OVERVIEW OF ENERGY SECTOR IN VIET NAM AND PARTNERSHIP INVESTMENT OPPORTUNITIES Nguyen Thai Son Director of Planning Department General Directorate of Energy MOIT 27-6-2012
Transcript

OVERVIEW OF ENERGY SECTOR IN VIET NAM AND PARTNERSHIP INVESTMENT OPPORTUNITIES

Nguyen Thai Son

Director of Planning Department

General Directorate of Energy – MOIT

27-6-2012

Content

Strategy for national energy development

Current status and development plan

Investment proposals

1

Q&A

Power sector

Oil and gas sector

Coal sector

Overview of socioeconomic

Renewable energy sector

Current status and development plan

In

tro

du

cti

on

O

ve

rvie

w o

f so

cia

leco

no

mic

2

Area 331.150,4 km2

Population 86,2 mil

Number of provinces 63

GDP growth rate

- 2006-2010 7%/year

- Year 2011 5,9%/year

- First 4months of year 2012 4%

- Planning for period of 2011-2015 6,5-7%/year

Strategy for national energy development

De

ve

lop

me

nt

str

ate

ry

3

- - Energy development must be closely linked to national social - economic development strategy and ensure a step ahead at high speed, sustained, coordinated, diversification of energy sources and energy saving technologies.

- Gradually set up the energy market, diversification of ownership and business methods, aims to satisfy the best interests of consumers. Accelerate the abolishing subsidies and remove exclusive, advanced to eliminate the implementation of social policy through energy prices;

- Synchronized and rational development of energy system: electricity, petroleum, coal, new and renewable energy, including interest in clean energy development, priority development of new and renewable energy;

- Improve efficiency, energy efficiency business. Focus on investment in energy efficiency, reduce losses;

- Development of energy tied to preserving the ecological environment, ensuring the implementation of sustainable energy development.

(Decision 1855/QĐ-TTg dated 27th December 2007)

Current status – Generation share & load growth

Cu

rre

nt

sta

tus &

de

vp

t. p

lan

4

Power sector

EVN

54%

Tư nhân

3%

Cổ phần

15%

TKV

3%

IPP, BOT nước

ngoài

10%

PVN

10%

Nhập khẩu

4%

Khác

1%

Thủy điện

40.3%

Nhiệt điện than

15.1%

Nhiệt điện dầu

2.7%

Tuabin khí

33.1%

Nhập khẩu

3.7%

Khác

2.8%

Nhiệt điện chạy khí

2.3%

Depend on owner Depend on kind of source

2011

Total installed capacity 23500MW

Commercial electricity 93,8 bil kWh

Electricity growth rate

Period of 2006-2010 13,7%

Year 2011 9,5%

CURRENT STATUS OF GENERATION SHARE

Current status – Grid

5

U« ngBÝ

Ph­ícLong

Cu

rre

nt

sta

tus &

de

vp

t. p

lan

Power sector

Voltage Line (km) Substation

(MVA)

220kV 10,015 22,004

110kV 13.449 5.960

6-35kV 135,371 39,804

LV 240,424

Voltage Line (km) Substation

(MVA)

500kV 3,890 10,650

Viewpoints for development

6

a) Development of the power sector must be associated with national social - economic development strategy, ensure enough electricity to supply the national economy and social life.

b) Efficient use of energy resources for power development internally the country, combined with the import of power, reasonable fuel imports, diversification of primary energy sources for electricity production, fuel conservation and ensure energy security for the future

c) Gradually improve the quality of electric power to provide electricity services to the increasing quality. Implementation of the electricity price under the market mechanism to encourage investment in power sector development and encourage the use of power saving and effective.

d) Power development along with protecting natural resources, environmental protection ecological guarantee the country's sustainable development

e) Progressive formation and development of competitive electricity markets, diversifying forms of investment and trading. Only State monopoly transmission grid to ensure the security of national energy system.

f) Development of power sector based on the rational use and effective source of primary energy resources of each region; to continue promoting rural electrification, guaranteed to provide full and continuous and safety for electricity demand in all regions nationwide.

