Date post: | 13-Dec-2015 |
Category: |
Documents |
Upload: | madeleine-holland |
View: | 214 times |
Download: | 0 times |
Owned and operated as a joint venture by a consortium of Canadian universities via a contribution through the National Research Council Canada
Propriété d’un consortium d’universités canadiennes, géré en co-entreprise à partir d’une contribution administrée par le Conseil national de recherches Canada
Canada’s National Laboratory for Particle and Nuclear Physics Laboratoire national canadien pour la recherche en physique nucléaire
et en physique des particules
Beam Line 4N
ARIEL Science WorkshopJuly 10-11, 2012
Y. Bylinski | Accelerator systems | TRIUMF
Outline
July 10, 2012 Y. Bylinski ARIEL Workshop 2
• Facility layout • Beam parameters • Design features• Cyclotron upgrade requirements • Schedule considerations• Cost and resources estimate • Summary
Beam Parameters Requirements
July 10, 2012 Y. Bylinski ARIEL Workshop 5
• Energy – 470-500 MeV
• Intensity – 1-100 μA
• Beam losses < 1 nA/m.
• Beam size at the target 2-10 mm (FWHM)
• Uniform beam density distribution on the target
• Beam spot position instability < 1mm
• Intensity instability <1%
BL4N design features
July 10, 2012 Y. Bylinski ARIEL Workshop 6
Original design was done by Rick Baartman in 2009
Main features:•Transport capacity: 200 A•Beam dump capacity: 200 A•Achromatic design •Compensation of cyclotron’s dispersion and foil move•Collimation of large angle scatters from foil (up to 1 μA)•Collimation of beam halo due to energy dispersion•Moderate aperture - 71 mm and small beam size < 15 mm•Low loss beam transport and easy access to all optics•Dedicated matching section to control beam size on target•Beam rastering on target with AC steerers at 500 Hz
BL4N Layout
July 10, 2012 Y. Bylinski ARIEL Workshop 8
Achromatic 68º bend
Periodic section
Beam dump
Achromatic 90º bend
Collimators
Cyclotron Capability
July 10, 2012 Y. Bylinski ARIEL Workshop 9
Last decade routine operation: 220-250μA extracted
Recently achieved:
MuSR program & 500 MeV isotopes:
•BL1A (120μA)
ISAC program:•BL2A (100μA)
Sr production:•BL2C (80μA)
•Total (300μA)
BL1A
BL2A
BL2C
BL4
Future Needs for Beam
July 10, 2012 Y. Bylinski ARIEL Workshop 10
Long term needs:MuSR program, UCN & 500 MeV isotopes:
•BL1A (120μA)
ISAC program:•BL2A (100μA)•BL4N
(<100μA)
Sr production:•BL2C (100μA)
•Total (<420μA)
BL1A
BL2A
BL2C
BL4
Cyclotron Upgrade & Development Needs
July 10, 2012 Y. Bylinski ARIEL Workshop 11
• New extraction probe
• 15-20% more RF power (RF distribution upgrade)
• Ion source upgrade to 1mA high brightness beam
• Centre region diagnostics upgrade
• Simultaneous extraction of 4 high intensity beams
• Total extracted beam intensity to reach ~400 μA
• Intensity stabilization for multiple extracted beams
Time Line Constraints
12
• Cyclotron vault work: 2-3 shutdowns• Old front-end cleanup• New front-end installation• Beam dump construction• New extraction probe installation
• BL installation in the tunnel: 4-6 months• Electron beam line re-configuration• Electron beam delivery interruption
• Early installation for cyclotron development:• Ex probe• Beam dump
Y. Bylinski ARIEL WorkshopJuly 10, 2012
Manpower (5YP estimate)
13
• Physicists 24• Engineers 120• Designers 80• Machine shop 75• Controls 30• Technicians 240• Outside contractors 21
Total: 590 men-months
Y. Bylinski ARIEL WorkshopJuly 10, 2012
Budget estimate
14
3 benders and 20 quads can be salvaged
• Rest of BL optics/PS 2100 k$• Vacuum equipment 300 k$• Diagnostics & probe 500 k$• Beam dump 500 k$• Infrastructure 500 k$• Controls 400 k$
• Total equipment budget: 4.3 M$Y. Bylinski ARIEL WorkshopJuly 10, 2012
Summary
July 10, 2012 Y. Bylinski ARIEL Workshop 15
• Basic BL4N design has been done and meets requirements
• Equipment first order count allowed budget estimate
• Detailed design has to be started ASAP
• Project may spread over 3+ years or/and seriously impact beam delivery schedule
• Early start of installations in cyclotron vault is recommended to allow time for cyclotron development
• Cyclotron upgrade activities are being coordinated with ARIEL proton beam needs
Canada’s National Laboratory for Particle and Nuclear Physics Laboratoire national canadien pour la recherche en physique nucléaire
et en physique des particules
Thank you!
Merci!4004 Wesbrook Mall | Vancouver BC | Canada V6T 2A3 | Tel 604.222.1047 | Fax 604.222.1074 | www.triumf.ca
July 10, 2012 Y. Bylinski ARIEL Workshop16