiting appointment

• Water St Bridge– Stage 1 completed by MMP– Stages 2-5 to be procured

• Docklands Infrastructure Phase 1– EIS & CPO submitted May 2008– Oral Hearing in progress– Decision expected in mid 2009 from ABP

Page 39: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Water Supply• Feasibility Report 2003 (Carl Bro)

– Upgrades to existing system required from Lee Road system – Primary source from Glashaboy Scheme– Extension of Tivoli Watermain – Phase 2

• Preliminary report currently being procured– WSIP– Stage 2 – tender submissions

• Tivoli Watermain (Phase1) being Constructed– Consultants – Atkins– Contractor – McGinty O’Shea– Dunkettle to Tivoli Ind. Estate– ~ €2.5 million– Completion April 2009

Page 40: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Water Supply• Drawing?

• 600mm dia Ductile Iron• Connect to 900mm CCHWSS Dunkettle• Connect to exiting 350mm Tivoli Ind. Est.•Adjacent to Cobh/Midleton Railway• Rail Culvert • Pipe bridge

Page 41: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

District Heating• Feasibility Report (Draft) 2009

(WYG) • Significant benefits

– Carbon savings– Reduced costs to developers– Compliance with Building regs– Future proofing against higher standards

• Proven Technology– CHP– Biomass– Geothermal

• Financial Model– Commercially viable– Strong Business Case

Page 42: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

District Heating

•Key Role of CCC– Leadership– Pipework

• Other Key Stakeholders– BGE– ESB– ESCO

• Next Steps (draft)– Develop Council Policy– Seek funding From SEI– Formalise group with interest– Investigate procurement– Undertake Preliminary report

Page 43: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Seveso

• COMAH Regulations• HSA Role – LUP Advice to LA•Gouldings• NORA• Topaz•Buncefield & PADHI (UK HSE) Guidance• Site-based Quantitive Risk Assessments• Tax Incentives

Page 44: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Other Project Briefs• Public Realm

– 2 No. Projects• Marina Park • Pocket Parks and Hard Landscaping

– Integrated & Cohesive Design Concept & Masterplan for all of Docklands and Marina Park

– Advert due in early February

• River Usage Management Plan– Recreational needs– Management of potential usage and

conflicts arising from increased usage

– Provision of Specific land based facilities (slipways, moorings and marinas)

– Key stakeholders : Port, Rowing clubs, public and future potential users

Page 45: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Conclusion• Significant role played by infrastructure• Large influence on framework layout• Estimated costs of approx €700 million• Significant procurement progressing• FUNDING

– Government Funding – Developer funding – Docklands development contribution scheme– Difficult times!

• Work with Port on Relocation •Assist in and encourage relocation of Seveso• Continue Planning and procuring – be ready for upturn!• THANK YOU FOR LISTENING

Page 46: Overview of Cork Docklands Infrastructure Engineers Ireland … · 2010-03-26 · The N.D.P (2007 – 2013) Vision for the Cork Gateway • The key challenge identified for Cork during

Overview of Cork Docklands Infrastructure

Engineers Ireland Presentation27 January 2009

Seamus Coghlan – Senior Engineer, Docklands Directorate – Cork City Council


Recommended