Cu

rre

nt

sta

tus &

de

vp

t. p

lan

Power sector

Development Plan – Generation share & elect. growth rate

7

Electricity growth rate

Period of 2011-2015 14,1-16%/yr

Period of 2016-2020 11,3-11,6%/yr

Period of 2021-2030 7,8-8,8%/yr

Cu

rre

nt

sta

tus &

de

vp

t. p

lan

Power sector

0

20,000

40,000

60,000

80,000

100,000

120,000

140,000

160,000

2015 2020 2025 2030

Nuclear Power

Renewable Energy

Imported

Coal Fired Thermal Power

Oil and Gas Fired Thermal Power

Hydropower & Pump Storage

Development Plan – Transmission grid

8

Cu

rre

nt

sta

tus &

de

vp

t. p

lan

Power sector

NOTE

500kV: Existing 500kV line

220kV: Existing 220kV line

Existing 500kV

substation Existing 220kV

substation

Existing TPP

500kV: 500kV line (- 2010)

500kV substation(-

2010)

500kV: 500kV line (- 2020)

500kV substation(-

2020)

MAP FOR NATIONAL

POWER SYSTEM PLANNING TO 2030

Pha

Lai Uong Bi

Hai Phong

Ninh Binh Thanh Hoa

Chem Ha Dong

Ha Tinh Vinh

Dong Hoi

Yaly Vinh Son

Plei Ku Quy Nhon

SongHinh

Thac Mo Da Nhim

Bao Loc Tri An

Ba

Ria

Tra

Noc Rach Gia Cai Lay

Phu Lam

LAOS NORTHERN REGION

CHINA

CAMBODIA Krong Buk

Dinh

Mai Dong

Hoc Mon

Nho Quan

Di Linh

Phu My Nha Be

Thuong Tin

Quang Ninh

D.Nai3&4

Nhon Trach Song May

Son La Soc Son

Nha Trang

Nuclear Power

Ban Sok

SOUTHERN REGION

CENTRAL REGION

Lai Chau

HOA BINH

Viet Tri

Quang Tri

Da Nang

Doc Soi

Sam Bor

Tan Dinh

O Mon

Thac Ba

Region

Period of 2011-2015 Period of 2016-2020 Period of 2021-2025 Period of 2026-2030

No. of

stat.

No. of

transf.

Cap.

(MVA)

No.

of

stat.

No. of

transf.

Cap.

(MVA)

No. of

stat.

No. of

transf.

Cap.

(MVA

)

No.

of

stat.

No. of

transf.

Cap.

(MVA)

Northern 8 11 6750 11 13 13100 11 14 12700 6 9 7500

Central 1 2 900 4 4 2400 1 1 900 4 4 2550

Southern 11 14 9450 11 13 11250 10 13 10800 10 13 10350

Total 20 27 17100 26 30 26750 22 28 24400 20 26 20400

Region

Period of 2011-2015 Period of 2016-2020 Period of 2021-2025 Period of 2026-2030

No. of trans.

lines Length (km)

No. of trans.

lines Length (km)

No. of trans.

lines Length (km)

No. of trans.

lines

Length

(km)

Northern 8 1443 18 2015 7 680 5 760

Central 3 1074 4 630 0 0 3 920

Southern 13 1361 11 1890 3 1554 6 1044

Total 24 3878 33 4535 10 2234 14 2724

Development Plan – Construction volume

Power sector

9

500kV transformer

500kV transmission line

Cu

rre

nt

sta

tus &

de

vp

t. p

lan

10

220kV transformer

220kV transmission lines

Region

Period of 2011-2015 Period of 2016-2020 Period of 2021-2025 Period of 2026-2030

No.

of

stat.

No. of

transf.

Cap.

(MVA)

No.

of

stat.

No. of

transf.

Cap.

(MVA)

No.

of

stat.

No. of

transf.

Cap.

(MVA)

No.

of

stat.

No. of

transf.

Cap.

(MVA)

Northern 68 74 155438 75 82 18063 64 76 17400 72 87 21250

Central 22 24 3925 20 20 3750 26 27 6000 26 27 5750

Sounthen 47 73 16500 56 75 17250 66 81 19375 78 107 26250

Total 137 171 175863 151 177 39063 156 184 42775 176 221 53250

Region

Period of 2011-2015 Period of 2016-2020 Period of 2021-2025 Period of 2026-2030

No. of trans.

lines Length (km)

No. of trans.

lines Length (km)

No. of trans.

lines Length (km)

No. of trans.

lines

Length

(km)

Northern 60 3864 41 1584 44 1606 31 2168

Central 28 2867 15 1546 9 1362 5 916

Sounthen 70 3906 45 2175 41 2584 41 1936

Total 158 10637 101 5305 94 5552 77 5020

Development Plan – Construction volume

Power sector

Cu

rre

nt

sta

tus &

de

vp

t. p

lan

Development Plan– Capital investment

11

Items

2011-2015

2016-2020

2021-2025

2026-2030

2011-2030

I- For Power generation

22,076/ 4,415

28,830/ 5,766

27,005/ 5,401

32,441/ 6,482

110,322/ 5,516

II- For Grid 7,245/ 1,449

10,523/ 2,105

12,345/ 2,469

15,868/ 3,174

45,981/ 2,299

Total

29,321/ 5,864

39,353/ 7,871

39,349/ 7,870

48,280/ 9,656

156,303/ 7,815

Total Capital Investment needed/ Average Capital Investment per year (Bil. USD)

No. Investor Capacity

(MW) Investment ratio

1 EVN + TKV+PVN 26.874 49,49%

2 BOT 16.128 29,70%

3 IPP + Others 11.292 20,80%

Total 54.294 100,00%

Investment ratio of power project in period of 2011-2020

Power sector

Cu

rre

nt

sta

tus &

de

vp

t. p

lan

Roadmap for electricity tariff

12

Power sector

Cu

rre

nt

sta

tus &

de

vp

t. p

lan

Competitive Generation

Market

(VCGM)

Electricity Wholesale Market Electricity Retail Market

2010 2014 2016 2022 2024

Pilot

Operation

Full

Operation

Pilot

Operation

Full

Operation

Pilot

Operation

Full

Operation

13

SUPPORTING MECHANISM FOR WIND POWER DEVELOPMENT PROJECS (Decision 37/2011/QĐ-TTg dated 29th June 2011)

• Underwriting electricity produced from grid-connected wind power plants;

• Investment incentives, taxes, fees;

• Preferential land infrastructure;

• Support price of electricity for grid-connected wind power project

Avoided cost tariff

(Decision 18/2008/QĐ-BCT dated 18th July 2008)

-The avoided costs of the national power system is calculated when there is a (01)kWh power from small power plants using renewable energy is emitted into the distribution grid;

-Avoided costs as production costs of the generator 1kWh have the highest cost in the national electricity system, these costs can be avoided if buyers purchase1kWh from a small power plants using renewable energy replacement.

Cu

rre

nt

sta

tus &

de

vp

t. p

lan

Renewable Energy sector

14

Development Plan– Resource

Capacity of Renewable Energy on-grid (MW)

Capacity 2011-2015 2016-2020 2021-2030 2011-2030

Total 1198 2408 9588 13194

Wind power 213 780 5200 6193

Small Hydro power 895 1100 2380 4375

Biomass (solid) 50 305 1500 1855

Waste 39 100 200 339

Geothermal 0 80 198 278

Solar power 1 9 45 55

Biogas 1 34 65 100

Capacity of Renewable Energy off-grid (MW)

Capacity 2011-2015 2016-2020 2011-2020

Solar system 12,3 10 14

Small Hydro power (off grid) 31,2 25,6 58

Biogas 1,3 1 5

Wind power-diesel system 3,6 3 8

Solar-diesel system 4,6 3,8 8

wind-diesel-solar system 3.6 2,3 9

Total 56,7 45,7 102,4

Cu

rre

nt

sta

tus &

de

vp

t. p

lan

Renewable Energy sector

15

For grid-connected electricity from renewable energy sources for the period of the chosen scenario (20 years) with average investment rate of 1.34 million USD/MW (13.194MW). However, this capital will be invested by the mobilize capital of enterprises. Capital estimated 350.000 billion VND.

For electricity from off-grid renewable energy source: Total investment of 14.969 billion VND. This support capital is invested by the state.

For renewable energy use for heating: The total investment for the period was 42,000 billion VND. This capital is invested by people for household equipment and installation. It will be considered a small support in the early stage to stimulate using renewable energy movement and market development.

The total subsidies for the basic plan implemented in the period from 2011 to 2020 with the current calculation is 20.773 billion VND. In particular for electricity from renewable energy on-grid is 3953 billion (19%), renewable electricity off-grid is 14.969 billion VND (72%) renewable heat is 1857 billion VND (9%).

Renewable Energy sector

Cu

rre

nt

sta

tus &

de

vp

t. p

lan

Development Plan– Capital investment

16

Oil &Gas sector

Viewpoints for development

Effective use of petroleum resources in the country, and to promote investment, search, exploration and exploitation of oil and gas abroad, combined import and export as a basis for sustainable development of the petroleum industry firmware, ensure energy security for the economy.

- Developing internal resources, combined with expanding international cooperation, attracting foreign investment in search activity, exploration, increases in oil and gas reserves verified.

- Prioritize search, exploration and exploitation of the deep water, offshore.

- Encourage participation of all economic sectors and foreign investment in developing the field of processing, distributing products and services etc..

Cu

rre

nt

sta

tus &

de

vp

t. p

lan

17

Planning – Exploration, exploitation, processing, transportation

Cu

rre

nt

sta

tus &

de

vp

t. p

lan

3. Development of gas industry:

+ Development towards diversification of markets, gas will be provided to the industry: power generation, fertilizer, chemical, industrial, transportation and civil-scale production of about 19 billion m3 in 2025.

+ Research pipeline connecting East - South West, a gas pipeline as a basis for transnational connection with gas pipeline in Southeast Asia.

+ Strengthening international cooperation and selection of strategic partner capable of long-term gas supply LNG, CNG, DME ... from Russia, the Middle East, Australia, Africa ... etc..

+ Prepare infrastructure, promote and encourage the construction contractor collection systems offshore.

+ Cooperation, research technology solutions to recover gas is burned off at the platform in separating the high-value products such as Ethan, propane-butane(LPG). Development and exploitation of gas fields with high CO2 content.

+ Research and Development projects of gas to form combinations of oil and gas industry, building separation Ethan tower system at the treatment plants to build gas processing plants Ethan-ethylene; processing gas into liquid fuels (GTL), DME from methanol.

4. Oil and gas processing industry:

+ By 2015, finish 3-5 petrochemical refineries construction with total capacity of filter around 26-32 million tons/year, construction and commissioning of 1-2 production of petrochemical products basic petrochemicals.

+ By 2025, complete the expansion and completion of construction 6-7 petrochemical refineries with total refining capacity of 45-60 million tons/year,50% meet the needs basic petrochemical products. ...

Exploitation

(million tons oil

equivalent / year)

Exploiting overseas

(million tons / year)

Crude Oil

(million tons / year)

Gas

(million m3/year)

Period to 2015 25 – 38 18 – 20 8 --19

Period 2016 -2025 40 – 45 7 --14 12 – 16 8 --19

1. Search, petroleum exploration: oil and gas reserves reach 35-45 million tons of oil equivalent / year.

2. Oil and gas exploration:

Oil &Gas sector

18

Development Plan– Capital investment (mil. USD)

Oil &Gas sector

Cu

rre

nt

sta

tus &

de

vp

t. p

lan

No. Type of Investment 2011-15

High Scenario (Billion USD) 65,170

1 Oil and gas exploration 28,784

2 Transportation &collection of gas 2,467

3 Gas Processing Plant 1,816

4 Oil Refinery & Petrochemical 18,785

5 Petroleum Services 10,983

6 Petrol & LPG depots 2,100

7 Topics, scientific research 235

The participation of the PVN: 26,020

19

Coal sector

Current status

+ 5 mines with a capacity of over 2 million tons/year

+ 15 mines with a capacity of 0,1-0,7 million tons/year

+ A number of extraction with a capacity of less than 0.1 million tons/year

Opencast:

Underground: + 9 mines with a capacity of over 1 million tons/year

+ over 20 mines with a capacity of less than 1 million tons/year

Cu

rre

nt

sta

tus &

de

vp

t. p

lan

Mining production in the period 2003-2010

Extraction

method Unit 2003 2004 2005 2006 2007 2008 2009 2010 Total

Opencast Mil. tons 12.98 17.33 22.06 26.1 26.78 25.33 25.76 26.52 182.86

Underground Mil. tons 6.81 9.78 12.48 14.71 16.33 17.6 18.17 20.44 116.32

Total Mil.

tons 19.79 27.11 34.54 40.81 43.11 42.93 43.93 46.96 299.18

20

Viewpoints for development

- Developing the coal industry on the basis of mining, processing, cost-effective use of coal resources of the country, to serve the domestic demand is primarily to ensure national energy security.

- Development of sustainable coal industry, associated with effective protection, improve the ecological environment of coal

- Maximize internal resources (capital, ability to design and manufacture of equipment in the country, etc.)

- Promoting foreign investment in exploration and exploitation to supplement the long-term coal for domestic needs.

- To diversify forms of investment and business in the coal industry. To do business under the coal market is the management of the State to serve the aim of ensuring national energy security.

Coal sector

Cu

rre

nt

sta

tus &

de

vp

t. p

lan

21

Planning – Exploration, exploitation, processing

Coal sector

Cu

rre

nt

sta

tus &

de

vp

t. p

lan

1. Coal exploration:

a) Northeast coalfield:

- Distribution mainly in Quang Ninh, a part in Bac Giang and Hai Duong. This area has resources and reserves of the country's largest anthracite coal are mobilized primarily on 2030 planning. - By the end of 2015, completing the resources exploration and coal reserves of upper-level and a minus 300m area for the North East coalfield. By 2020, basically complete the exploration of coal to the bottom floor.

b) Red River delta coal basin:

- Distribution is mainly in the provinces of Thai Binh and Hung Yen, Nam Dinh, have great potential in type A bituminous coal (sub - bituminous), low levels of exploration, mining conditions difficult, complex and sensitive environment, ecology. - During the period 2012 - 2015, selected area contains some promising coal, geological conditions - suitable for conducting mining exploration investment for the test

harness. - By 2030, completed basic exploration area contains coal mining favorable conditions improve Khoai Chau - Tien Hai.

2. Coal Mining:

+ Year 2012: 45 - 47 million tons; Year 2015: 55 - 58 million tons; Year 2020: 60 - 65 million tons; Year 2025: 66 - 70 million tons; Year 2030: greater than 75 million tons.

3. Processing of coal: Strive to 2020, processing of coal development in product diversification (direct fuel combustion, coal for metallurgy, coal gasification, coal to liquid fuels, raw materials for chemical industry etc. ..)

22

- From year 2015, Vietnam will have to import coal;

- Total capital investment needs for the coal sector to 2030 about 691 trillion VND (equivalent to 33billion USD);

- The average capital investment needs for the coal sector to 2030 about 34.55 trillion VND/year (equivalent to 1,6 billion USD/year).

Coal sector

Cu

rre

nt

sta

tus &

de

vp

t. p

lan

Development Plan– Capital investment

Inve

st.

pro

po

sa

ls

23

Power sector

STT Project name Type of

investment

Location

(province)

Operation

year

Capacity

(MW)

Total

investme

nt (bil

USD)

Progress

1 O Mon II BOT Can Tho 2016 750 0,6

The project is preparing bidding

document to select investors.

International bidding.

2 Quang Tri

IPP/BOT

(potential

BOT)

Quang Tri 2019-2020 2x600 2,3

Ministry of Industry and Trade is

studying the investment guidelines of

project preparation.

3 Vung Ang 3 BOT Ha Tinh 2026-2028 4x600 5

The project is preparing bidding

document to select investors.

International bidding.

4 Pump storage PP

No.3 IPP Ninh Thuan 2028-2030 4x300 0,8

5 Van Phong 2 BOT Khanh Hoa 2021 2x660MW 2,4 Not yet implemented

6 Nam Đinh 2 BOT Nam Đinh 2025 2x660MW 2,4 Not yet implemented

7 Son My 1 BOT Binh Thuan 2018 5x390MW 2

Ministry of Industry and Trade is

studying the proposals of the investors

for investment in BOT type and plan to

evaluate and approve the feasibility

study (in case the project is approved by

competent authorities as BOT type)

8 Song Hau 2 BOT Hau Giang 2027 2x1000MW 3,5

Ministry of Industry and Trade are

working to guide investors in project

preparation

Total 12140MW 19

24

Oil & Gas sector

No. Project name Size Location Operation year

Total

investm

ent (bil.

USD)

Calling

for

foreign

investm

ent

ratio

Status &

progress

1

Upgrading and

expanding Dung

Quat oil refinery

from 6.5

(existing) to 10

million tons/year

Dung Quat

Economic Zone,

Quang Ngai

province

To begin the

construction in

the period 2014-

2017, commercial

operation in 2017

2,7 49% Investment

project are set up

2 The Nam Van

Phong refinery

10 million

tons/year

Van Phong

Economic Zone,

Khanh Hoa

province

2015-2020 8 49%

Investment

project are set up

and looking for

joint venture

partners

3 Gas Pipeline Nam

Con Son 2

~400km length,

capacity of 7

billion m3 /year

Ba Ria – Vung

Tau province

Commercial

operation in 2015 1,3 49%

set the overall

technical design

(FEED)

4 Long Son oil

refinery

10 million

tons/year

Long Son oil and

gas industrial

zone, Ba Ria -

Vung Tau

province

2015-2020 8 75% Study and calling

for investment

Total 20

Inve

st.

pro

po

sa

ls

25

Coal sector

To request assistance in the field of research in the Red River Delta coal basin.

Support the implementation of projects related to environmental protection and safety in coal mining.

Enhancing ODA aid for projects in infrastructure development in Vietnam's coal industry, human resources training.